0% found this document useful (0 votes)
54 views3 pages

0255 PDF

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
54 views3 pages

0255 PDF

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

#

SAUDI ARAMCO ID/PIEU-31-May-2019 - REV.2019.05.00 (Standards Cutoff - May 31,2019) Rev.2019.05.00 31-May-19
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Coating Equipment Inspection SAIC-H-2026 29-Oct-19 COAT-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A General (Coating Equipment Physical Verification)

Coating equipment is verified by completing the Quality Control


Equipment Check Sheet (Attachment B or SATR-H-2004)
SAES-H-001
A1 Records are signed by the coating contractor supervisor and then signed
Para. 10.2.1
by Saudi Aramco Inspector.
Note: No work shall be allowed until this form is completed

B Air Supply Compressor:

Air Compressor is capable of providing a pressure of 90 psig at the


blasting nozzle side. **Note: The following are guidelines to ensure
satisfactory performance:
A. Compressor size is the next larger size compressor available
for the nozzle as shown in the following table:
(SSPC Chapter 2.4, Sec. III A, Table 1)
AIR CONSUMPTION
Nozzle Orifice CFM Reqd @ 100 psi Abrasive
Consumption
3/16" 60 cfm 260 lbs/hr
1/4" 105 cfm 490 lns/hr
5/16" 160 cfm 812 lbs/hr
B1 SAES-H-001,
3/8" 232 cfm 1152 lbs/hr
Para. 6.5.2
7/16" 315 cfm 1584 lbs/hr
1/2" 412 cfm 2024 lbs/hr
5/8" 580 cfm 2518 lbs/hr
3/4" 840 cfm 3174 lbs/hr
B. Air supply hose should be 3 or 4 times the nozzle orifice.
(Note: Internal Diameter of coupling connection should be
considered if installed on the inner diameter of the
hose - SSPC Chapter 2.4, Sec. III B).
C. Outlet connections and valves from air supply compressor are
replaced with 1-1/2' or 2" outlets to match the main air supply
hose - SSPC Chapter 2.4, Sec. III B.

Compressed air for blasting is not contaminated with oil, moisture or other
contaminants. This is determined by performing a blotter test as follows:
a) Attach a piece of blotter or absorbent paper to a clip board.
b) Operate the blast system for at least 5 minutes, then allow air
SAES-H-001,
B2 flow out of the blasting nozzle at a nozzle pressure of 50 psig.
Para. 6.5.1
c) Hold the paper approx. 45-60 cm in front of the nozzle for at
least 1 minute.
d) Satisfactory results shall be no water or oil contamination on
the blotter.

Compressor, blasting pot, blasting nozzles shall be properly earthed


(grounded). Blast Nozzle shall be electrically ground using grounding wire
SAES-H-102,
AWG 4 or larger.
B3 Para. 4.4.1.6 &
Note: Blasting hose, blast nozzle, blast machine & material to be blasted
4.4.2.2
shall be bonded & grounded to a resistance of 1 mega ohm or less. (GI-
0006.021,Para. 6.1)

C AIR RECEIVER:

# Saudi Aramco: Company General Use Saudi Aramco: Company General Use
#

SAUDI ARAMCO ID/PIEU-31-May-2019 - REV.2019.05.00 (Standards Cutoff - May 31,2019) Rev.2019.05.00 31-May-19
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Coating Equipment Inspection SAIC-H-2026 29-Oct-19 COAT-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

Air receiver between compressor and the blasting pot is built and stamped SAES-H-102,
C1
in accordance with ASME Sec. VIII, Div 1 or equivalent. Para. 4.4.1.4
Air receiver has been revalidated annually by a successful hydro test at
250 psig. SAES-H-102,
C2
Note: The hydro test certificate can be accepted as proof of the Para. 4.4.1.4
revalidation test.

The calibration period of Pressure gauges and relief valves has not
SAES-H-102,
C3 exceeded one year.
Para. 4.4.1.5
Note: The calibration certificate and tags shall be provided.

D Pressure Blast Machine (Blast Pot)

Blasting pot control valves, for air and abrasive mixing are operational SAES-H-001
D1
and good condition. (SSPC Chapter 2.4, Para. III F & Para V-A). Para. 8.1.4

Oil and Moisture separators at the blasting pot are operational and good
SAES-H-001
D2 condition verified by partially opening the moisture trap to drain moisture.
Para. 8.1.3
(SSPC Chapter 2.4, Para. III F & Para V-A).

E Hoses and Accessories

Blasting hoses are in good condition (free of kinks, and signs of wear and SAES-H-001
E1
tear such as thinning of ply wrapping and punctures). Para. 8.1.3

SAES-H-102,
E2 The blasting hose is the static dissipating type with external couplings
Para. 4.4.2.3
Blasting Nozzle is equipped with a remote control shut-off switch SAES-H-102,
E3
'deadman'. Para. 4.4.2.1
Blasting nozzle tip is not worn out (orifice size is maintained) or cracked. SAES-H-001
E4
(SSPC Chapter 2.4, Para. III E) Para. 8.1.3

Respirable air-fed hoods and OSHA approved in-line air filters are used SAES-H-102,
E5
by the blaster at all times. Para. 4.4.2.4
Compressor hoses, airlines and blast hoses are safety wired at each SAES-H-102,
E6
coupling using proper safety pins Para. 4.4.2.5

F Coating Equipment

SAES-H-101V,
F1 Spray Nozzle Tip Size is as per SAES-H-101V Data sheets. Coating
Data Sheet

Airless spray equipment components, hoses, spray gun are in good SAES-H-102,
F2
working condition. Hoses are of anti-static type and grounded. Para. 4.4.5
Airless spray equipment are grounded with a wire of size AWG-4 or
SAES-H-102,
F3 larger.
Para. 4.4.5.8

Safety pressure relief valves set at 5000 psi or less are provided on the
out bound side of pressure pump.
SAES-H-102,
F4 Note : Hoses, pumps, and accessories shall never be operated at
Para. 4.4.5.5
pressures exceeding their rated pressure. In no case shall the working
pressure in the paint line exceed 5000 psi.

The trigger safety catch and tip guard provided on the airless gun are in SAES-H-102,
F5
good operating condition. Para.4.4.5

G Other Accessories
SAES-H-102,
G1 Electrically driven power mixers shall be grounded
Para. 4.4.4.2
Ventilators provided are functioning well and provide adequate flow of air
SAES-H-102,
G2 in confined spaces. Note: Table 4-1 of SAES-H-102 provides the
Para. 4.2
ventilation requirements for various sizes of confined spaces.

# Saudi Aramco: Company General Use Saudi Aramco: Company General Use
#

SAUDI ARAMCO ID/PIEU-31-May-2019 - REV.2019.05.00 (Standards Cutoff - May 31,2019) Rev.2019.05.00 31-May-19
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Coating Equipment Inspection SAIC-H-2026 29-Oct-19 COAT-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

All electrical lighting, equipment, and connections shall conform to


SAES-H-102,
G3 National Electric Code, Class I, Division 1, Group D explosion proof
Para. 4.1.2
requirements (NEC Article 500).
Adequate washing facilities are provided to remove splashed paints and SAES-H-102,
G4
solvents from the body or in the eyes. Para. 4.3.3
REMARKS:

REFERENCE DOCUMENTS
1. SAES-H-001,Coating Selection and Application Requirements for Industrial Plants and Equipment (23 May 2019)
2. SAES-H-102: Safety requirements for Coating Applications (29 October 2017)
3. SAES-H-101V, Approved Saudi Aramco Data Sheets – Paints and Coatings, ( 16 October 2017 )
4. G.I.-0006.021, Safety Requirements for Abrasive Blast Cleaning, (19 June 2012 )
5. Steel Structures Painting Council (SSPC), September 1993

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED