J Slab Track - Taiwan HSR PDF
J Slab Track - Taiwan HSR PDF
Trackwork
(site visit on T240 in very brief…)
Does not take into consideration
technical issues, mix designs,
progress, dimensions, work
fronts, testing, monitoring, etc.
23 October 2003
Content
✓ J-Slabs
✓ Rails Installation
✓ Ballast
OCS Poles and Power
✓
Light rebar D13-D19 installation – Road bed is built directly onto the girder
deck (no anchorage) - 10m length x 3.2 wide, with average 300mm thick
Rebar installation for Projection Concrete (typ. ~520mm dia. x 230mm high)
Typical Projection Concrete rebar in between Road Bed joints and girder
Expansion Joints (EJ heavily reinforced due to double shear forces)
Chamfer
Road Bed formwork and with chamfer (cover to rebar: 50mm). Rebar
projecting outside of formwork for Protection Layer
Concreted by
pump from
ground level
Survey
benchmark will
be installed on
top of projection
Concrete
Rails Assembly
Rails Assembly
Rails (20m length x 60kg/m) stored on site with rail assembly line
Rails Assembly
Rails are lifted onto girders and rail assembly line may commence
Rails Assembly
Rails Assembly
Rails are “fused” together – equipment verifying rails connection and levels
Rails Assembly
Wheel grinded
(not acceptable)
Rails sections rolled out of “flash-weld” machine into storage – once 10 no.
of 20m rails are fused (200m), they will be stored in assembly line
Rails Assembly
Rails Assembly
Rails Assembly
J-Slabs
J-Slabs
Quick J-Slab factory
production: 300kg/cm2, 5m
length, rail fasteners anchors
set in factory, J-Slab are
turned upside down when
placed on site
J-Slab: 5m X 2.2m X
190mm thick
J-Slabs
J-Slabs
J-Slabs
J-Slabs
Final survey before CA Mortar – survey data shown on Derailment Wall (HR:
High Rail, HS: High Slab, W: Gauge Width) taken from top of Projection
Concrete and derived from Secondary Control Points
Rail Installation
Rail Installation
Rail Installation
Rail Installation
Fasteners
Rail Installation
Final product
Rail Installation
Rail Installation
1’1”
difference
same same
Cant: very important that the Cant is well leveled (comparison: Philip at
5’1” and Bob at 6’2” are of similar height in the curves)
Ballast
Ballast
Ballast, also know as Noise Absorption was not carried out yet on
T240, therefore no photographs are available
Basics
Basics
End