Boiler Hydro Test Field Side Check List

This document lists 44 activities that must be completed to prepare a boiler for a hydrotest at the BNK Power Solution RSPL site in Dwarka, Gujarat. The activities include closing isolation valves on vents, drains, and sample lines; ensuring manhole doors are open; and checking the condition of safety valves, gauges, and transmitters. A field engineer, shift incharge, and station manager must sign off to confirm all activities are completed.

Uploaded by

Sudipta Das
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
122 views

Boiler Hydro Test Field Side Check List

This document lists 44 activities that must be completed to prepare a boiler for a hydrotest at the BNK Power Solution RSPL site in Dwarka, Gujarat. The activities include closing isolation valves on vents, drains, and sample lines; ensuring manhole doors are open; and checking the condition of safety valves, gauges, and transmitters. A field engineer, shift incharge, and station manager must sign off to confirm all activities are completed.

Uploaded by

Sudipta Das
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

BNK POWER SOLUTION RSPL SITE ,DWARKA GUJARAT

BOILER HYDROTEST PREPARATION (BOILER FIELD SIDE ACTIVITIES)


Boiler:- Date :-
S.No. Activity Yes No. Remark
1 Boiler Hydro Pump Line Up & R/C valve Condition (0-mtr)
2 MSSV & its Bypass MOV close (40-mtr)
3 Emergency vent isolation valve & MOV close
4 Economiser Drain Valve : Close (6-mtr)
5 Drum down comers drain valve LHS/RHS open condition (6-mtr)
6 Ring Header drain valve LHS/RHS open (6-mtr)
7 Down comers, Ring Header & Economiser Drain Header to IBD isolation valve close (6-mtr)
8 Start up vent MOV & isolation open condition (Initially)
9 Drum Manhole door close (43-mtr)
10 Pent house door open LHS/RHS (40-mtr)
11 SH Enclosure panel all manhole LHS/RHS open condition
12 Super Heater Inspection door Open (33 mtr)
13 Economiser manhole door Open (32 mtr)
14 Furnace manhole door Open LHS/RHS (9-mtr)
15 Wind box door and wind box drain valve open
16 Steam purging Isolation valve Close
17 Saturated sample line isolation valve close (9-mtr)
18 CBD sample line isolation valve close (9-mtr)
19 Main steam sample line isolation valve close (9-mtr)
20 CBD isolation valve and MOV close
21 IBD isolation and MOV close
22 Primary super heater -1 vent valve open (initially)
23 Primary super heater -2 vent valve open (initially)
24 Secondary super heater vent valve open (initially) Close after
25 Economiser vent valve open (initially) Complete
Venting
26 Wing Wall LHS/RHS vent valve open (initially)
27 Drum vent LHS isolation valve & MOV open (initially)
28 Drum vent RHS isolation valve & MOV open (initially)
29 Feed water station all mov and isolation valve close (13-mtr)
30 Feed station floor attemp-1 MOV and isolation valve close (13-mtr)
31 Feed station floor attemp-2 MOV and isolation valve close (13-mtr)
32 Primary super heater -1 drain valve & MOV close (13-mtr)
33 Primary super heater -2 drain valve & MOV close (13-mtr)
34 Secondary super heater drain valve & MOV close (13-mtr)
35 Wing wall LHS/RHS drain isolation valve & MOV close (13-mtr)
36 Drain before MSSV close
37 Drum Safety valve Gag (LHS/RHS) condition
38 Main steam safety valve Gag condition
39 Drain after MSSV open
40 Start up vent isolation and MOV close @ 2.0 kg pressure
41 HP (phasphate ) dosing isolation valve closed condition
42 Drum Pre. Gauge line up and its working condition
43 Drum Local Gauge Glass LHS & RHS isolation valve condition.
44 Drum Level transmitter isolation valve condition
45 Drum Hydrastate LHS & RHS isolation valve condition

Field Eng.. Shift- Incharge Staion Manager