Indri 8a PDF
Indri 8a PDF
Mode Week -3 Week 1 Week 4 Week 7 Week 10 Week 13 Week 16 Week 19 Week 22 Week 25 Week 28 Week 31 Week 34 Week 37 Week 40
1 A. Determine 21 days Mon Mon
system 03/10/22 31/10/22
requirement
2 B. Determine the 7 days Tue Wed 1
workers involved 01/11/22 09/11/22
3 C. Identification 14 days Tue Fri 1
of system flow 01/11/22 18/11/22
4 D. Design 35 days Mon Fri 3;2
database 21/11/22 06/01/23
5 E. Design UI/UX 21 days Mon Mon 3
21/11/22 19/12/22
6 F. Coding 14 days Mon Thu 4
program 09/01/23 26/01/23
7 G. Evaluation 21 days Fri Fri 6;5
27/01/23 24/02/23
8 H. Program 35 days Mon Fri 7;6
testing 27/02/23 14/04/23
9 I. Documentatiom 35 days Mon Fri 8;7
17/04/23 02/06/23
10 J. Install 14 days Mon Thu 9
05/06/23 22/06/23
Project: TP M2 8A Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress