Summary Level 3 PDF
Summary Level 3 PDF
5 5 2
4 4 3 0 0 0 0 0 9
9 9 2
2
5
-
O
c
t
-
2
2
2
5
-
A
p
r
-
2
4
CP28-B Design & Build of Infras
Infrastructure and Landscape Works for Huzoom Lusail-Phase 1_R00
2
5
-
O
c
t
-
2
2
2
5
-
A
p
r
-
2
4
General
2
5
-
O
c
t
-
2
2
1
3
-
J
u
n
-
2
3
Design
2
5
-
O
c
t
-
2
2
2
5
-
O
c
t
-
2
2
Schematic Design-Inputs from Client/Authorities
Client/
2
5
-
O
c
t
-
2
2
2
5
-
O
c
t
-
2
2
Wet Utility Network
2
5
-
O
c
t
-
2
2
2
5
-
O
c
t
-
2
2
Dry Utility Network
2
5
-
O
c
t
-
2
2
2
5
-
O
c
t
-
2
2
Road Network
2
5
-
O
c
t
-
2
2
2
5
-
O
c
t
-
2
2
Buildings
7 0 2 2 5 2 9
2
5
-
O
c
t
-
2
2
2
9
-
J
a
n
-
2
3
Detailed Design
2
5
-
O
c
t
-
2
2
2
3
-
N
o
v
-
2
2
Utilities
7
-
N
o
v
-
2
2
8
-
N
o
v
-
2
2
Roads and Paving
3
-
N
o
v
-
2
2
1
4
-
D
e
c
-
2
2
Buildings
1
7
-
N
o
v
-
2
2
2
1
-
N
o
v
-
2
2
Substations
6 1 6 1
2
9
-
N
o
v
-
2
2
2
9
-
J
a
n
-
2
3
Landscape Works
5 8 1 5 7 6 9 0 1 3 5 4 4 6 5 4 6 5 5 4 8 9 9 9 9 7 9 8 8 7 8
3
-
N
o
v
-
2
2
1
6
-
M
a
y
-
2
3
Authority Approvals
3
-
N
o
v
-
2
2
9
-
J
a
n
-
2
3
Utilities and Asphalt Works
9 4 9 8 9 7 5 4 7 9 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
6
-
N
o
v
-
2
2
1
6
-
M
a
y
-
2
3
Buildings- DC1 and DC2
3
0
-
J
a
n
-
2
3
1
5
-
M
a
r
-
2
3
Landscape Works
2
9
-
N
o
v
-
2
2
1
3
-
J
u
n
-
2
3
IFC Drawings
2
9
-
N
o
v
-
2
2
2
2
-
F
e
b
-
2
3
Utilities
2
1
-
D
e
c
-
2
2
2
9
-
M
a
r
-
2
3
Roads and Paving
1
2
-
D
e
c
-
2
2
3
0
-
M
a
y
-
2
3
Buildings and Substations
2
7
-
D
e
c
-
2
2
1
5
-
F
e
b
-
2
3
Substations
1 3
2
2
-
J
a
n
-
2
3
1
3
-
J
u
n
-
2
3
Landscape Works
2
7
-
O
c
t
-
2
2
5
-
N
o
v
-
2
3
Engineering
1
-
N
o
v
-
2
2
2
-
F
e
b
-
2
3
Pre-Qualification
1
-
N
o
v
-
2
2
2
4
-
N
o
v
-
2
2
Trench Excavation
3
-
N
o
v
-
2
2
2
8
-
N
o
v
-
2
2
Geotechnical & Geophysical Survey
6
-
N
o
v
-
2
2
3
0
-
N
o
v
-
2
2
Lab Testing
8
-
N
o
v
-
2
2
1
-
D
e
c
-
2
2
BIM Works
1
0
-
N
o
v
-
2
2
5
-
D
e
c
-
2
2
GSAS Works
1
3
-
N
o
v
-
2
2
7
-
D
e
c
-
2
2
Asphalt Works
1
3
-
N
o
v
-
2
2
7
-
D
e
c
-
2
2
Road Marking Works
1
5
-
N
o
v
-
2
2
8
-
D
e
c
-
2
2
Dewatering Works
1
7
-
N
o
v
-
2
2
1
4
-
D
e
c
-
2
2
Microtunneling
2
3
-
N
o
v
-
2
2
2
1
-
D
e
c
-
2
2
Landscaping Works
2
9
-
N
o
v
-
2
2
2
7
-
D
e
c
-
2
2
Fabric Shades
1
-
D
e
c
-
2
2
2
9
-
D
e
c
-
2
2
GRC Works
4
-
D
e
c
-
2
2
1
-
J
a
n
-
2
3
Metal Works
1
0
-
D
e
c
-
2
2
5
-
J
a
n
-
2
3
Waterproofing
1
5
-
D
e
c
-
2
2
1
2
-
J
a
n
-
2
3
Play & Fitness Equipment
1
9
-
D
e
c
-
2
2
1
5
-
J
a
n
-
2
3
Gypsum Ceiling 2
1
-
D
e
c
-
2
2
1
7
-
J
a
n
-
2
3
LV Network
2
4
-
D
e
c
-
2
2
1
9
-
J
a
n
-
2
3
MV Network
2
6
-
D
e
c
-
2
2
2
2
-
J
a
n
-
2
3
Substation Works
2 2
7 2
7
-
J
a
n
-
2
3
2
-
F
e
b
-
2
3
Traffic Signal Control System
9 6 3 4 8 2 3 6 0 0 7 7 3 0 6 9 3 1 7 4 9 1 8 0 7 9 9 8 9 8 8 8 8 8 0 6 7 8 8 7 4 7 9 9
2
7
-
O
c
t
-
2
2
1
2
-
J
u
n
-
2
3
Material Submittal
1 2 2 2 2 1 3 1 5 1 1 2 2 1 2 3 2 1 1 1 3 2 3 2 2 2 2 2 2 2 2 2 2 3 2 2 2 2 2 3 2 2 2
7 1 2
2
7
-
O
c
t
-
2
2
2
0
-
A
p
r
-
2
3
Utilities
1
-
N
o
v
-
2
2
1
-
J
u
n
-
2
3
Roads and Paving
1
-
N
o
v
-
2
2
1
2
-
J
u
n
-
2
3
Buildings
1
-
N
o
v
-
2
2
2
8
-
N
o
v
-
2
2
Enabling Works
0 8 2 6
1
-
N
o
v
-
2
2
2
1
-
M
a
y
-
2
3
Landscape
5
-
D
e
c
-
2
2
5
-
J
u
n
-
2
3
Authority Approvals (Kahramaa)
1
5
-
D
e
c
-
2
2
5
-
N
o
v
-
2
3
Shop Drawing
1
5
-
D
e
c
-
2
2
2
3
-
M
a
y
-
2
3
Utilities
2
0
-
A
p
r
-
2
3
8
-
J
u
n
-
2
3
Roads and Paving
5 4 3 0 8 1 0 0 2 3 0 0
2
4
-
J
a
n
-
2
3
2
9
-
J
u
n
-
2
3
Substations
3
1
-
J
a
n
-
2
3
2
6
-
J
u
n
-
2
3
Utility Hub Substation
7
-
J
a
n
-
2
3
2
7
-
A
u
g
-
2
3
Terminal Sewage Pumping Station
7
-
J
a
n
-
2
3
2
5
-
J
u
l
-
2
3
Potable and Fire Water Pumping Station
Sta
1
4
-
J
a
n
-
2
3
1
8
-
J
u
l
-
2
3
TSE Tank and Pumping Station
2
5
-
D
e
c
-
2
2
3
1
-
J
u
l
-
2
3
Potable Water Reservoir
7
-
J
a
n
-
2
3
5
-
N
o
v
-
2
3
Storm Water Attenuation Tanks
2
8
-
J
a
n
-
2
3
1
6
-
A
u
g
-
2
3
Chlorination Room
8
-
F
e
b
-
2
3
1
4
-
J
u
n
-
2
3
Guard Room
1
0
-
J
a
n
-
2
3
2
3
-
M
a
y
-
2
3
Foul Water Lift Station
8
-
M
a
y
-
2
3
2
4
-
A
u
g
-
2
3
Landscape
1
-
N
o
v
-
2
2
2
8
-
A
u
g
-
2
3
Method Statement
1
-
N
o
v
-
2
2
2
8
-
N
o
v
-
2
2
Mobilization of Temporary Site Facilities
Facili
2
6
-
N
o
v
-
2
2
2
5
-
D
e
c
-
2
2
Trial Pits Excavation
1
0
-
D
e
c
-
2
2
5
-
J
a
n
-
2
3
Dewatering Works
1
2
-
D
e
c
-
2
2
9
-
J
a
n
-
2
3
Survey Works
1
4
-
D
e
c
-
2
2
1
1
-
J
a
n
-
2
3
Night Works
1
9
-
D
e
c
-
2
2
1
5
-
J
a
n
-
2
3
Micro-Tunneling
2
8
-
N
o
v
-
2
2
2
6
-
D
e
c
-
2
2
Remaining Works at Tree Nursery A
Area
2
1
-
D
e
c
-
2
2
1
7
-
J
a
n
-
2
3
Foul Water Network
2
1
-
D
e
c
-
2
2
1
7
-
J
a
n
-
2
3
Storm Water Network
4
-
J
a
n
-
2
3
3
1
-
J
a
n
-
2
3
Potable Water Network
2
-
J
a
n
-
2
3
2
9
-
J
a
n
-
2
3
TSE/Irrigation Network
2
7
-
D
e
c
-
2
2
2
3
-
J
a
n
-
2
3
Polymer Concrete Manhole
2
1
-
J
a
n
-
2
3
1
9
-
F
e
b
-
2
3
MV/LV Network
8
-
J
a
n
-
2
3
2
-
F
e
b
-
2
3
Telecom Network
4
-
F
e
b
-
2
3
2
-
M
a
r
-
2
3
ELV/MOI-SSD Network
2
-
J
a
n
-
2
3
2
9
-
J
a
n
-
2
3
Anti-Termite Treatment
4
-
J
a
n
-
2
3
3
1
-
J
a
n
-
2
3
Concrete Works
4
-
M
a
r
-
2
3
3
0
-
M
a
r
-
2
3
Wall, Floor and Ceiling Works
1
-
A
p
r
-
2
3
4
-
M
a
y
-
2
3
GRC Works
6
-
M
a
y
-
2
3
1
-
J
u
n
-
2
3
Doors and Windows 1
8
-
J
a
n
-
2
3
1
5
-
F
e
b
-
2
3
Waterproofing Works
1
-
F
e
b
-
2
3
1
-
M
a
r
-
2
3
Asphalt Works
Page 3 of 6
3 3 3 3 3 3 3 3 3 3 3 4 4 4 3 3 3 3 3 3 3 3 3 3 3 3 3 3
2 2 3 2 2 3 2 2 2 3 2 2 3 3 3 3 3 2 3 3 3 3 2 2 2 2 2 2 2 2 3 2 3 3 2 2 2 2 2 3 2 2 2 3 2
- -
r 2 - - 2 - - - 2 - - 2 2 2 2 2 -
r 2 2 2 2 - - - - - - - - 2 -
v 2 2 -
v - - - - 2 -
v -
v -
v 2 -
n a -
l g r - p p p - n r - - - - - a - - - - p b n n c c c c - - - c c c t - - c
u u u p v e e e p u p g p n n v v t t t e e a a e e e e c o c c o e e e c c o o o c e
J M J A A o S S S e J A u e o M o c c c S F J J D D D D e N e e N D D D O e N N N e D
- - - - - N - - - S - - A S a
J a
J N - N O O O - - - - - - - - D - D D - - - - - D - - - D -
Finish
9 9 1 8 0 - 7 7 5 - 8 0 - - - - - 6 - - - - 1 3 5 5 3 6 7 2 - 7 - - 5 3 0 6 5 - 9 5 0 - 9
2 2 3 2 1 3 2 2 2 1 2 3 5 1 9 9 3 2 3 5 6 6 2 1 1 1 1 1 1 1 5 2 3 9 2 1 2 2 2 6 1 2 3 6 1
CP28B – Design and Build of Infrastructure and
Landscape Works for Huzoom Lusail – Phase 1
3 3 3 2 2 2 2 3 3 2 2 2 2 2 2 2 2 3 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3
3 2 3 2 2 2 2 2 2 3 3 3 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 3 2 3 2 2 2 2 2 2 2 2
2 - - 2 2 2 2 2 - - - - - - 2 - - - - - - - 2 2 2 2 2
Actual Start
- - 2
- - r - - - v - - - - - v v v v v v - - - t t v v - c c c - - - - - - - - - - - - - -
r
7 8 8 8 8 6 2 2 0 3 7 2 4 1 4 1 1 1 7 7 7 4 2 1 0 0 8 7 5 5 7 8 8 8 2 6 4 5 5 5 7
2 2 2 2 2 3 3 3 3 2 1 8 1 9 4 4 3 1 3 3 3 3 1 4 3 3 3 3 3 3 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Milestone
summary
Critical Remaining Work
Activity Name
Remaining Work
Installation of Traffic Signs and Gantry
Gant
Landscaping - Hardscape Works
Landscaping - Softscape Works
Road S10-R27A
Road S10-R28A
Road S8-R25A
Road S9-R26A
Road S20-R9A
Road S21-R10
Road S24-R12
Road S25-R13
Road S10-R57
Road Markings
Road S23-R11
Asphalt Paving
Enabling Works
Road S7-R8A
Road S9-R58
Road S4-R59
Construction
Procurement
Road S5-R6
Road S4-R5
Road S3-R3
Road S4-R4
Road S2-R2
Road S6-R7
Traffic Signs
Wet Utilities
Actual Work
Dry Utilities
Hardscape
Landscape
Softscape
Buildings
Finishes
Zone 1A
Utilities
Utilities
MEP
Civil
Activity ID
S O N D J FM A M J J A S O N D J F M A M J J
2024
2023
Page 4 of 6
3 4 3 3 3 3 3 3 3 3 3 4 3 3 3 3 3 3 3 3 3 3 3 3 4 3 3 3 3 3 3 3 3 3 3 3
2 2 4 2 2 2 2 4 2 2 2 2 2 2 2 2 2 2 3 2 2 3 3 2 2 2 2 2 2 3 2 2 2 3 2 2 2 2 2 2 2 3 3 2 2
- - 2 - - - - 2 - - -
v -
v - - - - -
v - 2 - - 2 2 - -
v -
v -
v -
v - 2 - - -
v 2 - -
v -
v -
v - - - 2 2 - -
c n - c c c c - t t c n c c c - c t - -
v c c -
v n c - c c t c - - t t
e a n e e e e n c c o o e a e e o e c e c c e o o o o e a e o c e o o o e c e c c c c
D J D D D D O O N N D J D D N D e D O e o D N N N N D o J D N e D N N N D O D e e O O
- - a
J - - - - a
J - - - - - - - - - - D - - D N - - - - - - N - - - D - - - - - - - D D - -
Finish
5 5 - 7 4 3 7 - 1 1 1 6 4 1 1 0 5 1 - 3 1 - - 0 0 9 5 0 7 - 1 3 7 - 0 6 9 2 3 6 1 - - 5 5
2 1 2 1 1 2 1 2 3 3 1 1 2 1 1 1 2 1 7 1 1 7 8 2 2 1 2 3 1 4 1 1 2 3 1 2 2 2 1 2 1 7 4 2 2
CP28B – Design and Build of Infrastructure and
Landscape Works for Huzoom Lusail – Phase 1
3 3 2 2 2 2 2 2 2 3 3 3 3 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 3 3 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 - - - - - - - - - - - - - 2 2 2 2 - - - - - - - - -
Actual Start
- - v v v - c c c - - - - t t - v v - - c c c - - - - - - - - t t t - - - - v v v - c c c
b b
6 4 4 2 2 2 1 2 6 4 5 5 7 7 4 3 1 1 1 1 5 0 7 9 6 5 5 5 6 1 3 4 3 3 3 2 2 1 3 9 2 0 9 5 5
2 2 3 3 3 3 3 3 2 2 2 2 2 3 3 3 3 3 3 3 2 3 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 2 3 3 2 2 2
Milestone
summary
Critical Remaining Work
Activity Name
Remaining Work
Actual Level of Effort
Road S12-R32A
Road S31-R39B
Road S30-R39A
Road S11-R30A
Road S11-R31A
Road M2-R29A
Road S27-R21
Road S29-R23
Road S28-R22
Road S26-R14
Road S13-R17
Road S14-R18
Road S15-R16
Road S16-R19
Road S26-R36
Road S27-R37
Road S19-R35
Road S17-R33
Road S18-R34
Road S33-R40
Road S28-R38
Road S43-R55
Road S36-R43
Road S39-R47
Road S40-R48
Road S40-R49
Road S38-R46
Road S46-R50
Road S38-R45
Road S47-R51
Road S33-R54
Road S40-R63
Road S36-R61
Road S50-R52
Road S37-R44
Road S11-R60
Nursery Area
Nursery Area
Road M1-R20
Road S1-R24
Road S1-R15
Road S1-R1
Actual Work
Zone 1B
Zone 1C
Zone 1D
Activity ID
CP28B – Design and Build of Infrastructure and
Landscape Works for Huzoom Lusail – Phase 1
Activity ID Activity Name Original Actual Start Finish 2023 2024
Duration
S O N D J FM A M J J A S O N D J F M A M J J
2 2 2 2 2 1 1 2 1 3 3 2 2 3 2 2 1 2 1 7 2 2 2 2 3 2 7 7 4 3 3 2 2 2 1 1 1 1 1 2 1 1 1 3
7 5 5 5 6 7 6 6 7 6 3 9 9 1 8 5 8 0 9 1 9 9 3 4 0 6 2 2 1 4 6 5 4 4 9 8 6 7 7 7 9 1 9 3
1 9 2 4 8 1 9 8 2 8 7 3 3 6 1 4 9 1 5
1
2
-
J
a
n
-
2
3
2
-
D
e
c
-
2
3
Road S38-R62
1
8
-
J
a
n
-
2
3
2
3
-
N
o
v
-
2
3
Road S36-R42
2
8
-
J
a
n
-
2
3
2
5
-
N
o
v
-
2
3
Road S35-R41
3
0
-
J
a
n
-
2
3
2
9
-
N
o
v
-
2
3
Road S49-R53
2
2
-
M
a
y
-
2
3
1
3
-
F
e
b
-
2
4
Roads Works
1
0
-
J
u
n
-
2
3
3
0
-
D
e
c
-
2
3
Zone 1A
2
2
-
M
a
y
-
2
3
7
-
D
e
c
-
2
3
Zone 1B
2
2
-
M
a
y
-
2
3
1
3
-
F
e
b
-
2
4
Zone 1C
2
2
-
M
a
y
-
2
3
1
1
-
D
e
c
-
2
3
Zone 1D
8
-
J
a
n
-
2
3
1
0
-
J
a
n
-
2
4
Buildings
8
-
J
a
n
-
2
3
1
0
-
D
e
c
-
2
3
Utility Hub Buildings and Substation
4
-
F
e
b
-
2
3
2
3
-
N
o
v
-
2
3
Potable and Fire Water Pumping Sta
Station
1
1
-
F
e
b
-
2
3
3
0
-
N
o
v
-
2
3
TSE Tank and Pumping Station
8
-
J
a
n
-
2
3
1
9
-
N
o
v
-
2
3
Potable Water Reservoir
4
-
F
e
b
-
2
3
1
1
-
N
o
v
-
2
3
Terminal Sewage Pumping Station
4
-
F
e
b
-
2
3
4
-
D
e
c
-
2
3
Storm Water Attenuation Tank 1
1
-
M
a
r
-
2
3
1
4
-
O
c
t
-
2
3
Utility Hub Substation
2
7
-
F
e
b
-
2
3
2
5
-
O
c
t
-
2
3
Chlorination Building
9
-
M
a
r
-
2
3
2
9
-
O
c
t
-
2
3
Guard House
1
9
-
S
e
p
-
2
3
1
0
-
D
e
c
-
2
3
Boundary Wall
2 2 7 2 2 8
2
6
-
J
a
n
-
2
3
1
0
-
J
a
n
-
2
4
Storm Water Attenuation Tanks
2
6
-
J
a
n
-
2
3
1
0
-
J
a
n
-
2
4
Storm Water Attenuation Tank 2
2
2
-
F
e
b
-
2
3
2
-
D
e
c
-
2
3
Storm Water Attenuation Tank 3
4
-
M
a
r
-
2
3
1
7
-
D
e
c
-
2
3
Storm Water Attenuation Tank 4
7
-
F
e
b
-
2
3
5
-
D
e
c
-
2
3
Foul Water Lift Station
7
-
F
e
b
-
2
3
1
-
N
o
v
-
2
3
Substructure
1
2
-
A
u
g
-
2
3
2
-
N
o
v
-
2
3
Finishes
1
3
-
S
e
p
-
2
3
5
-
D
e
c
-
2
3
MEP
1
-
M
a
r
-
2
3
1
7
-
A
p
r
-
2
3
Enabling Works
1
-
M
a
r
-
2
3
9
-
A
p
r
-
2
3
Zone 1A
7
-
M
a
r
-
2
3
1
7
-
A
p
r
-
2
3
Zone 1C
4 8 3 0 6 9 3 3 7 8 4 8
2
2
-
F
e
b
-
2
3
2
3
-
D
e
c
-
2
3
Substations
1
-
M
a
r
-
2
3
2
3
-
D
e
c
-
2
3
Type 1 Substations (18)
2
2
-
F
e
b
-
2
3
9
-
D
e
c
-
2
3
Type 2 Substations (4)
5
-
J
u
n
-
2
3
1
6
-
J
a
n
-
2
4
Landscape
1
0
-
J
u
n
-
2
3
1
6
-
J
a
n
-
2
4
Zone 1A
5
-
J
u
n
-
2
3
2
3
-
D
e
c
-
2
3
Zone 1B
5
-
J
u
n
-
2
3
2
7
-
D
e
c
-
2
3
Zone 1C
5
-
J
u
n
-
2
3
2
7
-
D
e
c
-
2
3
Zone 1D
2
4
-
J
u
l
-
2
3
2
5
-
A
p
r
-
2
4
Testing, Commissioning and Handing
Ha Over
2
4
-
J
u
l
-
2
3
6
-
F
e
b
-
2
4
Testing and Commissioning 7
-
S
e
p
-
2
3
1
8
-
J
a
n
-
2
4
Utilities
2
4
-
J
u
l
-
2
3
6
-
F
e
b
-
2
4
Buildings
9
-
D
e
c
-
2
3
1
6
-
J
a
n
-
2
4
Road Works
Actual Level of Effort Remaining Work Milestone
Three (3) Months Look Ahead - Summary Page 5 of 6
Actual Work Critical Remaining Work summary
CP28B – Design and Build of Infrastructure and
Landscape Works for Huzoom Lusail – Phase 1
Activity ID Activity Name Original Actual Start Finish 2023 2024
Duration
S O N D J FM A M J J A S O N D J F M A M J J
7 1
7 8
1
8
-
O
c
t
-
2
3
1
6
-
J
a
n
-
2
4
Landscape
4 8 3 6 9 6
2
5
-
O
c
t
-
2
3
2
5
-
A
p
r
-
2
4
Handing Over
1 1 1 9 3
7 8 1
3
1
-
O
c
t
-
2
3
2
5
-
A
p
r
-
2
4
Utilities
2
5
-
O
c
t
-
2
3
2
4
-
A
p
r
-
2
4
Buildings
3
1
-
D
e
c
-
2
3
2
4
-
A
p
r
-
2
4
Road Works
1
7
-
J
a
n
-
2
4
2
4
-
A
p
r
-
2
4
Landscape
2
5
-
J
a
n
-
2
4
7
-
M
a
r
-
2
4
Handover Documents