4.3a "Signages"
7.3 Synchronization
10 UPS
Design Guide Requirement
The control system is the set of elements intended for the command
and supervision of the transfering station and the establishment of its
relationship with the distant operations center.
It includes the electric control executed in the kiosk from the span
control , which will have a "kiosk-room" switch (K-S) for the selection of
this control mode and its position will be informed to the remote
control system.
The command of a computer from the span level r will want the
position (K) of the switch (K-S) and the position (R) of the switch (L-R) of
the equipment.
The UC collects the information acquired by the UUPP, and controls the
applications for communications with the Regional Centers (CR) of the
company and other interconnected companies, local SCADA consoles
(CL), Event Protocolization consoles (PEV), logical and arithmetic data
processing, time synchronization acquisition, as well as being able to
exchange data with smart devices (IEDs).
At the distant operations center level , the control system will act as a
distributed configuration remote terminal unit (RTU)
At the station level , the control system will act from its UC as a master
unit, through an operations console.
The vain level control equipment will process the information and have
control of the span independently of the other spans, ensuring an
increase in the reliability of the system
Handle bra equipment
CBC transformers position.
The switches shall be equipped with duplicate and independent coils for
both tripolar and unipolar drive
• Immediate execution.
• With pre-operation verification.
Disconnector section of bar-side bar
Disconnector section of bar-center bar
Disconnector section of central section
Line Disconnector
In the existing installations of 500 Kv the voltage of 220 Vdc has been
adopted and in the levels of 220 and 132 Kv the voltage of 110 Vdc
predominates .
Can the main control system perform this task and avoid using
additional UP equipment to save cost? UUPP will only see 220 kV
GIS signals.
Define EAT, AT
Section is not applicable as generators are synchronizing to utility
through generator controller
Transformer tap changer voltage selection is programmed,
confirm if a selector device Is required.
De acuerdo
Los kioscos se ubican normalmente en la playa de la
estacion y tienen la operación y proteccion del vano
Interruptores
EAT es 500 kV, y AT es 220 y 132 kV
4.1 Architecture
The premises that make up the Main Building of Control can be:
• The Station Control Room, with the control equipment and control
panels or the terminals of the Central Processing Units.
• The Communications Room, with the equipment of carrier wave
systems and / or fibrto optics.
• The Battery and Charger Room, with the equipment for the supply
of auxiliary services in direct current for control and communications.
• The Room of Boards and Distributors or others that may be
required when the technology used for the control and command of the
facilities requires having the terminal panels to receive the information
from the beach and direct it to the control and communications system
In the battery room, a floor with antacid ceramic will be used and the
side walls will have a cementitious coating up to a height of not less
than 1.50 m.
The roofs of buildings in general shall be of the inclined metal type with
galvanized andpainted sheet, special attention shall be given to the
methods of fixing the roof without perforation of sheets and complete
sections of sheet metal without longitudinal splices shall preferably be
used
will materialize with ochavas at 45º to allow the laying and bending of
the cables comfortably
clarify "ochavas"
Confirmamos
3.1 General
Design Guide Requirement
4.2 redundancy
nominal voltage and clearances
4.1.3d Signages
4.1.3e Measurements in the TGSACA
D1 and D2
timed non-voltage relays
derived from the E ba r
The TGSACA board will have automatic transfer and interlocking of the
main switches to obtain, automatically or manually, from the
configurations in normal service, the different emergency alternatives.
Keep the three bars A, B and E permanently energized
The position status of the low voltage switches will be signaled at the
station control level and will also be sent to the operations center, by
remote control.
n the TGSACA
The switching keys of the consumptions with double feeding will be
manual.
Power to auxiliary services of main transformers and reactors or
compensation elements.
All essential consumerswill have double feeding: one from bar "E" and
one from one of the bars "A" or "B".
In the stations with kiosks, a board for 380/220 Vac will be installed in
each of them for segregation of the services of the corresponding EAT
and AT outputs, which are detailed below
Where "two-out kiosks " are used, they may be fed by garlands covering
two or three kiosks.
The batteries will be of the alkaline type (Níquel-Cadmium) or acid type
(Lead-Calcium), hermetic, in such a way that they do not produce
corrosive gases .
Per GUIAS EETT Control, 110 VDC is used for 220 kV system.
Confirm 110 VDC or 220 VDC should be used.
Not using the tertiary winding for power distribution only for
trapping harmonics with delta winding. Auxiliary power provided
through 2 winding transformer of 33 / 0.4 kV, 1 MVA
Is there definition of what these abbreviations mean?
Clarify, if D1/D2 is LV, it would have primary protection (either
motor or feeder)
Does this mean time-delay relays? LSIG?
clarify
Aceptado
El requerimiento es de 5 horas
Aceptado