METHOD STATEMENT - Trunking

The document provides a method statement for installing trunking. It outlines preparing approved materials and understanding installation procedures. It describes marking locations from drawings, ensuring supports are placed properly based on structural elements, drilling holes correctly, and installing brackets and channels for supporting the trunking. The trunking is then fixed to the supports, earth links are installed, and fire sealing is applied where needed. Trunking is labelled and inspected before cable can be laid.

Uploaded by

slurpeer teo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
312 views1 page

METHOD STATEMENT - Trunking

The document provides a method statement for installing trunking. It outlines preparing approved materials and understanding installation procedures. It describes marking locations from drawings, ensuring supports are placed properly based on structural elements, drilling holes correctly, and installing brackets and channels for supporting the trunking. The trunking is then fixed to the supports, earth links are installed, and fire sealing is applied where needed. Trunking is labelled and inspected before cable can be laid.

Uploaded by

slurpeer teo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Electrical works for

Method Statement for Trunking Installation


1 Preparation

1.1 Ensure that the materials to be used for installation are of the inspected and approved brands and type.

1.2 Ensure that the installation works procedures are fully comprehended by the supervisor and his workers.

1.3 Ensure that approved type of supports and anchors for trunking and conduit support are used

1.4 Studied the planned cable routing layout from the latest shop drawings.

2 Tray / Ladder Installation

2.1 From the working drawings, locations of cable tray/cable ladder are marked on site taking reference from the column and /
or beam grid lines.

2.2 Ensure that location of support shall be 100mm (minimum) away from structural pre-stressed cables. (For Hollow Core Slab
Area.)

2.3 Position of pre-stress cables can be determined from drawings provided by builder and confirmed by structural engineer
prior to drilling.

2.4 Correct size of holes are then drilled, and approved type of metal expansion bolts are used to fix threaded rods / brackets /
Channels on ceilings / walls /columns.

2.5 Cable trunking support / bracket shall be cut and install according to the required elevation, which can be checked by
referring to the CSD.

2.6 Cable Trunking are then fixed on the brackets and shall be anchored by using hexagonal bolts and nuts.

2.7 Earth links / strips shall be installed on the side of cable trunking, ensuring continuity throughout the trunking run.

2.8 Whenever cable trunking pass through fire rated walls or floors, the gaps between the wall and trunking shall be sealed with
fire rated compound having the same fire rating.

2.9 Cable trunking shall be labelled using standard labels at every 3-metre interval and at the point of Tee and Bends.

2.10 Boom lift or scissors lift will be used for high-level tray installation.

2.11 Supervisor to check and make sure all Cable Trunking is secured and ready for inspection.

2.12 Call for inspection with main-con and RTO.

2.13 Approval from RTO before laying cable