This document provides a master list of manuals, log sheets, and checklists for the UREA-2 unit at Engro Fertilizer Limited Daharki. It includes 12 manuals, 12 log sheets, and 11 checklists that are relevant to various areas and sections within the UREA-2 unit such as SYNCOM Post, ACES Post, and Finishing Post. It specifies the current issue number and date for each document, as well as the revision number if applicable, and the date by which each document is due for its next update. The list is approved by the UREA-2 Manager and aims to maintain control and consistency across operational documents.

Uploaded by

Hammad Hussain
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
87 views6 pages

Master List of Urea-2 Document PDF

This document provides a master list of manuals, log sheets, and checklists for the UREA-2 unit at Engro Fertilizer Limited Daharki. It includes 12 manuals, 12 log sheets, and 11 checklists that are relevant to various areas and sections within the UREA-2 unit such as SYNCOM Post, ACES Post, and Finishing Post. It specifies the current issue number and date for each document, as well as the revision number if applicable, and the date by which each document is due for its next update. The list is approved by the UREA-2 Manager and aims to maintain control and consistency across operational documents.

Uploaded by

Hammad Hussain
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

Engro Fertilizer Limited Daharki

Effective by : Jan, 2023 UREA-2


Prepared By: MAAB MASTER LIST OF MANUALS Rev No: 02
Approved By: AsJ Issue No: 02

Department: Plant-1 Production UNIT / SECTION: UREA-2 AREAS : All Posts

Current Issue Current Revion Updated due


S# Doc. No. Document Description
No Date No Date
UNIT MANAGEMENT MANUALS
1 PR‐UMM‐01 Unit Management Manual 8 Jan‐21 0 Jan‐21 Jan‐24
2 PR‐UR2‐SO Standing Order 6 Nov‐20 0 Nov‐20 Nov‐23
UREA-2 MANUALS
1 PR‐UR2‐M1 SYNCOM Manual 10 Sep‐21 0 Sep‐21 Sep‐24
2 PR‐UR2‐M2 ACES Post Manual 11 Sep‐21 0 Sep‐21 Sep‐24
3 PR‐UR2‐M3 Recovery Post Manual 8 Dec‐20 0 Dec‐20 Dec‐23
4 PR‐UR2‐M4 Finishing Post Manual 10 Nov‐20 0 Nov‐20 Nov‐23
5 PR‐UR2‐M5 Utilities Manual 8 Sep‐21 0 Sep‐21 Sep‐24
6 PR‐UR2‐M6 DCS Manual 7 Sep‐21 1 Sep‐21 Sep‐24
7 PR‐UR2‐P2 Emergency Handling Procedures 8 Aug‐22 0 Aug‐22 Aug‐25
8 PR‐UR2‐P4 Special Operating Procedure 7 May‐21 0 May‐21 May‐24
9 PR‐UR2‐P1 Main Unit Procedures 8 Nov‐20 0 Nov‐20 Nov‐23
10 PR‐UR2‐P6 Equipment Handover Manual 3 Aug‐21 0 Aug‐21 Aug‐24
11 PR‐UR2‐P3 Safety Critical Procedures 8 May‐22 0 May‐22 May‐25
12 PR‐UR2‐M7 Evaporation Ponds Manual 2 Sep‐21 0 Sep‐21 Sep‐24
EXTERNALLY CONTROLLED DOCUMENTS
1 S&E/ERM/SP Emergency Response Manual 1 Jun‐21 0 Jun‐21 Sep‐22

Asim Jamil
Manager UREA‐2

DISTRIBUTION:
1 DOCUMENT CONTROLLER
Engro Fertilizer Limited Daharki
Effective by : Jan, 2023 UREA-2
Prepared By: MAAB MASTER LIST OF LOG SHEET Rev No: 02
Approved By: AsJ Issue No: 02
Department: Plant-1 Production UNIT / SECTION: UREA-2 AREAS : All Posts

Revision Next Updation


Log Sheet No Description Current Issue
No Date
CR FRONTEND
001‐Log FRONT END BOARD DCS LOG SHEET 2 0 Nov‐22 Nov‐25
CR BACKEND
002‐Log BACK END BOARD DCS LOG SHEET 2 0 Nov‐22 Nov‐25
SYNCOM POST
101‐Log SYNCOM POST LOG SHEET 4 0 Nov‐22 Nov‐25
102‐Log SYNCOM POST LOG SHEET P‐202 B / C / E / F 2 0 Nov‐22 Nov‐25
ACES POST
201‐Log ACES POST LOG SHEET 2 0 Nov‐22 Nov‐25
NA E‐265's Temporary Dosing LOG SHEET 1 0 Nov‐22 Nov‐25
DEC/REC POST
301‐Log DECOMPOSITION & RECOVERY SECTION LOG SHEET 3 0 Nov‐22 Nov‐25
302‐ Log REPROCESSING LOG SHEET 2 0 Nov‐22 Nov‐25
FINISHING POST
401‐Log FINISHING POST LOG SHEET 2 0 Nov‐22 Nov‐25

Asim Jamil
Manager UREA‐2

DISTRIBUTION:
DOCUMENT CONTROLLER
Engro Fertilizer Limited Daharki
Effective by : JAN: 2023 UREA-2
Prepared By: MAAB Rev No: 02
MASTER LIST OF CHECKLISTS
Approved By: AsJ Issue No: 02
Department: Plant-1 Production AREAS : All Posts

Revision Next Updation Due in


Document No. Issue No.
Rev. No. Date
Frontend/Backend
001‐Chk FRONT END BOARD CHECKLIST 0 1 November‐22 Updation Due : Nov 2025
002‐Chk BACK END BOARD CHECKLIST 0 6 December‐22 Updation Due : Dec‐ 2025
003‐Chk Control Room Carseal Valve Checklist 2 0 January‐22 Updation Due : Jan‐ 2025
004‐Chk Cold Start‐up 3 0 July‐20 Updation Due : July 2024
005‐Chk Hold Start‐up 3 0 July‐20 Updation Due : July 2024
006‐Chk PLANT SHUTDOWN CHECKLIST FRONT END BOARD MAN 3 0 July‐20 Updation Due : July 2024
007‐Chk PLANT SHUTDOWN CHECKLIST BACK END BOARD MAN 3 0 July‐20 Updation Due : July 2024
SYNCOM Post
101‐Chk SYNCOM POST CHECKLIST 4 0 October‐22 Updation Due : Oct 2025
102‐Chk SYNCOM Post Carseal Valve Checklist 3 0 October‐21 Updation Due : Oct. 2024
103‐Chk SYNCOM POST INSTRUMENT / SECURITIES CHECKLIST 2 0 October‐20 Updation Due : Oct 2023
104‐Chk CATHODIC PROTECTION TRANSFORMER CHECKLIST 2 0 October‐20 Updation Due : Oct 2023
SYNCOM POST EMERGENCY DIESEL GENERATOR (EDG‐203)
105‐Chk 2 0 August‐22
STARTUP CHECKLIST Updation Due : August 2025
CO2 COMPRESSOR (C‐2 C / D) STARTUP CHECKLIST STARTUP
106‐Chk 3 0 October‐20
CHECKLIST Updation Due : Oct 2023
107‐Chk CO2 COMPRESSOR (C‐2E) STARTUP CHECKLIST 3 0 January‐21 Updation Due : Jan 2024
AMMONIA FEED PUMPS (P‐201 B / C / D / E / F) STARTUP
108‐Chk 2 0 October‐20
CHECKLIST Updation Due : Oct 2023
CARBAMATE RECYCLE PUMPS JSW (P‐202 B / C / E) STARTUP
109‐Chk 12 0 October‐20
CHECKLIST Updation Due : Oct 2023
CARBAMATE RECYCLE PUMP SUNDYNE (P‐202F) STARTUP
110‐Chk 2 0 October‐20
CHECKLIST Updation Due : Oct 2023
CARBAMATE RECYCLE PUMP EBARA (P‐202G) STARTUP
111‐Chk 2 0 October‐20
CHECKLIST Updation Due : Oct 2023
112‐Chk SYNCOM POST SHUTDOWN CHECKLIST 2 0 October‐20 Updation Due : Oct 2023

113‐Chk SYNCOM POST NON SAFETY CRITICAL SECURITIES CHECKLIST 2 0 October‐20


Updation Due : Oct 2023

113‐Chk SYNCOM POST NON SAFETY CRITICAL SECURITIES CHECKLIST 2 0 October‐20


Updation Due : Oct 2023
ACES Post
201‐Chk ACES POST CHECKLIST 1 0 October‐20 Updation Due : Oct 2023
202‐Chk ACES VESSELS LEAK DETECTION CHECKLIST 2 0 October‐20 Updation Due : Oct 2023
203‐Chk LUBE OIL / CHEMICAL INVENTORY CHECK LIST ACES POST 2 0 July‐21 Updation Due : July 2024
204‐Chk TRANSFORMER CHECKLIST 2 0 April‐21 Updation Due : Apr 2024
205‐Chk ACES POST CARSEAL VALVE CHECKLIST 3 0 October‐21 Updation Due : Oct 2024
206‐Chk ACES POST INSTRUMENT SECURITIES CHECKLIST 1 0 October‐20 Updation Due : Oct 2023
207‐Chk FIRE WATER SYSTEM LEAK TEST CHECKLIST 1 0 October‐20 Updation Due : Oct 2023
208‐Chk SECTIONALIZING VALVES OPERATION CHECKLIST 1 0 October‐20 Updation Due : Oct 2023
209‐Chk ACES POST PRE‐STARTUP CHECKLIST 1 0 October‐20 Updation Due : Oct 2023
210‐Chk ACES POST SHUTDOWN CHECKLIST 2 0 October‐20 Updation Due : Oct 2023
211‐Chk REACTOR (R‐1101) DRAINING CHECKLIST 1 0 October‐20 Updation Due : Oct 2023
212 Chk P 262`s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
213 Chk P‐206`s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
214 Chk P‐266`s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
215 Chk P‐266C Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
216 Chk P‐203A Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
217 Chk P‐204 Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
218 Chk P‐298s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
219 Chk P‐205`s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
220 Chk P‐263ABC Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
DEC/REC Post
301‐Chk DECOMPOSITION & RECOVERY POST CHECKLIST 2 0 October‐20 Updated on : Oct 2023
DECOMPOSITION & RECOVERY POST INSTRUMENT / Updated on : Oct 2023
302‐Chk 1 0 October‐20
SECURITIES CHECKLIST
DECOMPOSITION AND RECOVERY POST CARSEAL VALVE Updation Due : October. 2024
303‐Chk 3 1 October‐21
CHECKLIST
Updation Due : Oct 2023
304‐Chk PRE‐STARTUP CHECKLIST DECOMPOSITION & RECOVERY POST 3 0 October‐20
PLANT SHUTDOWN CHECKLIST DECOMPOSITION & RECOVERY Updation Due : Oct 2023
305‐Chk 3 0 October‐20
POST
306 Chk P‐244s Startup checklist 1 0 October‐20 Updation Due : Oct 2023
307 Chk P‐250s Startupr checklist 1 0 October‐20 Updation Due : Oct 2023
308 Chk P‐253s Startup checklist 1 0 October‐20 Updation Due : Oct 2023

Page No. 3 of 6
Engro Fertilizer Limited Daharki
Effective by : JAN: 2023 UREA-2
Prepared By: MAAB Rev No: 02
MASTER LIST OF CHECKLISTS
Approved By: AsJ Issue No: 02
Department: Plant-1 Production AREAS : All Posts

Revision Next Updation Due in


Document No. Issue No.
Rev. No. Date
Frontend/Backend
309 Chk P‐261s Startup checklist 1 0 February‐21 Updation Due : Feb 2023
310 Chk P‐264s Starrtup checklist 1 0 July‐20 Updation Due : July 2023
311Chk P‐274s Starrtup checklist 1 0 July‐20 Updation Due : July 2023
312 Chk P‐265s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
313 Chk P‐267s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
314 Chk P‐267A Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
315 Chk P‐245s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
316 Chk P‐274s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
317 Chk P‐264s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
318 Chk P‐280s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
319 Chk P‐221s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
320 Chk P‐221C Shart up Checklist 1 0 February‐21 Updation Due : Feb‐2024
321 Chk P‐223 Shart up Checklist 1 0 February‐21 Updation Due : Feb‐2024
322 Chk P‐265s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
323 Chk P‐247s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
324 Chk P‐298 Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
325 Chk P‐258 Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
326 Chk P‐271 Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
327 Chk B‐221 Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
328 Chk P‐280S Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
FINISHING POST
401‐Chk FINISHING POST CHECKLIST 5 0 September‐21 Updation Due : Sept‐2024
402‐Chk INSTRUMENT / SECURITIES CHECKLIST FINISHING SECTION 2 0 October‐20 UpdationDue : Oct 2023
403‐Chk Finishing Post Carseal Valve Checklist 1 0 October‐21 Updation Due : Oct 2024
404‐Chk PRE‐STARTUP CHECKLIST FINISHING SECTION 3 0 October‐20 Updation Due : Oct 2023
FINISHING SECTION EVAPORATOR (E‐245 A/B/C/D) LINE UP Updation Due : Oct 2023
405‐Chk 3 0 October‐20
CHECKLIST
406‐Chk SHUT DOWN CHECKLIST OF FINISHING POST 3 0 October‐20 Updation Due : Oct 2023
407‐Chk P‐254 's STARTUP CHECKLIST 1 0 July‐20 Updation Due : July 2023
408 Chk P‐241s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
409 Chk P‐255s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
410 Chk P‐270 Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
411 Chk P‐342s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
412 Chk P‐299s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
413 Chk VP‐241 Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
414 Chk B‐224s Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
415 Chk CO‐241 Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
416 Chk SC‐241 Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
417 Chk IDF‐245AB Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
418 Chk P‐242AB Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024
419 Chk P‐243ABCD Startup Checklist 1 0 February‐21 Updation Due : Feb‐2024

Asim Jamil
Manager UREA‐2
DISTRIBUTION:
DOCUMENT CONTROLLER

Page No. 4 of 6
Engro Fertilizer Limited Daharki
Effective by : Jan -2023
UREA-2
Prepared By: MAAB MASTER LIST OF SAFETY EQUIPMENT Rev No: 02
Approved By: AsJ CHECKLISTS Issue No: 02
Department: Plant-1 Production AREAS : All Posts

Revision Next Updation Due in


Document No. Issue No.
Rev. No. Date
CONTROL ROOM
001‐Chk CONTROL ROOM SAFETY EQUIPMENT CHECKLIST 4 1 August‐22 Updation Due : Aug ‐2025
SYNCOM Post
101‐Chk SYN COM POST SAFETY EQUIPMENT CHECKLIST 5 0 December‐21 Updation Due : Dec‐2024
ACES Post
201‐Chk ACES POST SAFETY EQUIPMENT CHECKLIST 3 0 April‐21 Updation Due : Apr 2024
DEC/REC Post
301‐Chk DEC & REC POST SAFETY EQUIPMENT CHECKLIST 4 0 January‐22 Updation Due : Jan 2025
FINISHING POST
401‐Chk FINISHING POST SAFETY EQUIPMENT CHECKLIST 3 0 October‐22 Updation Due : Oct ‐2025
PONDS
607‐Chk EVAPORATION PONDS AREA SAFETY EQUIPMENT CHECKLIST 1 0 April‐21 Updation Due : Apr 2024

608‐Chk EVAPORATION PONDS AREA SAFETY EQUIPMENT CHECKLIST 1 0 April‐21 Updation Due : Apr 2024

Asim Jamil
Manager UREA‐2

DISTRIBUTION:
DOCUMENT CONTROLLER

Page No. 5 of 6
Engro Fertilizer Limited Daharki
UREA-2
Effective by : Jan -2023
Prepared By: MAAB MASTER LIST OF NON SAFETY CRITICAL Rev No: 02
Approved By: AsJ CHECKLIST Issue No: 02
AREAS : All Posts

Revision Next Updation Due in


Document No. Issue No.
Rev. No. Date
Frontend/Backend
Document No : 130‐Chk UREA‐2 NON SAFETY CRITICAL LIST 2 0 July‐17 July‐20
Document No : 130‐Chk SYNCOM POST NON SAFETY CRITICAL SECURITIES CHECKLIST 2 0 July‐17 July‐20
Document No : 330‐Chk DEC & REC POST NON SAFETY CRITICAL SECURITIES CHECKLIST 2 0 July‐17 July‐20
Document No : 430‐Chk FINISHING POSTNON SAFETY CRITICAL SECURITIES CHECKLIST 2 0 July‐17 July‐20

Asim Jamil
Manager UREA‐2
DISTRIBUTION: