Individual Assignment-15%
Individual Assignment-15%
1. A 7-cy wheel loader will be used to load a crusher from a quarry stockpile of blasted
rock (average breakage) 180 ft away. The rock has a loose unit weight of 2,700 lb/cy.
Estimate the loader production in tons based on a 50-min-hour efficiency factor.
2. Evaluate cost and production using a 3-cy hoe to load wet gravel into 14-cy-size
trucks. Assume a bucket fill factor of 105% and that the hoe bucket swing cycle time
is 24 sec. Use the information in Fig. below, a truck net empty weight of 36,860 lb,
and a rated payload of40,000 lb. Dump time will be 1.3 min. The haul distance is 2.5
miles from the pit to the plant up a 3% grade. The rolling resistance of the haul road
will be maintained at 3%. The hoe and operator cost $97 per hour, and trucks cost $49
per hour. What is the most cost-effective mix of bucket loads to use in loading the
trucks and number of trucks to place on this job?
3. A grader will be used to maintain 2.5 miles of haul road. It is estimated that this work
will require three passes in first gear, leveling the road requires two passes in second
Page 1 of 2
Construction Equipment CEng5193
gear, and final shaping of the road requires two passes in fourth gear. Use an efficiency
factor of 60%. Grader speeds are given in the next chart. What is the time requirement
for this task?
Page 2 of 2