Line Sizing
Line Sizing
Fluid Velocity
• To predict noise, erosion, sonic velocity
Mechanical Consideration
• Rack Piping Minimum Size
• 1 inch (Some refines set 1.5” or 2” minimum)
• Avoid using 1-1/4”, 2-1/2”, 3”, 3-1/2” and 5” pipes
• To minimize purchasing, detailing and inventory
• For 2” and smaller pipe size, schedule 80 minimum is recommended.
• The pipe wall thickness required for a particular piping service is primarily a function of internal operating
pressure and temperature.
• The standards under which pipe is manufactured permit a variation in wall thickness below nominal wall
thickness.
• It is usually desirable to include a minimum corrosion/mechanical strength allowance of 0.050 inches for carbon
steel piping.
• The pressure design thickness required for a particular application may be calculated by the following equation:
Pi Do
t=
2(SE + Pi Y)
where: E = Longitudinal Weld Joint Factor
t = Pressure Design Thickness (in) = 1.0 for seamless
Pi= Internal Design Pressure (psig) = 0.85 for ERW
Do = Pipe OD (in) Y = Temperature Factor (0.4 for ferrous materials at
S = Allowable Stress in accordance with ANSI B31.3 900°F or below t < D/6)
(psi)
CHE Design
Pipe Roughness
ρϑD
Re =
μ
Where: Notes:
ρ= fluid density Re < 2000 Laminar Flow
ϑ=Flow velocity 2000 < Re < 4000 Transition Flow
D = Pipe diameter Re > 4000 Turbulent Flow
μ= Fluid Viscosity Re > 10000 Fully Turbulent
CHE Design
Where:
Churchill Equation:
General Rule:
CHE Design
Elevation ΔP:
CHE Design
Where: hw
Therefore, = Pressure Drop (inches of water)
Using Equivalent Length: Exact equivalent length is equal to the length between flange or wielding ends
CHE Design
Using Equivalent Length: Equivalent length are in terms of smaller diameter. Values applicable to DN 600
• For simplification, the pressure drop induced by fittings can be easily assumed by introducing a design factor (e.g. 3x of the
pipe length) rather than by calculating it one-by-one which is a more tedious method.
• Also, the introduction of a design factor can be done for revamp considerations.
• For manual valves, usually pressure drop is assigned as per project design criteria (e.g. check valve ΔP = 5.0 kPa).
1. For SS and titanium, the maximum velocity is limited by system design (available pressure drop/reaction forces)
2. Minimum velocity shall be normally be 0.8 m/s
3. Minimum velocity for CuNi is 1.0 m/s
When the service is intermittent, the velocity can be increased to 10 m/s. For CuNi the the maximum velocity is 6-10 m/s depending
on duration and frequency of operation
CHE Design
• Liquid with corrosion inhibitors velocity • Reciprocal Pump Suction and Discharge Line
With corrosion inhibited fluids in carbon steel piping, • The suction piping shall be sized based on NPSH
the velocity shall be limited by a wall shear stress of requirements
40 N/m2 to maintain the corrosion inhibiting film at
the pipe wall, with the corresponding maximum
velocity:
Notes:
1. The values in metric units are based on NORSOK
• Velocity Criteria for Liquid Transport Through standards
Control Valve (API RP 14E Standard) 2. The values in SI units are based on API RP 14E
Maximum flow velocity should not exceed 15 ft/s (4.6
m/s) at maximum flow rates to minimize flashing • Pump - Net Positive Suction Head (NPSH)
ahead of the control valve. • It is the absolute inlet total head (in m or ft liquid) above
Minimum flow velocity should not be practically less the head equivalent to the vapor pressure.
than 3 ft/s (0.9 m/s) to minimize deposition of sand • The requirement to achieve sufficient inlet head such
and other solids. that the pressure at suction is always above the vapor
pressure of the fluid to avoid cavitation.
• Centrifugal Pump Suction and Discharge Lines • Pump - Net Positive Suction Head Available (NPSHA)
• The suction piping shall be sized based on NPSH • It is the absolute pressure (in m or ft liquid) at pumping
requirements. Maximum velocity from the previous temperature available at the pump suction flange above
table and the following maximum pressure drops pressure.
shall in general be used:
MAXIMUM NPSHA = ±hs – hL+ hA- hv,
LIQUID TYPE PRESSURE DROP
(bar/100m) Where:
Subcooled Liquids 0.25 hs = Static suction head (+) or static suction lift (-), ft
Boiling Liquids 0.05 hL = Suction line losses (friction, entrance and fittings),
ft
The fluid temperature shall be at least 15°C below the fluid hA = Absolute pressure at the liquid's free surface, in ft
boiling point temperature to allow sizing based on the of liquid pumped
criterion for subcooled liquids. hv = Vapor pressure of liquid at pumping temperature,
converted to ft of liquid
The maximum velocity in the discharge piping is given in
the previous table. As a guideline, a pressure drop due to
friction up to 0.9 bar/100m may be assumed.
CHE Design
• Pump - Net Positive Suction Head Required (NPSHR) • Vertical Gravity Lines
• NPSH that results to 3% loss of head determined • When the Froude number is larger than 0.30, the entrained
by vendor by performance testing with water. vapor will be swept down with the liquid.
• It usually determine through vendor's pump curve. • For a Froude number between 0.30 and 1.2, frictional
• Recommended NPSH Margin resistance will compete with the gravitational forces and
• In general, NPSHA should always be greater than the flow will not be stable.
NPSHR (NPSHA > NPSHR) to avoid cavitation. • Froude number exceeding 1.2 will not manifest a stable
• A good rule of thumb is to require a 10% margin or flow.
5 ft of difference between NPSHA and NPSHR, • As general practice, Froude number should be keep below
whichever is greater. 0.30.
• Centrifugal Pump NPSH Margins • Exception to this is the drain line from a condenser to a
reflux drum with some non-condensable gas.
APPLICATION NPSH MARGIN (%)
Water (Cold) 10-35 (1)(2) B. For Gas Lines:
Hydrocarbon 10 • Maximum Velocity
Boiler Feed (Small) (3)
50 • In lines where pressure drop does not have a cost penalty,
High Energy (4)
100 - 200 gas velocity shall not exceed limits which may create noise
Notes: or vibration problems.
1. Depends on size, higher margin for larger pumps. • For trouble-free operation, the maximum velocity should
2. Min. 3 ft be maintained below 1/2 of the critical velocity or 60 m/s,
3. Up to 2500 hp at 3600 rpm which ever is lower.
4. Velocity> 100ft/s • Critical velocity is given by:
• Plug Flow
• This flow regime has liquid plugs that are separated by
elongated bubbles.
• Annular-Dispersed Flow
• At even larger gas flow rates, the liquid forms a
continuous annular film around the perimeter of the pipe,
• Annular Flow similar to that in vertical flow but the liquid is thicker at
This flow regime is particularly stable and is the desired the bottom than the top.
flow pattern for two-phase pipe flows. The liquid is expelled • The flow maps are only applicable to very long pipes with
from the center of the tubes and flows as a thick film on equilibrium. two-phase flow
the wall while the gas flows as a continuous phase up the
center of the tube. • Two phase Flow Pattern Map (Horizontal)
Baker Chart
• Two-Phase Flow Pattern (Horizontal Pipes):
• Dispersed Bubble
Flow
• The gas bubbles
are dispersed in
the liquid with a
high
concentration
of bubbles in
the half of the
tube due to their buoyancy. This flow regime typically
occurs only at high mass flow rates. • Two phase Flow Pattern Map (Vertical)
• Stratified Flow
• At low liquid and gas velocities, complete separation of
the two phases occurs
• Stratified-Wavy Flow
• Increasing the gas velocity in a stratified flow, waves are
formed on the interface and travel in the direction of flow.
• Slug Flow
• At higher gas velocities, the diameters of elongated
bubbles become similar in size to the channel height. The
liquid slugs separating such elongated bubbles can also be
described as large amplitude waves.
CHE Design
• Ground Equipment
• Wind Rose
• A graphic tool used to give a view of
Steps to Consider:
how wind speed and direction are
typically distributed at a particular • Define the system.
location. • Divide the system into segments at points where the
flowrate and fluid properties change.
• Prevailing Wind • Underground piping shall be assumed 1.0m below the
• The trends in speed and ground level, unless otherwise specified.
direction of wind over a • In a plot plan, measure the pipe length from point to point
particular point on the (as divided in the previous step), considering also the
earth's surface. changes in elevation.
• Create the model in an organized and systematic way.
• Input the process data and equipment data needed.
• Assume initial pipe size.
• Assign fixed pressure points, free pressure points and
calculated pressure points.
CHE Design
• Calculate.
• Check the result versus the criteria given in the project.
• Adjust the pipe size. (Do not forget to change the schedule
number when service class table is available.)
• Recalculate until all the criteria are satisfied.