RM Lecture 7
RM Lecture 7
Value-At-Risk
Lecture 7
Prof Youwei Li
1
Introduction to VAR
l Measures such a delta, gamma and vega represent
different aspects of the risk in a portfolio consisting
of options and other financial assets.
l Financial institutions usually calculate each of
these measures each day for every market variable
to which it is exposed.
l These risk measures provide valuable information
for the financial institution’s traders, but they are of
limited use to senior management.
2
Introduction
l Value at risk (VaR) is an attempt to provide a single
number summarizing the total risk in a portfolio of
financial assets for senior management.
l It has become widely used by corporate treasurers
and fund managers as well as by financial
institutions.
l Bank regulators also use VaR in determining the
capital a bank is required to keep for the risks it is
bearing.
3
Introduction
l VaR was devised at JP Morgan.
l In the aftermath of the 1987 stock market crash,
the CEO demanded that the market risk team
produced a simple report of the potential losses for
the next trading day – on a single page and
delivered no later than 45 minutes after market
close.
l Nowadays, it is a major activity for the bank to help
clients to calculate VaR of their financial asset
portoflios .
4
The VaR Measure
1. Introduction
Definition
VaR is the largest likely loss from market risk (expressed in currency
units) that an asset or portfolio will suffer over a time interval and with
a degree of certainty selected by the user (Choudhry (2006), p.32)
Or
VaR is a measure of the amount that could be lost from a position, portfolio
etc. VaR is generally understood to mean the maximum loss an investment
could incur at a given confidence level over a specified time horizon. (Wilmott
(2006)
5
The VaR Measure
1. Introduction
6
The VaR Measure
1. Introduction
7
The VaR Measure
2. Calculation
8
The VaR Measure (cont.)
2. Calculation
• The Time Horizon: VaR has two parameters: the time horizon in days, and the confidence interval,
X. In practice, analysts almost invariably set N = 1 in the first instance. This is because there is not
enough data to estimate directly the behaviour of market variables over time longer than one day.
The usual assumption is:
l and so on
Historical Simulation continued
l We are at end of day m, we want to simulate
what might happen on the m+2 day
Date Share
0 0.05 4000 1.51
: : : : :
: : : : : :
: : : : : :
: : : : : :
499 : : : :
500 : : : :
Example - Scenario 500/ 1000th
day
Date Share
0 0.05 4000 1.51
: : : : :
s X +Y = s + s + 2rs X s Y
2
X
2
Y
41
Potential Problems of VaR
l The portfolios in Figures 18.1 and 18.2 have the same VaR, but the
portfolio in Figure 18.2 is much riskier because potential losses are
much larger.
42
Potential Problems of VaR
l For example, with X=99 and N=10, expected shortfall is the average
amount the company loses over a 10-day period when the loss is in
the 1% tail of the distribution.
43
Potential Problems of VaR
l For example, with X=99 and N=10, expected shortfall is the average
amount the company loses is greater than the loss in the 1% tail of
the distribution.
44
Partly Moving to Expected
Shortfall
l For banks’ trading books (not the other
parts of their business), the regulators are
now requiring banks to move to use
expected shortfall by end of 2019.
l Basel Committee of Bank Supervision
consultative paper (2012): Fundamental
Review of Trading Book.
Next Week
l Stress testing
l Banking Regulation