PLC-part B

The document describes a pneumatic system with two cylinders (A and B) and limit switches to detect the piston movements. It asks to draw a ladder diagram to produce the sequence: A+, B+, A-, B-. The ladder diagram would control the single solenoid valves for cylinders A and B to move the pistons in and out based on the limit switch signals to achieve the requested sequence.

Uploaded by

Hey Whatever
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
43 views

PLC-part B

The document describes a pneumatic system with two cylinders (A and B) and limit switches to detect the piston movements. It asks to draw a ladder diagram to produce the sequence: A+, B+, A-, B-. The ladder diagram would control the single solenoid valves for cylinders A and B to move the pistons in and out based on the limit switch signals to achieve the requested sequence.

Uploaded by

Hey Whatever
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 40

9/19/2022 1

Example
Draw a ladder diagram for a penumatic system with single solenoid
controlled vales and involving two cylinders A and B, with limit switches
a-, a+, b-,b+ detecting the limits of the piston rod movements, so that
the sequence A+,B+,A-,B- is obtained. Include the Start Switch.

9/19/2022 2
Solution

9/19/2022 3
Solution

9/19/2022 4
Solution

9/19/2022 5
Solution

9/19/2022 6
Solution

9/19/2022 7
Solution

9/19/2022 8
Solution

9/19/2022 9
Solution

9/19/2022 10
Solution

9/19/2022 11
Multiple Outputs

Siemens
Mitsubishi

9/19/2022 12
Internal Relay

9/19/2022 13
Internal Relay

Resetting Latching

9/19/2022 Starting of Multiple Outputs 14


Example- Sequence as Cascade
For the cylinder valves and limit switches shown in the Figure, devise a
program to give the sequence A+,B+,B-,A-

9/19/2022 15
Example- Sequence as Cascade
1

5
9/19/2022 16
Example- Sequence as Cascade
1

5
9/19/2022 17
Example- Sequence as Cascade
1

5
9/19/2022 18
Example- Sequence as Cascade
1

5
9/19/2022 19
Example- Sequence as Cascade
1

5
9/19/2022 20
Example- Sequence as Cascade
1

5
9/19/2022 21
Example- Sequence as Cascade
1

5
9/19/2022 22
Example- Sequence as Cascade
1

5
9/19/2022 23
Timer-Ladder diagram

9/19/2022 24
Using Timer for Motor Sequencing
1

2 Time 5 Seconds

3 Time 10 Seconds

5
Sequenced Outputs
6

9/19/2022 25
Motor Sequencing
Counter

9/19/2022 26
Counter

9/19/2022 27
Example
Control of a machine which is required to direct six tins along one path for packaging in a
box then 12 tins along another path for packaging in another box. A deflector plate might
be controlled by a sensor which gives an output everytime a tin passes it and activates a
cylinder to move the plate. Thus the number of passes from the sensor has to counted
and used to control the deflector. (Use-Double acting cylinder controlled by 5/2 DCV
single side solenoid actuated and spring returned)

Cylinder-Deflector
Proximity sensor

12-tin box

9/19/2022 6-tin box 28


Solution

9/19/2022 29
Solution Start

9/19/2022 30
Solution Start

Counter 1

Proximity Sensor-Input

Solenoid

9/19/2022 31
Solution Start

Counter 1
Counts
6 boxes
Proximity Sensor-Input

Solenoid

9/19/2022 32
Solution Start

Output ON untill reset

Solenoid

Counter 2
Counts
12 boxes
Proximity Sensor-Input

9/19/2022 33
Solution Start

Reset Timer 1 Output ON untill reset

Proximity Sensor-Input

Solenoid

Counter 2
Reset Timer 2
Counts
12 boxes
Proximity Sensor-Input

9/19/2022 34
1

Example
2

Design a ladder program which will 3


enable a three cylinder, double
solenoid controlled arragement to
give the sequence
A+,A-, A+,A- A+,A-,B+, C+,B-,C- 4

9/19/2022 35
1

Solution 2
A+,A-, A+,A- A+,A-,B+, C+,B-,C-
3

9/19/2022 36
1

Solution 2
A+,A-, A+,A- A+,A-,B+, C+,B-,C-
3 Counts
when a- is
hit
(3 times)

9/19/2022 37
1

Solution 2
A+,A-, A+,A- A+,A-,B+, C+,B-,C-
3 Counts
when a- is
hit
(3 times)

9/19/2022 38
1

Solution 2
A+,A-, A+,A- A+,A-,B+, C+,B-,C-
3 Counts
when a- is
hit
(3 times)

9/19/2022 39
Thanks

9/19/2022 40