CCEC Lec06.1 Excavation
CCEC Lec06.1 Excavation
Construction
Excavation
Excavation
◼ Type of soil
◼ Required slope
◼ Bracing or Sheet piling
◼ Groundwater / pumping required
◼ Excavation
◼ be left on site
◼ or must be removed
◼ how far must be hauled
◼ Top soil be stock piled for future use
2
Calculating Excavation
◼ Determined from the site plan
◼ Scaled in feet (no inches)
3
Example-1 Required accuracy
Given the following dimensions, determine
the quantity to be excavated.
Length = 52.83 ft
Width = 75.75 ft
Depth = 6.33 ft
Volume = 52.83 x 75.75 x 6.33
=25,331.85 cf
= 25,332/27
= 938 cy
4
Swell and Shrinkage
◼ Excavation measured in cubic yards
◼ Must separate bank, loose, or compacted
◼ Bank: soils in original state (bcy)
◼ Loose: soils after excavation and before
compaction (lcy)
◼ Compacted: Soils after placement and
compaction (ccy)
5
Swell and Shrinkage
◼ Swell: increase in volume between bank
and loose condition.
◼ Expressed as percentage gained above the
original volume.
◼ Shrinkage: decrease in volume between
bank and compacted condition
◼ Expressed as a percentage of the bank
volume
6
Swell and Shrinkage
Percentage of Swell & Shrinkage
Material Swell Shrinkage
Sand and Gravel 10 to 18% 85 to 100%
Loam (sand, silt, clay) 15 to 25% 90 to 100%
Dense Clay 20 to 35% 90 to 100%
Solid Rock 40 to 70% 130%
Solid rock when compacted is less dense than its bank condition.
7
Formulas
CLAMSHELL
Earthwork- New grades
◼ Contour lines connect points of equal
elevation
◼ Existing elevation are shown with
dashed contour lines while proposed
new elevations are denoted with solid
lines.
Cut and Fill
◼ Cut: removal of soil to meet required
grade
Along line 2,
Between lines C & D, there is a point where there is no change in
elevation. This point is found first.
Total change in elevation (C – D) = 0.3’ + 0.7’ = 1.0’
Change in elevation per foot of run (C – D) = 1.0/50 = 0.02 per foot of
run Thus distance from C2 = 0.3/0.02 = 15’ (Point of no change in
elevation)
Along line 3
Total change in elevation (C – D) = 0.4 + 0.3 = 0.7
Change in elevation per foot run (C – D) = 0.7/50 = 0.014 per foot of run
Thus, distance from C3 = 0.4/0.014 = 29’ (Point of no change in
elevation)
Having this information , Grid 10 is divided into two distinct grids: One
for cut and one for fill
For further calculation, you can divide the area into rectangles/triangles
Cut and Fill in the Same Grid (Grid 10)
Example - 6 Cut and Fill in the same grid
These cuts and fills are entered into the cut and fill columns of the
worksheet (Fig. 9.16)
Cross-Section Method
◼ Always keep cuts and fills separate
◼ Need to take into account shrinkage
◼ Cuts are in bank cubic yards
◼ Fills are in compacted cubic yards
In shown Fig, the top of the rough grade is 0.50 foot below the top of pavement.