WEP For Gypsum Board False Ceiling
WEP For Gypsum Board False Ceiling
1
THE PROJECT FOR THE IMPROVEMENT OF
GOVERNANCE AND MANAGEMENT
RESEARCH AND TRAINING FACILITIES
PREPARED BY:
2
Table of Contents
1.0 PURPOSE .................................................................................................................................................. 3
2.0 SCOPE ...................................................................................................................................................... 3
3.0 PRODUCTS ............................................................................................................................................... 3
4.0 EQUIPMENT: ............................................................................................................................................ 3
5.0 SITE PREPARATION WORKS ..................................................................................................................... 3
5.1 SITE SURVEY ............................................................................................................................................... 3
5.2 SETTING OUT ............................................................................................................................................. 3
6.0 SUSPENDED CEILING INSTALLATION PROCEDURE .................................................................................. 4
6.1 Fixing of Suspension Grid .......................................................................................................................... 4
6.2 Fixing of Gypsum Board: ............................................................................................................................ 5
7.0 FIELD QUALITY CONTROL ........................................................................................................................ 5
8.0 SAFE WORK PLAN .................................................................................................................................... 6
3
1.0 PURPOSE
To ensure that the Gypsum Board Suspended Ceiling and related activities are executed safely and in
accordance with the contract requirements and that all quality assurance / control activities are
conducted in a systematic manner. To ensure that works are inspected, conformance is verified and
documented.
2.0 SCOPE
This procedure is applicable to the following works associated with the project for the installation of
the suspended ceiling as per approved drawings.
3.0 PRODUCTS
Elephant Brand: Siam Gypsum Industry Co. Ltd.
4.0 EQUIPMENT:
• Drills
• Knives: Knives used must be of good quality and for the required job, hand gloves to be used
• Screw drivers
• Sand paper
• Scrapers
• Level tools (Laser level)
The capacity / size of the above equipment shall be judged in accordance with site conditions,
requirements, and availability at the time of execution.
All the above tools or equipment will be operated by skilled labors, and will be checked and
maintained regularly by supervisor.
On receipt of the shop drawings approved by the Consultants, the site will be surveyed and any
discrepancy found will be notified to the Main Contractor for clarification.
Setting out & marking will be done as per approved shop drawing. The surveyor will carry out the
layout markings as per the approved drawings in concurrence with the schedule of works, area
availability and as per the Site Engineer’s instructions. Ceiling layout shall be marked based on the
datum line provided by the Main Contractor. Based on the datum lines, chalk lines will be marked for
4
fixing the wall angle according to the ceiling level. Any discrepancies to the drawing and the setting
out found will be brought to the notice of the main contractor. Once the wall angles are fixed the
framing of the ceiling is done and the same is submitted for inspection of the engineer for approval.
Before starting of the first fix services of false ceiling clearance will be obtained from the contractor,
consultant and MEP sub contractor as the first fix services of M.E.P above the false ceiling to be
completed and approved.
An area for mock-up will be prepared for inspection and approval before proceeding with the overall
installation.
QA/QC procedures shall be followed, WIR shall be raised, inspections shall be carried out at different
work tiers and clearances shall be
obtained at progressive levels as
mentioned therein.
• Suspension system of the gypsum board ceiling should not be in direct contact with M.E.P.
5
services especially A/C ducts.
Before starting of the Gypsum Board fixing services of false ceiling clearance will be obtained by the
contractor, consultant and M.E.P sub-contractor, services of M.E.P above the false ceiling to be
completed and approved as well inspection of the suspension frame of false ceilings should be carried
out by the consultant and should be rectified to comments if given by them.
• Two layers of Gypsum plaster board sheet as approved should be fixed to furring channels
with self-taping screws at every 100mm c/c and G.I angles @ the perimeter of walls.
• Extra furring channels should be provided at the joints of Gypsum plaster boards to its shorter
lengths and cut piece joints if required.
• Extra supports should be provided around access panel.
6
8.0 SAFE WORK PLAN
• The forklift will be used for lifting of material, safe for its use.
• The operator has a valid license to operate.
• Slings have been identified and are correctly certified.
• A toolbox talk is conducted prior to the start of the work, in accordance with procedure.
• One member of the erection crew will be assigned as banks man and shall be suitably trained
by supplier for the task.
• Only the banks man will give instructions to the operator.
• All required materials will be brought to the site location.
• Forklift operations will be under the control of the banks man who will have clear visual
contact at all times with the equipment.
• Ensure all Personal Protection Equipment like Steel Toe Safety Shoes. Safety helmets.
• Goggle, Safety reflective jacket, Safety Belt is worn prior to start of work.
• The work Involves working at a height of 1.8m from Floor Level all the time should wear full
body safety harness.
• All safety precautions to be taken when working at heights. Full body Safety harness to be
strapped at all times.
• Erection of scaffolding shall be by the certified scaffolders.
• All electrical cable shall be color coded by the competent person with monthly color coding.
• Lighting shall be provided in the night shift activities.