WEP For Gypsum Board False Ceiling

This document provides a work execution plan for installing a gypsum board false ceiling at the Bangladesh Institute of Governance and Management. It outlines the project scope, required materials and equipment, site preparation procedures, and step-by-step process for installing the suspension grid and attaching the gypsum boards. Quality control measures are also described to ensure work is performed safely and meets contract and design specifications.

Uploaded by

palash
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
219 views6 pages

WEP For Gypsum Board False Ceiling

This document provides a work execution plan for installing a gypsum board false ceiling at the Bangladesh Institute of Governance and Management. It outlines the project scope, required materials and equipment, site preparation procedures, and step-by-step process for installing the suspension grid and attaching the gypsum boards. Quality control measures are also described to ensure work is performed safely and meets contract and design specifications.

Uploaded by

palash
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

THE PROJECT FOR THE IMPROVEMENT

OF GOVERNANCE AND MANAGEMENT


RESEARCH AND TRAINING FACILITIES

1
THE PROJECT FOR THE IMPROVEMENT OF
GOVERNANCE AND MANAGEMENT
RESEARCH AND TRAINING FACILITIES

Work Execution Plan For

Gypsum Board False Ceiling

Document No. TCEL/BIGM/WEP/ Gypsum Board False Ceiling /REV.00

PREPARED BY:

The Civil Engineers LTD

MAIN CONTRACTOR: TAISEI CORPORATION

CLIENT: BANGLADESH INSTITUTE OF GOVERNANCE AND MANAGEMENT

WEP for Gypsum board false ceiling REV.00 20.02.2023


THE PROJECT FOR THE IMPROVEMENT
OF GOVERNANCE AND MANAGEMENT
RESEARCH AND TRAINING FACILITIES

2
Table of Contents
1.0 PURPOSE .................................................................................................................................................. 3
2.0 SCOPE ...................................................................................................................................................... 3
3.0 PRODUCTS ............................................................................................................................................... 3
4.0 EQUIPMENT: ............................................................................................................................................ 3
5.0 SITE PREPARATION WORKS ..................................................................................................................... 3
5.1 SITE SURVEY ............................................................................................................................................... 3
5.2 SETTING OUT ............................................................................................................................................. 3
6.0 SUSPENDED CEILING INSTALLATION PROCEDURE .................................................................................. 4
6.1 Fixing of Suspension Grid .......................................................................................................................... 4
6.2 Fixing of Gypsum Board: ............................................................................................................................ 5
7.0 FIELD QUALITY CONTROL ........................................................................................................................ 5
8.0 SAFE WORK PLAN .................................................................................................................................... 6

WEP for Gypsum board false ceiling REV.00 20.02.2023


THE PROJECT FOR THE IMPROVEMENT
OF GOVERNANCE AND MANAGEMENT
RESEARCH AND TRAINING FACILITIES

3
1.0 PURPOSE
To ensure that the Gypsum Board Suspended Ceiling and related activities are executed safely and in
accordance with the contract requirements and that all quality assurance / control activities are
conducted in a systematic manner. To ensure that works are inspected, conformance is verified and
documented.

2.0 SCOPE
This procedure is applicable to the following works associated with the project for the installation of
the suspended ceiling as per approved drawings.

3.0 PRODUCTS
Elephant Brand: Siam Gypsum Industry Co. Ltd.

Armstrong: Armstrong World Industries (AWI)

4.0 EQUIPMENT:
• Drills
• Knives: Knives used must be of good quality and for the required job, hand gloves to be used
• Screw drivers
• Sand paper
• Scrapers
• Level tools (Laser level)

The capacity / size of the above equipment shall be judged in accordance with site conditions,
requirements, and availability at the time of execution.

All the above tools or equipment will be operated by skilled labors, and will be checked and
maintained regularly by supervisor.

5.0 SITE PREPARATION WORKS

5.1 SITE SURVEY

On receipt of the shop drawings approved by the Consultants, the site will be surveyed and any
discrepancy found will be notified to the Main Contractor for clarification.

5.2 SETTING OUT

Setting out & marking will be done as per approved shop drawing. The surveyor will carry out the
layout markings as per the approved drawings in concurrence with the schedule of works, area
availability and as per the Site Engineer’s instructions. Ceiling layout shall be marked based on the

WEP for Gypsum board false ceiling REV.00 20.02.2023


THE PROJECT FOR THE IMPROVEMENT
OF GOVERNANCE AND MANAGEMENT
RESEARCH AND TRAINING FACILITIES

datum line provided by the Main Contractor. Based on the datum lines, chalk lines will be marked for

4
fixing the wall angle according to the ceiling level. Any discrepancies to the drawing and the setting
out found will be brought to the notice of the main contractor. Once the wall angles are fixed the
framing of the ceiling is done and the same is submitted for inspection of the engineer for approval.

6.0 SUSPENDED CEILING INSTALLATION PROCEDURE


Before start of suspended ceiling works the following works need to be completed and assessed by the
QAQC engineer from all concerned parties.

• Plaster works to walls up to the required height


• Stucco and primer work should be done to the required height
• All M.E.P woks of first fix services should be completed
• Protection of flooring

Before starting of the first fix services of false ceiling clearance will be obtained from the contractor,
consultant and MEP sub contractor as the first fix services of M.E.P above the false ceiling to be
completed and approved.

An area for mock-up will be prepared for inspection and approval before proceeding with the overall
installation.

QA/QC procedures shall be followed, WIR shall be raised, inspections shall be carried out at different
work tiers and clearances shall be
obtained at progressive levels as
mentioned therein.

6.1 Fixing of Suspension Grid

• I angle as per approved


materials and section
details of false ceilings will
be fixed on level markings
with self-taping screws and
royal plugs @ every
400mm c/c and at 100mm
near the wall corners and
joints of angles
• Vertical support of primary
channels or 3.5mm dia. G.I
wire with approved
materials and section
details will be fixed to
concrete slab @ 1200mm
c/c and 300mm near the
walls with 6mm dia. concrete plugs or rivets and extra supports should be provided near the
A/C duct if required
• Horizontal channels will then be fixed to vertical channels with self-taping screw
• For areas where the suspension height is much more than typical like the toilets, the C-
channels 38X15mm. shall be used as vertical support, the channels shall be fixed to the slab
with high screws from fisher supporting up to a weight of 50 kg per fix.

WEP for Gypsum board false ceiling REV.00 20.02.2023


THE PROJECT FOR THE IMPROVEMENT
OF GOVERNANCE AND MANAGEMENT
RESEARCH AND TRAINING FACILITIES

• Suspension system of the gypsum board ceiling should not be in direct contact with M.E.P.

5
services especially A/C ducts.

6.2 Fixing of Gypsum Board:

Before starting of the Gypsum Board fixing services of false ceiling clearance will be obtained by the
contractor, consultant and M.E.P sub-contractor, services of M.E.P above the false ceiling to be
completed and approved as well inspection of the suspension frame of false ceilings should be carried
out by the consultant and should be rectified to comments if given by them.

• Two layers of Gypsum plaster board sheet as approved should be fixed to furring channels
with self-taping screws at every 100mm c/c and G.I angles @ the perimeter of walls.
• Extra furring channels should be provided at the joints of Gypsum plaster boards to its shorter
lengths and cut piece joints if required.
• Extra supports should be provided around access panel.

7.0 FIELD QUALITY CONTROL


Above-Ceiling Observation: Construction Manager will conduct an above-ceiling
observation prior to installation of gypsum board ceilings and report any deficiencies in the
Work observed. Do not proceed with installation of gypsum board to ceiling support framing
until deficiencies have been corrected.
a. Notify Construction Manager one week in advance of the date and the time when the
Project, or part of the Project, will be ready for an above-ceiling observation.
b. Prior to notifying Construction Manager, complete the following in areas to receive
gypsum board ceilings:
- Installation of 80 percent of lighting fixtures, powered for operation.
- Installation, insulation, and leak and pressure testing of water piping systems
- Installation of air duct systems.
- Installation of air devices.
- Installation of ceiling support framing.
- Installation of mechanical system control air tubing.

WEP for Gypsum board false ceiling REV.00 20.02.2023


THE PROJECT FOR THE IMPROVEMENT
OF GOVERNANCE AND MANAGEMENT
RESEARCH AND TRAINING FACILITIES

6
8.0 SAFE WORK PLAN
• The forklift will be used for lifting of material, safe for its use.
• The operator has a valid license to operate.
• Slings have been identified and are correctly certified.
• A toolbox talk is conducted prior to the start of the work, in accordance with procedure.
• One member of the erection crew will be assigned as banks man and shall be suitably trained
by supplier for the task.
• Only the banks man will give instructions to the operator.
• All required materials will be brought to the site location.
• Forklift operations will be under the control of the banks man who will have clear visual
contact at all times with the equipment.
• Ensure all Personal Protection Equipment like Steel Toe Safety Shoes. Safety helmets.
• Goggle, Safety reflective jacket, Safety Belt is worn prior to start of work.
• The work Involves working at a height of 1.8m from Floor Level all the time should wear full
body safety harness.
• All safety precautions to be taken when working at heights. Full body Safety harness to be
strapped at all times.
• Erection of scaffolding shall be by the certified scaffolders.
• All electrical cable shall be color coded by the competent person with monthly color coding.
• Lighting shall be provided in the night shift activities.

WEP for Gypsum board false ceiling REV.00 20.02.2023