2020 - EE5102 - Distribution Systems
2020 - EE5102 - Distribution Systems
Faculty of Engineering
Department of Electrical Engineering
INSTRUCTIONS TO CANDIDATES
The marks assigned for each question and sections thereof are indicated in square brackets.
Assume reasonable values for any data not given in or with the examination paper. Clearly
state such assumptions made on the script.
If you have any doubt as to the interpretation of the wording of a question, make your own
decision, but clearly state it on the script.
Continued………..
Page 1 of 6
Question 1
a) Figures Q1(a1) and Q1(a2) indicate the 24-hour demand curves for Customer – A and
Customer – B respectively. Explain giving reasons, which type of customer (Customer – A
or Customer – B) would be preferred by the utility? [5 marks]
Customer – A Customer – B
Figure Q1 (b)
Load survey has revealed that the 15-minute maximum kW demand for the customers
connected to transformer T1 and T2 are given by the equations Q1(b1) and Q1(b2)
respectively.
Page 2 of 6
(i) Determine the demand factor of customer 1. [2 marks]
(ii) If the Diversity Factor varies with the number of customers as given in Table Q1,
determine the 15-minute maximum diversified kW demand for each transformer and at
the point N1. [10 marks]
Table Q1
No. of
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Customers
Diversity 1 1.6 1.8 2.1 2.2 2.3 2.4 2.55 2.6 2.65 2.67 2.7 2.74 2.78 2.8
Factor
(iii) Determine the monthly load factor for Transformer T1. [4 marks]
(iv) Assuming a power factor of 0.9, select suitable ratings for the transformers T1 and T2.
Consider 50 kVA, 75 kVA and 100 kVA transformers are available. [2 marks]
Question 2
a) Explain with illustrations how the “Network Protector” supports in improving the
reliability and compactness in designing a distribution feeder arrangement.
[5 marks]
b) An 11 kV feeder arrangement is shown in Fig. Q2 (b). The line impedance is (0.5 + j0.9)
Ω/km and total length of the feeder is 22 km. The loads are star connected three-phase
loads totalling 1.9052 MVA, 0.8 lagging power factor spaced as shown in Fig. Q2 (b).
Substation
Fig. Q2 (b)
Page 3 of 6
(i) Using the average method, calculate the percentage power loss in the feeder compared
to the supplied load. [5 marks]
(ii) Using the average method, calculate the percentage voltage drop at the furthest end of
the feeder. [4 marks]
(iii) Calculate the optimal capacitor size and its optimal placement (distance from the
substation) to minimize the power losses. [3 marks]
Fig. Q2 (c1)
Fig. Q2 (c2)
(ii) Explain the requirement of feeder selective relaying for distribution system.
[3 marks]
(iii) Identify the current range in which the feeder selective relay coordination is
satisfied for the given system. . [2 marks]
Page 4 of 6
Question 3
Fig. Q 3
The line-to-line source voltage at Node 1 is 12.47 kV and the distribution line impedance is
(0.1 + j0.5) Ω/km. All loads are star connected and balanced. Using the forward-backward sweep
method, compute the node voltages after 2 iterations. [25 marks]
Question 4
Table Q 4.1 shows the reliability parameters of the feeder sections and the distributors in the
simple radial distribution system shown in Fig. Q 4. Load point details of the same distribution
system are shown in Table Q 4.2. There are isolators installed at points t and u and fuses are
installed at points v, w and x.
Fig. Q 4
Page 5 of 6
Table Q 4.1
Component λ (failures/year) r (hours)
Feeder section 1 0.2 3.5
Feeder section 2 0.3 3.5
Feeder section 3 0.1 3.5
Distributor a 0.6 2.5
Distributor b 0.5 2.5
Distributor c 0.4 2.5
Table Q 4.2
Load point Number of customers Average load connected (kW)
A 500 3000
B 800 4500
C 1000 5000
Assume that all failures in feeder sections and distributors are short circuits and there are
no failures in fuses. The isolation and switching time is 0.5 hours.
Page 6 of 6