Execution Plan - Civil & Mechanical Work at Chaklala Terminal
Execution Plan - Civil & Mechanical Work at Chaklala Terminal
Activity ID Activity Name Duration Start Finish May 2023 June 2023 July 2023 August 2023 S October 2023 N D
(Days) 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 1017
Civil Works for Chaklala Terminal 227 02-May-23 14-Dec-23 14-Dec-23, Civil Works
A1190 IFC Drawing received form Shell 10 02-May-23 11-May-23 IFC Drawing received form Shell
A1140 Mobilization of Manpower & Equipment 14 02-May-23 15-May-23 Mobilization of Manpower & Equipment
A1150 Setup of Temporary Site Facilities 14 02-May-23 15-May-23 Setup of Temporary Site Facilities
A2430 Demolishing of Existing Structure (Sant Pit) 21 16-May-23 05-Jun-23 Demolishing of Existing Structure (Sant Pit)
A2435 Demolishing of Existing Structure (Fence) 45 06-Jun-23 20-Jul-23 Demolishing of Existing Structure (Fence)
A2440 Steel Reinforcement & Steel Embeded Parts 60 21-Jun-23 19-Aug-23 Steel Reinforcement & Steel Embeded Parts
Actual Level of Effort Remaining Work Page 1 of 3 Date Revision Checked Approved
04-May-23 Issue forApproval Rev.00
Actual Work Milestone
Execution Plan
Civil & Mechanical Work at Chaklala Terminal
Activity ID Activity Name Duration Start Finish May 2023 June 2023 July 2023 August 2023 S October 2023 N D
(Days) 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 1017
A2450 R.C.C.3000 psi 60 28-Jun-23 26-Aug-23 R.C.C.3000 psi
A2462 Bitumen Coating (Drain, Pits, Manhole, Fence) 30 27-Aug-23 25-Sep-23 Bitumen Coating (Drain, Pits, Manhole, Fence)
A2464 Water Proof Plasterin g (Drain, Pits, Manhole, Fence) 30 03-Sep-23 02-Oct-23 Water Proof Plasterin g (Drain, Pits, Manhole, Fence)
A2466 Brick Masonary (Sand Pits & Fence) 30 03-Oct-23 01-Nov-23 Brick Masonary (Sand Pits & Fence)
A2470 Plastering (Sand Pits & Fence) 45 10-Oct-23 23-Nov-23 Plastering (Sand Pits & Fence)
A2495 Aggregate Sub Base Course (Hardstanding Flooring) 60 25-Jul-23 22-Sep-23 Aggregate Sub Base Course (Hardstanding Flooring)
A2505 Stone Soling (Hardstanding Flooring & Collection Pits) 60 24-Aug-23 22-Oct-23 Stone Soling (Hardstanding Flooring & Collection
A2535 Road Cutting and Reinstatement Work 30 31-Oct-23 29-Nov-23 Road Cutting and Reinstateme
A2360 Surface Preparation & Painting of Piping 45 07-Jul-23 20-Aug-23 Surface Preparation & Painting of Piping
A2370 Installation of Piping & Fitting 45 28-Jul-23 10-Sep-23 Installation of Piping & Fitting
A2385 Apply Joint Sealant on Pipe Sleeve 2 13-Sep-23 14-Sep-23 Apply Joint Sealant on Pipe Sleeve
A2390 Installation of Valves & Flanges 5 15-Sep-23 19-Sep-23 Installation of Valves & Flanges
A2400 Installation of Foot Valves & Flanges 14 20-Sep-23 03-Oct-23 Installation of Foot Valves & Flanges
Actual Level of Effort Remaining Work Page 2 of 3 Date Revision Checked Approved
04-May-23 Issue forApproval Rev.00
Actual Work Milestone
Execution Plan
Civil & Mechanical Work at Chaklala Terminal
Activity ID Activity Name Duration Start Finish May 2023 June 2023 July 2023 August 2023 S October 2023 N D
(Days) 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 1017
A2040 Handover to Shell 5 10-Dec-23 14-Dec-23 Handover to Shell
Actual Level of Effort Remaining Work Page 3 of 3 Date Revision Checked Approved
04-May-23 Issue forApproval Rev.00
Actual Work Milestone