Execution Plan - Civil & Mechanical Work at Chaklala Terminal

The document outlines an execution plan for civil and mechanical works at Chaklala Terminal from May 2023 to October 2023. It involves 227 days of civil works including design, procurement, mobilization, construction activities like demolishing structures, excavation, concrete works and more. Mechanical works for 110 days include fabrication, painting and installation of piping. The civil works are scheduled to be completed by December 14, 2023 and mechanical works by October 3, 2023.

Uploaded by

Haseeb Babar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
142 views3 pages

Execution Plan - Civil & Mechanical Work at Chaklala Terminal

The document outlines an execution plan for civil and mechanical works at Chaklala Terminal from May 2023 to October 2023. It involves 227 days of civil works including design, procurement, mobilization, construction activities like demolishing structures, excavation, concrete works and more. Mechanical works for 110 days include fabrication, painting and installation of piping. The civil works are scheduled to be completed by December 14, 2023 and mechanical works by October 3, 2023.

Uploaded by

Haseeb Babar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Execution Plan

Civil & Mechanical Work at Chaklala Terminal

Activity ID Activity Name Duration Start Finish May 2023 June 2023 July 2023 August 2023 S October 2023 N D
(Days) 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 1017
Civil Works for Chaklala Terminal 227 02-May-23 14-Dec-23 14-Dec-23, Civil Works

Design Drawings 10 02-May-23 11-May-23 11-May-23, Design Drawings

A1190 IFC Drawing received form Shell 10 02-May-23 11-May-23 IFC Drawing received form Shell

Procurement 45 02-May-23 15-Jun-23 15-Jun-23, Procurement

A2090 Civil Material 30 02-May-23 31-May-23 Civil Material

A2100 MS Pipe 45 02-May-23 15-Jun-23 MS Pipe

Mobilization 14 02-May-23 15-May-23 15-May-23, Mobilization

A1140 Mobilization of Manpower & Equipment 14 02-May-23 15-May-23 Mobilization of Manpower & Equipment

Temporary Site Facility 14 02-May-23 15-May-23 15-May-23, Temporary Site Facility

A1150 Setup of Temporary Site Facilities 14 02-May-23 15-May-23 Setup of Temporary Site Facilities

QAQC & HSE 12 02-May-23 13-May-23 13-May-23, QAQC & HSE

A1160 Preparation of QA/QC Documents 7 02-May-23 08-May-23 Preparation of QA/QC Documents

A1170 Preparation of HSE Documents 7 02-May-23 08-May-23 Preparation of HSE Documents

A1210 Approval from Shell 5 09-May-23 13-May-23 Approval from Shell

Construction 208 16-May-23 09-Dec-23 09-Dec-23, Construction

Forecourt 208 16-May-23 09-Dec-23 09-Dec-23, Forecourt

Civil 208 16-May-23 09-Dec-23 09-Dec-23, Civil

A2430 Demolishing of Existing Structure (Sant Pit) 21 16-May-23 05-Jun-23 Demolishing of Existing Structure (Sant Pit)

A2435 Demolishing of Existing Structure (Fence) 45 06-Jun-23 20-Jul-23 Demolishing of Existing Structure (Fence)

A2437 Excavation 70 16-May-23 24-Jul-23 Excavation

A2439 P.C.C 60 06-Jun-23 04-Aug-23 P.C.C

A2440 Steel Reinforcement & Steel Embeded Parts 60 21-Jun-23 19-Aug-23 Steel Reinforcement & Steel Embeded Parts

Actual Level of Effort Remaining Work Page 1 of 3 Date Revision Checked Approved
04-May-23 Issue forApproval Rev.00
Actual Work Milestone  
Execution Plan
Civil & Mechanical Work at Chaklala Terminal

Activity ID Activity Name Duration Start Finish May 2023 June 2023 July 2023 August 2023 S October 2023 N D
(Days) 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 1017
A2450 R.C.C.3000 psi 60 28-Jun-23 26-Aug-23 R.C.C.3000 psi

A2462 Bitumen Coating (Drain, Pits, Manhole, Fence) 30 27-Aug-23 25-Sep-23 Bitumen Coating (Drain, Pits, Manhole, Fence)

A2464 Water Proof Plasterin g (Drain, Pits, Manhole, Fence) 30 03-Sep-23 02-Oct-23 Water Proof Plasterin g (Drain, Pits, Manhole, Fence)

A2466 Brick Masonary (Sand Pits & Fence) 30 03-Oct-23 01-Nov-23 Brick Masonary (Sand Pits & Fence)

A2470 Plastering (Sand Pits & Fence) 45 10-Oct-23 23-Nov-23 Plastering (Sand Pits & Fence)

A2475 Joint Sealant in Hardstanding 7 26-Sep-23 02-Oct-23 Joint Sealant in Hardstanding

A2480 Thermopore Backing Rod 21 03-Oct-23 23-Oct-23 Thermopore Backing Rod

A2485 Thermopore Expansion Joint 7 24-Oct-23 30-Oct-23 Thermopore Expansion Joint

A2495 Aggregate Sub Base Course (Hardstanding Flooring) 60 25-Jul-23 22-Sep-23 Aggregate Sub Base Course (Hardstanding Flooring)

A2505 Stone Soling (Hardstanding Flooring & Collection Pits) 60 24-Aug-23 22-Oct-23 Stone Soling (Hardstanding Flooring & Collection

A2515 Installation of Fence 30 31-Oct-23 29-Nov-23 Installation of Fence

A2525 Installation of Barbed Wire 30 10-Nov-23 09-Dec-23 Installation of Barbed Wire

A2535 Road Cutting and Reinstatement Work 30 31-Oct-23 29-Nov-23 Road Cutting and Reinstateme

Mechanical 110 16-Jun-23 03-Oct-23 03-Oct-23, Mechanical

A2340 Fabrication of MS Piping 45 16-Jun-23 30-Jul-23 Fabrication of MS Piping

A2360 Surface Preparation & Painting of Piping 45 07-Jul-23 20-Aug-23 Surface Preparation & Painting of Piping

A2370 Installation of Piping & Fitting 45 28-Jul-23 10-Sep-23 Installation of Piping & Fitting

A2375 Installation of Pipe Sleeves 2 11-Sep-23 12-Sep-23 Installation of Pipe Sleeves

A2385 Apply Joint Sealant on Pipe Sleeve 2 13-Sep-23 14-Sep-23 Apply Joint Sealant on Pipe Sleeve

A2390 Installation of Valves & Flanges 5 15-Sep-23 19-Sep-23 Installation of Valves & Flanges

A2400 Installation of Foot Valves & Flanges 14 20-Sep-23 03-Oct-23 Installation of Foot Valves & Flanges

Handover 5 10-Dec-23 14-Dec-23 14-Dec-23, Handover

Actual Level of Effort Remaining Work Page 2 of 3 Date Revision Checked Approved
04-May-23 Issue forApproval Rev.00
Actual Work Milestone  
Execution Plan
Civil & Mechanical Work at Chaklala Terminal

Activity ID Activity Name Duration Start Finish May 2023 June 2023 July 2023 August 2023 S October 2023 N D
(Days) 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 1017
A2040 Handover to Shell 5 10-Dec-23 14-Dec-23 Handover to Shell

Actual Level of Effort Remaining Work Page 3 of 3 Date Revision Checked Approved
04-May-23 Issue forApproval Rev.00
Actual Work Milestone  