Simplex Infrastructures Limited will undertake the construction of sub-structure and super-structure civil works including some finishing works for the "Sunshine One" project in Shriram Grand City near Kolkata. The work will involve piling, construction of floors up to the 18th floor using the mivan shuttering system, and terrace and finishing works for 5 residential towers between February 2021 to June 2022. The tentative program schedules the completion of different stages of work over this period for each tower.

Uploaded by

abir sengupta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
131 views1 page

15 Months Tentative Work Program - Sunshine One

Simplex Infrastructures Limited will undertake the construction of sub-structure and super-structure civil works including some finishing works for the "Sunshine One" project in Shriram Grand City near Kolkata. The work will involve piling, construction of floors up to the 18th floor using the mivan shuttering system, and terrace and finishing works for 5 residential towers between February 2021 to June 2022. The tentative program schedules the completion of different stages of work over this period for each tower.

Uploaded by

abir sengupta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

SIMPLEX INFRASTRUCTURES LIMITED

“Construction of Sub-Structure and Super-Structure Civil Works including part Finishing Works for Project ‘Sunshine One’ in ‘Shriram Grand City’,
Uttarpara, Hooghly, near Kolkata.”

Tentative Work Program:

LOCATION
SN DESCRIPTION REMARKS
TOWER 1A TOWER 2A TOWER 2B TOWER 3D TOWER 3E

Date of Commencement 26-02-2021 26-02-2021 26-02-2021 26-02-2021 26-02-2021

A Conventional Work:
1 Total Scope of Pile Cap 54 46 46 52 52
Plan to Complete Date of Conventional Work upto Ground
2 15-05-2021 31-05-2021 18-05-2021 28-05-2021 22-05-2021
Floor Bottom Level

B Mivan Work:
1 Ground Floor Slab (70% Mivan & 30% Conventional) 14-07-2021 30-07-2021 17-07-2021 27-07-2021 21-07-2021

2 Mivan 1st Floor 03-08-2021 19-08-2021 06-08-2021 16-08-2021 10-08-2021


3 Mivan 2nd Floor 15-08-2021 31-08-2021 18-08-2021 28-08-2021 22-08-2021
4 Mivan 3rd Floor 27-08-2021 12-09-2021 30-08-2021 09-09-2021 03-09-2021
5 Mivan 4th Floor 08-09-2021 24-09-2021 11-09-2021 21-09-2021 15-09-2021
6 Mivan 5th Floor 20-09-2021 06-10-2021 23-09-2021 03-10-2021 27-09-2021
7 Mivan 6th Floor 02-10-2021 18-10-2021 05-10-2021 15-10-2021 09-10-2021
8 Mivan 7th Floor 14-10-2021 30-10-2021 17-10-2021 27-10-2021 21-10-2021
9 Mivan 8th Floor 26-10-2021 11-11-2021 29-10-2021 08-11-2021 02-11-2021
10 Mivan 9th Floor 07-11-2021 23-11-2021 10-11-2021 20-11-2021 14-11-2021
11 Mivan 10th Floor 19-11-2021 05-12-2021 22-11-2021 02-12-2021 26-11-2021
12 Mivan 11th Floor 01-12-2021 17-12-2021 04-12-2021 14-12-2021 08-12-2021
13 Mivan 12th Floor 13-12-2021 29-12-2021 16-12-2021 26-12-2021 20-12-2021
14 Mivan 13th Floor 25-12-2021 10-01-2022 28-12-2021 07-01-2022 01-01-2022
15 Mivan 14th Floor 06-01-2022 22-01-2022 09-01-2022 19-01-2022 13-01-2022
16 Mivan 15th Floor 18-01-2022 03-02-2022 21-01-2022 31-01-2022 25-01-2022
17 Mivan 16th Floor 30-01-2022 15-02-2022 02-02-2022 12-02-2022 06-02-2022
18 Miivan 17th Floor 11-02-2022 27-02-2022 14-02-2022 24-02-2022 18-02-2022
19 Mivan 18th Floor 01-03-2022 17-03-2022 04-03-2022 14-03-2022 08-03-2022

20 Above Terrace & Finishing work. 30-05-2022 15-06-2022 02-06-2022 12-06-2022 06-06-2022

Duration in Months 15 16 15 16 15

Note: The above Program is subject to provide all inputs like, Drawings, Free issue materials, approval of front etc in time.