Planning and Scheduling Procedure - April 7 - 2014
Planning and Scheduling Procedure - April 7 - 2014
Control Procedure
Approved: EC OM TM FM HSEQ
Signature /
Date:
Page 1 of 15
EPO-CP-11 PROJECT PLANNING AND SCHEDULING PROCEDURE ISSUE No. 0
Contents
1. SCOPE OF DOCUMENT..............................................................................................................3
2. PURPOSE OF DOCUMENT.........................................................................................................3
3. AUTHORITY.................................................................................................................................3
4. KEY PERSONNEL’S RESPONSIBILITIES.................................................................................3
4.1 Project Leader (PL)...............................................................................................................3
4.2 Construction Leader (EPO/3)................................................................................................4
4.3 Engineering Contractor..........................................................................................................4
4.4 Integrated Service Contract Contractor (ISC)........................................................................4
4.5 Design Services Engineer (EPO/4)........................................................................................4
4.6 BLNG Planner/Scheduler......................................................................................................4
4.7 EPO TA Focal Point..............................................................................................................5
4.8 Shutdown Planner..................................................................................................................5
4.9 Procurement Coordinator (CP)..............................................................................................5
5. PROJECT PLANNING..................................................................................................................5
5.1 DEFINE Phase......................................................................................................................5
5.2 EXECUTION Phase Planning...............................................................................................7
5.3 List of Planning Softwares.....................................................................................................8
6. PROJECT SCHEDULING.............................................................................................................8
6.1 Level of Schedules................................................................................................................9
6.2 Scheduling Control..............................................................................................................11
6.3 Schedule Reviews................................................................................................................11
6.4 Project Schedule Development in Primavera P6..................................................................12
6.5 Schedule Resource Loading.................................................................................................12
6.6 Project Scheduling via ISC Project Execution.....................................................................12
7. SCHEDULE BASELINES...........................................................................................................13
7.1 Creation of Baseline Schedule.............................................................................................13
7.2 Re-Baselining......................................................................................................................13
8. SCHEDULE PROGRESS REPORT............................................................................................13
8.1 Progress Measurement.........................................................................................................13
8.2 Percentage Allocation of Weight Factors............................................................................14
8.3 Schedule Updating in Primavera.........................................................................................14
9. SHUTDOWN PLANNING AND SCHEDULING.......................................................................14
10. ABBREVIATIONS......................................................................................................................14
11. REFERENCES.............................................................................................................................15
12. ATTACHMENTS.........................................................................................................................15
Page 2 of 15
EPO-CP-11 PROJECT PLANNING AND SCHEDULING PROCEDURE ISSUE No. 0
1. SCOPE OF DOCUMENT
This procedure shall be applied to all the projects approved and executed by the different
departments within the BLNG organization. This procedure specifically cover the requirements of
the DEFINE and EXECUTE phase of the ORP as described in Section 1 of EPO-CP-006, Project
Governance and Project Assurance.
2. PURPOSE OF DOCUMENT
The purpose of this document includes but is not limited to the following:
a. Provide a standardized guideline and methodologies in developing the plans and schedules for
the various EPO and other BLNG department’s projects.
b. Identify the sources and custodians of planning and scheduling data.
c. Define the responsibilities of the respective personnel within the BLNG organization during
the planning and execution stages of projects.
d. Define the process of integration of various projects within BLNG in the approved annual
EMP and IAP.
e. Serve as a basis of the plans and procedures to be required from the Contractors during the
project tendering and execution.
f. Provide reporting templates to be used in the execution of the projects.
g. Provide supplementary stipulations to other EPO procedures that contain provisions or
paragraphs related to planning and scheduling. However, shall any conflict occur between the
statements described herein and those stated in the other EPO procedures, the more stringent
requirement among them shall be applied.
3. AUTHORITY
This document shall be implemented in all EPO projects upon its approval. No deviation shall be
allowed without the written approval of the Line Manager.
4. KEY PERSONNEL’S RESPONSIBILITIES
4.1 Project Leader (PL)
The Project Leader, in addition to the responsibilities identified in Section 1.2 of EPO-CP-01,
PROJECT INITIATION, APPROVAL & CLOSE OUT, shall have the following
responsibilities:
a. The Project Leader shall bear the overall accountability on the projects assigned to them
throughout the different phases of project development from the conceptual stage until its
close out.
b. Serve as the project’s focal point of communication and coordination.
c. Lead the overall direction in the various stages of project planning and scheduling.
d. Provide instructions to various project stakeholders in providing preliminary/confirmed
scheduling data for incorporation in the schedule.
e. Issue the necessary data and acceptable assumptions to form the basis of schedule to the
Planner/Scheduler.
f. Initiate consolidation of updated scheduling information from the project team members, the
Contractors and other BLNG department’s representatives through meetings and
coordination.
g. Ensure that the objectives and completion milestones of the project are addressed in
accordance with the approved PAF.
h. Initiate and lead the progress meetings and schedule reviews.
i. Approve project schedules and reporting formats prior to execution and utilization.
j. Attend the IAP meetings initiated and as timely invited by OPR/OPS appointed Focal Point or
coordinator.
Page 3 of 15
EPO-CP-11 PROJECT PLANNING AND SCHEDULING PROCEDURE ISSUE No. 0
Page 4 of 15
EPO-CP-11 PROJECT PLANNING AND SCHEDULING PROCEDURE ISSUE No. 0
Page 5 of 15
EPO-CP-11 PROJECT PLANNING AND SCHEDULING PROCEDURE ISSUE No. 0
The time related elements from all of the above documents should be captured and
integrated into the developed project schedule. The schedule developed at this stage
should already be in accordance with the requirements of this procedure and should at a
minimum contain the activities that cover the Engineering, Procurement and Construction
phases of the project.
5.1.2 Key Reference Schedules
BLNG being a multi-discipline organization maintain several schedules which are
respectively updated by different departments within BLNG.
Among these schedules are the following:
a. Engineering Master Plan issued by AMP
b. EMI Long Term Turn Around Plan updated by EMI
c. Production Schedule issued by OPR
d. BLNG IAP by OPR
The above schedules contain general or updated information of windows of opportunity
and could provide the planning basis for the completion of a project especially those
requiring unit or equipment shutdown to complete their final tie-ins. The
Planner/Scheduler should ensure that the above schedules are clearly referenced by
identifying the revisions or data date of these schedules at the time of their integration
into the project schedule. See Attachment 5.1.2 A, B and C and D for the sample of the
above schedules.
Attachment 5.1.2.E is the Scoping Flowchart prepared by OPR which described the
necessary flow of EMP development. All new personnel who come on board to BLNG as
a Planner/Scheduler is recommended to communicate with the OPR Focal point to gain
the basic knowledge on how things are done within the BLNG Operation and Production.
Planner’s understanding of the Scoping Flowchart is important relative to every project’s
overall planning.
5.1.3 Key Milestones
The schedule for the DEFINE stage should be made with details fit and concise for the
management requirement and understanding. One way of providing a general overview of
the project phases and objectives is to include milestones that define either the start or
completion of the major activities of the project. The following is a list of milestones
which could be incorporated in the schedule whenever applicable.
a. BDEP Approved by TA’s
b. PEP Completed
c. FID Approved by PLT/ITC
d. EPC/Design contract awarded
e. Long Lead Material PO Issued
f. Issuance of IFC drawings
g. Issuance of AFC drawings
h. Bulk Material PO Issued
i. Construction contract awarded
j. Construction Kick Off
k. Mechanical Completion
l. Tie-in or Shutdown Start
m. Ready for Start Up
n. Handover to Operation
As every project requirements are generally unique and may not necessarily include all of
the above milestones, a template has been developed by EPO/2 to capture the baseline
dates of each milestone as committed by the Project Leaders. This template also includes
Page 6 of 15
EPO-CP-11 PROJECT PLANNING AND SCHEDULING PROCEDURE ISSUE No. 0
Page 7 of 15
EPO-CP-11 PROJECT PLANNING AND SCHEDULING PROCEDURE ISSUE No. 0
Page 8 of 15
EPO-CP-11 PROJECT PLANNING AND SCHEDULING PROCEDURE ISSUE No. 0
Page 9 of 15
EPO-CP-11 PROJECT PLANNING AND SCHEDULING PROCEDURE ISSUE No. 0
Page 10 of 15
EPO-CP-11 PROJECT PLANNING AND SCHEDULING PROCEDURE ISSUE No. 0
Page 11 of 15
EPO-CP-11 PROJECT PLANNING AND SCHEDULING PROCEDURE ISSUE No. 0
E P 3 1 0 0 0 – C 6 2 0 – 1 0 5
Dep’t Code GBS – DBS – Sequential No.
The Activity ID should be read as an activity that belongs to a project being executed by EPO
Department, at Process Train No.1 and involves installation of aboveground piping.
In addition to the system described above, and Primavera P6 being a database program itself, it is
essential that the activity be populated with the relevant activity codes to facilitate its integration
into the overall BLNG IAP.
6.5 Schedule Resource Loading
The schedules submitted by the contractors should be required to be resourced loaded.
Manpower Histograms should accompany the submission of schedules for approval.
Resource loading helps to validate the reliability of the schedule and:
Helps ensure the feasibility of the schedule
Confirms the alignment between cost estimate and schedule
Page 12 of 15
EPO-CP-11 PROJECT PLANNING AND SCHEDULING PROCEDURE ISSUE No. 0
Page 13 of 15
EPO-CP-11 PROJECT PLANNING AND SCHEDULING PROCEDURE ISSUE No. 0
The progress derived above shall be entered into the physical percentage of each activity in the
P6 Schedule during updating.
8.2 Percentage Allocation of Weight Factors
The contractor at the beginning of the project shall submit to the project leader the sample of
tabular report they intend to use to measure their progress. This report should reflect their
proposed percentage allocated for each of the itemized activity in the schedule. The criteria to
allocate percentage for each major item of engineering, procurement and construction shall be in
accordance with the following:
Engineering – Engineering Manhours
Procurement – Material and Equipment Cost
Construction – Construction Direct Manhours
8.3 Schedule Updating in Primavera
Before updating the data date in Primavera, the contractor planner should make a copy of the
schedule for archiving. Sequential number should be provided for each update to allow
comparison and analysis of schedule if needed in the future. It is the responsibility of the
contractor to report any changes in the forecast completion of the activities to the Project leader
who in turn inform the Planner/Scheduler for the necessary schedule update of the project
schedule in BLNG Citrix based P6 production Database.
9. SHUTDOWN PLANNING AND SCHEDULING
Shutdown Planning and Scheduling should be in accordance with the latest revision of EC-CP-02,
“SHUTDOWN PLANNING AND EXECUTION”.
10. ABBREVIATIONS
AFC – Approved for Construction
AOS – Arrival On Site
BDEP – Basic Design Engineering Package
BLNG – Brunei LNG Sendirian Berhad
CL – Construction Leader (EPO/3)
EPCM – Engineering, Procurement Construction management Contractor
EPO – Project Engineering and Support Services
FID – Final Investment Decision
FEED – Front End Engineering and Design
Page 14 of 15
EPO-CP-11 PROJECT PLANNING AND SCHEDULING PROCEDURE ISSUE No. 0
Page 15 of 15