Critical Path Method
Critical Path Method
Ref: http://www.ehow.com/about_4703555_what-critical-
path.html#ixzz2igTEV3Q7
Critical Path
A Critical Path is the path with the least amount of float or
slack time. A float time is the amount of time that an activity
can be delayed without delaying the project.
A Critical Path is the longest amount of time it will take to
complete the project.
A Critical Path usually has 0 float but may have negative float
if the end task is constrained to an early finish date.
If any of the task identified in the critical path is late, then the
project will be late.
6. Steps for identifying Critical Path
1. Specify the activates, duration and dependencies
2. Draw a network diagram.
3. Perform the forward pass to identify all Early Start and Early Finish times for
the network.
Early Finish = Early Start + Duration
4. Perform the backward pass to identify all Late Start and Late Finish times
for the network.
Late Start = Late Finish – Duration
A 2 ----
B 2 A
C 1 A
D 3 A
E 1 C,D
F 3 B
G 2 E,F
Terminologies
ID – Task ID
D- Duration
ES – Early Start
EF – Early Finish
LS – Late Start ES EF
LF – Late Finish F ID DR
S - Slack
LS LF
2. Network Diagram
B 2 F 3
Activity
A 2 C 1 G 2
Duration
ES EF
D 3 E 1 F ID DR
LS LF
3. Forward Pass
2 4 4 7
B 2 F 3
Early Early
Start Finish Duration= 9days
7 9
0 2 2 3
G 2
A 2 C 1
2 5 5 6
ES EF
D 3 E 1
1st task starts at 0 F ID DR
EF = ES + DR
LS LF
ES = EF of predecessor
When more than one predecessor, pick the larger #
4. Backward Pass
2 4 4 7
B 2 F 3
2 4 4 7
1st task should end
with LS = 0.
2 3 7 9
0 2
C 1 G 2
A 2
5 6 7 9
0 2
Late Late
Start Finish
2 5 5 6 ES EF
D 3 E 1 F ID DR
LS = LF - DR 3 6 6 7 LS LF
LF = LS of successor
7 9
0 2 2 3
0 G 2
0 A 2 3 C 1
7 9
0 2 5 6
Float = LS – ES
2 5 5 6 ES EF
1 D 3 1 E 1 F ID DR
3 6 6 7 LS LF
2 5 5 6 ES EF
0 D 3 1 E 1 F ID DR
2 5 6 7 LS LF
LS = LF - DR
LF = LS of successor
Thank You!
Vazi Okhandiar, PMP, MCT, MBA, MSCS, BSEE
NR Computer Learning Center
1835 W. Orangewood, Suite 200
Orange, CA 92868
www.nrclc.com . (714) 505. 3475
[email protected]