Check List Fire Alarm

This document provides a checklist for inspecting a fire alarm installation with two parts: Part 1 checks the delivery and storage of equipment, including examining test reports, checking quantities against packing lists, and ensuring equipment is undamaged in proper storage. Part 2 checks the installation, including types and locations of panels, detectors, call points and strobes being as specified, with correct spacing, alignments within tolerances, and proper terminations, grounding and labeling. Housekeeping is also checked. Inspections note compliance and any needed re-inspections or rectifications.

Uploaded by

Kham Nguyen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
28 views

Check List Fire Alarm

This document provides a checklist for inspecting a fire alarm installation with two parts: Part 1 checks the delivery and storage of equipment, including examining test reports, checking quantities against packing lists, and ensuring equipment is undamaged in proper storage. Part 2 checks the installation, including types and locations of panels, detectors, call points and strobes being as specified, with correct spacing, alignments within tolerances, and proper terminations, grounding and labeling. Housekeeping is also checked. Inspections note compliance and any needed re-inspections or rectifications.

Uploaded by

Kham Nguyen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 5

FAE.

CHECK LIST FOR FIRE ALARM INSTALLATION WORKS


CHECK LIST FOR FIRE ALARM INSTALLATION WORKS (PART 1) Ref.No : NCV/KVN/CLT/[Building]/FAE/001

Project Project ID : 13004


Work Item Sheet : ____/____

BLDG/FLOOR/ROOM Building: Grid Line : Room:


Inspection 1 Time
st
Final Time
Person in charge Name Signature Date Name Signature Date

Result Re-inspection
No Check Item Check Method/Tool Tolerance Reason
Pass Failed Pass Failed

1 Factory Inspection and Acceptance

1.1 To examine the factory test report.


Material approval
Visual
document
1.2 To examine the factory inspection report.

2 Delivery

2.1 To examine the packing list.

2.2 To examine the mill certificate (domestic goods).

2.3 To examine the factory test report.

2.4 To check the goods in terms of type and quantity.


To check the goods for the status of being well
2.5 protected, well marked, well labelled, no damages,
staying intact. Visual Stored in storage
3 Storing

To check if the job of unloading, handling and carrying


3.1 to the storage facility is done in a proper way to
ensure no damages to the goods.

To check if the storage facility is airy, clean and big


3.2
enough in sizes.

To check if the goods is stored in a state of high


3.3
steadiness and being well protected.

4 Installation of FA Equipments

4.1 Type, sizes and quantity.

a. Main Panels

To check Main Panel type(s).

To check the number of Main Panels. Visual

To check capacity of each Main Panel.

b. Sub-Panels
MS/ Technical
specification/
To check Sub-Panel type(s). Shop drawing/
Material approval
document
To check the number of Sub-Panels. Visual

To check capacity of each Sub-Panel.

c. Heat Detectors

To check Heat Detector type(s).


Visual
To check the number of Heat Detectors.

- Result : marked X in the appropriate column

Comment Rectification method & Date to complete : KOA VN

Date :
KINDEN VN

Date :
CHECK LIST FOR FIRE ALARM INSTALLATION WORKS (PART 2) Ref.No : NCV/KVN/CLT/[Building]/FAE/002

Project Project ID : 13004


Work Item Sheet : ____/____

BLDG/FLOOR/ROOM Building: Grid Line : Room:


Inspection 1 Time
st
Final Time
Person in charge Name Signature Date Name Signature Date

Result Re-inspection
No Check Item Check Method/Tool Tolerance Reason
Pass Failed Pass Failed
d. Smoke Detectors

To check Smoke Detector type(s).


Visual
To check the number of Smoke Detectors.

e. Beam Detectors

To check the type(s) of Beam Detector composed of


Transmitter and Receiver.

To check the number of Beam Detectors. Visual

To check the alignment between Transmitter and


corresponding Receiver.

f. Manual Call Points

To check Manual Call Point type(s).


Visual
To check the number of Manual Call Points.

g. Strobes

To check Strobe type(s).


Visual
To check the number of Strobes.

h. Sirens/Horns/Bells

To check Siren/Horn/Bell type(s).


Visual
To check the number of Sirens/Horns/Bells.

4.2 Others

To check if there are no visible damages. Visual

To check the co-ordinate of installed location as per


Measuring tape ±3mm
drawings.

To check the vertical alignment. Level ±0.1%

To check the horizontal alignment. Level ±0.1%

To check the spacing/ distance in relation to other


Measuring tape ±10mm
equipment/ services.
To check the trademark(s) of every integral
Visual
components/ equipment.
To check the installation work in terms of firmness,
Visual and By hand
being well supported, good-looking finish.
To check and determine which group of loops/zones MS/ Technical
Visual specification/
corresponding to which Sub-panel.
Shop drawing/
To check the job of cable termination in terms of Material approval
physical solidity and cable curvature. document
Visual and By hand
To check the job of grounding of all panels.

To check the job of labeling.


Visual
4.3 To check the job of housekeeping.

- Result : marked X in the appropriate column

Comment Rectification method & Date to complete : KOA VN


Date :

KINDEN VN

Date :