Irrigation Engineering - PCJ
Irrigation Engineering - PCJ
CHAPTER
1 Introduction
Under the term “Irrigation” as applied to the agriculture, is included all of the operation, or practices in
artificially applying water to the land for the production of crop during base period of crop. Or irrigation
may also defined as “the artificial process of supplying water for the growth of crops as per crop
requirement in the absence of sufficient precipitation”.
Ordinarily water is supplied to the crop land by nature through rain but generally it is not sufficient for the
proper growth of the plants. Different types of plants require different quantities of water at different
times, till they grow up completely. In order to achieve this objective of irrigation, an irrigation system is
required to be developed, which involves planning, design, construction, operation and maintenance of
various irrigation works viz. a sources of supply, a different system for carrying water from the source to
the agricultural land and its application on the land, and various other associated works.
Irrigation involves artificially providing water to crops. This technique is used in farming to enable plants
to grow when there is not enough rain, particularly in arid areas. It is also used in less arid regions to
provide plants with the water they need when seed setting. About 66% of the world's water catchment is
used in farming, which continues to make increasing use of irrigation. But in most irrigation systems 50
to 60% of the water used does not benefit the plants. It is therefore necessary to set up more carefully
designed irrigation schemes that ensure optimum agricultural production while preserving this resource.
-1-
Irrigation and Drainage Engineering
rest of the period there may be no rain. Further in some part of the region there may be excessive
rain and remaining part may have little or almost no rain. The rainfall in Nepal has such
characteristics. The entire rainfall is received from the monsoon during the four months from June to
September and the rainfall during winter is scanty. With such uneven distribution of rainfall, it
would be necessary to use irrigation.
(iii) Growing crops round a year
The rainfall in a region may be sufficient to grow only one crop in a year for which no irrigation
may be required, for example rice in monsoon. However, in the same region if more numbers of
crops are to be grown during the same year it would be possible only if the irrigation facilities are
available. Moreover for some crops such as sugarcane have much longer period of maturity for
which irrigation is invariably needed.
(iv) Growing superior crops
Certain inferior or low-priced crops require less water and hence for growing such crops only the
rain water may be sufficient and no irrigation is therefore needed. However there are several
superior or high- priced crops which need frequent application of large quantity of water and for
growing such crops, irrigation is necessary.
There is a huge scope of irrigation development in Terai as well as in Hills of Nepal. In Terai (Plain
areas) a lot of agricultural areas are available without irrigation facility. These plains have high
fertility but in the absence of irrigation facilities they are limited to rain-fed cropping only. In Terai
there is a future scope of developing large irrigation systems with barrages, small dams and
reservoirs to produce a variety of crops in large quantity.
In hills there are small commanded areas which need small irrigation systems. In hills a lot of Farmer
Managed Irrigation Systems (FMIS) are available but they are not designed properly by engineers.
Farmers are facing difficulty in operation and maintenance of these systems. Hence there is a scope for
improving these small FMIS and construction of new irrigation systems in hills of Nepal.
Irrigation and drainage are two face of the same coin. Surface irrigation is a boon only if it is practiced
with great care. Due to steep topography, mountains and hills are less susceptible to water logging,
hence less need of drainage. In hills and mountains due to presence of sufficient natural drainage there
is less requirement of drainage. Remodeling of exiting natural drainage is sufficient to drain off the
excess water. But in case of plain areas during monsoon season, there is great chance of water logging.
To remove the excess water, there is necessary to introduce the surface and subsurface drainage. By
providing drainage facilities in Terai, optimum crop production can be assured.
-2-
Introduction
• In hills where more head is available there is less agricultural fields and in plains where more
agricultural fields are available there is less head.
• Isolated communities have out of necessity concentrated on growing subsistence food crops.
Due to difficult remote area, isolated farmers communities are not encouraged to adopt new
cropping pattern for want of market access.
• Due to poor agricultural support services improved seed varieties and agricultural techniques
are often not available to the farmers.
• Due to deforestation, rainfall runoff is more rapid, increasing the frequency of severs floods.
• Landslide and erosion causing damage to irrigation structure (particularly intakes) and
clogging canals.
• Conflicts between water users and political interferences.
• Misconceptions and lack of coordination between developer agencies.
• Problem in collection of Irrigation Service Fees.
There are several challenges as above mentioned however there are good opportunities for irrigation
development in Nepal. For irrigation development we need sufficient water source, croplands, suitable
crops, suitable climate, skilled human resources, construction materials and technology. These all are
more or less available in Nepal. For the source of irrigation water in Nepal different rivers, streams, lakes,
springs and ground water can be used. Agricultural and crop lands are abundantly available in all parts of
the country. Different types of crops such as rice, wheat, maize, tobacco, sugarcane, millet including
vegetables are suitably grown in the country. The climate of Nepal is also favorable for growing different
variety of crops and fruits. At present we have sufficient national experts in different areas for designing
and construction of irrigation projects. Basic construction materials such as cement, sand, brick, boulder
and steel are also available in Nepal. Fast growing technology can also be used to develop the irrigation
projects.
-3-
Irrigation and Drainage Engineering
saw the countrywide implementation of the minor irrigation program with the emphasis on the
participation of the beneficiaries. The government investment in irrigation development – especially in
the large-scale irrigation systems in the Terai increased tremendously from 1970 onwards. This was due
to the increase in the borrowing of international capital in the form of loans and grants for the country’s
overall economic development. This is clearly reflected in the surge of irrigation development targets in
the subsequent five-year development plans- from the Fourth Plan (1970-75) onwards.
Until the middle of 1980s, irrigation development by the government focused largely on the construction
of physical infrastructure of canals and structures, and very little attention was given to the effective
management of the completed systems. Attention began to be paid to the improved management of
government-operated irrigation systems from 1985 onwards. This is reflected in the implementation of a
number of management-oriented projects in 1985-89: the USAID-funded Irrigation Management Transfer
Project (IMTP) in 1985, the Irrigation Line of Credit (ILC) in 1988 financed by the World Bank, the
Irrigation Sector Project (ISP) in 1988 financed by the ADB, and the Irrigation Sector Support Project
(ISSP) in 1989 under the co-financing of the UNDP, the World Bank and the Asian Development Bank
(ADB). All these projects have specifically emphasized the participatory approach to irrigation
development and management of irrigation facilities. Further, following the introduction of the Basic
Needs Program (BNP) in 1987, the working Policy on Irrigation Development for the fulfillment of Basic
Needs’ was formulated in the early 1989.
This was immediately followed by the promulgation of the Irrigation Regulations (IR) in April 1989.
These Regulations placed emphasis on the greater collaboration with water users in all phases of
irrigation projects – planning, construction, operation and maintenance. The strategy of increasing farmer
participation was mainly based on the recognition that government resources alone were inadequate to
meet the country’s irrigation development objectives and sustain the management of government
irrigation systems after their completion. The government expected to increase the rate of irrigation
development and develop maximum farmers’/water users’ responsibility in the operation and
maintenance of completed irrigation systems. The Irrigation Regulations gave water users, for the first
time, a legal mandate to form water users’ associations in accordance with the 1976 Association
Registration Act. It institutionalized the participation of actual water users in irrigation. In 1989, the
action plans and policies for the turnover of small irrigation systems and the participatory management of
large irrigation systems were formulated.
This was followed by the promulgation of Water Resources Act and Irrigation Policy in 1992 with the clear
vision of irrigation development. Later this policy was amended in 1997 and now Irrigation Policy 2004 is in
practice. Similarly Irrigation Master Plan 1990, Agriculture Perspective Plan 1995, Water Resources Strategy
2002 and National Water Plan 2005 are other few documents which guide irrigation development in Nepal.
Out of total area 1,47,181 km2, Nepal has cultivable area of 26,42,000 ha. Out of total cultivable area irrigable land
is 17,66,000 ha. At the end of F.Y. 071/72, the area covered by the different irrigation methods are as follows.
Surface irrigation = 779694 ha.
Subsurface irrigation = 391080ha.
Farmers channel = 198140 ha.
Some irrigation systems of Nepal are given in Table 1.1 with their commended area and average design discharge.
-4-
Introduction
Table:1
Table:1.1 List of irrigation system and their commanded area with discharge (Source: - Department of Irrigation)
Asar-Kartik Mangsir-Falgun Chaitra-Jestha
Possible
Irrigation Commanded Average Average Average
S.N District Irrigated Irrigated Irrigated Irrigated
System Area (ha) Discharge Discharge Discharge
area (ha) Area (ha) Area (ha) area (ha)
(lps) (lps) (lps)
Morang
Sunsari
2 and 68000 50000 66000 22000 58000 15000 17700 0
Morang IS
Sunsari
Chandra
3 Mohana Sunsari 1800 1650 1500 1500 1000 1100 900 0
IS
Chandra
4 Saptari 10500 8000 10000 6000 7000 1500 300 100
Canal IS
Koshi
5 West Saptari 11000 9900 11000 9900 9000 9900 5000 7000
Canal IS
Kashi
6 Pump Saptari 13000 7000 10000 5000 7000 5000 0 2000
Canal IS
Siraha
and
7 Kamala IS 25000 28800 25000 8000 10000 4000 0 2000
Dhanus
ha
Hardinath Dhanus
8 2000 1600 1700 400 800 210 200 0
IS ha
Manushm
9 Sarlahi 5200 5800 5000 4300 3000 3200 1500 0
ara IS
Sarlahi
Bagmati and
10 45600 34000 39700 10200 25500 7700 13000 0
IS Rautaha
t
Rautaha
11 Jhaanjh IS 2000 3500 2000 1200 1500 1200 500 500
t
Bara
Narayani
12 and 28700 19200 28000 12000 18000 10000 500 12000
IS
Parsa
Bara
Narayani
13 and 2800 280 600 280 600 100 300 0
Tubel IS
Parsa
Narayani Chitwa
14 4700 5500 3700 2000 300 2000 0 3200
Lift IS n
Chitwa
15 Khageri IS 3900 6200 3600 2100 500 1500 500 0
n
Pokhara
16 Jal Kaski 1030 9000 1000 6000 500 4000 200 0
Upayog IS
-5-
Irrigation and Drainage Engineering
Bijayapur
17 Kaski 1280 6000 1100 3000 500 2000 500 0
IS
Phalebash
20 Parbat 440 700 340 350 130 100 75 0
IS
Nepal
Gandak Nawalp
21 10300 8500 10000 4500 8000 4000 1300 2700
West arasi
Canal IS
Bhairahaw
a Lumbini
Undergrou Rupand
22 20309 10500 13500 10000 8000 10000 5000 0
nd Water ehi
Resource
IS
Marchwaa Rupand
23 3500 5200 3200 4000 2500 3200 0 600
r lift IS ehi
Baangang Kapilba
24 6200 3000 6000 2500 3600 1500 100 0
a IS stu
Praganna
25 Banke 5800 25000 5600 15000 5600 6000 600 3500
Canal IS
Dunduwa
26 Dang 1250 2046 500 1527 200 300 50 0
IS
Chaurjaha
27 Rukum 600 1200 600 500 300 300 0 200
ri IS
28 Babai IS Bardiya 13500 18000 11000 6500 6500 3000 1500 1500
29 Rajapur IS Bardiya 13000 35000 13000 15000 7000 8000 2000 6000
Patharaiya
30 Kailali 2000 2000 2000 700 1000 400 50 0
a IS
Mohana
31 Kailali 2000 1000 1200 400 600 200 50 0
IS
Mahakali Kancha
32 11600 28000 11000 4500 9000 4500 200 4000
IS npur
-6-
Introduction
• l;FrfO k|0ffnLsf] ljsf; Pj+ Joj:yfkgdf hg;xeflutfd"ns k4ltnfO{ k|efjsf/L ?kdf nfu" ug{ pkef]Qmf
;+:yfnfO{ lhDd]jf/ / pQ/bfoL t'Nofpg] .
• l;FrfO If]qsf] k|efjsf/Ltf j[l4 ug{ ;+:yfut ;'b[9Ls/0f tyf hgzlQmsf] ljsf; / kl/rfng ug]{ .
• hg;+Vof j[l4, cfk|jf;g, hnjfo' kl/jt{g tyf hnhGo k|sf]ksf sf/0f kfgLsf ;|f]t tyf ltgsf] l;FrfOhGo
pkof]udf k/]sf] k|lts"n k|efjsf] cWoog u/L cg's'ng ;DaGwL sfo{s|dx? ;Frfng ug]{ .
• ljs]Gb|Ls/0fsf] cjwf/0ff cg'?k ;fgf l;FrfOsf] ljsf; / Joj:yfkgdf :yfgLo lgsfosf] Ifdtf / ;+nUgtf j[l4 ug]{ .
(www.doi.gov.np )
-7-
Irrigation and Drainage Engineering
-8-
Introduction
-9-
Irrigation and Drainage Engineering
-10-
Introduction
-11-
Irrigation and Drainage Engineering
Works may be carried out by construction contractors or by direct labor. In the former case, pre -
and post - construction surveys need to be carried out for measuring the completed quantities of
work. Quality control will include:
- Approving contractors' methods of working
- Supervising and testing earthworks, concrete works, etc.
- Sampling and testing materials
- Sampling and testing completed works
- Checking completed works for compliance with specified dimensions and tolerance
A socio - economic baseline study undertaken at the end of construction will be necessary, if the
impact of the scheme is to be assessed and used for monitoring and evaluation purposes.
Stage 6: Operation and maintenance
Once construction is complete, the works can be put into operation. At this stage, an operation and
maintenance manual is normally produced. This specifies procedures for operating the system under
various conditions, and provides schedules for maintenance of the works. An important aspect of
operation is performance evaluation and reporting. This allows feedback on planning, design and
construction implications for operation and maintenance to be incorporated into future solutions on
similar projects. Evaluation should not only focus on shortcomings, but should also highlight
positive aspects of performance.
Pre-fensibility study
Screning and ncorporation
into implementation
programmes
Feasbility study
Appraisal for financing
-12-
Introduction
With the introduction of irrigation, there have been many advantages, as compared to the total
dependence on rainfall. These may be enumerated as under:
• Increase in crop yield: The production of almost all types of crops can be increased by
providing the right amount of later at the right time, depending on its shape of growth. Such a
controlled supply of water is possible only through irrigation.
• Protection from famine: The availability of irrigation facilities in any region ensures
protection against failure of crops or famine due to drought. In regions without irrigation,
farmers have to depend only on rains for growing crops and since the rains may not provide
enough rainfall required for crop growing every year, the farmers are always faced with a risk.
• Cultivation of superior crops: With assured supply of water for irrigation, farmers may think
of cultivating superior variety of crops or even other crops which yield high return. Production
of these crops in rain-fed areas is not possible because even with the slight unavailability of
timely water, these crops would die and all the money invested would be wasted.
• Elimination of mixed cropping: In rain-fed areas, farmers have a tendency to cultivate more
than one type of crop in the same field such that even if one dies without the required amount
of water, at least he would get the yield of the other. However, this reduces the overall
production of the field. With assured water by irrigation, the farmer would go for only a single
variety of crop in one field at any time, which would increase the yield.
• Economic development: With assured irrigation, the farmers get higher returns by way of
crop production throughout the year, the government in turn, benefits from the tax collected
from the farmers in base of the irrigation facilities extended.
• Hydro power generation: Usually, in canal system of irrigation, there are drops or differences
in elevation of canal bed level at certain places. Although the drop may not be very high, this
difference in elevation can be used successfully to generate electricity for local use.
• Domestic and industrial water supply: Some water from the irrigation canals may be utilized
for domestic and industrial water supply for nearby areas. Compared to the irrigation water
need, the water requirement for domestic and industrial uses is rather small and does not affect
the total flow much.
• Raising of water table: Due to the excessive seepage of water through the bed and bank of the
canals the water table is in surrounding area may be raised which may constantly saturate the
root zone of the crop and soil may develop alkaline property which may be harmful to crops.
-13-
Irrigation and Drainage Engineering
• Formation of marshy land: Excessive seepage and leakage of water from the irrigation canal
may lead to formation of marshy land along the course of canal. These marshy land form the
colonies of mosquitoes which may be responsible for diseases.
• Dampness in weather: The temperature of Commanded area of an irrigation project may be
lowered considerably and the area may become damped. Due to dampness, the people residing
around the area may suffer from cold, cough and other such diseases originating from dampness.
• Loss of valuable land: Valuable land may get submerged when storage reservoir is formed by
constructing barrage or dams and some valuable land also may be lost while constructing
irrigation canals.
• Chances of soil erosion due to flood and over irrigation: Due to construction of the canal
the flood water may enter to the commanded area through the canal which may create soil
erosion and inundation in the area.
There are certain crops which have a longer period between their sowing and harvesting times which
extends from one crop season to the other. For example sugarcane is sown sometimes during February to
March and it is harvested sometimes during November to March of next year. Thus sugarcane takes
almost a full year of maturity covering both the crop seasons and hence it is classified as perennial crops.
Similarly cotton also requires relatively longer time for maturity. Cotton is sown in May or early June and
harvested in December or January next of year. Since cotton requires about eight months for maturity, it
is classified as eight month crop.
The above noted classification of the crops is based on the crop season, that is, on the sowing and
harvesting times of the crops. However the crops may also be classified on the basis of their irrigation
requirements as dry crop and wet crop. Dry crops are those crops which are ordinarily grown without
irrigation, but they utilized the moisture stored in the soil during rainfall. The dry crops are grown only in
those areas where the irrigation facilities are normally not available, however sometimes dry crops are
also irrigated, especially in the years of deficient rainfall, in which case these are known as irrigated dry
crop. On the other hand wet crops are those crops which cannot normally be grown without irrigation.
-14-
Introduction
Cropping Dates
Region Alternate
pattern Seeded Transplant/Plant Harvest
I Rice Spring Mar 1 Apr 1 July 1
Rice monsoon June 2 July 2 Nov 1
Wheat - Nov 2 Mar 1
Hills (<1000m II Maize - Mar 2 June 1
amsl) Rice Monsoon May 2 June 2 Oct 2
Wheat - Nov 2 Mar 1
III Rice June 1 July 1 Nov 1
Wheat - Nov 2 Mar 2
I Rice May 1 June 1 Oct 1
Wheat - Nov 2 Apr 1
Hills (1000m –
II Vegetable
2000m amsl)
Winter - Nov 2 Mar 1
Summer - Jul 1 Oct 2
I Rice Spring Apr 1 May 1 Aug 1
Rice Monsoon July 1 Aug 1 Nov 2
Wheat - Dec 1 Apr 2
II Rice June 1 July 1 Nov 1
Wheat - Nov 2 Mar 2
III Rice June 1 July 1 Nov 1
Wheat - Nov 2 Mar 1
Mungbean - Apr 1 June 1
IV Rice June 1 July 1 Nov 1
Potato - Nov 2 Apr 1
Terai
V Rice May 1 June 1 Sep 2
Maize - Oct 1 Nov 2
VI Jute - Mar 1 July 2
Rice July 1 Aug 1 Nov 2
VII Rice Apr 2 May 2 Sep 2
Pulses/ oilseed - Oct 1 Mar 2
VIII Sugarcane - Feb 1 Dec 2
IX Vegetables
Winter - Nov 2 Mar 1
Summer - July1 Oct 2
-15-
Irrigation and Drainage Engineering
Table 1.3:
1.3: Crop and their required water depth. (FAO, 2017)
C: Perennial crops
Cropping Intensity
Cropping intensity is defined the ratio of net area sown by different crops to the total cultivable (cropped)
area in a year. For example the cultivated area is 120 ha, now in a particular year if rice has been cropped
in 90 ha and wheat is cultivated after rice in 80 ha only, then the annual cropping intensity will be
90 80
× 100 + × 100 = 141.66%.
120 120
In Nepal cropping intensity varies from place to place. In Terai (plain area) the cropping intensity may be
about 200% (because two crops are grown in whole area in a year). In mountain areas the cropping
intensity may be only 100% or less (because only one crop may be grown in a year and not in whole
cultivated area). In valley floor of mid - hills like in Panchkhal valley the cropping intensity is 400%
(because 4 crops i.e. early paddy, monsoon paddy, potato and potato are grown in a year in whole
cultivable area).
-16-
Introduction
-17-
Irrigation and Drainage Engineering
-18-
Introduction
-19-
Irrigation and Drainage Engineering
-20-
Introduction
-21-
Irrigation and Drainage Engineering
-22-
Introduction
-23-
Irrigation and Drainage Engineering
The water distribution is quite uneven. The method is suitable for all medium of fine texture
soils. It has low cost and doesn’t interfere with tillage.
The disadvantages of the method are
– Wasteful use of water
– Non-uniform distribution of water
– Excessive soil erosion on steeper slopes
– Require drainage arrangement to reduce ponding
Supply
channel
Field channels 15 to 45m
Field channel
Field channel
Figure 1.5: Control Flooding
-24-
Introduction
Advantages Disadvantages
(i) Utilizes large water streams safely. (i) Required proper levelling
(ii) Requires less labour and time: low (ii) High initial cost
maintenance cost. (iv) A large supply of water is needed.
(iii) Provide uniform wetting and efficient
use of water.
Borders of Levee's
-25-
Irrigation and Drainage Engineering
Field channel
Field channel
-26-
Introduction
Supply
Channel
Field channel
Field channel
-27-
Irrigation and Drainage Engineering
permeable soils. Water is conveyed to the basin or preferably through small ditches
feeding individual basins. The merits and demerits of the method are broadly the same as
indicated for border irrigation method.
Basins Orchards
O O O
Field channel
O O O
2. Contour Farming
It is adapted to hilly areas with steep slopes and quickly falling contours. The land is divided into
longitudinal curved plots, the bunds of the plots following the contours. The irrigation water stored
higher up in some depressions flows between the bunds. The cultivation of crops is along the
contour lines instead of the usual down the slope. Contour cultivation reduces runoff and soil loss.
Bunds or levees
Terraces
-28-
Introduction
Advantages Disadvantages
• Low evaporation losses as only one half of • Not recommended for very light soil
irrigated land surface is wetted. having high infiltration capacity.
• It is possible to cultivate earlier, in heavy • Ditch may interfere with tillage.
soils.
• Usually expensive from the consideration
• Furrows serve as drainage ways for surface of time and labour cost.
runoff in areas of heavy rainfall. • Serious erosion hazard
• Especially suitable for crops like maize that • Adequate drainage need to be provided
are injured by contact with water.
•
• No wastage of land in field ditches.
• Fairly efficient in sue of water.
• Relatively cheap to construct and maintain.
• Efficient in its use of water.
Furrows
Field channel
Tail channel
-29-
Irrigation and Drainage Engineering
Advantages Disadvantages
• Sprinkler provides protection to small plants • Pressure head and sediment free water is
from wind damage and soil from blowing, required so not suitable at plain land.
when crops such as onions carrots, lettuce and • Initial cost is relatively high. And regular
other small seed crop are grown on dry operation is required due to frequently
organic soils the soil dries out quickly and clogging of system.
seed may be blown away or covered too
• Doesn’t suitable for paddy crop.
deeply for germination. When such plants are
small they are also easily damaged by • High air flowing area is affected during the
windblown soil particles. operation.
• Sprinklers provides protection against freezing • Due to circular spraying of water there is
injury to crops sprinkling is most successful chances of over irrigation and no irrigation at
against radiation frost. some area.
• Sprinkler can control the soil temperature
during period of high incoming radiation soil
temperature can rise upto 20o C above the
ambient air temperature.
-30-
Introduction
Advantages Disadvantages
• Only the root zone of the plant is supplied with • Frequent clogging of dripper; constant
water, with proper system management deep supervision may be needed in hill area where
percolation losses can be minimized. the spring water may carry sediment,
• Evaporation losses are minimized because biological or chemical matter.
only a portion of the ground area is wetted. • This type of irrigation may not be suitable to
some crops as salinity can develop as salts
• Effective weed control especially for ground
tend to accumulate along the fringes of the
area that is not wetted.
wetted surface strip.
• Reduced percolation and evaporation losses
• Root development may be restricted to the
resulting in greater economy of water use.
wetted soil volume near each emitter.
• Bacteria, fungi and other pests and diseases
• Not suitable for very closely seeded crops
that depend on the moist environment are
such as carrots, radishes etc.
reduced as above ground plant parts are
completely dry. • Initial cost can be more than overhead
systems.
• Fertilizer and nutrient loss is minimized due to
localized application and reduced leaching. • The sun can affect the tubes used for drip
irrigation, shortening their usable life.
• Water application efficiency is high if
managed correctly • For subsurface drip the irrigator cannot see the
water that is applied. This may lead to the
• Field levelling is not necessary.
farmer either applying too much water (low
• Fields with irregular shapes are easily efficiency) or an insufficient amount of water,
accommodated. this is particularly common for those with less
• Moisture within the root zone can be experience with drip irrigation.
maintained at field capacity. • Waste of water, time and harvest, if not
• Soil type plays less important role in installed properly. These systems require
frequency of irrigation. careful study of all the relevant factors like
• Soil erosion is lessened. land topography, soil, water, crop and agro-
• Weed growth is lessened. climatic conditions, and suitability of drip
irrigation system and its components.
• Water distribution is highly uniform,
controlled by output of each nozzle. • In lighter soils subsurface drip may be unable
to wet the soil surface for germination.
• Labor cost is less than other irrigation
Requires careful consideration of the
methods.
installation depth.
• Variation in supply can be regulated by
• The PVC pipes often suffer from rodent
regulating the valves and drippers.
damage, requiring replacement of the entire
• Foliage remains dry, reducing the risk of tube and increasing expenses.
disease.
• Drip irrigation systems cannot be used for
• Usually operated at lower pressure than other damage control by night frosts (like in the case
types of pressurized irrigation, reducing of sprinkler irrigation systems)
energy costs.
-31-
Irrigation and Drainage Engineering
Sustainability of sprinkler and drip irrigation systems in the Hills of Nepal (Hill Irrigation
Engineering, 1995)
• Sprinklers and drips need pressure head and sediment free water which is easily available in
the Hills of Nepal. In the hilly region the source of water is spring or small stream with small
catchment area which have relatively clean water.
• The cropping pattern in the hills are suitable for sprinkler and drip irrigation. Sprinkler can be
used for scattered crops like carrot, radish, wheat, mustard, millet etc. which are cultivated in
hills. Drip can be used for row crops like tomato, cabbage, cauliflower, chilly etc. which are
grown in hills of Nepal.
• These systems require network of pipe lines hence the construction of the canal and other
costly structures like headworks, river training works, drops, cross-drainages etc. as in canal
irrigation system, are not required and the construction cost for sprinkler and drip is
comparatively very low as well as operation and maintenance cost also reduced.
• Due to steep slope in hills the construction of canal is difficult and costly hence the
conveyance of water through the pipe system is most suitable in hilly region. The pipes can be
easily transported by yak, donkey and/or human effort.
• The flexible tubing, quick connecting couplers and sprinkler heads and lateral pipes can be
easily transported to remote areas hence sprinkler and drip are appropriate.
• In case of blockage which can be very frequent in system suing spring water sources, the
flexible tubing quick connecting couplers and sprinkler heads can be easily dismantled and
refitted after cleaning. Hence operation and maintenance cost is reduced.
• All movable components (the main pipe from the collection tank to the irrigated area will
usually be buried and anchored to the ground to prevent theft) can be removed for safety each
day at the end of irrigation. (Hills farmers of Nepal live several hours walking distance up hills
of their cultivated land.)
• Sprinkler and Drip can also be used on land with slope and undulations of the hilly terrain.
-32-
Introduction
• It must provide a basis for the preparation of short term investment programs that are
consistent with the long term strategy, based on identification and ranking of investment
opportunities and on assessment of urgent needs and of the implementation capabilities of
government institution.
• It must provide a sound database and planning methodology to facilitate regular updating, to
incorporate new data as they become available, to reflect changing policies and priorities, and
to reflect actual progress achieved in the irrigation sector.
The process of planning of an irrigation project can be divided into the following two stages:
(i) Preliminary planning (ii) Detailed planning
Preliminary plans, based on available information, are generally approximate but set the course for
detailed planning. Based on preliminary planning, the detailed measurements are taken and the detailed
plans are prepared. Obviously, detailed plans are more accurate. Alterations in the detailed plans may be
necessary at all stages of the project. The preparation of plans of an irrigation project in an undeveloped
region is a complicated task and needs the expertise of specialists in areas of engineering, agriculture, soil
science, and geology. The following are the main factors which must be determined accurately during the
planning stage of an irrigation project:
• Type of project and general plan of irrigation works,
• Location, extent and type of irrigable lands,
• Irrigation requirements for profitable crop production,
• Available water supplies for the project,
• Irrigable (culturable) areas which can be economically supplied with water,
• Types and locations of necessary engineering works,
• Needs for immediate and future drainage,
• Feasibility of hydroelectric power development,
• Cost of storage, irrigation, power, and drainage features,
• Evaluation of probable power, income, and indirect benefits,
• Method of financing the project construction,
• Desirable type of construction and development,
• Probable annual cost of water to the farmers,
• Cost of land preparations and farm distribution systems, and
• Feasible crops, costs of crop production, and probable crop returns.
Most of these elements of project planning are interrelated to some extent. Hence, the studies of the factors
listed above should be carried out concurrently so that necessary adjustments can be made promptly as
planning progresses. The preliminary planning of an irrigation project consists of collecting and analyzing
all available data for the current study, securing additional data needed for preparing preliminary plans for
major project features by limited field surveys, and determining the feasibility of the proposed development
-33-
Irrigation and Drainage Engineering
by making the preliminary study of major features in sufficient detail. While investigations for the
preliminary planning of irrigation projects should be conducted with minimum expenditure, the results of
the preliminary study must be sufficiently accurate. For preliminary investigations, hydrological studies can
be based on the records of stations in the vicinity of the proposed project site. Suitability of land for
cultivation purposes can be examined at representative sample areas. Foundation conditions at major
irrigation works can be determined from surface and a few subsurface explorations. For detailed planning,
accurate data on all aspects of the proposed irrigation project are required to work out the detailed plans and
designs of various engineering works and to determine their economic site locations. Physical data needed
for detailed planning are collected by topographic and location surveys, land and soil investigations and
geological explorations (surface as well as subsurface) at the sites of major engineering works. Results of
such surveys are suitably tabulated or plotted for convenient use in design offices and for planning further
field work, if necessary. Hydrological data are usually determined by extensive studies of all available
records and collecting additional data, if possible. Photographic records of pre-construction (and also during
construction) condition at locations of all engineering works and aerial surveys for dams and reservoir sites
must be supplemented by accurate ground surveys. Geological explorations are also needed at the sites of
dams, reservoirs, and major structures. Such data are useful in studies of water loss due to leakage and
foundation designs. Sources of suitable amounts of building material (such as earth material, concrete
aggregates, etc.) must be located and explored. In case of insufficient supplies at the site, additional sources
must be located. Having collected the required data for detailed planning, general plans for irrigation
structures are prepared. Such plans are dependent on topography, locations of irrigable areas, available water
sources, storage requirements and construction costs. There can be different types of possible feasible plans
for a particular project. Advantages and disadvantages of all such possible alternatives must be looked into before
arriving at the final plan for the project. Possibilities of using irrigation structures (dams and canal falls) for the
development of hydroelectric power should also be examined in project planning. (Asawa, 2005).
-34-
Introduction
Exercise 1
1. Define irrigation and drainage. What are the advantages and disadvantages of irrigation?
2. Describe the different types of irrigation methods with neat sketches.
3. Explain status and need of irrigation development in Nepal.
4. Explain methods of field irrigation and their suitability.
5. Define the importance of irrigation in Nepal.
6. What are the challenges and opportunities of irrigation development in Nepal?
7. Discuss about the suitability and appropriateness of drip and sprinkler irrigation system in Nepal.
8. What are the factors which must be determined during the planning stage of an irrigation project?
9. What do you understand by cropping pattern and cropping intensity?
10. Define different commanded area used in irrigation.
-35-
Irrigation and
and Drainage
Drainage Engineering
Engineering
CHAPTER
140 days
28 days 28 days 28 days 28 days 28 days
7.5cm 7.5cm 7.5cm 7.5cm 7.5cm
Number of watering required = 140/28 = 5
The depth of water required in 140 day = 5 × 7.5 = 37.5 cm
Hence ∆ for wheat = 37.5 cm.
Duty
The duty of water is defined as the number of hectares that can be irrigated by constant supply of water at
the rate of one cumecs (m3/sec) throughout the base period. It is expressed in hectares/ cumecs, and is
denoted by D. The duty of water is not constant, but it varies with various factors like soil condition,
methods of ploughing, methods of application of water etc.
For particular crop,
Area of land = 10 ha
Quantity of water = 5 m3/sec
10
Duty = = 2 ha/cumecs
5
Base Period
It is define as the period from the first to the last watering of the crop just before its maturity. It is denoted
by B and expressed in no of days.
-36-
Crop Water Requirement
Crop Period
Crop period is the total time that elapse between the sowing the crop and its harvesting. Thus crop period
represent the total time during which crop remains in the field. It is expressed in days.
Last watering
First watering Base period
Crop period
Seeding or sowing Harvesting
Let 1 cumecs of water be applied to this crop on the field for B days.
Now, the volume of water applied to this crop during B days (V) = 1 × (60 × 60 × 24) × B=86400 m3.
By definition of duty (D); one cumecs supplied for B days matures D hectare of land.
8.64B
This total depth of water is called delta (∆)= m
D
Example 2.2
Find the ∆ for sugarcane when its duty is 730 ha/cumec on the field and base period of crop 110 day.
Solution:
8.64B
We have the relation, ∆ = m
D
8.64 × 110
Now, = = 1.302m = 130.2 cm
730
Example 2.3:
Wheat requires total depth of water 1.230m. The duty at the field is 1400 ha/cumecs, Compute the
base period.
Solution:
-37-
Irrigation and
and Drainage
Drainage Engineering
Engineering
Example 2.4:
Three distributaries are used for irrigation. The details are given below. Find which one is more
efficient.
Discharge 15 m3/sec 20 m3/sec 25 m3/sec
C.C.A 15000 ha 25000 ha 30000 ha
Irrigation intensity 60% 80% 50%
Base period 200 days (cotton crop) 120 days (Wheat crop) 365 days (Sugarcane)
Solution:
1. Area under the cotton crop = 1500 × 0.6 = 9000 ha
900
Duty = = 600 ha/cumecs
15
2. Area under the wheat crop = 25000 × 0.80 = 20000 ha
20000
Duty = = 1000 ha/cumecs
25
3. Area under the sugar cane crop = 30000 × 0.50 = 15000 ha
15000
Duty = = 600 ha/cumecs
25
The distributary with a higher duty will be more efficient. So distributary II is more efficient.
-38-
Crop Water Requirement
-39-
Irrigation and
and Drainage
Drainage Engineering
Engineering
-40-
Crop Water Requirement
Deep percolation
Run off
Figure 2.1: Process of rainfall and effective rainfall for crops
Example 2.5
2.5
An irrigation project has 6000 Ha of CCA and ETo is 150 mm/day, effective rainfall is 30
mm/month and overall efficiency of the project is 30%. Calculate the irrigation demands in cumecs
for Rice Crop.
Solution:
Here,
CCA= 6000 Ha
ETo= 150mm/day
-41-
Irrigation and
and Drainage
Drainage Engineering
Engineering
-42-
Crop Water Requirement
Soil Texture
This refers to the relative sizes of soil particles in a given soil. According to their sizes, soil particles are
grouped into gravel, sand, silt and day. The relative proportions of sand, silt and clay is a soil mass
determines the soil texture. Figure 2.3 presents the textural classification of 12 main classes as identified
by the US department of agriculture, which is also followed in Nepal.
According to textural gradations a soil may be broadly classified as:
• Open or light textural soils: these are mainly coarse or sandy with low content of silt and clay.
• Medium textured soils: these contain sand, silt and clay in sizeable proportions, like loamy soil.
• Tight or heavy textured soils: these contain high proportion of clay.
-44-
Crop Water Requirement
-45-
Irrigation and
and Drainage
Drainage Engineering
Engineering
Field Capacity
Non available
moisture
Time
-46-
Crop Water Requirement
• Soil infiltration rate- how quickly the water is absorbed by the soil, the rate of which also decreases
as the soil becomes wetter, also often expressed in inches or mm per hour.
• Slope (topography) of the land being irrigated as this affects how quickly runoff occurs, often
expressed as a percentage, i.e. distance of fall divided by 100 units of horizontal distance (1 m of fall
per 100m would be 1%).
• Soil available water capacity, expressed in units of water per unit of soil, i.e. inches of water per foot of soil.
• Effective rooting depth of the plants to be watered, which affects how much water can be stored in
the soil and made available to the plants.
• Amount of allowable moisture stress which may be placed on the plant. For high value vegetable
crops, this may mean no allowable stress, while for a lawn some stress would be allowable, since the
goal would not be to maximize production, but merely to keep the lawn green and healthy.
• Timing to avoid interfering with other activities such as sporting events, holidays, lawn
maintenance, or crop harvesting.
Irrigation interval
FC
Moisture Content
RAM
PWP
OMC = FC – RAM
Time
The frequency of irrigation should be worked out in advance so that it can be applied in proper intervals.
The frequency of irrigation may be ascertained by the following expressions
-47-
Irrigation and
and Drainage
Drainage Engineering
Engineering
γs × d γs
Depth of water to be applied in each watering = × [FC – OMC] = × d × RAM
γw γw
Here FC stands for Field Capacity and OMC stands for Optimum moisture Content and d is root zone depth.
Example 2.6
The field capacity of a certain soil is 20% and its apparent specific gravity is 1.6. Before applying
irrigation water, a wet sample of soil was taken and its mass was found as 150 gm. The same sample
weighed as 136 gm after oven drying. Determine the depth of water that must be applied to irrigate
the soil to a depth of 0.9m.
Solution:
150 – 136
Moisture content before irrigation = × 100 = 10.29%
136
∴ Depth of water required to bring the moisture up to field capacity
γd
= × d [FC - Moisture content before irrigation]
γw
= 1.6 × 0.9 [0.2 – 0.1029]
= 0.14m = 140 mm.
Example 2.7
2.7
During a particular stage of the growth of a crop, consumptive use of water is 2.8 mm/day.
Determine the interval in days between irrigations, and depth of water to be applied when the
amount of water available in the soil is:
(i) 25%, (ii) 50%, (iii) 75% (iv) 0% of the maximum depth of available water in the root
zone which is 80mm. assume irrigation efficiency to be 65%. Field Capacity
Solution:
80 × (1 – 0.25)
(i) Frequency of irrigation = = 21.43 days = 21 days (say)
2.8
80 × (1 – 0.25)
(ii) Depth of water to be applied = = 92.31 mm = 93.00 mm (say)
0.65
Other calculations have been shown in the following table:
Amount of soil moisture depleted to
25% 50% 75% 0%
-48-
Crop Water Requirement
Example 2.8
2.8:
After how many days will supply water to soil in order to ensure sufficient irrigation of the given
crop if,
i. Field capacity of the soil= 28%
ii. Permanent wilting point= 13%
iii. Dry density of soil=1.3 gm/cc
iv. Effective depth of root zone=70 cm
v. Daily consumptive use of water for the given crop=12mm
Solution:
Available moisture = Field Capacity – Permanent wilting point
= 28% – 13% = 15%
Assume that Readily Available Moisture = 80% of Available Moisture
RAM = 0.8 × 15% =12%
Optimum moisture = 28% –12% = 16%
It means that the moisture will be filled by irrigation between 16% and 28%.
γd
Depth of water stored in the root zone between these two limits = × d × (FC – OMC)
γw
1.3
= × 0.7 × (0.28 – 0.16) = 10.92 cm
1
Here, water available for Evapotranspiration =10.92 cm.
Given that; 1.2 cm of water will be utilized by the plant in 1 day.
1 × 10.92
10.92 cm of water will be utilized by the plant in = = 9.1 days ≈ 9 days
1.2
Hence, after 9 days, water should be supplied to the given crop.
Example 2.9
2.9:
Find the field capacity of a soil for the following data:
(i) Depth of root zone = 2m
(ii) Existing water content = 5%
(iii) Dry density of soil = 1500 kg/m3
(iv) Water applied to the soil = 600 m3
(v) Water lost due to Evaporation and Deep Percolation =10%
(vi) Area of land irrigated = 900 m2
Solution:
Total water applied = 600 m3
Loss of water = 10%
Water retained in the soil = 600 × 90/100 = 540 m3
-49-
Irrigation and
and Drainage
Drainage Engineering
Engineering
-50-
Crop Water Requirement
-51-
Irrigation and
and Drainage
Drainage Engineering
Engineering
-52-
Crop Water Requirement
Solution:
Wf
(i) Water Conveyance efficiency ηc = × 100%
Wr
Wf = 110lps
Wr = 125 lps
ηc = 80%
Ws
(ii) Water application efficiency ηa = × 100%
Wf
2460
Now, water application efficiency = × 100% = 85.4%
2880
Ws
(iii) Water storage efficiency ηs = × 100%
Ww
Additional water requirement in the root zone = 34 – 17 =17 cm = 0.17m × 1.6 × 104 m2 = 2720 m3
2460
Water storage efficiency = × 100%
2720
= 1 –
Average Deviation
× 100%
Average Depth Applied
1.7+1.3
D = Mean depth of water stored in the root zone = =1.5m
2
ηd = 1 –
0.2
× 100% = 86.66%
1.5
-53-
Irrigation and
and Drainage
Drainage Engineering
Engineering
-54-
Crop Water Requirement
Since both the crop has same season, design discharge = QA + QB = 1.13 m3/sec
Example 2.13
2.13:
13:
The culturable commanded area for a distributary channel is 10,000 hectares. The intensity of
irrigation is 30 per cent for wheat and 15 per cent for rice. The kor period for wheat is 4 weeks, and
for rice 3 weeks. Kor watering depths for wheat and rice are 135 mm and 190 mm, respectively.
Estimate the outlet discharge.
-55-
Irrigation and
and Drainage
Drainage Engineering
Engineering
Solution:
Since the water demands for wheat and rice are at different times, these are not cumulative.
Therefore, the distributary channel should be designed for the larger of the two discharges i.e.
1.7m3/sec. The above calculations exclude channel losses and the water requirement of other major
crops during their kor period.
Example 2.14
2.14:
With the following data, FC = 80%, PWP = 35%, root depth= 60 cm, dry density of soil = 1.58
gm/cc, ETc = 5 mm/ day, application efficiency=80%, Conveyance loss = 55% and Distribution
loss=65%. Calculate,
i. Available moisture content
ii. Readily available moisture content
iii. Depth of irrigation at the outlet of the field.
iv. Irrigation interval
v. Irrigation requirement at the headwork.
Solution:
i. Available moisture content (AMC) = FC – PWP = 45%
ii. Readily available moisture content (RAM)
Assume RAM = 80% of AMC
Then, RAM = 0.8 × 45%= 36%
γd
iii. Depth of water available for consumptive use = × d × RAM
γw
1.5
= × 0.6 × 0.36 = 0.324m = 324mm
1
324mm 324mm
Depth of water required at the out let of the field= = = 405mm
Application Efficiency 0.8
324 324
iv. Irrigation interval= = = 64.8 days adopt 64 days
ETc 5
405mm
v. Irrigation water required at head work = = 2571.42 mm
0.45 × 0.35
-56-
Crop Water Requirement
Example 2.15
2.15:
Table below gives the necessary data about the crop, duty of water and the area under each crop
Commanded by a canal taking off from a storage reservoir. Taking a time factor for the canal to be
12/20, calculate the discharge required at the head of the canal. If the capacity factor is 0.8,
determine the design discharge.
Duty of water at the head of the
Crop Base Period (days) Area (ha)
canal (ha/cumecs)
Sugarcane 320 900 580
Overlap for sugarcane in 90 150 580
hot weather
Wheat (winter) 120 750 1600
Rice (summer) 120 600 2000
Vegetable (hot weather) 120 320 600
Solution:
Here,
900
Discharge required for sugarcane = = 1.552 m3/sec
580
150
Discharge required for overlapping sugarcane = = 0.259 m3/sec
580
750
Discharge required for wheat = = 0.469 m3/sec
1600
600
Discharge required for rice = = 0.3 m3/sec
2000
320
Discharge required for vegetable = = 0.533 m3/sec
600
Since sugarcane has a base period of 320 days, it will required water during winter, summer and hot
weather. Thus
Discharge required in winter = 1.552+0.469 = 2.021 m3/sec
Discharge required in summer = 1.552+0.3 = 1.852 m3/sec
Discharge required in hot weather =1.552 + 0.259 + 0.533 = 2.344 m3/sec
Out of three demands the maximum demand is 2.344 m3/sec which is during the hot weather.
The time – factor is the ratio of the number of days the canal has actually run to the number of days
the canal was supposed to run. In this case time factor is 12/20.
Discharge required at the head of the canal = 2.344 × 20/12= 3.907 m3/sec
Mean dischaege required 3.907
Design discharge = = = 4884 m3/sec
Capacity factor 0.8
-57-
Irrigation and
and Drainage
Drainage Engineering
Engineering
Example 2.16
2.16:
The base period, intensity of irrigation & duty of various crops under a canal irrigation system are
given in the table below. Find the reservoir capacity if the canal losses are 18% and reservoir losses
are 14%.
Crop Base periods (days) Duty at the field (ha/Cumecs) Area under the crop (hectares)
-59-
Irrigation and
and Drainage
Drainage Engineering
Engineering
Irrigation requirements
Example 2.19
Wheat is to be grown n field having a field capacity equal to 27% and the permanent wilting point
15.13%. Find the storage capacity is 80cm depth of soil, if the dry unit weight of the soil is
1.58m/cc. If the irrigation water s to be supplied when the average soil moisture falls to 18%, find
the water depth required to be supplied to field if the field application efficiency is 80%. What is the
amount of water needed at the canal outlet if the water lost in the water course and the field channel
is 15% of the outlet discharged?
Solution:
(i) Maximum storage capacity = Available moisture
γd.d
= [FC – PWP]
γw
1.5 × 80
= [0.27 – 0.13]
1
= 16.8 cm
1.5 × 80
(ii) Depth of irrigation water = [FC – OMC]
1
1.5 × 80
= [0.27 – 0.18]
1
10.8
(iii) Field irrigation requirement = = 13.5 cm
0.8
The consumptive use requirements of a crop are 0.2 cm/day for days 1 to 15, 0.3 cm/day for days 16
to 40, 0.5 cm/day for days 41 to 50 and 0.1 cm/day for days 51 to 55. Effective rainfall of 3.5 cm,
distributed uniformly during the 36th and 45th days (both inclusive) is predicted. Compute the total
quantity of water (in cu. m) to be delivered to a 50 hectares area for the whole crop season with a pre
- sowing requirement of 5 cm of water.
-60-
Crop Water Requirement
Solution:
Water Requirements per hectare
15 × 0.2
(i) 1 to 15 days i.e. 15 days @ 0.2 cm/day = × 104 = 300 m3
100
25 × 0.3
(ii) 16 to 40 days i.e. 25 days @ 0.3 cm/day = × 104 = 750 m3
100
10 × 0.5
(iii) 41 to 50 days i.e. 10 days @ 0.5 cm/day = × 104 = 500 m3
100
5 × 0.1
(iv) 51 to 55 days i.e. 5 days @ 0.1 cm/day = × 104 = 50 m3
100
5
Pre - sowing Requirement = × 104 = 500 m3
100
Total = 2100 m3
3.5
Effective rainfall/ hectare during 36th and 45th day (i.e. 10 days)= × 104 = 350 m3
100
Net water quantity to be delivered per hectare = 2100 – 350 = 1750 m3
Now, Total quantity of water to be delivered to 50 hectares = 50 × 1750 = 87500 m3
Exercise
1. Define Delta, Duty, base period, and crop period. Establish a relationship between duty and delta.
2. Write down the steps for calculating irrigation requirement for Rice crop.
3. Explain all types of irrigation efficiencies and Project efficiency.
4. Write down the methods to calculate Crop water requirement using Penman’s method.
5. Explain Operational water requirement for paddy crops.
6. Explain evaporation and seepage losses in a canal.
7. Explain steps of irrigation water requirement for rice and wheat.
8. Define Soil moisture irrigation relationship with neat sketches.
9. Explain depth and frequency of Irrigation.
10. Explain how to estimate the design discharge for canal.
11. Describe different calculation methods of reference crop evapo-transpiration.
12. What do you understand by crop coefficient? What are the factors that affect the value of crop coefficient?
13. Calculate the optimum soil moisture and permanent wilting point of the silty loam soil, for following data:
Density of soil =1.38 gm/cm3; Depth of the irrigation= 6.15 cm; Field capacity=22.6%; Depth of
root cone= 95 cm; Available moisture holding capacity= 12.36 cm.
14. If FC = 35cm/m; PWP = 15cm/m; root depth = 90cm; soil density = 1.5 gm/cc; Etc = 5 mm/day;
application efficiency = 60% and RAM = 80% of AMC, than calculate:
-61-
Irrigation and
and Drainage
Drainage Engineering
Engineering
-62-
Canal Irrigation System
System
CHAPTER
-63-
Irrigation and Drainage Engineering
HFL
Canal
(b)
Canal
River
(c)
Canal
(a)
Figure 3.1: Nature of sources of supply
2. Based on their function (Purpose)
(i) Irrigation canal
The canal which is constructed to carry water from the sources to the agricultural land for the
purpose of irrigation is known as irrigation canal.
(ii) Navigation canal
The canal which is constructed for the purpose of inland navigation is known as navigation
canal. This type of canal is also utilized for irrigation.
(iii) Power canal
The canal which is constructed to supply water with very high force to the hydroelectric power station
for the purpose of moving turbine to generate electric power is known as power canal or hydel canal.
(iv) Feeder canals
The canal which is constructed to feed another canal or river for the purpose of irrigation or
navigation is known as feeder canal.
3. Based on carrying capacity
(i) Main canal
The main canal takes its supplies directly from the river through the head regulator and acts as
a feeder canal supplying water to branch canals and major distributaries. Usually, direct
irrigation is not carried out from the main canal.
(ii) Branch canal
Branch canal take their supplies from the main canal. Branch canals generally carry a discharge
higher than 5 m3/sec and acts as feeder canals for major and minor distributaries. Large
branches are rarely used for direct irrigation. However, outlets are provided on smaller
branches for direct irrigation.
-64-
Canal Irrigation System
System
(iii) Major distributary
Major distributary carry 0.25 m3/sec to 5 m3/sec discharge. These distributaries take their
supplies generally from the branch canal and sometimes from the main canal. The distributaries
feed either watercourses through outlets or minor distributaries.
(iv) Minor distributary
Minor distributaries are small canals which carry a discharge less than 0.25 m3/sec and feed the
water courses for irrigation. They generally take their supplies from major distributaries or
branch canals and rarely form the main canals.
(v) Water courses
A water course is a small channel which takes its supplies from an irrigation channel (generally
distributaries) through an outlet and carries water to the various parts of the area to be irrigated
through the outlet.
River
Main Canal
Branch canal
Water course
Distributaries
4. Based on alignment
Depending upon the alignment, the canals are designated as
a. Ridge or watershed canal
b. Contour canal
c. Side slope canal
(i) Ridge or water shed canal
The canal which is aligned along the ridge line (watershed line) is known as ridge canal or
watershed canal. The advantage of this type of canal is that it can irrigate the areas on both
sides. Again there is no possibility of crossing any natural drainage and hence no cross-
drainage work is necessary.
-65-
Irrigation and Drainage Engineering
(ii) Contour canal
The canal which is aligned approximately parallel to the contour lines is known as contour
canal. This canal can irrigate the areas on one side only. This canal may cross natural drainage
and hence cross- drainage works are necessary.
(iii) Side slope canal
The canal which is aligned approximately at right angle to the contour lines is known as side
slope canal. It can irrigate the areas on one side only. Again, it doesn’t cross any natural
drainage and hence the cross drainage works are not necessary.
1302
1298
1294
1290
-66-
Canal Irrigation System
System
6. Based on financial output
(i) Productive canal
It is one which earns revenue to the nation.
(ii) Protective canal
It is one which is constructed with an idea of saving a particular region from famine.
-67-
Irrigation and Drainage Engineering
3.3 Selection of Alignment of Canal
Desirable locations for irrigation canals on any gravity project, their cross-sectional designs and
construction costs are governed mainly by topographic and geologic conditions along different routes of
the cultivable lands. Main canals must convey water to the higher elevations of the cultivable area.
Branch canals and distributaries convey water to different parts of the irrigable areas.
On projects where land slopes are relatively flat and uniform, it is advantageous to align channels on the
watershed of the areas to be irrigated. The natural limits of commanded of such irrigation channels would be
the drainages on either side of the channel. Aligning a canal (main, branch as well as distributary) on the
watershed ensures gravity irrigation on both sides of the canal. Besides, the drainage flows away from the
watershed and, hence, no drainage can cross a canal aligned on the watershed. Thus, a canal aligned on the
watershed saves the cost of construction of cross-drainage structures. However, the main canal has to be
taken off from a river which is the lowest point in the cross-section, and this canal must mount the watershed
in as short a distance as possible. Ground slope in the head reaches of a canal is much higher than the
required canal bed slope and, hence, the canal needs only a short distance to mount the watershed.
In general following points should be kept in mind while marking the tentative alignment of a canal:
• The alignment should not pass through the valuable lands, religious places, villages etc. to
avoid unnecessary compensation and unwanted conflict.
• The alignment should be short as far as possible, but to make it short the alignment should not
be taken through the area where irrigation is not at all possible.
• The alignment should be straight as far as possible.
• If the curve is unavoidable in the alignment, then it should be provided according to IS 5968-1970
Some references are given in the following table:
Discharge (m3/sec) Radius (m)
80 – 100 1200 – 1500
30 – 80 800 – 1000
15 – 30 400 – 600
5 – 15 100 – 150
• The alignment should cross the natural stream, drainage etc approximately at right angles. At the
crossing point, the width of the drainage should be minimum and the banks should be well defined.
• The alignment should not involve heavy cutting or banking. It is preferable if balancing depth
of cutting and banking may be achieved.
• The alignment along the ridge line or watershed line is very good as the watershed canal can
irrigate the areas on both sides. Moreover, the cross drainage works may be avoided.
• The alignment should be such that the maximum area may be irrigated with minimum length of canal.
• The alignment should not pass through the marshy land or water logged area, because the canal
may collapse due to heavy moisture in the area.
• The alignment should not pass through sandy soil as the percolation loss will be more and the
duty of canal will be less.
-68-
Canal Irrigation System
System
3.4 Alluvial and Non-alluvial canals
1. Alluvial canals
The soil which is formed by transportation and deposition of silt through the agency of water, over a
course of time is called the alluvial soil. The canals when excavated through such soils are called
alluvial canals. Canal irrigation (direct irrigation using a weir or a barrage) is generally preferred in
such areas, as compared to the storage irrigation (i.e by using a dam).
2. Non alluvial canals
The soil which is formed by disintegration of rock formation is known as non – alluvial soil. It has an
uneven topography, and hard foundations are generally available. The rivers, passing through such
areas, have no tendency to shift their courses, and they do not pose much problems for designing
irrigation structures on them. Canals, passing through such areas are called non – alluvial canals.
Berm
Filling
Bed Level
Figure 3.5: Elements of canal
A typical and most desired section of a canal is shown in Figure 3.5. This section is partly in cutting and
partly in filling, and aims at balancing the quantity of earth work in excavation with that in filling.
Sometimes, when the ground level is above the top of the bank, the entire canal section will have to be
built in cutting, and it is called canal in cutting.
And if the ground level is below the bed level of canal, the entire section will be in filling and it is called
canal in filling.
1. Side slopes
Side slopes in an unlined channel depend mainly on the nature of geological formations through
which the channel is excavated. Side slopes in an unlined channel should be flatter than the angle of
repose of saturated bank soil so that portions of side slopes will not slough into the channel. For
similar conditions, the prevalent practice is to keep side slopes flatter for channels in filling than the
side slopes for channels in cutting. However, there is no justification for this practice as a natural
earth fill should not behave differently from an earth fill compacted sufficiently and having the same
characteristics as those of the natural earth fill. Initially, flatter slopes are provided for reasons of
stability. Later, with the deposition of fine sediments, the side slopes become steeper and attain a
value of (1/2) H : 1V irrespective of the initial side slope provided. These steeper side slopes are
stable and the design is usually based on these slopes. Side slopes for unlined channels in different
types of soil, generally recommended are given in Table 3.1.
-69-
Irrigation and Drainage Engineering
Table 3:1 Side slope for unlined channel
d2 h
d1 r1:1
X
Figure 3.6: Berm
For usual side slopes of 1.5:1(H:V) (in filling) and 1:1(H:V) (in cutting), a berm of width equal to
half the depth of cutting will make the horizontal distance between the bed and top of the bank (i.e.,
XY) equal to 1.5 times the height of the top of the bank with respect to the channel bed. As a result
of silting on berm, an impervious lining is formed on the banks. This helps in reduction of seepage
losses. In addition, the berm protects the banks against breaches and the eroding action of waves.
These berms break the flow of rain water down the bank slope and, thus, prevent guttering. An
additional berm may also be provided in channel sections which are in deep cutting.
-70-
Canal Irrigation System
System
3. Freeboard
Freeboard is the vertical distance from the water surface at full supply level to the top of bank.
Freeboard provides the margin of safety against overtopping of the banks due to sudden rise in the
water surface of a channel on account of improper operation of gates at the head regulator, accidents
in operation, wave action, landslides, and inflow during heavy rainfall. The excessive growth of
vegetation or accumulation of sediment deposits may also result in the gradual rise of water surface
levels above the design levels. Design of channels should specify adequate freeboards to prevent
overtopping of the banks during sudden rises in water surface. Adequate freeboard would depend on
dimensions of the flow section, flow condition, bank material, method of construction of banks, and
resulting damage due to failure of banks.
Freeboard in unlined channels vary from about 0.3 m in small channels to about 2 m in large
channels. For channels of intermediate size, freeboard is sometimes estimated by adding 0.3 m to
one quarter of the flow depth.
Table 3:2 Freeboard in irrigation canal (Singh, 1988)
Bed width (m) Discharge (m3/sec) Freeboard (m)
Less than 1.0 - 0.30
1 to 1.5 - 0.35
Greater than 1.5 Less than 3.0 0.45
- 3 to 30 0.60
- 30 to 60 0.75
- Greater than 60 0.90
USBR has proposed the following formula for the estimation of freeboard F (in meter) in canals.
F = CD
Where, C is a constant varying from 0.45 (for discharge up to 0.07 m3/sec) to 0.76 (for discharge
greater than 85 m3/sec) and D is the water depth in meter.
4. Canal Banks
Canal banks hold water within the water section of a channel. Suitable bank dimensions of an earth
channel depend on size of channels, height of water surface above natural ground, amount and
nature of excavated earth available for bank construction, and need of inspection roads along the
channel. Bank widths at all elevations must provide stability against water pressure at the sides of
the channel section. They should also keep percolating water below ground level outside the banks
and prevent piping of bank materials.
A canal bank should be of such width that there is a minimum cover of 0.5 m above the saturation
line. For large embankments of major canal projects, the position of the saturation line is determined
as in case of earth dams and the stability of slope is computed using principles of soil mechanics.
The saturation line for small embankments is drawn as a straight line from the point where full
supply level meets the bank. The slope of the saturation line, i.e., the hydraulic gradient, may vary
from 4H: 1V for relatively impermeable material (such as ordinary loam soil) to 10H: 1V for porous
sand and gravel. For clayey soils, the hydraulic gradient may be steeper than 4(H): 1(V). If the bank
section does not provide a minimum cover of 0.5 m above the saturation line, a counter berm, shown
in Figure. 3.7 (b), is provided. Alternatively, the outer slope of the bank is flattened.
-71-
Irrigation and Drainage Engineering
A Dowel or Dowla is provided on the side of a service road between the service road and
channel. The top of the dowel is kept above the FSL in the channel the Dowel are provided as a
measure of safety for automobile driven on the service road. They acts as a kerb on the side of
the road way towards the canal.
When the quantity of earth obtained from excavation or cutting is deposited near the cutting in
the form of bank is known as spoil bank.
When the earth work in filling exceeds excavated quantity at particular section borrow pit are
required to make good requirement of filling.
-72-
Canal Irrigation System
System
t
n:1 FSL
h−y h−y n:1
z:1
Filling z:1 y
D h
B
Figure 3.8: Balancing depth
Let h be the height of bank above the channel bed
D be the full supply depth
B be the bed width of channel
Y be the balancing depth
t be the top width of canal
n:1 be the side slope of the channel in filling
z:1 be the side slope of the channel in cutting.
Thus, area of cutting = By + zy2
Area of filling = 2[ t (h – y) + n (h – y)2]
Equating area of cutting and filling we get
By + zy2 = 2[ t (h – y) + n (h – y)2]
y2 (2n – z) – (B + 4nh + 2t) y + h(2t + 2nh) = 0
Solving this equation and determine balancing depth.
The method of finding the balancing depth is described here.
Example 3.1
Find the balancing depth for canal section having the following data.
Base width of canal B = 8m
Side slope in cutting z = 1:1
Side slope in banking n = 1.5:1
Top width of bank t = 3m
Total height of canal = 3m
3m 3m
1.5:1 FSL
3−y 3−y 1.5:1
8 + 2d
15m 1:1 15m
1:1 y 3
8m
-73-
Irrigation and Drainage Engineering
Solution:
From figure:
Equating the area of cutting and filling we get
(B + zy) y = 2 [t + n (h – y)] (h – y)
Substituting the values and we get
(8 + y) = 2 [3 + 1.5 (3 – y)] (3 – y)
Solving we get, y= 1.92m
Hence the balancing depth is 1.92m.
Ridge line
Main canal
River
B
M
River
B = Branches
D = Distributaries
M = Minors
-74-
Canal Irrigation System
System
3.7 Methods of Water Distribution System
The objectives of the distribution system operation are to deliver the right amount of water to the right
place, at the right time to meet crop needs. Ideally, water should be distributed equitably among farmers
according to their needs. Irrigation systems in Nepal are generally of small to medium size, taking water
from rivers origination in the non – snow fed mountains. This results in large variation in the supply,
often with adequate supplies during the monsoon and insufficient water to feed the whole commanded
area between November and May. This makes distribution difficult, and the design of the distribution
system needs to be able to cope reasonably with large variations in the water available for delivery. In
many cases, where all year cropping is required, there will be little alternative other than to supplement
low river flows by groundwater abstraction, and to use this conjunctively with the available surface water.
Schemes fed from the larger rivers which have more reliable, perennial flows have other problems,
principally siltation. Flood damage can be a problem on all types of schemes. While silt and flooding are
best managed at the head of the system, the problem of low water availability has to be accommodated
throughout.
There are many types of distribution system which differ according to the requirements and constraints
placed on them. Some of the water distribution systems are as follows:
(i) On demand
(ii) Continuous flow
(iii) Scheduled
The advantages and disadvantages of some common types of distribution systems are summarized in
Table below.
Types Advantages Disadvantages
On – demand Farmers can take the water they Storage, high peak canal
want, when they want it. capacities and sophisticated
structures usually mean high cost.
Water is often wasted.
Continuous flow Simple to operate, minimal Farmers get the same flow
number of control structures regardless of what crop they are
needed. Well suited to come growing or the crop needs at the
crops, especially rice which time. Flows are often small, so
grows in puddled conditions. that losses are unacceptably high.
Scheduled Farmers receive water according Difficult to manage – requires a
to a schedule which takes account lot of calculation, canal operations
of crop type and growth stage and and cooperation between farmers.
thus meets (theoretical) crop Farmers perceived water needs
needs. are often different form
calculated/ delivered needs,
creating conflict.
-75-
Irrigation and Drainage Engineering
Some of the principal factors affecting distribution system are described in table below. (M.8 Distribution
systems, 1990)
Sources of water Schemes fed form one (usually surface) source are a
single entity with a canal hierarchy. Schemes fed
from multiple sources (e.g. groundwater) normally
comprise a number of discreet sub – systems.
-76-
Canal Irrigation System
System
Exercise 3:
Determine the balancing depth. Draw a neat x-section of the canal illustrating the various
dimensions and levels.
9. Draw the typical cross sections of canal in (i) Filling (ii) Cutting (iii) partial cutting & filling.
10. Explain the canal distribution system and water distribution system.
-77-
Irrigation and Drainage Engineering
CHAPTER
4 Design of Canal
4.1 Design Capacity of Canals
The design discharge of the main canal off taking from a diversion headwork is fixed so as to achieve the
optimum utilization of available water in the river during different parts of the year. The transit losses in
the canal are estimated to determine the discharge that will be available at the canal outlets. (Arora, 2011)
Knowing the available discharge, the cropping pattern and duty of water, the culturable Commanded area
can be worked out as follows:
1. Determine the water requirement of different crops for each month from the cropping pattern
and the consumptive use.
2. Determine the outlet discharge required for each month for a culturable Commanded area.
3. Estimate the discharge available in the river for each month.
Allowing for suitable transit losses, determine the discharge available at the outlets.
4. Determine the CCA which can be irrigated in each month from the available discharge found
in step 3 and the required outlet discharge found in step 2.
5. The minimum of CCA found in step 4 is the designed CCA of the canal.
6. Determine the head discharge from the designed CCA and the maximum outlet discharge in
step 2.
The above procedure is explained below with an example:
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Outlet
discharge
required for 15.1 9.2 13.5 8.6 11.1 17.5 20.6 27.0 19.2 18.4 16.2 14.9
1 lakh ha
(m3/sec)
Available
discharge 65 59 56.5 54.2 65.2 108.2 201 310.2 210 130 110 85
(m3/sec)
C.C.A in
4.3 6.4 4.19 6.3 5.87 6.18 9.76 11.49 10.94 7.07 6.79 5.70
Lakh ha
Maximum outlet discharge required (In Aug.) = 27.00 cumecs for 1 lakh ha.
Designed C.C.A. (In March) = 4.19 Lakh ha.
Assume transit losses = 30%
27.0 × 4.19
Head discharge of main canal= = 161.61 cumecs.
0.7
-78-
Design of Canal
-79-
Irrigation and Drainage Engineering
P1
P2
τo
W
1
2
L
Figure 4.1: Forces Acting on a Flowing Fluid
Since the flow is uniform there is no acceleration, sum of forces acting in the flow direction must be zero
(flow direction be x).
∑F x =0
P1 - P2 + W sinθ - τ0 × wetted area = 0
P1 = P2 (Equal and opposite hydrostatic pressure force).
W sinθ = τ0 ×P × L
W sinθ
τ0 =
P×L
-80-
Design of Canal
γ A × L × S0
τ0 = For small angle sinθ = tanθ = slope of the bed.
P×L
τ0 = γ R S0 . . . 4.1
Equation 4.1 represents the equation for the unit tractive force or some time it is called normal shear
stress. In a wide open channel, the hydraulic radius is equal to the depth of flow y: hence
τ0 = γ y S0
Unit tractive force in canal except for wide rectangle is no uniformly distributed along the wetted
perimeter. A typical distribution along with its pattern on unit tractive force acting on the bed and side
slops of the trapezoidal canal is shown in Figure 4.2. As an approximation for a trapezoidal channel τ0 at
the bottom be assumed to equal to γ y S0 , and along the side slope to be equal to 0.75 γ y S0 . Figure 4.3
shows maximum unit tractive force on sides and bottom of various canal sections.
y
4y
Figure 4.3: Maximum Unit Tractive Force on Sides and Bed Incipient Motion Condition
-81-
Irrigation and Drainage Engineering
Equation 4.1 is developed on the assumption that no any particle on the bed and banks are moving.
However, for the given configuration of channel section if we increase the shear stress the time comes
when the particles will just start to move. The shear stress at which the channel materials (particles) just
move from the stationary condition is called critical shear stress τc and fine motion is called incipient
motion or motion is impending. In such condition of motion the particle diameter (generally d60) on the
bed is called critical particle diameter.
The particle size is usually denoted by d. For the identification of a particular grain size distribution its
“percentage finer” value is used as sub index. The size is thus diving between equal weights of finer and
coarser particles in a sample. It is some time erroneously termed as “mean diameter”.
T = B + 2zy
Free surface
y
1
Ws cos θ θ
Ws Z
B
Figure 4.4: Trapezoidal channel section with forces
As shown in Figure 4.4, particles on the side slope of channel are less stable than those on the bed
with similar condition of flow. This is because the component of weight of submerged particles (Ws
sinθ) along the side slope tends to roll the material down the slope, thereby causing instability. If the
resultant of two forces (force of flowing fluid and Ws sinθ) are more than the resisting force the
erosion of canal slope may occur.
In the bottom of channel only the force of flowing fluid may scour the element. So bottom surface is
more safety for scour than side slope. If the resistance force is less than that force scour may occur.
So for designing mobile boundary channel the stability of side slope is the major concern.
Let’s calculate these forces for channel at side slope and bed. Consider a particle of projected area “a
“resting on the sloping side of a trapezoidal channel as shown in Figure 4.5. Let τs be the shear
stress on the side, which will just cause the particle to move and let τs be the shear stress on the bed
which will just cause the particle to move. Let Ws be the submerged weight of particle, θ be angle
of side slope and ϕ be the angle of internal friction (angle of repose, property of soil forming the
channel boundary)
-82-
Design of Canal
Flow
τs. a
Wssinθ R
τb.a
θ
Ws
Ws tan2θ
τs = cosθ tanφ 1- . . . 4.3
a tan2φ
Similarly, when motion of particle on the bed level is impending owing to the tractive force τb x a,
the following equation may be written (θ =00).
τb × a = Ws tan φ
Ws
τb = tanφ . . . 4.4
a
τs
Ratio of is called tractive force ratio K and it is very important factor for design mobile boundary
τb
channel.
τs tan2 θ
K= = cosθ 1- . . . 4.5
τb tan2Ф
sin2 θ
K= 1- . . . 4.6
sin2Ф
Equations 4-5 and 4-6 are mathematical identical. For given value of θ and ϕ we can calculate the
tractive force ratio K, and this is important factor for designing mobile boundary channel. Figure 4.6
gives the angle of repose with particle size.
-83-
Irrigation and Drainage Engineering
Figure 4.7: Reduction factor for critical shear stress for side slope
-84-
Design of Canal
The maximum tractive stresses or permissible tractive stresses on the bed and sides τmax.b and τmax.s
can be obtained for known values of B, y and z (bottom width, depth and side slope) from Figure
4.3. The design requires the determination of a section in which
τmax.s < τs ; τmax.b < τb; . . . 4.7
The design capacity of such channel can be obtained by using Manning’s coefficient in which the
rugosity coefficient is defined by Strickler’s equation as
d901/6
n= . . . 4.8
24
The design is usually carried out by using a trial and error process. The first step in the design of
mobile boundary channels by this method is to select an approximate channel section i.e. B/y ration
and z by experiences or from the design table given in the literature, collecting material forming the
channel boundary and determining the coefficients (angle of repose). With these data, the designer
investigates the section by applying tractive force analysis to ascertain probable stability by reaches
and to determine the minimum section that appears stable.
One thing it must be noted that for trapezoidal channel as already mention above, the maximum
tractive force on the sloping sides is always less than that on the bottom: hence, this force is the
controlling value in the analysis. The section dimension of channel is carried out for the maximum
tractive force on the sides; however, it is necessary to checking the proportioned dimensions for the
maximum unit tractive force on the bottom.
The tractive force method of designing mobile boundary channel is more rational, than the regime
theory, because it utilizes the laws governing sediment transport and resistance to flow. The regime
theory is purely empirical
2. Shield’s Tractive Force Theory
For particle purpose it is convenient to use Shield diagram for designing mobile boundary channel.
Shields combined expressions for the destabilizing forces, drag and lift, against weight or friction as
the stabilizing force into a general formula for the equilibrium of particles;
τ0 γ R S0
Cs = = . . . 4.9
(γs – γw)d
( ρs −ρw ) g d
Here Cs is the dimension Shields number, ρs and ρw are density of dry particle and density of water
and d is the diameter of the particle and generally consider as d50. According to Shields, magnitude
of the tractive force on the grain size depends on the fact whether the grain size outside or inside of
the laminar sub-layer. If the thickness of the laminar sub-layer δ is more than the d50 i.e., grain is
completely submerged in laminar sub-layer then tractive force on the grain depends on viscous or
laminar flow (case when δ/d50 < 1). If δ/d50 > 1, grain size remains outside the laminar sub-layer,
then tractive force depends on turbulent flow outside laminar sub – layer.
τ0
Thus, the tractive force is directly related to d50/δ, i.e., = . . . 4.10
(γs – γw) d
The equation of laminar sub-layer in boundary layer theory as given by Nikuradse’s experimental
data is (refer boundary layer for explanation):
µ
δ = 11.6 . . . 4.11
v*
-85-
Irrigation and Drainage Engineering
Where δ is the thickness of laminar sub-layer, µ is the kinematic viscosity of water and V* is the
shear velocity equal to
τ0
V* =
ρ . . . 4.12
µ
From equation 4.11 we can see that laminar sub-layer is directly proportional to . Or we rewrite
V*
this as:
1
δ ∞V*µ » dδ ∞ V*µ d . . . 4.13
τ0 V *d
∞
(γ s − γ w ) d ν
V* × d
Here Re* = µ is called particle Reynolds number or roughness Reynolds number
τ0
So it indicates that = f (Re*) . . . 4.14
(γs - γw)d
Plotting equation 4.13 on a log-log paper the well-known Shields curve (Figure 4.8) in sediment
transport theory is obtained. This curve was found by experiments, using particles of different
densities. It is therefore valid also for other materials than ordinary rock and other fluids than water.
-86-
Design of Canal
rises and becomes horizontal at about Re* ≈ 400. When Re*>400 than the value of
τ0
Cs = ≈0.06
(γs - γw) × d
Becomes independent of Re* i.e., flow is fully turbulent. Value of Cs below the curve indicates
stability against motion. Values on the curve indicate start of motion and are labeled critical Shields
number Cs.
The corresponding shear stress is labeled as critical shear stress τc. The diagram is made for uniform
sediments, but may be used for mixed sediments with good accuracy using d60 (60% finer) for d. For
practical use Cs =0.06 can be used for grain diameters larger than 1 mm. For gravel Bed Rivers or
rivers with coarse bed material the bed will not form. For gravel bed rivers or if the river bed is flat
the flow resistance can be estimated based on Strickler’s formula for the Manning’s number n as
(Lysne, Glocer, & Teskar, 2003):
d901/6
n= and d90 = (1.75 to 2.0) d60 . . . 4.15
24
Mittal and Swamee has worked out a general relation between τc and d which gives results within
+5% of the values given by Shild’s curve, for all values of d. The relation for water and soil of Ss =
2.65, is given by equation
0.409 d2mm
τc(N/m2) = 0.155 + . . . 4.16
1+0.177d2mm
Example 4.1:
Water flows at depth of 0.6m in a wide stream having a bed slope of 1 in 2500. The median
diameter of the sand bed is 1.0mm. Determine whether the soil grains are stationary or moving,
and comment as to whether the stream bed is scouring or non – scouring.
Solution:
Since the given size of bed particles is 1.0 mm, which is less than 6mm, we cannot use shield’s
equation, since Re* in this case will be less than 400. We will, therefore, use the general
equation by mittal and swamee as follows:
0.409 d2mm
τc(N/m2) = 0.155 +
1+0.177d2mm
0.409 × 12
= 0.155 + = 0.53 N/m2.
1+0.177 ×12
Also, we have
τ0 = γ R S0
=9810 × 0.6 × 1/2500 = 2.35 N/m2 which is greater than τc ,
Since τ0 > τc, the soil grain will move and scouring and sediment transport will occur.
-87-
Irrigation and Drainage Engineering
For incipient motion condition i.e., the shear stress has reached its critical values τc, let’s say
particle diameter also as critical diameter dcr. In this situation the expression for Cs would be:
τ0
Cs = ≥ 0.06 ⇒ τ 0 ≥ 0.06(γ s − γ w )d cr
(γ s − γ w ) × d
But τ =γ
0 w RS0, where R being the hydraulic radius and S0 is the bed slope.
γ w RS 0 R S0
d cr ≈ =
(γ s − γ w ) × 0.06 γ
0.06 s − 1
γw
γs
We know that γ is the specific gravity of the sediment ≈ 2.65
w
RS0 R S0 RS0
dcr ≈ = =
(2.65 −1) × 0.06 0.06×1.65 0.099
d cr ≈ 10 R S 0
For safety propose dcr = 11 RSo
Example 4.2
A canal is to be designed to carry a design discharge as 50 m3/sec. The slope of the canal is
1:1000 and passes through medium with mean particles as 50mm. Assuming a trapezoidal
section, determine the stable depth of canal assuming angle of repose of canal bed and side
particles as 360.
Solution:
Given Q = 50 m3/sec
S0= 1:1000
d= 50mm
Ф=360
Assume that side slope of the channel θ = 300 ( θ should be less than Ф)
sin2 θ
Calculate tractive force ratio K = 1–
sin2Ф
τs
= 0.525
τb
Minimum shear stress required to remove the grain on the side slope is
τs = 0.525τb
-88-
Design of Canal
P = B + 2y 1+z2 = B+10
d901/6
Manning’s coefficient n =
24
A 2.5 (B + 4.33)
R= =
P B + 10
-89-
Irrigation and Drainage Engineering
Example 4.3
Using tractive force approach, design a channel in alluvial soil for the following data:
(i) Discharge Q = 45 cumecs,
(ii) Bed slope = 1/4800
(iii) Manning's n = 0.0225,
(iv) Permissible tractive stress = 0.0035 kN/m2
Side slope = 0.5:1
Solution:
τc 0.0035
R= = = 1.713 m
γw × S 9.81 × 1/4800
1 2/3 1/2 1
V= R S = × 1.7132/3 × (1/4800)1/2 = 0.918 m/sec
n 00225
A = Q/V = 45 / 0.918 = 49 m2
P = A/R = 49/ 1.713 = 28.61 m
P = 28.61 = B + 2.236 D
A = 49 = BD + 0.5 D2
Solving these, we get D =1.94 m and B = 24.27 m
-90-
Design of Canal
Lined canal can made a range of velocities, as erosion in not an issue. However, for easy management of
water, the permissible velocities should be critical or sub - critical.
Bed width to water depth (B/D) ratio for trapezoidal canals
The recommended bed width and water depth (B/D) ratio for earthen trapezoidal canals are given in table
below:
Table 4.2: Recommended B/D ratio
The bed width should be wide enough to allow easy cleaning. A bed width of 0.2 - 0.25 m is considered
to be the minimum, as this still allows the cleaning of the canal with small tools such as a shovel. Lined
trapezoidal canals could have similar B/D ratios as given table.
The design procedure is as follows:
1. Assume suitable permissible velocity (non silting and non scouring). If the amount of silt
transport is low, it is recommended to assume higher side of maximum permissible velocity.
This will also increase the discharge.
2. Longitudinal or bed slope can be fixed out considering the topography of land through which
the channel has to pass.
3. Select Manning’s co – efficient based on the material lining on the bed and side slope. It can be
found in the literature.
4. Side slope of the channel z:1 (H:V) is to be assumed. It is recommended to select z =1.
-91-
Irrigation and Drainage Engineering
5. If B is the bottom width and y is the full supply depth, then cross - section area can be
calculated as (for trapezoidal channel section)
A = ( By + z y2) . . . (i)
6. Once discharge Q and velocity V are known, it means A is also known.
7. Using Manning’s formula write the equation in terms of V and B as
1 A 2/3 1/2
V= S . . . (ii)
n P
Here V, A, z, n and S are known. Unknown values are B and y, which can be found by solving
(i) and (ii).
8. Finally a free board is necessary to provide. Generally it is consider as 5% for low flow and
30% for high flow.
Free board of the channel is the vertical distance between full supply level to the top of the
bank. It prevents over toppling of bank when wave is produced due to the wind.
Example 4.4
4.4:
Design a rigid boundary irrigation channel laid on a slope of 0.0016 with discharge 9.1 m3/sec.
assume Manning’s n = 0.015 with permissible velocity 1.3 m/sec.
Solution:
Given, Q= 9.1 m3/sec, n = 0.015, S= 0.0016, V= 1.3 m/sec. and assuming side slope z = 0.5.
Q= AV
A= Q/V = 9.1/1.3 = 7.0 m2
Also A = (By + z y2) = 7 m2 . . . (i)
2
1 A 3 S1/2
V=
n B + 2y 1+0.52
2
1 7 3
1.3 = 0.00161/2
0.015 B + 2y 1+0.52
7
0.34 = . . . (ii)
(B + 2.236y)
Solving (i) and (ii)
y= 0.35m
b= 19.8m
Assume free board = 25% of y = 0.125m
Bottom width B = 19.8m
-92-
Design of Canal
-93-
Irrigation and Drainage Engineering
Case I:
Given Q, n, CVR and S
The procedure of designing alluvial channel by this method is as follows:
Assume a trial value of flow depth y
1. Determine the critical velocity V0 by using equation V0 = CVR x 0.55 y0.64
2. Determine area by dividing discharge by velocity A = Q/V0
3. Determine the channel cross section i.e. wetted perimeter.
4. Finally compute the actual mean velocity V that will prevail in the channel of this cross
section, by using Kutter’s formula, Manning’s formula etc.
a. Kutter’s equation
V = C R S0
1 0.00155
+ 23 +
n S
C=
0.00155 n
1 + (23 + )
S R
1 0.00155
+ 23 +
n S
Now, V = RS
0.00155 n
1 + (23 + )
S R
b. Mannings’ equation
1 2/3 1/2
V= R S
n
5. Repeat the calculation till the two values of velocities determine in step 2 and 5 are nearly the
same.
Case II
Given Q, n, CVR and B/D
i. Calculate A interms of D as indicated below.
Let, B/D = x (which is given)
B = Dx
Since A = BD + z D2
A = xD2 + zD2 = D2(x + z)
ii. Substitute the value of A from step 1 and the value of V from equation V0 = 0.55 x CVR x D0.64
in Q = A × V.
Q = D2(x + z) (0.55 CVR D0.64)
Solve for D;
In this equation Q, CVR , x and z are known. Hence D is determine.
-94-
Design of Canal
-95-
Irrigation and Drainage Engineering
Example 4.6
4.6:
Design an irrigation canal to carry a discharge of 5 cumecs. Assume Kutter rugosity n = 0.0225,
CVR = 1 and B/D= 3.24.
i. B/D = 3.24
A = BD + z D2 assume z = 0.5
A= D2(3.24 +0.5) = 3.74D2
ii. V0 = 0.55 CVR × D0.64
Q = A.V
5 cumecs = 3.74 D2 (0.55 × 1 × D0.64)
D = 1.40m
iii. B = 3.24x 1.40 = 4.54m
BD +zD2
R= = 0.956m
B + 2D 1 + z2
iv. V0 = 0.55 CVR x D0.64 = 0.682 m/sec.
1 0.00155
+ 23 +
n S
v. V= RS
0.00155 n
1 + (23 + )
S R
Where n = 0.0225; R =0.956 and, using calculator
s= 1/4000
Example 4.7
4.7
Design an irrigation channel to carry a discharge of 5 cumecs. Assume n = 0.0225 and critical
velocity ratio m = 1. The channel has a bed slope of 0.2m per kilometer.
Solution:
Step 1: Assume a trial depth of D = 1.0m
Step 2: V0 = 0.55 x m x D0.64 = 0.55 m/sec
Step 3: Area A = Q/v = 5/0.55 = 9.09 m2
Step 4: A = BD + D2/2
or, 9.09 = B × 1.0 + 12/2
B = 8.59m
Step 5: Perimeter P = B + D 5 = 8.59 + 1.0 5
R = A/P = 9.09/10.83 = 0.84m
1 0.00155
+ 23 +
n S
Step 6: V= RS [Where R = 0.84; S= 0.2/1000; n = 0.0225]
0.00155 n
1 + (23 + )
S R
Now v = 0.555m/sec
Step 7: Ratio of velocities found in steps (6) and (2) = 0.555/0.55 = 1.009 ≈1
Hence the assumed D is satisfactory.
-96-
Design of Canal
Example 4.8
4.8
Determine the dimensions of the irrigation canal for the following data:
B/D ratio =3.7; n = 0.0225; m = 1.0; s= 1:4000. Side slope of the channel is ½ horizontal to 1
vertical. Also determine the discharge which will be flowing in the channel.
Solution:
Here,
B/D = 3.7
B = 3.7D
For a channel with side slopes ½ :1
2
BD + D
2 3.7D2 + 0.5D2
R= = = 0.708D
B + D 5 3.7D + D 5
From Kennedy’s equation V0 = 0.55 × m × D0.64 =0.55D0.64
1 0.00155
+ 23 +
n S
From Kutter’s formula V= RS
0.00155 n
1 + (23 + )
S R
1
+ 23 + 0.00155 × 4000
0.0225 0.708D
V=
0.0225 4000
1 + (23 + 0.00155 × 4000)
0.708D
0.975D1/2
V=
1 + 0.781D-1/2
Equating the two values of V, we get
0.975D1/2
0.55D0.64 =
1 + 0.781D-1/2
On solving we get, D = 1.0m
B = 1 × 3.7 = 3.7m
V=0.55m/sec
A = 4.2 m2
Q = A × V = 2.31 cumecs.
4.5.2 Lacey’s Regime Theory
Better and modified method of designing alluvial channel by empirical method was developed by Lacey.
His regime theory considered the dimensions of bed width, depth and shape attain a state of equilibrium
called regime state. In other word, a regime channel may be defined as a stable channel whose width,
depth and bed slope have undergoes modification by silting and scouring and are so adjusted that they
have attained equilibrium. Lacey also differentiated between initial and final regime condition of channel.
-97-
Irrigation and Drainage Engineering
The initial condition is attained shortly after it is put into operation after construction and the canal begins
to adjust its bed slope either by silting or scouring although bed widths in snot altered. The canal then
appears to have attained stability, but it is not actually the final state of stability and hence: it still
represent the initial regime condition.
Eventually continuous action of flowing water overcomes the resistance of the banks and setup a
condition such that the canal that the canal adjust its complete section, the final or true regime condition is
attained. After analyzing the large number of data of stable irrigation canal in Indo – Gangetic plains, he
obtained a relation which in its converted from F.P.S to SI or metric units is as follows
2
V= fR . . . 4.17
5
Where, V = mean velocity of flow in m/sec.
f = silt factor
R= hydraulic mean radius in m.
This was the first regime equation given by Lacey.
For determining the channel dimension second equation would be necessary giving either cross sectional
area A or perimeter P. lacey on the basis of plotted data thus evolved a relationship between A and V
which is as follows.
Af2 = 140 V5 . . . 4.18
2
[Where A= cross sectional area in m ]
Other Derived Equations
1. Silt factor – Grain size relation
According to Lacey the silt factor f is dependent on the mean particle size of the boundary material
in the channel. The value of f may be determined by the following relation given by Lacey.
2
1
i.e. V =
Qf 6
140
-98-
Design of Canal
-99-
Irrigation and Drainage Engineering
determination of flood discharge by the use of Manning’s or Kutter’s equation is unreliable. At the
time of floods river is temporarily in regime and hence equation 4.20 may be applied which would
give quite accurate and reliable results.
From these equations for determining the bed sloe of a regime channel three equations may be
obtained as indicated below.
5. Regime slope equation
(i) S – f – R relation
We have the equation V= 10.8 R2/3S1/3
Cubing both side of equation
V3 = 1260 R2 S . . . (i)
Also we have another equation
2
V= fR
5
Again cubing this equation
V3 = (2/5)3/2 f3/2 R3/2 . . . (ii)
Hence from equation (i) and (ii) we have
1260 R2S = (2/5)3/2 f3/2 R3/2
On solving,
0.0002 f3/2
S= . . . 4.21
R1/2
(ii) S – f – Q relation
We have
2
V= fR . . . (i)
5
Q f 2 1/6
V= . . . (ii)
140
Equating equation (i) and (ii)
Q f 2 1/6
fR=
2
5 140
5 1/2 Q f 2 1/6
R2/3 = . . . (iii)
2f 140
Substituting the value of R1/2 from equation (iii) in equation 4.21, we get
1
f3/2 8.96f 6
S=
4980 Q
f5/3
S= . . . 4.22
3340 Q1/6
S – f – q relation
-100-
Design of Canal
We have V3 = 1260 R2 S
This can be written as
5
V2 3
S=
1
. . . (i)
R 1260 (RV)1/3
2
Again squaring both side of equation V = fR
5
2
V2 = fR
5
V2 2
= f . . . (ii)
R 5
Further if q is discharge per unit width of the channel, then assuming it to be a wide channel,
we have
q = RV . . . (iii)
Introducing equation (ii) and (iii) in equation (i) we get
2 5/3
S = f
1
5 1260 q1/3
0.000178 f5/3
S= . . . 4.23
q1/3
Summary of Lacey’s Formulas
(i) P = 4.75 Q . . . 4.24
(ii) f = 1.76 dmm . . . 4.25
1
f2 Q 6
(iii) V = . . . 4.26
140
1
5 V2
= 0.48 3
Q
(iv) R = . . . 4.27
2 f f
3 × 10-4 f 5/3
(v) S = . . . 4.28
Q1/6
Here P is the wetted perimeter in m, R is the hydraulic radius in m, Q is the discharge m3/sec, d is the
diameter of sediment particle and f is the silt factor which depended on the types and size of sediment.
Example 4.9
4.9
A channel section is to be designed for the following data.
Discharge Q = 5 cumecs.
Silt factor f = 1.
Side slope (H:V) = 0.5:1
Also determine the bed slope of channel.
-101-
Irrigation and Drainage Engineering
Solution:
1
f2 Q6
Step 1: Velocity V =
140 = 0.574 m/sec
Step 2: Area A= Q/V = 8.71 m2
Step 3: Perimeter P = 4.75 Q = 10.62m
Step 4: A = BD + zD2
8.71 = BD + 0.5 D2 . . . (i)
P=B+ 5D
10.62 = B + 5 D . . . (ii)
From (i) and (ii), we get
B = 8.44m
D = 0.98m
Step 5: R =A/P = 0.823
5 V2
Let’s check with R = = 0.824m ≈ 0.823 m hence Ok.
2 f
f5/3 15/3 1 1
Step 6: Bed slope s = 1/6 = = ≈
3340 Q 3340 × 51/6 4368 4400
Hence, the channel has bed width B = 8.44m, D = 0.98m and bed slope S = 1:4400.
4.10
Example 4.10
Design a stable irrigation canal carrying a discharge of 50 m3/sec, which passes through alluvium
dmean = 0.50mm. Draw sketch of the designed section.
Solution:
Step 1: f = 1.76 dmm = 1.244
2
1
Velocity V =
f Q 6
Step 2:
140 = 0.906 m/sec
Step 3: Area A= Q/V = 50/0.906 = 55.187 m3/sec.
Step 4: Perimeter P = 4.75 Q = 33.587m
Step 5: A = BD + zD2 assume side slope z = 0.5
55.187 = BD + 0.5 D2 . . . (i)
0.75m
1.81m
29.53m
-102-
Design of Canal
P=B+ 5D
33.587 = B + 5 D . . . (ii)
Form (i) and (ii), we get
B = 29.53m
D = 1.81m
Adopt free board = 0.75m
Overall depth = 2.56m
Step 6: R = A/P = 1.643m
5 V2 5 0.9062
Let’s check with R = = × = 1.649m ≈ 1.643m. Hence Ok.
2 f 2 1.244
f5/3 1.2445/3 1 1
Step 7: Bed slope s = 1/6 = = ≈
3340 Q 3340 × 501/6 4455.27 4500
Example 4.11
4.11
Design an irrigation channel in alluvial soil according to Lacey’s silt theory for the following data.
Full supply discharge = 10 cumecs
Lacey’s silt factor = 0.9
Side slopes of channel = 0.5:1 (H:V)
Solution:
2
1
Velocity V =
f Q 6
Step 1:
140
2
1
V =
0.9 x 10 6
140 = 0.62m/sec
Step 2: Area A = Q/V = 10/0.62 = 16.13 m2
5 V2 5 0.622
Step 3: Hydraulic mean radius R = = x = 1.07m
2 f 2 0.9
Step 4: Perimeter P = A/R = 16.13/1.07 = 15.07m
Step 5: P = B + 5 D =15.07 . . . (i)
2 2
Step 6: A = BD + 0.5D = 16.13m . . . (ii)
Form (i) and (ii), we get
B = 12.27m; D = 1.25m
Step 7: Check P = 4.75 Q = 15.02m
P = B + 5 D = 15.07m
These two values of P are nearly equal and hence the computations are correct.
f5/3 0.95/3
Step 8: Bed slope s = 1/6 = = 1/5844≈ 1/5850
3340 Q 3340 × 101/6
-103-
Irrigation and Drainage Engineering
Example 4.12
4.12
The slope of a channel in alluvium is 1/4000, Lacey’s silt factor is 0.9 and side slopes are 0.5:1 (H:
V). Find the channel section and maximum discharge which can be allowed to flow in it.
Solution:
f5/3
We have the S – f – Q relation S = Form this equation,
3340 Q1/6
Q = 1.03 m3/sec
f3/2
We also have S – f – R relation S =
4980 R1/2
R = 0.47m
We also have; P = 4.75 Q = 4.82m
A = PR = 4.82 x 0.47 = 2.27m2
A = BD + 0.5D2 = 2.27 . . . (i)
P = B + 5 D = 4.82 . . . (ii)
Solving (i) and (ii), we get
B = 3.48m
D = 0.60m
-104-
Design of Canal
-105-
Irrigation and Drainage Engineering
Calculation of benefits
The major benefit then can be readily assessed in terms of money is from the saving of seepage water
which would have been lost from unlined channel. This water when supplied to farmers will yield
revenue.
Let q cumecs be the water saved in the lined reach and R1 rupees be the cost of water per cumecs. Then
the total saving = q × R1 rupees.
The other benefit is through a considerable reduction in the maintenance cost of a lined channel,
compared to that of an unlined channel. Let p be the percentage saving in annual maintenance cost which
is rupees R2 for unlined channel. Then the saving in annual maintenance cost = p × R2 rupees.
Thus total benefit (B) per year = q × R1 + p × R2 rupees.
Saving in maintenance cost is usually taken to be around 40% so that p = 0.4
Besides the above benefits, there will be a considerable indirect benefits accrued from the prevention of
water logging caused due to excess seepage, but as these are difficult to assess in terms of money, the
minimum annual benefit (B) is considered as B = q×R1 + p×R2
Annual cost of extra expenditure on lining
Let the extra expenditure on canal lining be C rupees. If Pt is the total perimeter of lining, L is the length
of lining and c is the cost of lining in rupees per m2 , Cost C = c × Pt × L. The extra expenditure is to be
calculated by subtracting the saving in land cost, cost of drainage works, cost of bridges and earthwork
etc. form the total cost of lining.
Let the life of lining be N years and i be the percentage rate of interest expressed as fraction per year.
Then the capital recovery factor or annual cost of extra expenditure on lining equal to
i ( i + 1 )N
=C
( 1 + i )N – 1
Therefore benefit cost ratio B.C.R. is given by
[q R1 + p R2] [ (1 + i)N – 1] B [(1 + i)N – 1]
B.C.R. = =
C × i ( 1 + i )N C i (1 + i )N
Example 4.13
4.13
An unlined channel in alluvial soil has a seepage loss of 2.5 cumecs / million sq. m. of wetted perimeter.
The channel has a wetted perimeter of 25 m and has maintenance cost of Rs. 1 per sq. m of wetted
perimeter. There is a huge scarcity of water in the area and as such the canal is to be lined with cement
concrete lining 12 mm thick so as to reduce seepage loss to 0.02 cumecs/ million sq. m. of wetted
perimeter. The lined channel will have a wetted perimeter of 20 m. The extra cost of lining work out to be
Rs. 100 per sq. m. If the average annual revenue per cumecs of water is Rs. 20 lakhs and percentage
reduction in annual maintenance cost is 40%, decide whether it is economically feasible to provide canal
lining. Assume the life of canal lining as 50 years and the interest rate is 6% per year.
Solution:
For the purpose of calculations assume 1 km length of channel
(i) Annual benefit
(a) Seepage
Area of wetted perimeter for unlined channel in 1 km = 25 × 1000 = 25000 sq. m.
-106-
Design of Canal
-107-
Irrigation and Drainage Engineering
We can see from the Equation 4.30 that for a given discharge Q, Manning’s n and bed slope S, the wetted
perimeter P is minimum when the flow area A minimum. For minimum P and A, cost of excavation as
well as lining used to prevent seepage and erosion will be minimum. Thus in the design of canal
considering P to be minimum is termed as method of economic section. Further when discharge Q is
maximum, P is minimum for a given value of n, S and A.
Most of the channels which are in practice are trapezoidal in shape, in lined channel side slope is taken
0.5:1 or 1: 1 (H: V). Thus, the method requires only finding best hydraulic sections i.e. the relationship of
flow depth y with respect to bottom width B.
Theoretically, a semi - circular section is the best for open channel. For practical consideration, a
trapezoidal or triangular section rounded corners is usually selected. Generally triangular section is
selected for design discharge < 85 cumecs.
θ 1
Area A = π y2 π + 2 y (y cotθ) = y2 (θ + cot θ)
2
y2 (θ + cot θ)
Hydraulic mean depth = 2y (θ + cotθ) = y/2 . . . 4.31
(ii) Trapezoidal
1
Area = By + 2 (πy2 θ/2π) + 2 y (y cotθ) FSL
2
θ θ
A = By + y2θ +y2cot θ . . . 4.32 θ y
y θ
A = y(B + yθ + y cotθ)
The channel is, then designed, according to Manning’s formula. The value of rugosity coefficient (n)
depends upon the roughness of the channel boundary, and is different for different kinds of linings.
Different values of n for different types of lining materials are as shown is in table below.
-108-
Design of Canal
Example 4.14
4.14:
Design an economical concrete lined trapezoidal channel to carry a discharge of 200 cumecs at a
slope of 30 cm/km. The side slope of the channels is 1.5:1. The value of n may be taken as 0.017.
Assume limiting velocity in the channel as 2m/sec.
Solution:
S= 0.3/1000 = 0.0003
V= 2m/sec
n= 0.017
Step 1: Calculate R;
1 2/3 1/2
V= R S
n
R= 2.75 m
A = Q/V = 200/2=100m2
Now, A = BD + D2(θ+cotθ)
Cot θ = 1.5
-109-
Irrigation and Drainage Engineering
P = B + 2D (θ + cotθ)
36.36 = B + 2D (θ + cot θ)
B = 22.04 m
D = 3.43m
Example 4.15
4.15:
Design a triangular shaped lined channel to carry a discharge of 15 cumecs. The available and
accepted slope is 1 in 900. Assume suitable values of side slopes and good brickwork in lining.
Solution:
Given that: Q = 15 cumecs
S0 = 1/900
Assume; side slope 1.25: 1 [H: V]
n = 0.018 for brick lining.
Tan θ = 1/1.25
θ = 38.659 × π/180 = 0.675 rad.
Using A = y2 (θ + cotθ)
P = 2y (θ + cotθ)
We get, A =y2 (0.675 +1.25) = 1.925y2
P = 2y (0.675 +1.25) = 3.85y
R=A/P = y/2
Using Manning’s equation
1 2/3 1/2
Q=A R S
n
1
15 = (1.925y2) (y/2) 2/3 (1/900)1/2
0.018
y = 2.04m
-110-
Design of Canal
1 2/3 1/2 1
V= R S = × 1.7132/3 × (1/4800)1/2 = 0.918 m/sec
n 00225
A = Q/V = 45 / 0.918 = 49 m2
P = A/R = 49/ 1.713 = 28.61 m
P = 28.61 = B + 2.236 D
A = 49 = BD + 0.5 D2
Solving these, we get D =1.94 m and B = 24.27 m
Exercise 4:
-111-
Irrigation and Drainage Engineering
6. A wide irrigation channel is laid at a slope of 1 in 4000. The size of the sand is 3.0mm. Water flows
at a depth of 0.8m. Find whether the bed is moving or stationary. If the size of the sand is increased
to 7mm, and the slope to 1in 1000 what will happen to the channel bed?
7. An irrigation channel is to be constructed in course alluvium gravel with 5mm particle size. The
channel has to carry 2.9cumecs of discharge and the longitudinal slope is 0.01. The banks of the
channel will be protected by grass against scouring. Find the minimum width of the channel.
8. Water flows at a depth of 0.7m in a wide stream having a bed slope of 1 in 2500. The diameter of
the sand bed is 1.0mm. Determine whether the soil grains are stationary or moving. Also comment
whether the stream bed is scouring or non-scouring.
9. An irrigation channel is to be constructed in course alluvium gravel with 4cm size. The channel has
to carry 5 cumecs of discharge & the longitudinal slope is 0.04. The banks of the channel will be
protected against scouring. Find the minimum width of the channel.
10. An irrigation channel is to be designed for the following data. Q = 35cumecs, S = 1 in 1400, d =
35mm, φ = 37°. The side slopes of the trapezoidal channel are unprotected.
11. A canal is to be designed to carry a discharge of 60cumecs. The bed slope is kept 1 in 1200. The soil
is course alluvium having a grain size of 5cm. Assuming the canal is trapezoidal and unlined with
unprotected banks, determine a suitable section for the canal. Assume φ = 37°.
12. An irrigation canal carries a discharge of 40m3/sec and is laid on a slope of 1 in 2500. If CVR = 1.2
and n = 0.025, design the channel.
-112-
Diversion Headworks
CHAPTER
5 Diversion Headworks
An irrigation channel takes its supplies from its source which can be either a river (in case of main canal)
or a channel (in case of branch canals and distributaries). The structures constructed across a river source
at the head of an off-taking main canal are termed as “canal headworks” or “headworks”. The headworks
can be either diversion headworks or storage headworks.
Diversion headworks divert the required supply from the source channel to the off-taking channel. The
water level in the source channel is raised to the required level so as to divert the required supplies into
the off-taking channel. The diversion headworks should be capable of regulating the supplies into the off-
taking channel. If required, it should be possible to divert all the supplies (at times of keen demand and
low supplies) into the off-taking channel. The headworks must have an arrangement for controlling the
sediment entry into the channel off-taking from a river. By raising the water level, the need of excavation
in the head reaches of the off-taking channel is reduced and the commanded area can be served easily by
flow irrigation. Storage headworks, besides fulfilling all the requirements of diversion headworks, store
excess water when available and release it during periods when demand exceeds supplies
The site selection of a barrage/weir depends mainly on the location and elevation of the off-take canal, and a
site must be selected where the river bed is comparatively narrow and relatively stable. The pondage
requirement and interference with the existing structures such as bridges, urban development, valuable
farmland, etc., must be considered, as well as available options to divert the flow during construction.
-113-
Irrigation and Drainage Engineering
selection of the site should be made such that it results in the most economical alternative. The following
features of the two stages should be considered while selecting the site for headworks.
i. The initial cost of headworks in the boulder stage is generally smaller than that in the alluvial stage
because of:
• Local availability of stones,
• Smaller width of river (requiring smaller length of weir),
• Smaller scour depths which reduce the requirements of cutoffs and other protection works, and
• Close proximity of higher banks which requires less extensive training works.
ii. An irrigation canal off-taking from a river in the boulder region will have a number of falls which
may be utilized for generation of electricity. There is almost no scope for the generation of
electricity in this manner in the alluvial reach of a river.
iii. If the existing irrigation demand is less but is likely to develop with the provision of irrigation
facilities, it is desirable to divert the river water into an irrigation channel by constructing a
temporary boulder bund across the river. This bund will be washed away every year during the
floods and will be reconstructed every year. This will, no doubt, delay the Rabi crop irrigation, but it
is worthwhile to use temporary bunds for a certain period; when the irrigation demand grows,
permanent headworks may be constructed. In this manner, it would be possible to get returns
proportional to expenditures incurred on the headworks. Construction of temporary bunds is
generally not possible in the alluvial stage of the river.
iv. An irrigation channel off – taking in the boulder stage of a river will normally require a large
number of cross-drainage structures. Because of the nature of the boulder region, there is always a
strong subsoil flow in the river bed. This causes considerable loss of water and is of concern during
the periods of short supply. Similarly, there will be considerable loss of water from the head reach of
the off-taking channel. In alluvial reach of the river this loss of water is much less.
v. The regions close to the hills usually have a wet climate and grow good crops. The irrigation
demand in the head reach of the channel off-taking in the boulder stage is, therefore, generally
small. However, this demand would increase with the provision of irrigation facilities. In alluvial
regions, the demand for irrigation is high right from the beginning.
For irrigation purposes, the site for headworks should result in a suitable canal alignment capable of
serving its commanded area without much excavation. For siting the headworks, the river reach should, as
far as possible, be straight and narrow and have well-defined and non-erodible high banks. In the case of
a meandering river, the headworks should be located at the nodal point.
From sediment considerations, the off – taking channel should be located at the downstream end of the
outside of a river bend so that it has the advantage of drawing less sediment. However, a curved reach
would need costly protection works against the adverse effect of cross currents. Moreover, if canals take
off from both the banks, the canal taking off from the inner bank draws relatively more sediment.
In order to ensure adequate supply to the off-taking canal at all times, the undersluice should be sited in
the deep channel. A river reach with deep channels on both banks and shallow channel at the center is
more suitable when canals take off from both sides.
Besides, the site must be accessible and suitable for making the river diversion and other related
arrangements at a reasonable cost.
-114-
Diversion Headworks
5.2 Component Parts of Weir and Barrage
u/s
9 9
5 A 1. Weir/Barrage
7
2. Undersluices
6 2 1 3. Divide wall
4. Fish ladder
5. Head regulator (intake)
6. Approach canal
8 7. Silt excluder
8. Silt ejector
10
4 9. River training works (GB and MB)
A 10. Stilling basin (energy dissipater)
d/s
(a)
Pond level Weir crest level
-115-
Irrigation and Drainage Engineering
1. Weir and Barrage
Weirs and barrages are relatively low-level dams constructed across a river to raise the river level
sufficiently or to divert the flow in full, or in part, into a supply canal or conduit for the purposes of
irrigation, power generation, navigation, flood control, domestic and industrial uses, etc. Figure 5.1
These diversion structures usually provide a small storage capacity. In general, weirs (with or
without gates) are bulkier than barrages, whereas barrages are always gate controlled. Barrages
generally include canal regulators, low-level sluices to maintain a proper approach flow to the
regulators, silt excluder tunnels to control silt entry into the canal and fish ladders for migratory fish
movements. Weirs are also used to divert flash floods to the irrigated areas or for ground water
recharging purposes. They are also sometimes used as flow measuring structures. Figure 5.1 (b)
shows the section of a weir and Figure 5.1 (c) shows the section of a barrage.
The basic differences between weir and barrage are provided in Table 5.1.
Table 5.1: Differences between
between Weir and Barrage
Weir Barrage
Function Weir is an impervious barrier which When adjustable gates are installed over a
is constructed across a river to raise weir to maintain the water surface at
the water level on the upstream side different levels at different times is known
is known as a weir. Here the water as a barrage. The water level is adjusted by
level is raised up to the required operating the gates or shutters. The gates are
height and the surplus water is placed at different tiers and these are
allowed to flow over the weir. operated by cables from the cabin. The gates
Generally it is constructed across an are supported on piers at both ends. The
inundation river. distance between the pier to pier is known as
Bay.
Sedimentation Chances of silting on upstream is Silting may be controlled by judicial
more operation of gates.
Flow control Low control on flow Relatively high control on flow and water
levels by operation of gates.
Back water Afflux created is high due to Due to low crest of the weirs (the ponding
effect relatively high weir crests being done mostly by gate operation), the
afflux during high floods is low. Since the
gates may be lifted up fully, even above the
high flood level.
Construction Low cost High cost
Cost
2. Under- Sluices
These are controlled opening in the weir and barrage (even if weir doesn’t have gated structure) with
crests at low level (river bed level). They are located on the same side near the off - taking canal. If
two canals take off on the either side of river, it would be necessary to provide under - sluices on
both sides.
-116-
Diversion Headworks
Discharge capacity of the under sluices in provided higher of the following:
• Two times the maximum discharge in the off – take canal.
• 20% of the maximum flood discharge
• Maximum winter discharge.
3. Divide Wall
The divide wall is constructed parallel (or nearly parallel) to the canal head regulator. It separates
the main weir bays from the bays of the under sluice as shown in Figure. 5.1. The wall extends on
both sides of the weir. Extension of the divide wall towards the downstream of the weir avoids
cross-flow in the immediate vicinity of the structure which, otherwise, may cause objectionable
scour. The divide wall is usually extended up to the end of either the impervious floor or the loose
apron on the downstream side. The divide wall serves the following purposes:
• It isolates the canal head regulator from the main river flow and creates a still pond of water in
front of the canal head regulator. This results in deposition of sediment in the pocket and entry
of relatively sediment - free water into the off taking canal. It also improves scouring of the
undersluices by ensuring straight approach.
• It separates the weir floor from the floor of the undersluices which is at a lower level than the weir floor.
• If the main current has a tendency to move towards the bank opposite to the canal head
regulator, the weir forces the water towards the canal head regulator. This causes cross-currents
which may damage the weir. Under such adverse flow conditions, additional divide walls at
equal intervals along the weir are provided to keep
• The cross-currents away from the weir.
When only one canal takes off from a river, the length of the divide wall should be half to two-thirds
the length of canal regulator. When more than one canal takes off from the same bank, the divide
wall should extend a little beyond the upstream end of the canal farthest from the weir. Some
experimental studies have shown that a slight divergence of the divide wall from the regulator
improves its efficiency. This divergence should not exceed 1 in 10. To reduce the scour at the nose
of the divide wall, the nose end of the wall is given a slope of 3(V):1(H).
The divide wall is generally constructed as a strong masonry wall with a top width of about 1.5 to
2.25 m and checked for safety for the following two conditions:
• For low stage of the river, the water levels on the two sides of the walls are the same but the silt
pressure is assumed to correspond to the sediment deposit up to full pond level on the pocket side.
• For the high stage of the river, the under sluice are discharging. At this condition, the water levels
on the two sides are assumed to be different; the weir side level being higher by about 1.0 m.
It the river curvature is not favorable to sediment-free entry of water into the off-taking canal by
inducing convex curvature opposite the head regulator, a second pocket of river sluice adjoining the
under sluice improves flow conditions considerably. Such provision is useful in case of wide rivers
to guide the river to flow centrally, minimizing cross-flow, and prevent shoal formation in the
vicinity of the head regulator. The location and layout of the river sluice should be decided by model
studies for satisfactory performance.
-117-
Irrigation and Drainage Engineering
4. Fish Ladder
This is an artificial upstream fish passage, most commonly used for heads up to 20 m consisting of
• A fish entrance
• A fish ladder proper and
• A fish exit. Sometimes an auxiliary (additional) water supply is also provided to attract fish to
the entrance.
The fish ladder proper consists of a series of traverses (cross-walls) and pools circumventing an
obstruction (such as a weir or dam) for the fish to migrate to the head waters in easy stages. This is
achieved by creating a series of drops of around 300mm – 450mm between pools Figure. 5.2 on a
gradient of around 1 in 8 to 1 in 15 (for high heads). Rest pools of a larger size (normally twice the
size of an ordinary pool) are also provided after every 5 – 6 pools.
The actual arrangement of pools and traverses is chosen according to a particular obstruction; a low
level weir or dam may need a fish pass of shallow gradient (corresponding to the surrounding
gradient of the land) whereas a tightly folded pass may be necessary in case of a high weir or dam.
The fish pass is designed to take a fixed proportion of the flow over the main weir or spillway. This
is normally achieved by sitting the invert level of the uppermost notch lower than the adjoining weir
or spillway crest; the discharge and head calculations may be achieved by using appropriate weir –
notch or orifice formulae.
The entrance to the fish pass (ladder) must be located in the downstream parallel to the main flow,
whereas the exit (at the upstream end) should be well within the reservoir away from the spillway
structure. The pools are usually 1 – 2 m deep, 2 – 5 m long and 2 – 10 m wide, depending on the
number of fish migrating. Cross-walls may be provided with staggered notches–orifices, with the
velocities in the ladder being around 0.5m/s. (Guiny, 2005) investigated the efficiency of different
passages through the baffles in a fish pass (orifice, slot, weir) and found – with limited data – a
strong preference of the migrating juvenile Atlantic salmon for the orifice type.
Head loss • 300 mm
Pool
Pool Flow
Flow
(b) Plan
Figure 5.2: Fish ladder
-118-
Diversion Headworks
5. Canal Head Regulator (Intake)
The intake structure (or head regulator) is a hydraulic device constructed at the head of an irrigation
or power canal, or a tunnel conduit through which the flow is diverted from the original source such
as a reservoir or a river. In other word the structures controlling diversion into a supply canal are
called regulators. The design principles are the same as those used in the design of barrages, except
that the regulators are a smaller version of barrages. The entry sill of a regulator must be such that it
permits entry of the maximum flow at various poundage levels. Another important consideration in
designing the regulator is silt exclusion from canals. Silt-excluder tunnels are often provided in the
barrage bays adjacent to the regulator, so that the heavier silt-laden bottom layers of water bypass
through the tunnels Figure. 5.3. The main purposes of the intake structure are:
• To admit and regulate water from the source, and possibly to meter the flow rate,
• To minimize the silting of the canal, i.e. to control the sediment entry into the canal at its intake,
• To prevent the clogging of the entrance with floating debris.
In high-head structures the intake can be either an integral part of a dam or separate; for example, in
the form of a tower with entry ports at various levels which may aid flow regulation when there is a
wide range of fluctuations of reservoir water level. Such a provision of multilevel entry also permits
the withdrawal of water of a desired quality.
The layout of a typical intake structure on a river carrying a heavy bed load is shown in Figure. 5.3.
The following are its major appurtenances:
• The raised inlet sill to prevent entry of the bed load of the river.
• The skimmer wall (with splitter pier) at the inlet to trap floating ice and debris
• The coarse rack (trash rack) to trap subsurface trash, equipped with either manual or automatic
power-driven rack cleaning devices
• The settling basin (sand trap) followed by a secondary sill (entrance sill) diverting the bottom
(sediment-laden) layers towards the de-silting canal
• The flushing (de-silting) sluice to flush the deposited silt
• The intake (head regulator) gates to control the flow rate into the canal
• The scouring tunnel (silt excluder) or undersluices in the diversion weir to flush the bed load
deposited in upstream of the inlet sill.
-119-
Irrigation and Drainage Engineering
Figure 5.3: Canal intake on a river carrying heavy bed load (after Mosoni, 1987)
6. Approach Canal
The portion of canal from intake to settling basin is approach canal. Which drawn water from intake.
This canal should withstand the negative pressure created by water because the velocity of water at
this section is high. This canal should be stable against higher velocity for this purpose this canal is
design by using either Manning's relation or Chezy's relation.
River training works direct the main river flow as centrally as possible to the diversion structure. They
also safeguard the barrage from erosion and may be designed so that a desirable curvature is induced to
the flow for silt exclusion from the canals. The side slopes of the guide banks must be protected by
stone pitching, with a sufficient ‘self-launching’ stone apron at the lowest feasible level (Detail in
chapter 6). The top levels of the guide banks will depend on the maximum increase in the flood level
upstream of the barrage. The afflux (level difference between the headwater and tail water during the
passage of maximum flood flow) results in a backwater curve upstream of the barrage, and flood banks
have to be provided along the upstream reach of the river to contain the flood flow.
Stilling basins may be defined as the structure in which the energy dissipating action is confined. If
the phenomenon of hydraulic jump is basically used for dissipating this energy, it may be called a
hydraulic jump type stilling basin. The auxiliary devices like chute blocks, baffle piers, sill and
dented sills may be used as additional measures for controlling the jump. For the particular site, the
type of energy dissipater and its arrangement shall be decided based on the relationship between the
height of hydraulic jump vs the tail water depth.
-120-
Diversion Headworks
-121-
Irrigation and Drainage Engineering
(a) Only concrete floor (b)Method of increasing creep length with sheet piles
Figure 5.5: Creep Length due to Subsurface Flow
If H is the total loss of head, then the loss of head per unit length of the creep shall be
H H
C= = . . . 5.1
L [B + 2 (d1 + d2 + d3)]
Bligh called the loss of head per unit length of creep as Percolation coefficient. The reciprocal, (L/H) of
the percolation coefficient is known as the coefficient of creep C or Bligh's coefficient CB.
Assumptions:
• Hydraulic slope or gradient is constant throughout the impervious length of the apron.
• The percolating water creep along the contact of the base profile of the apron with the sub soil
head loss in creep path, proportional to length of its travel. The length is called creep length. It
is the sum of horizontal and vertical creep length.
• Stoppage of percolation by cut off or piles is possible only if it extends up to impermeable soil strata.
-122-
Diversion Headworks
Safety against Uplift Pressure
The second criterion for the safe design of a hydraulic structure on a pervious foundation is that the weight of the
impervious floor must counterbalance the uplift pressure. The floor is usually designed as a gravity section.
Figure 5.6 (a) shows a simple horizontal floor length L, subjected to a seepage head of H. the residual
head (h) at any point P is given by
H
h= H – ×l . . . 5.2
L
Where l is the horizontal length from the entry point A to the point P.
The residual head (h) can also be obtained from the subsoil hydraulic gradient line. It may be noted that
the vertical intercept h of the subsoil HGL is measured from the top surface of the floor. It h’ the vertical
intercept measured above the bottom surface of the floor.
h' = h + t
From Figure 5.6 (b) shows the uplift pressure diagram on the bottom surface.
It is more convenient to measure the intercept h than the intercept h'. The intercept h' above the bottom
surface of the floor can be determined only after the thickness t has been determined or t has been
assumed. For the determination of the floor thickness t. let us consider the force acting on the unit area of
the floor (shown hatched).
The downward force W due to the weight of the floor material is given by
W = (G γw) × t . . . 5.4
For equilibrium, the upward force should be counterbalanced by the weight. Hence from equation 5.3 and 5.4.
U=W
γwh' = G γw t
As h' = h + t, γw(h + t) = G γw t
t ( G – 1) = h
h
t= . . . 5.5
(G – 1)
4h
Generally a factor of safety of 4/3 is adopted. Thus t = . . . 5.6
3 (G – 1)
-123-
Irrigation and Drainage Engineering
Equation 5.6 gives required thickness t of the floor if the height h of the subsoil hydraulic gradient line
above the top surface of the floor is known. In this equation, G is the specific gravity of the floor material.
For plain concrete floor, the value of G usually varies from 2.0 to 2.30, depending upon the type of
aggregate used. For the design of irrigation structure, a value of 2.24 is generally adopted.
For portion of floor upstream of barrier only nominal thickness need to be provided since the weight of
water will counterbalance the uplift pressure. A certain minimum length of impervious floor is always
necessary to the downstream of the barrier (thickness of downstream floor for worst condition).
H' H
h h'' D/S BED
A P B No tail water
t
l
L
(a)
h'
H'
(b)
Figure 5.6: Bligh’s theory
Limitations of Bligh’s theory
Bligh’s theory has several limitations. They are:
i. In his theory Bligh made no distinction between horizontal and vertical creep lengths.
ii. The idea of exit gradient has not been considered.
iii. The effect of varying lengths of sheet piles not considered.
iv. No distinction is made between inner or outer faces of the sheet piles.
v. Loss of head is considered proportional to the creep length which in actual is not so.
vi. The uplift pressure distribution is not linear as assumed but in fact it follows a sine curve.
vii. Necessity of providing end sheet pile not appreciated.
5.3.2 Lane’s Theory
Lane analyzed a large number of dams and weir founded on pervious foundations which failed or did not
fail. He brought out deficiencies in Bligh’s creep theory and gave a new theory on statistical basis. The
theory is known as Lane’s weighted creep theory. This theory gives the weightage factor of 1/3 for the
horizontal creep, as against 1.0 for the vertical creep.
From Figure 5.5 b. L = B/3 + (2d1+2d2+2d3)
-124-
Diversion Headworks
Safety against Piping
To ensure safety against piping, according to this theory, the creep length L, must not be less than C1HL,
where HL is the head causing flow, and CL is Lane’s creep coefficient given in table below.
Table 5.3: Values
Values of Lane’s safe Hydraulic Gradient for different types of soils.
4m
A B C
Solution:
(a) From Bligh’s theory
i. Creep length L= 2 × 6 + 35 + 2 × 8=63m.
1 1
Hydraulic gradient i = H/L = 4/63 = < safe
15.75 15
ii. Uplift pressure head
1
At point A = 4 – (2 × 6 + 15) = 2.29m
15.75
1
At point B = 4 – (2 × 6 + 25) = 1.65m
15.75
1
At point C = 4 – (2 × 6 + 35) = 1.02m
15.75
1
Check uplift pressure head at point C from end point = × 2 × 8 = 1.02m OK
15.75
-125-
Irrigation and Drainage Engineering
iii.Thickness of floor
4h
We have, t =
3 (G – 1)
4 × 2.29
At point A, t = = 2.46 m
3 (2.24 – 1)
4 × 1.65
At point B, t = = 1.77 m
3 (2.24 – 1)
4 × 1.02
At point C, t = = 1.10 m
3 (2.24 – 1)
(b) From Lane’s theory
Weighted creep length, Lw = 35/3 + 2 × 6 + 2 × 8 = 39.67m
Hydraulic gradient = H/Lw = 4/39.67 = 1/9.92 < 1/8.5 (safe)
Uplift pressure at point A = 4 – (2 × 6 +15/3)/9.92 = 2.29m
At point B = 4 – (2 × 6 + 25/3)/9.92= 1.95m
At point C = 4 – (2 × 6 + 35/3) = 1.61 m
[Check uplift pressure at point C = (2 × 8)/9.92 = 1.61m Ok]
4 2.29
Thickness of floor At point A = = 2.46m
3 2.24 – 1
4 1.95
At point B = = 2.10m
3 2.24 – 1
4 1.61
At point C= = 1.73m
3 2.24 – 1
It may be noted that the uplift pressure are quite different from those obtained by Bligh’s theory
basically in down stream and Lane's thickness is in safe side.
5.3.3 Khosla’s Theory
The seeping water does not creep along the bottom contour as stated by Bligh and Lane, it moves along a
set of streamlines as shown in Figure 5.7.
H
h
A 1 B C D
12
2 11
3
4 5 6 10
Flow lines 7 8 9
Equipotential
lines Impervious strata
-126-
Diversion Headworks
This steady seepage in a vertical plane for a homogeneous soil can be expressed by Laplacian equation:
d 2φ d 2φ
+ =0
dx 2 dz 2
Where, φ – flow potential. φ = kh; where, k is the coefficient of permeability as defined by Darcy and h
is the residual head at any print within the soil.
w + (∂w/∂z)* dz v + (∂v/∂y)* dy
u u + (∂u/∂x)* dx
dz
dy
v dx
∂u ∂v ∂w
u + dx dzdy + v + dy dzdx + w + dz dxdy . . . . (ii)
∂x ∂y ∂z
If the flow is steady & incompressible, the quantity entering is equal to quantity leaving.
∂u ∂v ∂w
+ + dxdydz = 0
∂x ∂y ∂z
Since, dx dy dz ≠ 0;
∂u ∂v ∂w
+ + =0 . . . . (iii)
∂x ∂y ∂z
Now, Darcy law is given by
dh
V=K
dx
∂h ∂h ∂h
Hence, u=k , v = , &w =
∂x ∂y ∂z
-127-
Irrigation and Drainage Engineering
Further, φ = kh, so that
∂φ ∂φ ∂φ
u= ,v = , &w = ,
∂x ∂y ∂z
Putting their value in equation (iii)
∂ 2φ ∂ 2φ ∂ 2φ
+ + =0 . . . . (iv)
∂x 2 ∂y 2 ∂z 2
Equation (iv) is known as Laplace’s equation
For two-dimensional flows:
d 2φ d 2φ
+ =0
dx 2 dz 2
Above equation represents 2 sets of curves intersecting each other orthogonally (see Figure: 5.7). AB is
the first equipotential line and CD is the last.
The residual head causes drag or seepage pressure at any point. The determination of residual pressure
(uplift) is possible by flowing methods:
• Trial and error or graphical method
• Mathematical solution of Laplace's equation
• Khosla’s method of independent variables
• Method of electrical analogy
• Method of relaxation
Why Khosla’s method is preferable than other methods?
• Difficult to plot the flow net graphically
• All other methods are complicated & time consuming
• Khosla's method is simple, quick & accurate
The usual barrage and weir section do not conform to a simple elementary form and a direct solution of
the Laplace equation not feasible. To apply the analytical solution to any practical composite profile of a
weir or a barrage, Khosla’s and his associates evolved the method of independent variables. In this
method a composite barrage or weir section is split up into a number of simple standard forms of known
analytical solutions. The most useful standard forms among these are.
a. A straight horizontal floor of negligible thickness with a sheet pile at either end (Figure 5.9 (a)
and (b))
b. A straight horizontal floor depressed below the bed but no vertical cutoff. (Figure 5.9 (c))
c. A straight horizontal floor of negligible thickness with a sheet pile line at some intermediate
position. (Figure 5.9 (d))
-128-
Diversion Headworks
H H
E1 C1 E C
d b b d
D1 (a) (b) D
H H
D1 D D D d E C
d
b b
D
(c) (d)
Figure 5.9: Standard forms – Khosla’s methods of independent variables
In general, the usual weir section consists of a combination of all the three forms mentioned above; the
entire length of the floor with any of the pile lines, etc. making up one such form. Each elementary form
is then treated as independent of the others. The pressures at the key points are then read off from the
Khosla’s curves (Annex I). These key points are the junction points of the floor and the pile line of that
particular elementary form, the bottom point of that pile line and the bottom corners in the case of
depressed floor.
The percentage pressure observed from the curves for the simple form into which the profile has been
broken up, is valid for the profile as a whole if corrected for:
(i) Mutual interference of sheet piles
(ii) The floor thickness
(iii) The slope of the floor
(i) Correction for mutual interference of piles
Let C, be the correction to be applied as percentage of head, b' be the distance between the two pile
lines. D be the depth of the pile line, the influence of which has to be determined on neighboring
pile of depth d. D is to be measured below the level at which interference is desired. d be the depth
of pile on which the effect is to be determined.
D d + D
C = +19
b' b
-129-
Irrigation and Drainage Engineering
This correction is positive for points in the rear of back water and subtractive for points forward in
the direction of flow.
In the case of intermediate piling shallower than the end pile (D <d) and b' ≥ 2d the mutual
interference is negligible.
1:1 11.2
1:2 6.5
1:3 4.5
1:4 3.3
1:5 2.8
1:6 2.5
1:7 2.3
1:8 1
The correction is applicable to the key points of the pile line fixed at the beginning or the end of the
slope. The percentage correction given by the above table is to be further multiplied by the
proportion of the horizontal length of slope to the distance between the two pile lines in between
which the sloping floor is located. The correction is minus for the up and plus for the down slopes in
the directions of flow.
-130-
Diversion Headworks
1+ 1+ α2
Where, λ= 2 . . . 5.8
b
α=d
1
From the curves in Annex II for any value of α or b/d, the corresponding value of can be read off.
π λ
Knowing the values of H and d, the value of GE is easily calculated. It is obvious from equation 5.5 that if
d = 0, GE is infinite. It is therefore, essential that a vertical cutoff should be provided at the downstream
end of the floor. To safeguard against piping, the exist gradient of soils are given in Table 5.5. The uplift
pressures must be kept as low as possible consistent with the safety at the exit, so as to keep the floor
thickness to the minimum.
Table 5.5
5.5: Permissible
Permissible exit gradients for different types of soils
Example 5.2:
A weir has a solid horizontal floor length of 40m with two lines of cutoff 5m depth below the river
bed at its two ends. The floor thickness is 5m at the upstream end and 2m at downstream end, with
its upper level being in flush with the river bed. For an effective head of 4m over the weir, calculate
the uplift pressure at the two inside corner points (junction of bottom of floor with the cutoff) and
also exit gradient.
Solution:
4m
1m 2m
5m C1
E2 5m
D1 D2
40m
Given: Maximum barrage head (Hs) = 4m
Length of weir (b) = 40m
U/S and D/S cutoff depth (d, and d2) = 5m
-131-
Irrigation and Drainage Engineering
For D/S cutoff:
b 40
α= = =9
d 5
1+ 1 + α2 1 + 1 + 82
λ= = = 4.531
2 2
cos–1
λ – 2 1
= cos–1
1 4.531 – 3
φE2 =
π λ π 4.531 = 0.3113 = 31.3%
cos–1
λ – 1 1
= cos–1
1 4.531 – 1
φD2 =
π λ π 4.531 = 0.2155 = 21.55%
φE – φD 31.13 – 21.55
Correction due to thickness = ×t= × 2 = 3.83%
d 5
D d + D 5 5 + 5
C = –19 = –19 = –1.68%
b' b 40 40
D d + D
C = 19 = 1.68%
b' b
Exit radiant,
H.S. 1 5 1 1
GE = = =
d π 8π 10.7
λ 4.531
-132-
Diversion Headworks
Example 5.3:
Calculate the uplift pressure at key points of the pile of the structure shown below. Also check the
thickness provided and safe exit gradient GE = 1/5.
RL 103.0 m
RL 100.0 m Q
1.0m 1.5m 1.25m 1.0m
2.0m
3.0m
1.5m
10m 20.0m
Solution:
Let split composite profile into simple profile,
ΦE ΦC ΦE ΦC ΦE ΦC
1 1 2 2 3 3
ΦD ΦD ΦD
1 2 3
Pile 1 Pile 2 Pile 3
For pile no 1 For pile no 2 For pile no 3
b= 30m b1= 10m b= 30m
d=2m b2=20m d=3m
α = b/d= 15 d=3m α = b/d= 10
1+ 1+α2 α1= b1/d =3.33 1+ 1+α2
λ= = 8.02 α2= b2/d = 6.67 λ= =5.52
2 2
100 0-λ 1+α12 - 1+ α22 100 λ-2
ФE1 = cos-1 = 100% λ1 =
2
= -1.634 ФE3 = cos-1 = 27.99%
π λ π λ
100 1-λ 1+α12 + 1+ α22 100 λ -1
ФD1 = cos-1 = 83.93% λ= = 5.11 ФD3 = cos-1 = 19.46%
π λ 2 π λ
100 2-λ 100 λ1-1 100 λ-0
ФC1 = cos-1 = 77.02% ФE2 = cos-1 = 67.24% ФC3 = cos-1 = 0%
π λ π λ π λ
100 λ1 - 0
ФD2 = cos-1 = 60.36%
π λ
100 λ1+1
ФC2 = cos-1 = 53.96%
π λ
-133-
Irrigation and Drainage Engineering
Correction for Corrected
HGL
Thickness (2)% Mutual Pressure Pressure
Pressure (masl)
ФD - ФC interference (3) Ф% Head (m)
Point Ф% = ×t Slope = 103
d % (5) = (1) + (6) = (5) ×
(1) % (4) - Hs+
ФD - ФE D d+D (2) + (3) + Hs/100
or × t =± 19 (6)
d b' b (4)
E1 100 0 0 0 100 3 103
D1 83.93 0 0 0 83.93 2.52 102.52
C1 77.02 3.46 0.85 0 81.33 2.44 102.44
E2 67.24 -3.44 -0.28 0 63.52 1.91 101.91
D2 60.36 0 0 0 60.36 1.81 101.81
C2 53.96 3.20 0.52 0 57.68 1.73 101.73
E3 27.99 -2.84 -0.80 0 24.35 0.73 100.73
D3 19.46 0 0 0 19.46 0.58 100.58
C3 0 0 0 0 0 0 100.0
Sample calculation
ФD – ФE 60.36 – 67.24
Correction for thickness at point E2 = ×t= ×1.5 = – 3.44
d 3
D d+D 0.5 1.5 + 0.5
Correction for mutual interference at point E2 = –19 = – 19 = – 0.28
b' b 10 30
1.0m
1.5m
2.0M
D = 0.5
d = 1.5
b' = 10.0m
RL 103.0m
102.44
101.91 Hs = 3.0m
100.73
101.73
100% 0%
Q
81.33% 24.35%
63.52% 57.68%
83.93%
19.46%
60.36%
10.0m 10.0m
-134-
Diversion Headworks
Thickness required
Pressure at point Q at the beginning of D/S floor = 1.91m [Take maximum pressure head at that point]
h 1.91
Thickness required = = = 1.56m
G – 1 2.24 – 1
Provided thickness = 1.50m < 1.56 hence unsafe.
0.73
Thickness at the end of floor = = 0.588
2.24 – 1
Provided thickness = 1m > 0.588. Hence safe.
Exit Gradient
H 1
GE = H = 3m
d π λ
d = 3m λ = 5.52 GE = 1/7.38 < 1/5 (safe)
Example 5.4:
5.4:
Find whether the section is safe against uplift at A, also determine the safe against piping.
Pond level 134.0
130.75
1:4
1:5
129.0
127.0
128.40 B
A 126.4
126.0
122.0 122.0
16m 25m 20m
120.0
Solution:
Let split composite profile into simple profile,
-135-
Irrigation and Drainage Engineering
For pile no 1 For pile no 2 For pile no 3
b= 61m b1 = 16m b = 61m
d=129 – 122 = 7m b2 =45m d =127 – 120 = 7m
α = b/d= 8.714 d =129 – 122 = 7m α = b/d= 8.714
1+ 1+α2 α1 = b1/d 1+ 1+α2
λ= = 4.885 α2 = b2/d λ= =4.885
2 2
100 0-λ 1+α12 - 1+ α22 100 λ-2
ФE1 = cos-1 = 100% λ1 = = -2.0 ФE3 = cos-1 = 29.88%
π λ 2 π λ
100 1-λ 1+α12 + 1+ α22 100 λ -1
ФD1 = cos-1 = 79.26% λ= = 4.5 ФD3 = cos-1 = 20.73%
π λ 2 π λ
100 2-λ 100 λ1-1 100 λ-0
ФC1 = cos-1 = 70.11% ФE2 = cos-1 = 73.28% ФC3 = cos-1 = 0%
π λ π λ π λ
100 λ1 - 0
ФD2 = cos-1 = 64.70%
π λ
100 λ1+1
ФC2 = cos-1 = 57.171%
π λ
Correction for
Corrected Pressure HGL
Pressure Thickness (2)%
Poin ФD – ФC Mutual interference (3) % Pressure Ф% Head (m) (masl)
Ф% = ×t Slope
t d D d+D (5) = (1) + (2) (6) = (5) = 134 –
(1) = ± 19 % (4) × Hs/100
ФD – ФE b' b + (3) + (4) Hs + (6)
or ×t
d
E1 100 0 0 0 100 7 134.00
D1 79.26 0 0 0 79.26 5.54 132.54
C1 70.11 0.78 2.52 0 73.41 5.13 132.13
E2 73.28 – 0.73 – 2.52 0 70.02 4.90 131.90
D2 64.70 0 0 0 64.70 4.53 131.53
C2 57.17 0.64 1.99 – 0.51 59.29 4.15 131.15
E3 29.88 – 0.78 – 1.05 0 28.04 1.96 128.96
D3 20.73 0 0 0 20.73 1.45 128.45
C3 0 0 0 0 0 0 127.00
Sample calculation
64.70 – 57.17
Correction for thickness at point C2 = × 0.6 = 0.645%
7
Correction for mutual interference
Effect of pile no 3 on pile no 2
D =128.4 – 120 = 8.4m
d= 128.4 – 122.0 = 6.4m
b’= 45m
b = 61m
D d+D 8.4 6.4 + 8.4
Correction = 19 = 19 = 1.99%
b' b 45 61
-136-
Diversion Headworks
Correction for slope
bs
Slope correction at point C2 = Cs ×
b'
Vertical height = 130.75 – 129.0 = 1.75m
Sloping length bs= 1.75 × 4 = 7m
b' = 45m
Cs = 3.3 for 4:1 slope (from Table 5.4)
bs
Correction = Cs × = – 0.513% (negative for upward)
b'
134.0
131.900
131.149 130.75
1:4
1:5
129.0 128.968
127.0
128.40 B
A 126.4
126.0
122.0 122.0
16m 25m 20m
120.0
Check for uplift press at A
4.149
2.931 128.968
127.0 HGL
127.0
25m 20m
Now, uplift pressure at A, h = 2.931m
h 2.931
Thickness required at A, t = = = 2.363. But provided thickness is = 1m Hence unsafe.
G - 1 2.24 - 1
Now check for exit gradient
H 1
GE =
d π λ
H=7m
d = 127 – 120 = 7 m
λ = 4.18
7 1
GE = = 1/6.42 < 1/5. Hence, the weir is safe against piping.
7 π 4.18
-137-
Irrigation and Drainage Engineering
5.4 Design of Sloping Glacis Weir Bay
Stepwise procedure for the design of the Barrage
Data needed:
i. Maximum flood discharge Q
ii. Stage discharge curve of the river at barrage site
iii. Minimum water level
iv. Cross – section of the river at barrage site.
The following have to be decided:
• Lacey’s silt factor f = 1.76 d where d = mean diameter of particles in mm.
• Length of waterway, discharge per meter and afflux.
• Safe exit gradient
• Depth of sheet piles in relation to
– Scour depth
– Exit gradient
• Level and layout of horizontal part of downstream impervious floor in coordination with hydraulic jump.
• Thickness of downstream impervious floor:
– With reference to uplift pressures.
– With reference to hydraulic jump or standing wave.
• Length and thickness of protection works beyond PCC floor upstream and downstream.
Procedure:
Step 1: Determine head loss HL for different flow conditions.
If there is no retrogression, HL = afflux.
If allowance for retrogression is taken in downstream bed level, then HL = Afflux +
retrogression. Usually 0.5m retrogression will be sufficient in most cases.
Step 2: For known values of q and HL, read corresponding values of Ef2 from Blench curves (Annex
III), with known values of Ef2 read corresponding values of d2.
Cistern level = downstream T.E.L. – Ef2
Step 3: Ef1 = Ef2 + HL, knowing Ef1, Ef2 and q read values of d1 and d2 from Annex IV energy of flow
curves. Provide minimum cistern length 5(d2 – d1); desirable 6(d2 – d1).
Step 4: Determine scour depths from the formula:
R= 1.35(q2/f)1/3 . . . 5.9
Depth of upstream sheet pile from scour consideration = (1 to 1.25) × R
Depth of downstream sheet pile from scour consideration = (1.25 to 1.5) × R.
An intermediate sheet pile line need not normally be provided. If at all provided, its depth
should not be less than that of the upstream pile line.
1 1 d
Step 5: Work out the value of from the equation = GE for the given value of GE and the
π λ π λ H
known value of d (downstream sheet pile) and H (maximum static head). Corresponding to the
1
value of , read the value of d from Annex II
π λ
-138-
Diversion Headworks
Step 6: Provide total length of floor b = α d.
Deposition of total floor length may be as follows:
– Cistern length = 5(d2 – d1) to 6(d2 – d1)
– Glacis length = 3 to 5 times (crest level – cistern level) from 3:1 to 5:1 slope of glacis plus
crest width.
– Upstream floor = the balance.
If the total length is excessive, it would be economical to reduce it by providing a deeper
downstream sheet pile.
Step 7: In order to determine uplift pressure acting on the floor, the % pressures at upstream and
downstream sheet pile lines are worked out. The pressure distribution from upstream sheet pile
line to downstream sheet pile line is assumed to be linear.
Correction due to floor thickness
The thickness of the floor at the location of the sheet piles are tentatively assumed for
correcting the values of ФC in the upstream and ФE in the downstream. If t1 is the floor
thickness at upstream sheet pile of depth d1, correction due to floor thickness = t1/d1 (ФD – ФC)
which is positive. If t2 is the floor thickness at downstream sheet pile of depth d2, the correction
= t2/d2 (ФE – ФD) which is negative.
Correction due to mutual interference of sheet piles
The correction due to mutual interference of sheet pile is worked out by the formula
D d + D
C = +19
b1 b
Correction due to slope
This is applicable only in case where an intermediate pile line is provided. The values of
correction are discussed earlier.
Step 8: After knowing the corrected percentage pressures under the key points the sub – soil pressure
gradient line and hydraulic gradient line for surface flow is plotted with reference to the
corresponding downstream water level as datum. The corresponding water profiles before and
after the jump formation are also plotted for the given value of discharge intensity q.
Knowing q and Ef1 at different location of the glacis, corresponding values of d1 are read from
annex III and thus the water profile before jump formation can be plotted. For plotting water
profile after jump, the Froud number Fr is determined from the relation
q
Fr =
gd12
Knowing Fr relation between the abscissa and ordinate of the profile can be read from the Annex IV.
The uplift pressure which will occur with the maximum pond level upstream and no flow
downstream should also be determined. The requirement of floor thickness is worked out by
taking the larger of the two uplift pressure and dividing it by (G – 1), G being the density of
floor material and (G – 1) the submerged density of floor material.
Step 9: The protection works are designed for the scour depth will discussed in chapter 6.
-139-
Irrigation and Drainage Engineering
5.5 Sediment Control Measures and Devices at the Headwork
The rivers flowing in erodible valleys carry heavy sediment load during floods. The channel which take
off from these rivers draw heavy sediment which they cannot carry due to their slopes being milder than
that of the river. This results in silting of the channel in head regulators. The entry of coarse particles in a
power channel may in addition cause damage to the turbine blades.
In a flowing river the sediment concentration in the bottom portion is much higher and coarser than that
in the upper layers. If the bottom layers are removed without disturbing the natural sediment distribution
in the stream large quantity of sediment in suspension, saltation or moving on the bed shall be removed.
The aim of all sediment control and exclusion measures and devices is to prevent or remove sediment
concentrated in the bottom layers so that the channels are left with sediment near to their sediment-
carrying capacity. In power channels particles larger than 0.25mm is generally required to be removed to
prevent damage to the turbine blades (Varshney, 2001).
5.5.1 Classification of sediment control measures and devices
The various means of controlling sediment into the canal and ejecting that enter the canal may be
categorized as follows:
1. Sediment preventive measures
Entry of sediment into the channel can be discouraged by adopting certain preventive measures
which are generally incorporated in the layout of headworks itself. These include:
(i) River approach conditions. (ii) Alignment of head regulators
(iii) Alignment of guide bunds (iv) Length of divide wall
(v) Relative crest levels of under sluices and the head regulator and
(vi) River regulation
2. Sediment control devices
The bed load moves in the lower layer of flow. A number of devices in the form of submerged bars
have been evolved to diver the bed load away from the head regulator. Some devices have been
conceived with the idea of deflecting upper layers of flow from the main channel into the canal.
The devices may be classified as under:
• Guide vanes
• Skimming platform and
• Vortex tube
3. Sediment exclusion devices
The following devices are included in this category:
(i) Sediment excluder (ii) Sediment ejector
(iii) Settling basin
Sediment excluders are constructed in the river pocket adjacent to the head regulator in order to
exclude the coarse sediment by removing bottom layers of river water. Sediment ejector is
constructed in the head of the canal to eject the slit which may enter the canal inspite of sediment
control measures taken and sediment exclusion devices provided. Settling basins are found to be
quite effective in case of low dams which work on the principle that at a low velocity the sediment is
deposited in the basin and clear water is drawn into the canal or water conductor system.
-140-
Diversion Headworks
5.5.2 Sediment Preventive Measures
I. River approach condition
The curvature of the river flow approaching the canal head regulator is very important from the
point of view of sediment entry into the canal. It has been observed that the canal head regulator
located near the downstream end of a concave curvature is the best for minimum sediment entry.
The river channel leading to the head regulator should however not be very deep.
II. Alignment of head regulator
It has been observed that generally setting back of the upstream abutment of the head regulator from
the line at right angles to the barrage axis is helpful in reducing sediment entry into the canal.
In past, head regulators have been generally aligned at 100 to 105 degrees with barrage axis.
However recent model studies have indicated that the head regulators at an angle between 105 to
110 degrees with the barrage axis are optimum for minimum sediment entry into the canal.
III. Alignment of guide bunds
Suitable alignment of guide bunds helps in generating favorable curvature of flow for minimum
sediment entry into canal. It has been observed that the influence of guide bunds in reducing the
sediment is considerably reduced due to formation of islands upstream of the barrage which is a
common feature in wider barrages. The exact alignment depends on the river approach condition.
IV. Length of divide wall
A divide wall at the end of under sluices helps in creation of favorable flow conditions. In old headworks
very long divide walls have been provided. However, it has been observed that very long divide walls are
not advantageous. Divide wall extending up to 2/3rd the width of the head regulator in case of one head
regulator, and extending up to the end of second head regulator is considered optimum.
V. Relative crest levels of undersluices and head regulator
Crest level of undersluices are kept lower than other barrage bay about 1 m. this helps in maintaining
well defined channel in front of head regulator, the crest level of head regulator is kept 1 m to 4 m
higher than the crest of undersluices. Raised crest of the regulator is found effective in reducing
sediment entry into the canal in case the canal discharge is a small proportion of the river discharge.
VI. River regulation
The river regulation involves the sequence of gate operation for passing the flood discharge through
various barrage bays. The river regulation has a bearing on the sediment entry into the canal. The
usual practices of river regulation are:
(a) Still-pond – when the undersluices bays are entirely closed and flood is passed through other
barrage bays. The canal thus draws the discharge from the still pond in the pocket.
(b) Semi-still pond regulation- when the gates in the undersluices pocket are partially opened and
canal is drawing the discharge from a flowing stream.
(c) The open-flow regulation- when all the gates in the undersluices pocket are fully open. This
condition is conductive to more sediment entry in canal. Both the model and prototype
observations have proved the superiority of still-pond regulation over other methods.
If still pond regulation in which frequent flushing of the pocket is required cannot be adopted
especially on power channels, semi-still pond regulation with progressive increased opening of gates
away from the head regulator may be adopted.
-141-
Irrigation and Drainage Engineering
5.5.3 Sediment Control Devices
Guide vanes in the form of submerged bars may divert the bed load away from the head regulator. This
arrangement can be used for distributary heads. Descriptions of various types of vanes are as follows:
I. King's Vanes
These silt vanes are vertical diaphragm walls parallel to each other, starting in line with the current
and terminating at an angle with it. They are at low height, so as to diver bottom layers of water
loaded with sediment away from the head regulator.
II. Skimming Platform
It consists of a slab supported on piers so as to exclude silt laden bottom water and leaves such
quantity of top water that should fill the offtake. The best shape of the platform is as shown in
figure. However one or both ends can be made square.
The following criteria of design may be adopted.
(i) The minimum depth should be 0.6 m deeper tunnels are preferred.
(ii) Width of platform should be sufficient so that enough water passes over it to fill the offtake
with some spare say 20 to 25%.
(iii) Pier number may be decided from structural considerations. The pier noses should slope 1 in 3.
The noses should be cut water shape.
(iv) The downstream edge of the platform may be made at an angle of 60° to the center line of the
parent channel. The upstream edge may be parallel to the other edge but it should be at 1.5 to
3.0 m "upstream of the upstream" edge at the off-take.
III. Vortex Tube
It consists of an open tube placed across the bottom of the canal either normal to it or at an angle
greater than 30°. To control the flow out of the tube, its downstream end is regulated by a valve. The
upper portion of the tube is removed to trap the sediment. As water passes over the tube, a shearing
action across the open portion sets up a vortex motion within the tube, this has sufficient velocity to
prevent sediment deposition in tube.
5.5.4 Sediment Excluders
The first approach to control sediment entry into the canals was made by F.V. Elsden in 1922. He
suggested diversion of the bottom layers of flow through the tunnels back into the river by putting a
diaphragm at a suitable height without disturbing the sediment distribution. However, the idea took a
practical shape in 1934 when H. W.Nicholson constructed an excluder in the pocket of Lower Chennab
canal at Khanki head works. The design consisted of six tunnels of different lengths covering the full
length of the regulator and discharging into first two layers of the undersluices.
5.5.5 Sediment Ejectors or Extractors
Despite measures which may be taken to prevent sediment entry in the canal, a part of the suspended
sediment of the river would always enter the canal. If the sediment transporting capacity of the canal is
not adequate to carry this sediment, the canal would be silted. In such cases ejectors are provided in the
head reaches to eject part of the coarse sediment that entered the canal.
The the principle of design of various components of the ejector are the same as for excluder.
-142-
Diversion Headworks
5.5.6 Settling basins or sedimentation chamber
Provision of silt excluder is possible in barrages having their crests close to the river bed. In case of high
dams most of the sediment particles settle down in the reservoir and no exclusion devices are required. In
case of low dams which have very little trap efficiency, it is generally necessary to construct sediment
exclusion devices. In such dams, silt excluders cannot be provided and only silt excluders are possible.
When it is desired to exclude very fine suspended particles, settling basins or tanks are used for sediment
exclusion. The low lying area along the canal is converted into a basin by constructing bunds. Silt water
enters from one side and clear water flows back into the canal through the other end. The sediment which
drops down in the basin is either mechanically removed or is flushed out.
Settling tanks or sedimentation chambers have been provided on many irrigation and multipurpose
projects in the country to remove every particle. The recent examples being Seti multipurpose project
Kaski, Trisuli hydropower project and etc.
5.5.7 Advantages and Disadvantages of Excluders and Ejectors
According to F.F Haigh (1934) the advantages and disadvantages of excluders and ejectors are as given
below:
Advantages of Excluders:
(i) The head across the barrage for its operation is usually available.
(ii) Economy is affected by the use of barrage gates and cisterns,
(iii) Large orifices unlikely to be checked by rolling submerged floating debris can be provided
easily.
Disadvantages of Excluders:
(i) The difficulty of securing good approach conditions.
(ii) The undersluices bays covered by the excluders cannot be used simultaneously for the passage
of flood discharge.
(iii) The structure being subject to the river action has to be robust.
Advantages of Ejectors:
(i) Good approach conditions are secured with ease.
(ii) The extent of extraction can be improved by constructing a series of ejectors in the canal.
Disadvantages of Ejectors:
(i) There is difficulty in securing a working head with High River and low canal discharges.
(ii) The size of the head regulator has to be increased to pass additional discharge for the escape.
(iii) The canal section has to be increased upstream of the ejector to accommodate the escape
discharge.
(iv) Comparatively small orifices are liable to be blocked by debris and may necessitate the
provision of trash rack at the canal head regulator.
Despite various advantages and disadvantages of excluders and ejectors, it may be essential to provide
both devices in important canal system.
-143-
Irrigation and Drainage Engineering
5.6 Design of Under Sluice and Silt Excluder
5.6.1 Under sluices
Discharge over weir – bay and sluice bay sections:
Before starting the actual design of weir, the discharge passing over the weir – bay section and that over
the undersluice section should be decided.
The discharge over the undersluice section should be equal to or greater than the greatest of the following:
• It should be at least equal to twice the full supply discharge of the offtaking canal.
• It should be greater than the dry weather flow of the ricer during winter so that the weir crest
gates (or shutters) are not required to be opened.
• It should be a substantial portion of the total design discharge so that small floods can be
passed over the sluice section, without lifting the weir crest gates. It is the usual practice to take
the discharge over the sluice section about 20% of the total discharge and the remaining 80%
discharge over the weir – bay section.
Design Procedure
The design procedure is similar for the undersluice section and the weir bay section. However, the levels
of the two portions are different. Generally, Khosla’s theory is used for design. The procedure may be
summarized as follows:
(i) Fix the discharge over the weir – bay and undersluice bay sections, as discussed above.
(ii) Fix the crest level of the undersluice section and the weir bay section.
• The crest of the undersluice section is usually kept flush with upstream floor. The slope of the
D/S glacis is usually kept between 3:1 and 5:1.
• In the case of weir bay section, as the crest level is higher than the bed level, an upstream glacis is
also provided with a slope of 1:1 to 3:1. The top width of the crest is kept about 2.0m to 3.0m.
(iii) Fix the water way for the weir – bay and undersluice sections.
(iv) Determine the characteristics of the hydraulic jump for the high flood condition and the pond level
condition, with:
• No flow concentration and no retrogression and
• Blow concentration and with retrogression.
(v) Calculate the normal scour depth and determine the bottom levels of the upstream and downstream
piles. If necessary, provide an intermediate pile.
(vi) Find the total length of the impervious floor from the exit gradient consideration. Also fix the
lengths and levels of the upstream and downstream floors. The D/S floor level is fixed below the
point at which the hydraulic jump is formed.
(vii) Calculate the percentage uplift pressure at the key points of all piles by Khosla’s theory for the
following conditions.
• No flow condition
• High flood condition and pond level condition, without flow concentration and without
retrogression.
• High flood condition and pond level condition, with flow concentration and with retrogression.
Draw the subsoil hydraulic gradient line (H.G.L.) for each case.
-144-
Diversion Headworks
(viii) Determine the uplift pressure at various points from the subsoil H.G.L. for low flow condition. Also
determine the suction pressure at the jump through for high flood condition and pond level
condition.
(ix) Calculate the thickness of the floor at various points for the maximum of the uplift obtained for the
three conditions mentioned in step vii.
(x) Provide concrete block protection on the upstream and downstream sides.
(xi) Provide launching aprons on the upstream and downstream sides.
Example 5.5
5.5:
Design the undersluice section of a diversion headworks with the following data:
- Design flood discharge in the river = 9000 m3/sec
- Deepest bed level of the river = 200.00
- High flood level before construction = 206.00
- Full supply level of canal = 203.00
- Permissible afflux = 1.0m
- Bed retrogression = 0.50m
- Discharge concentration factor = 20%
- Lecey’s silt factor = 1.0
- Safe exit gradient = 1/6
- Pier contraction coefficient = 0.10
- Full supply discharge of canal = 200.0 m3/sec
The stage discharge curve of the river at the site is shown below. Assume suitable data if necessary.
-145-
Irrigation and Drainage Engineering
Solution:
Step 1: Crest level
Crest level of undersluice = deepest bed level = 200.00
Crest level of weir bay = 200.00 + 1.5 = 201.50
Pond level = F.S.L. + modular head = 203.00 + 1.0 = 204.00
Step 2: Water way
2 1 2 1
Normal scour depth from Lacey’s formula = R = 1.35 3 = 1.35
q 20.18 3
f 1.0 = 10.00m
Velocity of approach = q/R = 20.18/10 = 2.02 m/s
v2
Head due to velocity of approach=
2g = 0.21m
U/S T.E.L. = U/S HFL + Head due to velocity of approach = 207.00 + 0.21 = 207.21
-146-
Diversion Headworks
(a) Undersluices
Head over the undersluices crest = 207.21 – 200 = 7.21
Since the U/S floor and the crest of the undersluices are at the same level, the width of
crest is large and it will behave as a broad crested weir. Therefore, discharge is given by:
Q = 1.705 (L' – 0.1 × n He) He3/2
Where n is the number of end contraction. Assuming that the end near the divide wall and
the abutment are suppressed, n = 8
Q = 1.705 (80 - 0.1 × 8 × 7.21) 7.213/2 =2450.30 cumec
(b) Weir – bay
Head over the weir bay crest = 207.21 – 201.50 = 5.71m
2H
Let us assume the crest width of weir as 2m. As the crest width B < , the weir will act
3
as a sharp crested weir. Therefore discharge is given by
Q = 1.84 ( L' – 0.1 × n × He) He3/2 = 1.84 ( 300 – 0.1 × 48 × 5.71) 5.713/2 = 6843.61 cumec
Total discharge Q = 2450.30 + 6843.61 = 9293.91 cumecs > 9000 cumecs OK
Let us verify whether the discharge through undersluice is adequate.
Twice the design full supply discharge of canal = 400 cumecs
20% of the total design flood discharge = 1800 cumecs
The discharge capacity of undersluice is more than the minimum required by above two criteria
and may be adopted. As the dry weather flow is not given the third criterion cannot be applied.
Step 4: Design of undersluice section
Let us find out the discharge intensity q and head loss HL for different conditions.
(a) High flood conditions
(i) Without flow concentration and without retrogression
q = 1.705 (He)3/2 = 1.705 × (7.21)3/2 = 33.00 cumecs/m
D/S TEL = 206.00 + 0.21 = 206.21
U/S TEL = 207.00 + 0.21 = 207.21
Head loss, HL = 207.21 – 206.21= 1.00m
(ii) With 20% flow concentration and retrogression of 0.5m
q = 1.20 × 33.0 = 39.6 cumecs/m
He = Head over the crest = (39.6/1.705)2/3 = 8.14m
U/S TEL = 200.00 + 8.14 = 208.14
D/S TEL after retrogression = 206.21 – 0.5 = 205.71
Head loss, HL= 208.14 – 205.71 = 2.43m
-147-
Irrigation and Drainage Engineering
(b) Pond level conditions
At the pond level condition, the velocity of approach can be found from the
discharge which occurs at that level.
Q = 1.705 (80 – 0.1 × 8 × 4.0) (4.0)3/2 + 1.84 (300 – 0.1 × 48 × 2.5) (2.5)3/2
2 1 2 1
Normal scour depth, R = 1.35 3 = 1.35
q 7.05 3
f 1 = 4.96m
Velocity of approach, va=q/R = 7.05/4.96 = 1.42m/sec
va2
Head due to velocity of approach =
2g = 0.10m
U/S TEL = 204.0 + 0.1 = 204.10
The water level on the D/S of the weir when a discharge of 3142.24 cumecs occurs
in the river is obtained from the stage discharge curve as 203.50m.
-148-
Diversion Headworks
Table 5.6
5.6: Hydraulic jump calculation with different conditions
High flood condition Pond level condition
No with No with
S.N. Item concentration concentration concentration concentration
and and and and
retrogression retrogression retrogression retrogression
Discharge
1 intensity q 33.00 39.60 14.15 16.98
cumecs/m
U/S water
2 207.00 207.00 204.00 204.00
level
3 U/S TEL 207.21 208.14 204.10 204.63
D/S water
4 206.00 205.50 203.50 203.00
level
5 D/S TEL 206.21 205.71 203.60 203.10
Head Loss
6 1.00 2.43 0.50 1.53
(HL)
Ef2 from
7 8.60 10.10 4.60 5.80
blench curve
Level at which
the hydraulic
8 197.61 195.61 199.00 197.30
jump is formed
(5) - (7)
Ef1= Ef2 + HL
9 9.60 12.53 5.10 7.33
= (7) + (6)
Pre jump
depth y1(from
10 2.80 2.90 1.80 1.60
montague's
curve)
Post jump
depth , y2
11 (from 7.60 9.00 3.80 5.30
montague
curve)
length of
12 horizontal floor 24.00 30.50 10.00 18.50
= 5(y2 - y1)
Initial Froud
13 q2 2.25 2.56 1.87 2.68
no =
gy3
14 Fr2 5.06 6.55 3.50 7.10
1
q2
15 yc = 3 4.80 5.43 2.73 3.09
g
HL
16 z = 0.21 0.45 0.18 0.50
yc
-149-
Irrigation and Drainage Engineering
The lowest water level at which the hydraulic jump is formed corresponds to the high flood
condition with flow concentration and retrogression and is 195.61. Let us adopt the
downstream floor level is 195.50. The greatest length of the horizontal floor is 30.50 m. Let us
adopt the length of the D/S horizontal floor as 31.0m.
200.00
1m 3
1
199.00 195.00
4.149
2m
191.80 193.00
1+ 1+α2 1+ 1+α2
Now λ = or 3.648 = or α = 6.22
2 2
b = α d or b = 6.22 × 8.50 = 52.9m
Let us adopt the overall length of 53 m as shown above figure.
Length of U/S floor = 8.50m
Length of D/S glacis = 13.50m
Length of D/S floor = 31.00m
-150-
Diversion Headworks
Step 8: Uplift pressure calculations
Let us assume the thickness of U/S floor as 1.0m and that of the D/S floor at the end as 2.00m
for the purpose of calculating the uplift pressures. Khosla’s theory is used for uplift pressure
calculations.
For pile no 1 For pile no 2
b= 53m b= 53m
d=8.20m d=8.5m
α = b/d= 6.46 α = b/d= 6.23
1+ 1+α2 1+ 1+α2
λ= 2 =3.77 λ= 2 =3.65
100 0–λ 100 λ–2
ФE1 = π cos-1 λ = 100% ФE2 = π cos-1 λ =35.07%
100 1–λ 100 λ–1
ФD1 = π cos-1 λ = 76.27% ФD2 = π cos-1 λ = 24.13%
=19
d + D D
=19
d + D D
b b'
= b b'
=19
6.50 + 1.70
1.70
19
7.2 + 12 12
= 0.53%
53 53
= 3.28% 53 53
Corrected ФC1 = 65.56 + 1.30 +3.28 = Corrected ФE2 = 35.07 – 3.95 – 0.53 =
70.14% 31.97%
The level of subsoil hydraulic gradient line HGL can be calculated assuming linear variation
between key points C1 and E2 for different flow condition. As shown in table below.
Table 5.7
5.7 Uplift pressure calculation
U/S D/S Seepage Height of subsoil HGL above D/S water level and its elevation
S. Flow
water water Head U/S pile D/S pile
No. condition
level level (m)
ФC1 = 100 ФC1= 76.27% ФC1 = 70.14% ФC1 = 30.59% ФC1 = 18.29% ФC1 = 0%
8.45 8.5 6.48 5.96 2.6 1.55 0
1 No flow 204 195.5
RL 204 201.98 201.46 198.1 197.05 195.5
High flood
with flow 1.5 1.5 1.14 1.05 0.46 0.27 0
2 concentration 207 205.5
and RL 207 206.64 206.55 205.96 205.77 205.5
retrogression
Flow at pond
level with 1 1 0.76 0.7 0.31 0.18 0
3 flow condition 204 203
and
RL 204 203.76 203.7 203.31 203.18 203
retrogression
-151-
Irrigation and Drainage Engineering
Step 9: Hydraulic jump profile
For high flood condition and flow at pond level, the suction pressure is computed from the
hydraulic jump profile.
(a) Pre jump profile
(b) High flood flow with 20% concentration and 0.5m retrogression.
(c) Pond level flow with 20% concentration and 0.5m retrogression.
The hydraulic jump forms at RL for 195.61 in the first case and 197.30 in the second case, as
already calculated in table 5.8.
Table 5.8
5.8: Pre jump profile calculation
Note: * Point at which hydraulic jump forms for pond level condition.
-152-
Diversion Headworks
For pond level condition, with concentration and retrogression,
For determination of the post jump profile, different values of (x/y1) are assumed and
corresponding values of (y/y1) are read from Annex V, for the known values of Fr2.
Calculations are shown in table 5.9. The distance x and y are measured from the point P where
the hydraulic jump is formed.
Table 5.9
5.9: Post – jump profile calculations
Uplift pressure at various points can be calculated by plotting the hydraulic jump profile for the
two conditions along with the subsoil HGL. Figure 5.10 (a) shows the plot for the high flood
condition. Figure 5.10 (b) shows the plot for the pond level condition. From these plots, it is
found that the maximum unbalanced head (Hd) in the jump trough is equal to 7.80m. The
thickness of the glacis should be designed for 2/3 of this head (i.e. 5.2 m head) or for the static
condition uplift pressure, whichever is greater. Figure 5.10 (c) shows the uplift pressure for no
– flow condition (static condition).
-153-
Irrigation and Drainage Engineering
207.00 206.31
Water surface
7.80m
200.00
198.51
195.61 195.50
8.5m 13.17m
P
(a) High flood conditon
204.00 203.58
203.0
200.00 4.68m Water surface
198.00
197.30 195.50
8.5m 8.10m
200.00 200.00
4.56
Table 5.10 gives the uplift pressure at various points under three conditions. The controlling
uplift is taken the larger of the static condition and 2/3 of the dynamic condition.
It is seen that the dynamic uplift pressure governs the floor thickness up to a length of about
18.50m from the end of crest, whereas the static head governs the rest of the D/S floor
thickness. Provide the floor thickness as shown in figure.
-154-
Diversion Headworks
Table 5.10
5.10:
10: Uplift pressure for different conditions
Distance Level
controlling thickn
from of unbalance Unbalanc
S.No. Unbalnce water water uplift head ess t=
end of glacis HGL head hd 2hd/3 HGL e head hd 2hd/3
HGL (3) head (4) level level (h) (13) h/g-1
crest (1) or (6) (7) = (6) - (8) (10) (11) = (11)
= (3) - (2) (5) (9)
floor (5) (10) - (9)
(2)
1 0 200 200.92 0.92 205 206.46 1.46 0.97 202.5 203.64 1.14 0.76 0.97 0.78
2 3 199 200.73 1.73 202.9 206.42 3.52 2.35 201 203.37 2.37 1.58 2.35 1.89
3 6 198 200.54 2.54 201.45 206.39 4.94 3.29 199.7 203.59 3.89 2.59 3.29 2.66
4 8.1 197.3 200.4 3.1 200.56 206.36 5.8 3.87 198.9 203.58 4.68 3.12 3.87 3.12
5 12 196 200.16 4.16 198.95 206.32 7.37 4.91 200.51 203.55 3.04 2.03 4.91 3.96
6 13.17 195.61 200.09 4.48 198.51 206.31 7.8 5.20 200.71 203.54 2.83 1.89 5.20 4.19
7 13.5 195.5 200.06 4.56 198.7 206.3 7.6 5.07 5.07 4.09
8 18.5 195.5 199.75 4.25 200.4 206.25 5.85 3.90 4.25 3.43
9 23.5 195.5 199.43 3.93 201.6 206.19 4.59 3.06 3.93 3.17
10 28.5 195.5 199.11 3.61 202.86 206.14 3.28 2.19 3.61 2.91
11 33.5 195.5 198.8 3.3 203.58 206.08 2.5 1.67 3.30 2.66
12 38.5 195.5 198.46 2.96 203.91 206.03 2.12 1.41 2.96 2.39
13 44.5 195.5 198.1 2.6 204.31 205.96 1.65 1.10 2.60 2.10
-155-
Irrigation and Drainage Engineering
(ii) Launching apron
Let us provide 9 rows of cement concrete block 1.2m × 1.2m × 1m, having 10cm
gaps filled with bajri.
-156-
Diversion Headworks
-157-
Irrigation and Drainage Engineering
Example 5.6
5.6:
Design the weir bay section for the data given in example 5.5.
Solution:
Crest level of the weir bay section = 201.50.
Let the crest width = 2.0m
Step 1: Determination of discharge intensity (q) and head loss (HL)
Let us find out the discharge intensity (q) and the head loss (HL) for different conditions.
(a) High flood conditions
(b) Without flow concentration and retrogression
As B<2H//3, the weir act as a sharp – crested weir. He = 207.21 – 201.50 = 5.71m
q = 1.84 (He)3/2 = 25.11 cumecs/m
U/S TEL = 207.21, D/S TEL = 206.21m
Head loss, HL = 1.00mWith flow concentration and retrogression
q = 1.2 × 25.11 =30.13 cumecs/m
Head over the crest = (30.13/1.84)2/3 = 6.45m
U/S TEL = 201.50 + 6.45 = 207.95 m
D/S TEL after retrogression = 206.21 – 0.5 = 205.71m
Head loss HL= 207.95 – 205.71 = 2.24m
(c) Pond level conditions
(i) Without flow concentration and retrogression
U/S TEL, as calculated in example 5.4 = 204.10m
Head over the crest = 204.10 – 201.50 = 2.60m
q = 1.84(2.60)3/2 = 7.71 cumecs/m
D/S TEL = 203.60m
Head loss HL = 204.10 – 203.60 = 0.50m
(ii) With flow concentration and retrogression
q = 1.20 × 7.71 = 9.25cumecs/m
Head over the crest = (9.25/1.84)2/3 = 2.93 m
U/S TEL = 201.50 + 2.93 = 204.43
D/S TEL = 203.10m
Head loss HL = 204.43 – 203.10 = 1.33m
-158-
Diversion Headworks
Step 2: Depth of sheet piles
Total discharge over the weir – bay section = 6843.61 m3/sec
Overall water way = 300 + 48 = 348 m
Average discharge intensity, q = 6843.61/348 = 19.67 cumecs/m
Normal scour depth, R = 1.35 (q2/f)1/3 = 1.35 (19.672/1)1/3 = 9.84 m
Bottom level of D/S pile = D/S water level after retrogression – 1.50R
= 205.50 – 1.5 × 9.84 = 190.74, say 190.50m
Bottom level of U/S pile = U/S water level – 1.25 R
= 207.00 – 1.25 × 9.84 = 194.70 say 194.50m
Depth of D/S file below floor = 197.00 – 190.50 = 6.50m
Depth of U/S pile below river bed = 200.00 – 194.50 = 5.50m
Step 3: Hydraulic jump calculation
15
yc = (q2g)1/3
4 4.52 1.82 2.06
1+ 1+α2 1+ 1+α2
Now, λ = or = 4.23 or α = 7.39, b= 7.39 × 6.5 = 48.05m say 50.0m.
2 2
Provide the floor lengths as follows
U/S glacis (1:1) = 1.5m
Crest width =2m
D/S glacis (3:1) = 13.50m
D/S horizontal floor = 28.00m
U/S horizontal floor = 5.00m
Total length = 50.00m
Step 5: Uplift pressure calculation
Let us assume the thickness of the upstream floor as 1.00m and the thickness at the end of the
D/S floor as 2.00m.
For pile no 1 For pile no 2
b= 50m b= 50m
d=5.5m d=6.5m
α = b/d= 9.09 α = b/d= 7.69
1+ 1+α2 1+ 1+α2
λ= 2 =5.07 λ= 2 =4.38
= 19
d + D D
= 19
d + D D
b b' b b'
= 19
4.50 + 0.5 0.5
= 19
4.5 + 8.5 8.5
= 0.19%
50 50
= 2.04% 50 50
Corrected ФC1 = 70.70 + 1.63 + 2.04 Corrected ФE2 = 31.71 – 3.00 – 0.19
= 74.37% = 28.51%
-160-
Diversion Headworks
The levels of the sub – soil hydraulic gradient line (HGL) have been calculated in Table below.
Height of elevation of subsoil HGL
U/S D/S
S. Seepage
Flow Condition water water U/S Pile D/S pile
No. Head
level level
ФE1 ФD1 ФC1 ФE2 ФD2 ФC2
1 No flow 7 5.58 5.21 2 1.54 0
204 197 7
204 202.58 202.21 199 198.54 197
High flood with
flow
concentration 1.5 1.2 1.11 0.43 0.33 0
and 207 205.5 1.5
2 retrogression
207 206.7 206.61 205.93 205.83 205.5
Flow at pond
level with flow
concentration 1 0.8 0.74 0.29 0.22 0
and 204 203 1
3 retrogression
204 203.8 203.74 203.29 203.22 203
For high flood condition and pod level condition, the suction pressure is computed from the
hydraulic jump calculation given in table below.
High flood condition Pond level condition
Distance
from the RL of U/S TEL = 207.95, q = 30.13 cumecs/m U/S TEL = 204.43, q= 9.25 cumecs/m
end of glacis
Ef = U/S TEL - Depth y Water Ef = U/S TEL - Depth y Water
crest
RL of glacis (m) level RL of glacis (m) level
0 201.5 6.45 2.93
3 200.5 7.45 3.4 203.9 3.93 1.3 201.8
6 199.5 8.45 2.9 202.4 4.93 1.05 200.55
7.5* 199 8.95 2.7 201.7 5.43 1 200
9 198.5 9.45 2.6 201.1
12 197.5 10.45 2.4 199.9
13.02** 197.16 10.79 2.35 199.51
Note *: Point at which hydraulic jump is formed for pond level condition.
**: Point at which hydraulic jump is formed for high flood condition.
The pre jump profile and post jump profile are calculate as per above example.
The maximum dynamic uplift pressure hd = 6.81m, 2/3hd = 4.54m
The maximum static pressure = 3.80m.
4.54
Thickness at the toe of glacis = = 3.66 say 3.70m.
(2.24 – 1)
-161-
Irrigation and Drainage Engineering
This thickness shall be provided upto a distance of 5.50m from the toe of glacis. Static uplift
pressure at the end of D/S floor = 199.00 – 197.00 = 2.00m.
2
Thickness at the end of D/S floor = = 1.61m say 1.7m
(2.24 – 1)
The thickness is reduces in step from 3.70 m to 1.70m.
Step 6: Protection works
(a) D/S protection works
(i) D/S concrete blocks
Normal scour depth R = 9.84m
Maximum scour depth = 2R = 19.68m
Scour level = 205.50 – 19.68 = 185.82
Depth D2 below the D/S floor level = 197.00 – 185.82 = 11.18m
Length of inverted filter = 1.5D2 = 16.77m
Provide 13 rows of cement concrete blocks 1.2m × 1.2m × 1m, having 10cm gaps
filled with bajri.
Total length = 13 × 1.2 + 12 × 0.1 = 16.80 m
Provide 0.50 m thick graded filter beneath the blocks.
Total thickness of the concrete block and filter = 1 + 0.5 = 1.50m.
(ii) Launching apron
Horizontal length of launching apron = 1.5D2 = 16.80m (say)
Volume of stone in the launching apron = 2.24D2 = 25.04m3/m
Thickness of the apron in the horizontal position = 25.04/16.80 = 1.50m
(b) U/S protection works
(i) U/S concrete blocks
Normal scour depth R = 9.84m
Maximum scour depth = 1.5R = 14.67m
Scour level = 207.00 – 14.67 = 192.24
Depth D1 below the U/S floor level = 200.00 – 192.24 = 7.76m
Length of concrete blocks = 1.5D1 = 11.6m
Provide 9 rows of concrete blocks of the size 1.2m × 1.2m × 1m, having 10cm gaps
filled with bajri.
Total length = 9 × 1.2 + 8 × 0.1 = 11.60m
Thickness of gravel pack below the concrete blocks= 0.5m
Total thickness of concrete block and the gravel pack = 1.0 + 0.5 = 1.50m
(ii) U/S launching apron
Horizontal length of launching apron = 1.5D1 = 11.60m
Volume of stone = 2.24D1 = 2.24 × 7.76 = 17.38 m3/m.
Thickness of apron in the horizontal position = 17.38/11.60 = 1.50m
Figure below shows the cross section of weir.
-162-
Diversion Headworks
-163-
Irrigation and Drainage Engineering
5.6.2 Silt Excluder
The silt excluder is a device constructed in the river bed just upstream of the regulator to excludes silt
from the water (source) entering the canal. It is so designed that the top and bottom layers of flow are
separated with the least possible disturbance, the top sediment-free water being led towards the canal
while the bottom sediment-laden water is discharged downstream of the diversion structure through under
sluices. The device basically consists of a number of tunnels (Figure. 5.13) in the floor of the deep pocket
of the river, isolated by a dividing wall. The sill or crest level of the regulator is kept the same as that of
the top level of the roof slab of the tunnels.
The capacity of the tunnel is usually kept at about 20% of the canal discharge, and they are designed to
maintain a minimum velocity of 2 – 3 m/sec (to avoid deposition in tunnels). (P.Novak., 2007)
The tunnel have bell – mouthed entrance so as to increase so as to increase the zone of suction. The radius
of bell – mouthing varies between 2 – 6 times the tunnel width; the larger radius is for the tunnel away
from the head regulator. The tunnels are throttled at the exit to increase the velocity to prevent silt
deposition and to reduce the discharge. The roof of the tunnels must be designed to withstand the full
water load up to the high flood level, with no water inside. The tunnels should be safe against impact by
debris, boulders shingles etc.
Section A − A
Sediment-laden flow
Piers Tunnel
sluices
Openings TUNNEL
for sediment
entry
Edge of slab
Dep ressed
floor pocket
-164-
Diversion Headworks
The height (h) of the tunnel is given by, h = crest level of head regulator – upstream floor level of the
undersluice – thickness of the roof slab.
The height (h) generally varies from 0.5 m to 0.6m for rivers with sand particles and 0.8m to 1.2m for
rivers with boulder.
Knowing the total area of cross – section (A) of the tunnels and the height (h), the clear width can be
found. Thus B = A/h
The clear width (B) is suitably divided into a number of tunnels such that the span of the roof slab is not
very large and a suitable number of complete tunnels, and their divide walls, can be accommodated in
each undersluices opening.
The difference of upstream and downstream water levels during floods (i.e. afflux) is usually between 0.6
m to 1m, which is sufficient for the silt excluder to work satisfactorily. However, it is preferable to
provide more head than the minimum required head in order to pass extra discharge for better flushing.
To ensure that the silt – laden water is promptly removed through the silt excluder, sometimes a separate
outfall channels is provided on the downstream of the excluder, especially in rivers with gravel and
boulders. For closing the tunnels, grooves are provided at their entrances in which temporary gates are
inserted whenever required.
Example 5.7
5.7:
Design a silt excluder for the driven head works for the following data:
Full supply discharge of canal = 200 m3/sec
Solution:
Let us take the design discharge as 20% of that of canal design discharge.
Provide 6 no of tunnel, hence each tunnel width = 11.11/6 = 1.85m provide 2 m width each.
-165-
Irrigation and Drainage Engineering
5.7 Silt Ejector or Extractor
The silt ejector is a device constructed on the canal downstream of the head regulator but upstream of the
settling basin (if any), by which the silt, after it has entered the canal, is extracted.
Escape channel
Curved vanes
Curved vanes
A A
B
Section A − A
Diaphragm Canal bed
-166-
Diversion Headworks
2. Vortex type ejector
The vortex tube ejector (Figure 5.15) consist of pipe with a silt along its top, places across the
bottom of the canal at an angle of around 300 – 900 to the direction of flow. The vortex motion
within the tube draws the sediment into it, and the wall velocities along the tube eventually eject the
sediment at its discharge end. A properly designed vortex tube ejector can be more efficient than any
other conventional ejector, with less water loss.
Canal bed
Vortex tube
Figure 5.15: Silt ejector vortex type
Table 5.11:
5.11: Differentiate between Silt Excluder and Silt Ejector
-167-
Irrigation and Drainage Engineering
5.8 Design of Head Regulator
A head regulator is provided at the entrance to the off taking main canal at the diversion headworks. It is
located on the bank of the river just upstream or the undersluice pocket.
1. Crest level
The crest level of the head regulator is usually kept 1.25 to 1.50m higher than the crest level of the
undersluices. However, if a silt excluder is provided in the undersluices section, the crest level of the
head regulator is kept 1.75 to 2.25m higher that of the undersluices.
2. Discharge formula
(a) Pond level condition
The head regulator is usually provided with a very wide and shallow waterway. The drowned
weir formula is generally used for computing the discharge. Figure 5.16 (a)
HFL Gate
h1 FSL
h
Crest x
d FSL
(a) (b)
Figure 5.16: Flow condition at head regulator
2
Q= Cd × B × 2g × [(h + ha)3/2 – ha3/2] + Cd2 × B × d × 2g × (h+ha) . . . 5.10
3 1
Where Cd1 and Cd2 are the discharge coefficients for the free portion and drowned portions,
respectively. Their values are generally taken as 0.577 and 0.80 respectively.
h= head causing flow = pond level – FSL
d = depth of water over crest on the D/S
B = length of crest and
ha = head due to velocity approach.
Neglecting velocity head (small quantity) and solving by using Cd1 = 0.577 and Cd2 = 0.80, we get
Q = 1.71 × B × h3/2 + 3.54 × B ×d × h1/2
(b) High flood conditions
During high floods, the water level on the upstream rises and the regulator gates are partly
closed. Let x be the height of the gate opening when the canal takes the full supply discharge
during floods Figure 5.16 (b). The submerged orifice formula is used for the discharge. Thus
Q = Cd A 2gh1 . . . 5.11
Where h1 is the head causing flow= U/S HFL = FSL
Cd = discharge coefficient (0.62)
A = area of flow
Therefore Q = 0.62 × x × B × 2gh1 . . . 5.12
The value of x can be determined from the known values of Q, B and h1.
-168-
Diversion Headworks
3. Discharge intensity and loss of head
(a) Pond level conditions
Discharge intensity, q = Q/B
Loss of head HL = Pond level – FSL
(b) High flood conditions
Q
Velocity through gates, V =
xB
v2
Velocity head, hd =
2g
v2
Loss of head at entry = 0.5
2g
TEL just upstream at gates= U/S HFL + velocity head in the river
v2
TEL just downstream of gates = TEL just U/S of gate – 0.5
2g
Loss of head HL = TEL just D/S of gate – FSL
Discharge intensity, q = Q/B
4. Depth of piles
(a) U/S pile
The depth of U/S pile is kept the same as in the case of the undersluices.
(b) D/S pile
The bottom level of the D/S pile is taken at a depth of 1.25 R to 1.50 R below FSL.
5. Hydraulic jump calculations
Hydraulic jump calculations are done for the pond level condition and the high flood condition. The
level at which the hydraulic jump is formed is located and the length of jump is determined, as in the
case of the undersluices section. The level of the D/S floor is fixed below the lowest level at which
the hydraulic jump is formed.
6. Thickness of impervious floor
The uplift pressures are determined at the key points of the upstream and downstream piles for the
following conditions:
• No flow conditions
• Pond level flow condition
• High flood flow condition
Thickness of the impervious floor is determined for the worst case.
7. Protection works
(a) U/S protection work
The upstream protection works are similar to those in the case of undersluices.
-169-
Irrigation and Drainage Engineering
(b) D/S protection work
The maximum scour depth is taken as 2R. The length of inverted filter is taken equal to the
depth d2 of the pile below the downstream bed.
The concrete blocks 1.25m × 1.25m × 1.0m with 10cm gaps filled with bajri, are usually
provided over 0.8cm thick invert filter. Thus a total thickness of 1.80m is provided.
The horizontal length of the D/S launching apron is obtained from the volume of stone equal to
2.24d2, and a thickness equal to 1.80m in the horizontal position.
Example 5.8:
Design a head regulator for the data given below:
Crest level of under sluices = 200.00m
Pond level = 204.00m
U/S high flood level = 207.00m
Head due to velocity of approach = 0.21m
Full supply discharge = 200 m3/sec
Full supply level = 203.00m
Bed level of canal = 199.50m
A silt excluder is provided in the undersluices. Take GE = 1/6
Solution:
Crest level of the head regulator = crest level of undersluices + 2.0m
= 200.00 + 2.00 = 202.00m
From equation 5.10,
2
Q= Cd × B × 2g × [(h + ha)3/2 – ha3/2] + Cd2 × B × d × 2g × (h+ha)
3 1
Where h = pond level – FSL = 204.00 – 203.00 = 1.00m
d = 203.00 – 202.00 = 1.00m
Taking Cd1 = 0.577, Cd2 = 0.80 and neglecting the velocity of approach.
2
200= × 0.577 × 4.43 × B × (1)3/2 + 0.80 × B × 1 × 2g × 1
3
200 = (1.704 + 3.544) B or B = 38.11m say 40m.
Provide 5 bays of 8.0m each, with a clear waterway of 40.00m.
Provide 4 piers each of 1.5m thickness.
Overall waterway =5 × 8 + 4 × 1.5 = 46m
At pond level, loss of head, HL = 204.00 – 203.00 = 1.00m
Discharge intensity, q = 200/40 = 5 cumecs/m
At high flood level, let x be the height of gate opening.
-170-
Diversion Headworks
From equation 5.12, 200 = 0.62 x × x 40 2 × 9.81 × 4.0
x = 0.91m
200
Velocity through opening, V = = 5.49 m/sec.
0.91 × 40
v2
Loss of head at entry = 0.5 = 0.77m
2g
TEL just upstream of gate = 207.00 + 0.21 = 207.21m
TEL just D/S of gate = 207.21 – 0.77 = 206.44m
Head loss HL = 206.44 – 203.00 = 3.44m
Discharge intensity q = 5 cumecs/m
Hydraulic jump calculation
The calculations are given in table below:
High flood Pond level
S. No. Item
condition condition
1 Discharge intensity q (cumecs/m) 5 5
2 U/S water level (m) 207 204
3 D/S water level (m) 203 203
4 U/S TEL just upstream of gate (m) 206.44 204
5 D/S TEL (m) 203 203
6 Loss of head (HL) 3.44 1
7 D/S specific energy, Ef2 (from blench curve) (m) 3.3 2.65
8 U/S specific energy, Ef1 = Ef2 + HL (m) 6.74 3.65
9 Pre jump depth y1 from Montague curve (m) 0.45 0.65
10 Post jump depth y2 from Montague curve (m) 3.1 2.5
11 level at which hydraulic jump is formed = (5) - (7) (m) 199.7 200.35
12 Length of impervious floor = 5(y2 – y1) (m) 13.25 9.25
q
Froud no. Fr =
13 gy3 5.29 3.05
2
14 Fr 27.98 9.3
Provide D/S floor at 199.50. Length of D/S floor = 13.50m
Depth of sheet pile
(a) U/S pile
Bottom level of U/S pile will be kept at an elevation of 191.80m as in the case of undersluices.
Depth of U/S pile below the bed = 200.00 – 191.80= 8.20m
-171-
Irrigation and Drainage Engineering
(b) D/S pile
Discharge intensity q = 5.0 cumecs/m
1 1
q2 3 52
Scour depth R = 1.35 = 1.35 3 = 3.95m
f 1
Maximum scour depth = 1.5R = 5.93m
Bottom level of D/S pile = D/S water level – 5.93 = 203.00 – 5.93 = 197.07 m
Depth of D/S below bed, d2 = 199.50 – 197.07 = 2.43m
Provide d2 = 5.00m to reduce exit gradient.
Therefore, bottom level of D/S pile = 199.50 – 5.00 = 194.50m
Length of impervious floor
Seepage head (H) = 207.00 – 199.50 = 7.50m
H 1 1 7.5 1
Now, GE = or = or λ = 8.20
d π λ 6 5 π λ
1+ 1+α2
Now = 8.20 or α = 15.36, α = b/d = 15.36
2
b = 15.36 × 5 = 76.36m say 77m.
Provide the length as follows:
Length of U/S floor = 54m.
Width of crest = 2.00m
D/S glacis = 7.50m
D/S floor = 13.50m
Total = 77.00m
Uplift pressure calculation
Let us assume the thickness of U/S floor as 1.0m and that at the end of D/S floor as 1.50m
(a) U/S pile
d = 8.20m, b = 77m, α = 9.39, λ=5.22
100 0–λ
ФE1 = π cos-1 λ = 100%
100 1–λ
ФD1 = π cos-1 λ = 79.97%
100 2–λ
ФC1 = π cos-1 λ = 71.16%
79.97 – 71.16
(i) Correction for thickness for ФC1= × 1.00 = 1.07%
8.20
-172-
Diversion Headworks
(b) D/S pile
d = 5.0m, b = 77m, α = 15.4, λ=8.22
100 λ–2
ФE2 = π cos-1 λ =22.68%
100 λ–1
ФD2 = π cos-1 λ = 15.86%
100 λ–0
ФC2 = π cos-1 λ = 0%
22.68 – 15.86
(i) Correction for thickness for ФE2 = × 1.50 = 2.05%
5
-173-
Irrigation and Drainage Engineering
Protection works
Depth d2 below the D/S floor = 199.50 – 195.10 = 4.40m. Take d2 as 5.0m
The length of the inverted filter = d2 = 5.0m. Provide 1.25m × 1.25m × 1.00m thick concrete
block, with 10cm gaps filled with bajri, over 0.8 thick graded filter. Thus a total thickness of
1.80m is provided.
Example 5.9:
The accompanying figure shows the profile of a weir. The various levels shown in the figure are in
meters. Determine the uplift pressures at the key points and the exit gradient and find whether the
section provided is safe against piping if it is founded on fine sand with permissible exit gradient of
1/6. Also find uplift pressure at point X and check whether it is safe against uplift.
-174-
Diversion Headworks
100.00
100.00
98.00 ∆
97.00
96.00
X
∆
16m
∆
97.00
93.00
89.50 89.50
65m
Solution:
For pile no 1 For pile no 2 For pile no 2
b = 65m b1= 48m b = 65m
d = 100 – 91 = 9m b=65m d = 6.5m
1/α = b/d = 0.14 d=96 – 89.5 = 6.5m 1/α = d/b= 0.1
From Khosla’s Curve α1= b/d= 65/6.5=10 From the Khosla’s curve
ФD1= 77% b1/b = 48/65=0.746 ФE3 = 29%
-175-
Irrigation and Drainage Engineering
41 – 34
(i) Correction for floor thickness for ФE2 = × 3.00 = 3.2%
6.5
34 – 26
(ii) Correction for floor thickness for ФC2= × 3.00 = 3.7%
6.5
-176-
Diversion Headworks
GE = 1/6.85 which is less than permissible exit gradient 1/6 hence safe.
Px = 4.98 –
4.98 – 2.72
48 × 32 = 3.47m
Px
The floor thickness required at X = = 2.8m
(G – 1)
Actual thickness provided = 3m
Hence it is safe against uplift.
Example 5.10:
An irrigation barrage has to be designed to pass a flood of 10,000 m3/sec, through alluvium media
(mean diameter of particles = 0.33mm). The flood level, pond level and downstream floor level are
207.0m, 204.0m and 198.0m respectively. If the safe exit gradient is 1/6, compute minimum total
impervious floor length required to safeguard the structure from piping. Prepare a conceptual section
of the designed structure.
Solution:
Given, High flood discharge Q = 10000 m3/sec
d50 = 0.33mm
HFL before construction = D/S HFL = 207.0 m
Pond level = 204.0 m
D/S bed level = 198.0 m
-177-
Irrigation and Drainage Engineering
6 1
Now, 1/6 =
6.375 π λ
1
= 0.177
π λ
λ = 3.234
1+ 1+ α2
We have λ =
2
1+ 1+ α2
3.234 =
2
Now α = 5.375
Again α = b/d
Now b = α × d = 5.375 × 6.375 = 34.265m≈34.3m
Hence minimum total impervious floor length required to safe guard the structure from piping = 34.3 m.
34.3m
191.625
Example 5.11:
A river discharge 2000 cumecs of water at high flood level of 273 m. A weir is constructed for flow
diversion with a crest length of 150m and total length of concrete floor as 50m. The weir has to
sustain the under seepage at a maximum static head of 2.4m. The silt factor and the safe exit
gradient for the river bed material are 1.1 and 1/6 respectively. Determine the depth of cutoff
required at the downstream end of the concrete floor. Take the level of downstream concrete floor
level 270m. Check for exit gradient.
Solution:
Given, Q = 2000 cumecs
Length weir, L = 150m
Silt factor, f = 1.7
Q 200
Now, discharge per unit length, q = = = 13.33 cumecs/m
L 150
2 1/3
Scour depth, R = 1.35 = 7.35m
q
f
-178-
Diversion Headworks
HFL before construction or D/S HFL = 273m
Now, R.L. of D/S cutoff = D/S HFL – 1.5R = 273 – 1.5 × 7.35 = 261.975m
R.L of D/S concrete floor = 270m
Depth D/S cutoff =270 – 261.975 = 8.03m
Hr 1
Exit gradient, GE =
d π λ
Here, Hs = 2.4m
d = D/S cutoff depth = 8.03m
Length of concrete floor, b = 50m
b
Now, α = = 6.23m
d
1+ 1 + α2
λ= = 3.654
2
2.4 1 1 1
Now, GE = × = <
8.03 π 3.65 20.08 6
Hence, the weir floor is safe against piping.
D/S HFL 273m
Hs = 2.4
270.00m
1.5R
261.97m
b = 50m
Example 5.12:
A river carries a high flood discharge of 16000m3/sec with its average bed level at 200.0m. A canal
carrying 200m3/sec is to take off from the headworks. The full supply level of the canal at its head is
203.0m. The high flood level before construction is 205.7m and Lacey’s silt factor is equal to unity.
Fix suitable values for the water way and crest levels of weir, under sluices and canal head regulator.
Assume suitably any other data if required.
Solution:
Design discharge for under sluices is taken maximum of:
• 20 % of high flood = 3200 m3/sec
• 2 times the canal design flow = 2 × 200 = 400 m3/sec
Hence design discharge for under sluices = 3200 m3/sec.
Remaining flood discharge of (16000 – 3200 = 12800 m3/sec) will be passed through weir
-179-
Irrigation and Drainage Engineering
Weir Portion
H= 5.51 m
2 1
Maximum scour depth, R = 1.35 3 =11.173 m
q
f
Approach velocity, Va = q/R = 23.81/11.173 = 2.131m/sec
Crest level of canal head regulator = crest level of under sluices + 2 = 200 + 2 (assume) = 202m
which should be less than full supply level of canal.
-180-
Diversion Headworks
Now pond level = full supply level + loss in canal head regulator = 203 + 0.5 (say) = 203.5m
2
Q= Cd × B × 2g × [(h + ha)3/2 – ha3/2] + Cd2 × B × d × 2g × (h+ha)
3 1
Where Cd1 = 0.577 and Cd2 = 0.80 and ignoring velocity head,
Q = B h (1.69h + 3.54d)
Exercise 5
1. Explain site selection of Headwork.
2. Differentiate between weir and barrage with sketches.
3. Draw neat sketch of the general layout of a diversion head works and detail explanation of each
component of head works.
4. With the help of neat sketches, explain how silt excluders and silt ejectors control the bed load in an
irrigation system.
5. Write with definition sketches, how do you determine the pressure along the foundation of the
structure and ensure safety against uplift pressure using Bligh's creep theory.
6. Draw four simple Khosla's profiles for a weir of complex profiles. What corrections Khosla
suggested to accommodate such simplifications?
7. How the bed load is controlled at head works?
-181-
Irrigation and Drainage Engineering
CHAPTER
River training is an essential part of any canal development, when water is diverted from a river, after
constructing a weir across the river and a head regulator for the channel. Sometimes the alignment of
channel can come close to the river or some other stream, and it becomes necessary to divert the
menacing river away from the channel (Varshney, 2001).
The rivers in alluvial plains frequently change their courses. They also overflow their bank and cause
floods. River training works are required to stabilize the river channel along a certain alignment and with
a certain cross section so that river does not cause damage to the land and property adjacent to its bank.
River training works are also required at or near various hydraulic structures such as weirs, aqueducts,
bridges etc. to prevent outflanking of these structures and minimizing cross flows. In case of weirs, these
are also required to provide a favorable curvature of flow at the head regulator for the control of silt entry
into the main canal. The main objectives of the river training works are summarized as follows.
• To provide a safe passage to pass flood without over flowing its banks and thus to prevent
flooding of the adjoining areas.
• To prevent the river from changing its course and eroding adjoining lands.
• To prevent the erosion of banks and hence improve the alignment by stabilizing the river channel.
• To help the river transport the bed load and suspended sediment load efficiently.
• To prevent outflanking of the hydraulic structures and to guide the river to the structures in a
straight and non – tortuous alignment.
• To provide the minimum desired depth of flow required for navigation.
• To provide a favorable curvature of flow at the weir to control entry of silt in to the canal.
• To reduce cross currents in the river which may endanger the hydraulic structures or protection works.
• To deflect the river flow away from a bank or to attract the river flow towards a bank.
• To control and regulate the river bed configuration.
-182-
River Training Works
reaches), meandering, i.e. consisting of a series of bends of alternate curvature connected by short,
straight reaches (crossings), or braided, i.e. the river divides into several channels which continuously join
and separate. The various stages of a schematized river (de Vries, 1985) are shown in Figure 6.1:
Head waters
Middle course
Lower Course
Erosion base
Braided
Meandering
Sea
River regions stages can be divided according to the topography of river basins. Usually they are four:
• The mountainous - Flashy Rivers
• The sub-mountainous - Incised and Boulder Rivers
• The flood plain - Alluvial Rivers
• The deltaic - Tidal and Deltaic Rivers
The characteristics of different (regions) are shown in Table 6.1 (Varshney, 2001):
Table 6.1 Characteristics of River
Course - Narrow, fixed & Well defined Meandering with Very wide
Deep in valley to wide shallow &
meandering changing
Material - Heavy stones Boulders and Gravel and sand Silt and sand
shingles
-183-
Irrigation and Drainage Engineering
-184-
River Training Works
1. Marginal Embankments
Marginal embankments (or levees or dikes or marginal banks) are the earthen embankments which
are constructed parallel to the river banks to confine the flood waters within the cross – section
available between them. These are usually placed at some distance away from the river bank so that
the area of flow is increased Figure 6.2. Generally, the marginal embankments are on both sides of
the river channel, but if the topography is such that one bank is already quite high, there would be a
marginal embankment only on the other side. The marginal embankments prevent the spread of
flood water over the adjoining land. The purpose of these embankments is mainly to control the
river flood. The marginal embankments are generally required for the meandering rivers. The
alignment of these embankments follows the normal pattern of meandering of the river. The distance
by which an embankment is constructed away for the main channel. Is called retirement. Besides the
technical factors, human and political factors should also be considered while deciding the
retirement because the land laying between the two marginal embankments on the opposite banks
remains unprotected from floods.
Levee
River
Levee
2. Guide Banks:
While selecting a site for hydraulic structure on river crossing like barrage, weir, cross drainage
structures bridges, culverts on an alluvial river certain requirements are always kept in mind. These
requirements include straight reach of the river and small width of the river at the bridge site. The
crossing reach between two successive bends of a meandering site is suitable from these
considerations. However, the meandering pattern itself migrates and, hence, steps must be taken to
ensure that the flow path does not change through the waterway at the bridge site, and also that the
approach road embankment is not endangered due to the smaller waterway provided. For this
purpose, earthen embankments are provided on one or both sides of the river at the bridge site.
These embankments are known as guide banks (or guide bunds).
The layout of the guide banks should be such as to guide the flood smoothly through a work
constructed across the river. The guide banks are provided in pairs symmetrical in plan and may
either be kept parallel or converge slightly towards the work, and usually extend a little distance
-185-
Irrigation and Drainage Engineering
downstream from the abutments of the work. They are meant to confine the river within a
reasonable waterway, and direct the flow in a manner that would ensure its safe and expeditious
passage. They should also protect the works from outflanking, and adjacent land from flooding due
to the afflux caused as a result of construction of an obstruction in the river.
The effect of confining the river between the guide banks is to:
a. Increase the rate at which the flood wave travels down the stream
b. Increase the water surface elevation of the river at flood
c. Increase the maximum discharge at all points downstream
d. Increase the velocity and the scouring action through the leveed section
e. Reduce the surface slope of the stream above the leveed portions.
The method of constriction a river for the construction of a bridge and controlling is to make is flow
axially through the bridge and controlling is to make is flow axially through the bridge by means of
a system of guide bunds (first introduced by Bell). This system known as Bell's guide bunds system,
has become a standard practice.
3. Groynes or Spurs
Groynes are structures constructed transverse to the river flow and extend from the bank into river.
These structures are known by several names, the most popular being spurs, Cut-off spur dikes and
transverse dikes, they are probably, the most widely used training works.
(i) Functions of Groynes
Groynes serve one or more of the following functions:-
- Training the river alone a desired course by attracting, deflecting or repelling, the flow in
a channel;
- Creating a slack flow with the object of silting up the area in the vicinity;
- Protecting the river bank by keeping flow away from it; and
- Contracting a wide river channel, usually for the improvement of depth for navigation.
(ii) Types of Groynes
Groynes can be classified as follows:-
- Classification according to method and materials of construction – permeable and
impermeable (solid)
- Classification according to the height of spur below high water – submerged or non-
submerged
- Classification according to the function served – attracting, deflecting and repelling.
- Special types - Denehy's T-headed groynes, Hockey type, Burma Type etc.
SH
SH
SH = Scour Hole
45° - 60° 60° - 80° SP
SP = Still Pocket
Deflecting Repelling
Attracting
-186-
River Training Works
-187-
Irrigation and Drainage Engineering
an erodible material. Ultimately, the river takes the course, where R is the hydraulic radius and L is
the length. A deep and hydraulically efficient pilot channel is required for inducing the artificial cut.
Because the tractive force is directly proportional to the depth of the channel, a deep cut is useful for
the rapid development of the cutoff.
Plan
Figure 6.3: Artificial cutoff
5. Bank Protection and Pitched Banks
Purpose of the bank protection may be anyone or more of the following:
• Training the river
• Protection of adjacent land and valuable property
• Protection of hydraulic structures
• Protection of flood embankment
• Affording facilities for water transportation
Bank protection works may be classified as direct and indirect. Direct protection includes works
done on the bund itself such as providing vegetation cover, pavement, pitching and grading of slope
etc. Indirect protection includes works constructed not directly on the banks, but in front of them for
deducing the erosive action of the current. If the current is strong protection has to be provided by
stone pitching or various types of mattress such as willow, asphalt or articulated concrete. Stone is
the most commonly used material for protection of banks where available locally. The thickness of
pitching required is governed by the velocity of the current near the bank.
6. Pitched islands
A pitched island is an artificially created island in the river bed, either made of masonry or stone
pitched on all sides. On account of the turbulence created by the island placed in a series, a deep
river channel is created and flow is diverted away from the bank in danger. These are used for the
following purposes:
• To train the river to have an axial flow
• To improve channel for navigation purpose
• To correct the adverse curvature for effective sand exclusion
-188-
River Training Works
7. Bandalling
Bandalling is a method of river training which is used to confine the low water flow of a shallow
river in a single channel for maintaining the required depth for navigation. Bandalling is started after
the flood season is over and the water level begins to fall. A bandal consists of a framework of
vertical bamboos, 3 to 6m long, driven into the river bed. The bamboos are driven in a line at a
spacing of 0.6m and are held in position by means of horizontal ties and are supported by struts at
every 1.2m. A number of such bandals are erected depending upon the width of river. Bamboo
mattings are tied to bamboo frameworks with the help of coir ropes. These mattings are usually
0.9m wide and are strengthened at the edges by strips of split bamboos. Bandals are usually erected
at an angle of 300 to 400 to the direction of flow, inclined downstream.
Check the flow and cause sediment deposition parallel to and behind them. Thus a deep channel is
formed in front of the bandals with sand deposition on either side. The whole discharge of the river
is now directed through this deep channel, and therefore the depth of flow is increased. The process
of deepening of the channel usually take about 2 to 3 weeks. Once a channel has deepened, it
remains in that condition till the next flood. It does not require much maintenance. After the flood
has receded, bandals are again constructed.
Deep channel
Bandals
-189-
Irrigation and Drainage Engineering
Divergent bunds exercise an attracting influence on the flow. They are suitable where the river
current has been oblique to the structure. Such bunds have the disadvantages of shoal formation in
between them, if splay is excessive.
Convergent bunds have the disadvantage of excessive attack and heavy scour at the head and
shoaling all along the bank, rendering the end bays ineffective. Due to these drawbacks convergent
guide bunds are rarely used. Thus symmetrical and parallel guide bunds are generally used unless
the local conditions dictate otherwise. The actual layout of the guide bunds depends upon the local
topography site of the structure, alignment of approach embankment, afflux bunds and off-taking
channels.
P = 4.75 Q
Where, P = Lacey’s Regime perimeter in meter
Q = Design flood discharge in cumecs.
The width of large river is approximately equal to its wetted perimeter in alluvial plains. In case of
bridge, weir and barrage, obstruction caused by piers should be accounted for, and the above
equation should be taken to represent the clear effective waterway. It should be remembered that the
regime conditions are disturbed after the construction of the weir, and the above formula is not
strictly applicable. Most of the existing weirs and bridges have been provided with a clear waterway
from 10% to 50% more than that given by Lacey’s Regime Perimeter. Mathematically, Length of
waterway L = (1.1 to 1.5)P
3. Length of Bund
Spring and Gales co-related the length of the guide bund with the length of the structure (water weir)
between abutments (L) and have recommended the upstream length of the guide bunds as 1.25L for
flood discharge up to 20,000 cumecs and 1.5L for flood discharge more than 20,000 cumecs.
-190-
River Training Works
In some cases where the channel bank is wide, the guide bunds according to this criterion may not
provide enough protection to the approach embankments. Therefore in such cases the length and the
layout of the guide bunds should be determined in a manner that the approach embankments are safe
against the worst possible embankment.
If the distance of the channel edge is large, a double loop may be formed. The alignment of the
approach embankment plays an important role in deciding the length of the guide bund. The
approach embankment curved in the upstream are protected in the zone of possible meander and are
frequently attacked in spite of the provision of suitable guide bunds. The approach embankment
should, therefore be located along the axis of work up to the channel edge preferably with a curve
towards downstream to counterbalance the inadequacy of the guide bunds.
On the downstream the river fans outs as to attain its normal width. The downstream portion of
the guide bank ensures the safety of approach embankments and prevents the river from
attacking them. This purpose can be well served by providing short guide bund with sharp
curved head. A radius equal to half of the radius at the upstream side may be adopted here and
sweep angle of 45° to 60° may be provided.
-191-
Irrigation and Drainage Engineering
A
x Impregnable
head
x
120° to 140° B
y y
HFL
t = 0.06 Q1/3
2 y
1 T = 1.9t
1.5D
D xR
(b) Section at x − x
-192-
River Training Works
HFL
t = 0.06 Q1/3
2 y
1 T = 1.9t
1.5D
D xR
(c) Section at y − y
The straight portion of the guide bank BC (in Figure 6.6(a)) is called the shank portion. The guide
banks should have a minimum top width of 4 meters so as to provide sufficient carriage way. Extra
width may, however be provided for storing pitching materials, etc. Side slopes may vary from 1.5H
:1V to 2.5H:1V. (But generally kept as 2H:1V), depending on the construction materials and the
height of the bund. A freeboard of 1.2 to 1.5 m is generally provided.
6. Slope Pitching
The river side should be pitched with one man stone weighing 40 to 50 kg or concrete blocks. The
rear shank slope may be covered with a coating of 0.3 to 0.6 m earth for growth of vegetation to
resist rain and wind erosion.
7. Launching apron
The face of the guide bund is protected at river bed level by stone pitching so that during floods the
sloping face is not damaged. Scour would occur at the toe with consequent undermining and
collapse of the stone pitching. To obviate such damage to the slopes, a stone cover known as apron
is laid beyond the toe on horizontal river bed so that scour undermines the apron first starting at its
farther end and work backwards towards the slope. The apron then launches to cover the face of the
scour, with stones forming a continuous carpet below the permanent slopes of the guide bunds.
Adequate quantity of stones for apron has to be provided to ensure complete protection of the whole
of the scoured face. Generally scour slope of 2H:1V is assumed. In this case the length of the
scoured face will be equal to 5 D . The thickness of apron in launched position is assumed as 1.25t,
where t is the thickness of slope pitching. Then the volume of stone required in the launched apron
per unit length= 22 + 12 × D × 1.25t = 2.5 t D.
-193-
Irrigation and Drainage Engineering
The launching apron is generally laid in a width equal to 1.5 D. where D is scour depth below the
original bed. The total scour below HFL is taken as xR, where R is the Lacey’s normal scour depth
1
given by equation. R=0.47 Q 3
f
Where Q is the discharge and f is the silt factor, values of x are tabulated for different below places
of guide band.
S. N. Locations Mean value of x D = xR – y (water depth above bed)
1. Noses of guide banks 2.25 2.25R – y
2. Transitions from noses to 1.5 1.5R – y
straight portions
3. Straight reaches of guide 1.25 1.25R – y
bunds
If the width of unlaunched apron is 1.5D, then the thickness of the unlaunched apron T is given as:
2.8 × t × D
T= =1.87t = 1.9t
1.5D
Example 6.1:
A bridge is to be constructed across a river, having the following hydraulic data:
• Maximum discharge = 17000 cumecs
• Highest flood level = 288.0 m
• River bed level = 280.0 m
• Average diameter of the river bed material = 0.10 mm
Find out the desired waterway for the bridge. Design Bell’s guide bunds including launching apron
and also guide banks on either side to train the river. Big boulders are available in a hilly torrent
nearby.
Solution:
Step 1: Length of waterway
Lacey’s regime perimeter
P = 4.75 Q
P= 4.75 17000 = 619.32 m
Allowing 20% extra for piers etc. the length of the overall waterway between two guide banks
at the bridge site is obtained as:
L= 1.2 × 619.32 = 743.189 ≈ 744 m
Step 2: Length of guide bank
The length of the guide bank upstream of bridge = 1.25 × L = 1.25 × 744 = 930 m
The length of the guide bank downstream of bridge = 0.25 × L= 0.25 × 744= 186 m
-194-
River Training Works
The radius of U/S curved head of the guide bank = 0.45 × L = 334.8 m
The U/S curved head may be provided with a sweep angle of 135O.
The radius of D/S curved head of the guide bank = R/2 = 334.8/2 = 167.4m
The top width of the guide bank is assumed as 4 m and the side slopes as 2:1
Now, Height of guide bank above the bed of the river = 289.5 – 280.0 = 9.50m
Thickness of stone pitching on the side slopes of the guide bank is given by
The volume of stone required for pitching per meter length = 5 × 9.50 × 1.55 = 32.926
m3/m≈33 m3/m
At the nose:
Depth of scour below the river bed (D) = xR – Y = 2.25 × 14.66 – 8 = 25m
-195-
Irrigation and Drainage Engineering
135° B
744m
y y
289.5m
HFL = 288.0m
t = 1.55 m
2 8
1 T = 2.945m
280.0m
37.5m
25 xR
(b) Section at x − x
-196-
River Training Works
289.5m
HFL = 288.0m
t = 1.55m
2 8
1 T = 2.945m
280.0m
37.5m
25 xR
(c) Section at y − y
Eroded Bank
Groine IV Groine V
Groine III
Groine VI
Groine VII
Future Bank
Groine II
B
Groine I
A
Rectified Bank
-197-
Irrigation and Drainage Engineering
Permeability
Where it is necessary to provide a significant reduction in flow velocity, a high level of flow control, or
where the structure is being used on a sharp bend, the spur's permeability should not exceed 35 percent.
• Where it is necessary to provide a moderate reduction in flow velocity , a moderate level of
flow control, or where the structure is being used on a mild to moderate channel bend, the
spurs with permeability up to 50 percent can be used.
• In environments where only a mild reduction in velocity is required, where bank stabilization
without a significant amount of flow control is necessary, or on mildly curving to straight
channel reaches, spurs having effective permeability up to 80 percent can be used. However,
these high degrees of permeability are not recommended unless experience has shown them to
be effective in a particular environment.
• It is recommended that jack and tetrahedron retardance spurs be used only where it can be
reasonably assumed that the structures will trap a sufficient volume of floating debris to
produce an effective permeability of 60 percent or less.
• It is recommended that Henson-type spurs be designed to have an effective permeability of
approximately 50 percent.
• The greater the spur permeability, the less severe the scour pattern downstream of the spur tip.
As spur permeability increases, the magnitude of scour downstream of the spur decreases
slightly in size, but more significantly in depth.
• The vertical structural members of permeable spurs should be round or streamlined to
minimize local scour effects. The greater the spur permeability, the lower the magnitude of
flow concentration at the spur tip.
• If minimizing the magnitude of flow deflection and flow concentration at the spur tip is important to a
particular spur design, a spur with permeability greater than 35 percent should be used.
• The more permeable the spur, the shorter the length of channel bank protected downstream of
the spur’s riverward tip.
• Spurs with permeability up to approximately 35 percent protect almost the same length of
channel bank as do impermeable spurs; spurs having permeability greater than 35 percent
protect shorter lengths of channel bank, and this length decreases with increasing spur
permeability.
• Because of the increased potential for erosion of the channel bank in the vicinity of the spur
root and immediately downstream when the flow stage exceeds the crest of impermeable spurs,
it is recommended that impermeable spurs not be used along channel banks composed of
highly erodible material unless measures are taken to protect the channel bank in this area.
-198-
River Training Works
Spur Length
• As the spur length is increased,
– The scour depth at the spur tip increases,
– The magnitude of flow concentration at the spur tip increases,
– The severity of flow deflection increases, and
– The length of channel bank protected increases.
• The projected length of impermeable spurs should be held to less than 15 percent of the
channel width at bank-full stage.
• The projected length of permeable spurs should be held to less than 25 percent of the channel
width. However, this criterion depends on the magnitude of the spur’s permeability. Spurs
having permeability less than 35 percent should be limited to projected lengths not to exceed
15 percent of the channel’s flow width. Spurs having permeability of 80 percent can have
projected lengths up to 25 percent of the channel’s bank-full flow width. Between these two
limits, a linear relationship between the spur permeability and spur length should be used.
Spur Spacing
• The spacing of spurs in a bank-protection scheme is a function of the spur’s length, angle, and
permeability, as well as the channel bend’s degree of curvature.
• The direction and orientation of the channel’s flow thalweg plays a major role in determining
an acceptable spacing between individual spurs in a bank-stabilization scheme.
• Reducing the spacing between individual spurs below the minimum required to prevent bank
erosion between the spurs results in a reduction of the magnitude of flow concentration and
local scour at the spur tip.
• Reducing the spacing between spurs in a bank-stabilization scheme causes the flow thalweg to
stabilize further away from the concave bank towards the center of the channel.
• A spacing criteria based on the projection of a tangent to the flow thalweg, projected off the
spur tip should be used.
Spur Angle/Orientation
The primary criterion for establishing an appropriate spur orientation for the spurs within a given spur
scheme is to provide a scheme that efficiently and economically guides the flow through the channel
bend, while protecting the channel bank and minimizing the adverse impacts to the channel system.
• Spurs angled downstream produce a less severe constriction of flows than those angled
upstream or normal to flow.
• The greater an individual spur’s angle in the downstream direction, the smaller the magnitude
of flow concentration and local scour at the spur tip. Also, the greater the angle, the less severe
the magnitude of flow deflection towards the opposite channel bank.
• Impermeable spurs create a greater change in local scour depth and flow concentration over a
given range of spur angles than do permeable spurs. This indicates that impermeable spurs are
much more sensitive to these parameters than are permeable spurs.
• Spur orientation does not in itself result in a change in the length of channel bank protected for
a spur of given projected length. It is the greater spur length parallel to the channel bank
associated with spurs oriented at steeper angles that results in the greater length of channel
bank protected.
-199-
Irrigation and Drainage Engineering
Spur Height
• The spur height should be sufficient to protect the regions of the channel bank impacted by the
erosion processes active at the particular site.
• If the design flow stage is lower than the channel bank height, spurs should be designed to a
height no more than three feet lower than the design flow stage.
• If the design flow stage is higher than the channel bank height, spurs should be designed to
bank height.
• Permeable spurs should be designed to a height that will permit the passage of heavy debris
over the spur crest and not cause structural damage.
• Permeable spurs should be designed with level crests unless bank height or other special
conditions dictate the use of a sloping crest design.
• Impermeable spurs should be designed with a slight fall towards the spur head, thus allowing
different amounts of flow constriction with stage (particularly important in narrow-width
channels), and the accommodation of changes in meander trace with stage.
-200-
River Training Works
• Careful consideration must be given to designing a spur that will maintain contact with the
channel bed and channel bank so that it will not be undermined or outflanked. Methods and
examples presented herein can be used to ensure adequate bend and bank contact.
• The spur head or tip should be as smooth and rounded as possible. Smooth, well-rounded spur
tips help minimize local scour, flow concentration, and flow deflection.
Exercise
1. What is river training works? Explain with sketch three methods of training works normally adopted
in Nepalese river.
2. Design the length, radius of curved head, length and thickness of launching apron of a guide bund to
train a river with the following data.
4. The launching apron of a guide bank is laid in a width equal to 1.8 times the depth of scour below
original bed. If a scour slope of 3:1 is to be maintained with thickness 1.5t, find the thickness of
apron before it get launched. Draw neat sketch of designed structure.
5. Calculate the thickness of a 7m long launching apron of loosed stones for a shank portion of guide
bund at a bridge site of a river having design flood of 8000 m3/sec and flood depth of 5m. Assume
that average diameter of river bed material at flood time is 0.3mm.
-201-
Irrigation and Drainage Engineering
C HA P T ER
7 Regulating Structures
The structures (or masonry works) constructed on a canal to control and to regulate discharge, velocity,
depth etc. are known as canal regulation works. These structures are required for proper and efficient
functioning of an irrigation canal system. The water which enters the main canal through a head regulator
installed at the canal headworks is distributed into different branches and distributaries. To distribute the
water effectively, the discharge is regulated in these smaller channels.
The distributary head regulator is constructed at the head of a distributary (or a branch canal) to control
and to regulate the flow of water into the distributary. Thus a distributary head regulator provides a
necessary link between the parent channel and the offtaking channel.
A cross – regulator is generally constructed across the parent channel at the downstream of the off – take
point of the offtaking channel for raising up the water level in the parent channel when its discharge is
less than the full supply discharge. Cross regulators are also constructed for various other purposes.
A canal fall is a structure constructed on a channel to effect a sudden change in the bed level of the
channel. Canal falls are required on a channel when the slope of natural ground along the alignment of a
channel is steeper than the bed slope of the channel. If a fall is not provided, the channel will go in
excessive filling, which is not desirable.
The offtaking channel should take its proportionate share of sediments of the parent channel. Various silt-
excluding devices are provided at the distributary head regulator. The aim of all such devices is to
separate the bottom layers of water charged with the concentrated sediment load from the top layers and
to draw top layers of clear water into the offtaking channel without causing any disturbance.
1. The best alignment of the offtaking channel is when it makes nearby zero angle with the parent
channel initially and then separates out gradually along a transition curve as shown in Figure 7.1.
The transition curve should be properly designed to avoid accumulation of silt in the form of a silt
jetty and to ensure equitable distribution of silt.
-202-
Regulating Structure
Distributary head
regulator
2. If the transition curve are not provided, the alignment shown in Figure 7.2 may be adopted. In this
case, the offtaking channel as well as the parent channel on downstream make an angle with the
parent channel on upstream of the offtake point.
Parent canal
Cross regulator
3. If it is essential to keep the parent channel straight the edge of the channel rather than the center line
should be considered while deciding the angle of off take as shown in Figure 7.3 (a). An angle of
600 to 800 is quite suitable. However, for large and important works the model studies should be
conducted to determine the most suitable angle.
-203-
Irrigation and Drainage Engineering
Figure 7.3 (b) shows an unbalanced offtake, which should be avoided as far as possible. This usually
results in the formation of silt jetty. Moreover, the deviated current of water scours the bed along the
deviated line to make up the loss of silt due to jetty formation.
Parent canal
Cross regulator
(a)
Cross regulator
Silt jetty
(b)
4. When a number of channels off-take from one parent channel, the alignment shown in Figure 7.4 is
generally adopted. In this case, the off-taking channels are generally flumed to accommodate all the
off-takes in the normal width of the parent channel. In this case, only one cross – regulator serves
the purpose of a number of cross – regulators which would have been required if separate off – take
points were provided for different off-taking channels.
-204-
Regulating Structure
DHR
Parent canal
7.2 Function of Head regulator, Cross Regulator, Outlet, Drop and Escape
The regulators are required on a channel to regulate and control the supply of water. The functions of the
distributary head regulator and the cross – regulator are summarized below.
7.2.1 Function of Distributary Head Regulator
A distributary head regulator serves the following main purposes.
1. It regulates the supply of water from the parent channel to the offtaking channel.
2. It controls the entry of silt into the offtaking channel.
3. It can serve as a meter for the measurement of discharge.
4. It is used for shutting off the supply into the offtaking channel when water is not needed, or when
the offtaking channel is required to be closed for repairs or maintenance.
7.2.2 Function of Cross Regulator
1. The main function of cross regulator is to raise the water level in the parent channel in the upstream
so that the offtaking channel can take its full supply even when the water level in the parent channel
is lower than F.S.L.
2. It is also used to close the supply in the parent channel on its downstream. The supply in that case is
usually directed to other channels. If an escape is also provided in conjunction with a cross
regulator, the water can be directed to the escape channel.
3. There is usually a bridge on the cross regulator, which provides a means of communication.
4. It helps to absorb fluctuations in the various section of the canal system and thus prevents braches in
the tail reaches.
5. It can be used to control discharge at an outfall of a canal into another canal or a lake.
-205-
Irrigation and Drainage Engineering
6. It can be very easily combined with a canal fall: in which case, it helps to control the water surface
slope for bringing the canal to a regime slope and to a balanced depth.
7. It can be sued to control the drawdown when the subsoil water levels are high to ensure safety of
canal lining.
8. Cross regulators are useful for effective regulation of the entire canal system. In a good canal
system, a large number of cross regulators are usually provided.
7.2.3 Function of Outlet (Modules)
A canal outlet or a modules is small structure built at the head of the watercourse so as to connect it with
a minor or a distributary channel. Thus the water course takes water from the distributary channel at the
outlet and carries it to the agricultural fields. An outlet for a water course serves the same purpose as a
distributary head regulator serve for the distributary. Of course its size is much smaller. The importance
of an outlet is considerable because it is a connecting link between the distributary maintained by the
government and a water course maintain by farmers. The functions of the outlet are as follows:
1. To take water from minor or distributary channel.
2. It distributes water in required proportions in fields.
3. An out let may also be used for the measurement of discharge being supplied to the water course.
7.2.4 Function of Escapes
An escape is a structure constructed in irrigation channel for disposal of surplus water from the channel.
Hence it is also called surplus water escape or canal surplus escape.
Function of escape:
1. It helps to overflow the extra surplus water from the canal safely.
2. It prevents the damage and de – function of irrigation canal due to flood water.
3. It prevents the damage of the farming land by spilling the excess water to streams.
4. It helps scouring of excess bed silt deposited in canals.
7.2.5 Function of Drop Structure
Whenever the available natural ground slope is steeper than the designed bed slope of the channel, the
difference is adjusted by constructing vertical falls or drops in the canal bed at suitable interval.
Function of fall:
1. It lowers the bed level and water level of the channel to maintain the ground level.
2. It provides safety against erosion in bed and bank due to excess energy flow.
-206-
Regulating Structure
(b) The crest level of a distributary head regulator is generally kept 0.3m to 1m higher
that the crest level of the cross regulator [Figure 7.6]
Gated structure
Wing wall
U/S FSL
D/S FSL
U/S Bed Crest level
∆ ∆ 2:1 D/S Bed
∆ ∆ ∆
yn/3 + 0.6 ∆ yd/2 + 0.6
U/S FSL
-207-
Irrigation and Drainage Engineering
h1
1
Refer Chapter 5
-208-
Regulating Structure
-209-
Irrigation and Drainage Engineering
2
Water way: Q = Cd 2g B [(h + hv)3/2 – hv3/2] + Cd2 B h1 2g (h + hv)
3 1
Ignoring velocity head; Cd1 = 0.577 and Cd2 = 0.8
Q = B h [1.7 h + 3.54 h1]
Here h = U/S FSL – D/S FSL = 118.10 – 117.90 = 0.2m
h1 = D/S FSL – Crest level = 117.90 – 115.60 = 2.3m
Now; 140 = B 0.2 [1.7 × 0.2 + 3.54 × 2.3]
Solving; B = 27.65m
Provide 4 bays of 7m each with a clear water way = 4 × 7 = 28 m
Provide 3 number of pier of 1.5m width each = 4.5 m
Thus the overall waterway = 28 + 4.5 = 32.5 m.
Step 2: Design of impervious floor
1. Level of impervious floor
Q = 105 m3/sec.
q = Q/B= 105/28 = 3.75 cumecs/m
HL = U/S FSL – D/S FSL = 0.2
From Blench curve (Annex III); Ef2 = 1.95m
(a) D/S floor level = D/S FSL – Ef2 = 117.90 – 1.95 = 115.95m
(b) D/S bed level = D/S FSL – D/S flow depth = 117.90 – 2.5 = 115.40m
Hence provide the cistern or D/S floor at RL = 115.40m (Lower of a and b)
2. Length of D/S floor
(a) From Energy consideration
Length of D/S floor required = 5(y2 – y1)
From Annex III for Ef2 = 1.95; y2 = 1.7 m
Ef1 = Ef2 + HL = 1.95 + 0.2 = 2.15m; y1 = 0.7m
Length = 5(y2 – y1) = 5 (1.7 – 0.7) = 5m
(b) From exit gradient consideration
H 1
GE = Where; H = maximum static head, which is caused when there is full water
dπ λ
on U/S and there is no water on D/S.
H = U/S FSL – D/S bed level = 118.10 – (117.90 – 2.50) = 2.7 m
d = D/S cutoff depth = yd/2 + 0.6 = 2.5/2 + 0.6 =1.85m
1 2.7 1
=
5 1.85 π λ
1
= 0.137 ; λ = 5.3983
π λ
-210-
Regulating Structure
1 + 1+α2
We have λ =
2
Solving we get α = 9.74
b = α.d = 9.74 × 1.85 = 18.03 m say 18.1m
2
Minimum D/S floor length required = × b = 12.1m
3
Hence provide 12.1m as the D/S floor length
Provide sloping glacis with slope 2:1
Now glacis length = 2 × (115.60 – 115.40) = 0.4m
The balance, i.e. 18.1 – 12.1 – 0.4 = 5.6 m is provided as U/S floor length, as shown in
figure below.
2:1
118.10
117.9
115.6 Crest level
2:1 115.4
1.5m 2m
-211-
Irrigation and Drainage Engineering
-212-
Regulating Structure
1
= 0.137 ; λ = 5.3954
π λ
1 + 1+α2
We have λ =
2
The depth of U/S cutoff below U/S floor level = (yu/3 + 0.6) = 2.5/3 + 0.6 = 1.43m ≈ 1.5m
RL of bottom of U/S cutoff pile = 115.60 – 1.5 = 114.10 m
(b) D/S cutoff
The depth of U/S cutoff below U/S floor level = (yd/2 + 0.6) = 1.6/2 + 0.6 = 1.4m adopt 1.5m.
RL of bottom of U/S cutoff pile = 115.5 – 1.5 = 114.0 m
The floor thickness should be provided by Khosla’s seepage theory as worked out in
examples of chapter 5.
-213-
Irrigation and Drainage Engineering
Gated structure
7.4 Outlets
The canal outlet is a small structure built on the bank of a distributary channel through which water is
supplied to a water course (or a field channel). In other words, the canal outlet is a structure provided at
the head of the water course to connect it to the distributary channel. Thus the water course takes water
from the distributary channel at the outlet and carries it to the agricultural fields.
An outlet for a water course serves the same purpose as a distributary head regulator serves for the
distributary. Of course, its size is usually much smaller. The importance of an outlet is considerable
because it is a connecting link between the distributary maintained by the department and a water course
maintained by the cultivators.
An out let may also be used for the measurement of discharge being supplied to the water course. The
discharge through an outlet is usually less than 85 lps. A canal outlet is also called an irrigation outlet or a
module. The adjective canal in canal outlets is necessary to avoid the ambiguity with the dam outlets.
The design of a canal outlet is of great importance for the canal management as well as for the cultivators.
The cultivators aim is usually to get an ample supply of water for the crops whereas the aim of the
department is to ensure an equal distribution of water when the supply is limited. An outlet plays an
important role in the equitable distribution of available water to all the cultivators.
7.4.1 Requirements of Good Canal Outlets
A good canal outlet should fulfill the following requirements.
1. It should be simple in design, construction and maintenance.
2. It should be quite strong and durable. It should not have any movable part which is likely to be
easily damaged or which requires periodical maintenance.
3. The outlet should be such that it is not easily tampered with by the cultivators to increase the discharge in
the water course. Moreover, if tampered with, it should be easily detectable and repairable.
4. It should be able to work efficiently and draw its full discharge even under a small working head.
5. It should draw its due share of silt.
6. It should not be expensive.
7. Its design should be such that it can be easily constructed by the local workers.
8. The design of the outlet should be such that it draws discharge according to the fluctuation of the
discharge in the distributary. In other words, it should draw proportionately less water when the
discharge in the distributary is less.
-214-
Regulating Structure
-215-
Irrigation and Drainage Engineering
5. System of assessment
The out-let capacity is related to the method of assessment of the water supplied to the cultivators. If
the assessment is based on the volume of water supplied or on the capacity of the outlet, the outlets
should have a constant capacity. On the other hand if the assessment is based on the area irrigated,
the outlet capacity should vary with the variation in the water levels of the distributary and the water
course.
The pipe is usually provided with face walls at its upstream and downstream ends. The pipe is laid on a
concrete foundation of lean concrete to prevent uneven settlement and consequent leakage. The pipe is
generally fixed horizontally at right angles to the direction of flow in the distributary. Its inlet is kept
about 22.5 cm below the water level in the distributary. However, in the case of main canal or a branch
canal, where considerable fluctuation in water level can take place the inlet is fixed at a suitable level
taking into consideration the minimum water level likely to occur.
-216-
Regulating Structure
Because there is considerable disturbance at the entrance to the pipe, this type of outlet usually takes its
due share of silt. If required, the silt conduction can be further improved by depressing the inlet of pipe
and placing the pipe sloping upwards from the inlet to the exit at a slope not steeper than 1 in 12. It is the
common practices to place the pipe inlet at a bed of distributary to enable the outlet to draw a fair share of
silt carried by the distributary.
Sometimes, a non – modular outlet consists of a rectangular or circular opening with a pavement. It may
also be an open sluice instead of a pipe.
Discharge formula
The discharge through a pipe (or barrel) non – modular outlet is determined by equating the difference (h)
in the water levels in the distributary and the water course to the sum of losses at entry, due to friction and
at exit. Thus,
V2 f L V2 V2
h = 0.5 + + . . . 7.1
2g 2gd 2g
Where h = difference in water levels of the distributary and the water course,
V = velocity through the pipe.
L and d = length and diameter of the pipe respectively.
q = C a × 2gh . . . 7.3
Where C is the coefficient of discharge which depends upon the friction factor, length and diameter of
pipe and is given by
1
C= 2
d
1.5d + f L
The value of the friction coefficient ' f ' varies from 0.02 for clean pipe to 0.04 for slightly encrusted iron
pipes. For earthen pipes, its value is usually taken as 0.03.
In general the values of C varies from about 0.61 to 0.51 for encrusted pipes of diameter 10 to 25 cm and
of length of 3 to 15m. For an average value of 0.55, the discharge can be expressed as
-217-
Irrigation and Drainage Engineering
Example 7.2
Design a non – modular pipe outlet for the following conditions:
Discharge through the outlet = 0.02 cumecs
Length of the outlet = 15m
FSL of the distributary = 200.00
Available working head = 5cm
Coefficient of discharge = 0.51
Solution:
We have q = C a × 2gh
π × d2
0.02 = 0.51 × × 2 × 9.81 × 0.05
4
d = 0.2245m say 22.5cm.
Water surface level in the water course = 200.0 – 0.05 = 199.95m
Example 7.3
Design an irrigation outlet for the following data
Full supply discharge of outlet = 50 lps
FLS in distributing canal = 200.00m
FLS in water course = 199.92m
Full supply depth in distributing canal = 1.05m
Solution:
Available head across the outlet = FSL of distributary – FSL of water course = 200 – 199.92 =
0.08m
Since the available head is very small, a non – modular outlet (submerged pipe outlet) will have to
be provided.
We have, Q = Cd a × 2gh
Here Q =0.05 m3/sec
Cd = 0.73 (assumed for submerge condition)
h = 0.08m
Now, Q = Cd a × 2gh
A = 0.055m2
Diameter of pipe d = 0.264m
Hence, provide diameter of pipe = 30cm
The R.L. of the bed of the distributing canal = 200 – 1.05 = 198.95m
-218-
Regulating Structure
The pipe top can be fixed at about 22 cm below the FSL of distributing canal.
BERM
Ho Water course
1.05
Water course
Figure 7.8: Pipe outlet (discharging freely)
-219-
Irrigation and Drainage Engineering
Solution:
From equation 7.5, Q = C a 2gHo
0.085 = 0.62 a 2 x 9.81 x 0.70
a = 0.037 m2
πd2/4 = 0.037 or d= 0.22m
Let us select as 25cm (0.049m2) diameter pipe.
Therefore, 0.085 = 0.62 x 0.049 2 x 9.81 x Ho
Ho = 0.40m < 0.70 m O.K.
The outlet will be a semi – modular outlet because there is free falling flow i.e. pipe outlet is higher
than the water level in the water course.
Example 7.5
Design a pipe outlet for the following data:-
Full supply discharge at the head of the watercourse = 90 lps
FSL in distributing canal = 205.0m
FSL in water course = 204.0m
Solution:
Available head across the outlet = FSL of distributary – FSL of watercourse
= 205.0 – 204.0 = 1m
Coefficient of discharge Cd = 0.62
Full supply discharge Q = 0.09 m3/sec
Now, the discharge through such an outlet is given as Q = C a x 2gHo
Assuming the diameter of pipe = 25cm
π x 0.252
Now, 0.09 = 0.62 x 4 x 2gHo
Ho = 0.44m
R.L. of center of outlet of pipe = 205 – 0.44 = 204.56m
R.L. of bottom level of pipe = 204.56 – 0.25/2 = 204.43m which is greater than FSL of water coarse
i.e. 204.00m
Hence, a pipe of 25cm diameter can be laid horizontal with its bottom or sill level at R.L. 204.43m
and it will be discharging freely as a semi – module.
0.44
204.43 25cm 204.0
Water course
-220-
Regulating Structure
Baffles
Eddy chamber
Rising pipe
Inlet pipe
Spout 1 to 10 Field
channel
Plan
FSL Divergence
Head wall Baffles Eddy chamber FSL
Field channel
Inlet pipe
-221-
Irrigation and Drainage Engineering
Canal bed
D/S FSL
-222-
Regulating Structure
d/s FSL
-223-
Irrigation and Drainage Engineering
Figure 7.15: Sloping glacis type fall with USBR type III stilling basin
-224-
Regulating Structure
E1 EC y
D1 C Hdr
p'
D2
dc
LC
Figure 7.17: YMGT – type drop (Japan)
-225-
Irrigation and Drainage Engineering
The complete design of the Sarda type fall consists mainly of the design of the following components:
1. Crest wall 2. Cistern
3. Impervious floor 4. D/S bed protection works
5. U/S wing walls 6. D/S wing walls
7. D/S side protection
Design of Sarda type fall
Step 1: Design of Crest
Length of the crest
The crest length is normally kept equal to the bed width of the canal; however, an increase in
length by an amount equal to the flow depth takes into account any future increase in
discharge.
Thus Length of crest L = Bed width of channels (U/S)
Shape of the crest
For discharge up to 14 m3/sec Rectangular shaped crest wall
3
For discharge > 14 m /sec Trapezoidal shaped crest wall
1. For Rectangular crest wall
Top width B = 0.55 d
Bt = top width of crest wall
d = height of the crest wall above the D/S bed level.
h+d
Base width of crest wall B1 =
G
B1 = base width of crest wall (m)
h = Height of water surface above the top of the crest
G = Sp. Gr of material of crest wall
H 1
Discharge Q = Cd 2g L H3/2 6 . . . 7.6
Bt
Where Q = discharge cumecs.
L = length (m)
H = head over the crest (m)
Bt = top width of crest wall (m)
Cd = coefficient of discharge 0.415
Now, equation 7.6 becomes,
H 1
Q = 1.84 L H3/2 6
Bt
2. For trapezoidal crest wall
Top width of crest wall B = 0.55 H + d
Where, H = head over the crest
d = Height of crest wall above the D/S bed level in m.
H 1
Discharge Q = Cd 2g L H3/2 6 . . . 7.7
Bt
Where Q = discharge cumecs.
-226-
Regulating Structure
L = length (m)
H = head over the crest (m)
Bt = top width of crest wall (m)
Cd = coefficient of Discharge = 0.45
Now, Equation 7.7 becomes,
H 1
Q = 1.99 L H3/2 6
Bt
Crest level
Crest level = U/S TEL – Head over the Crest
While neglecting velocity head
Crest level = U/S FSL – Head over the Crest
Head over the crest is obtained from (7.6) or (7.7) depend on shape of crest wall.
Height of crest wall
Height of crest wall = D1 – h. refer figure.
U/S TEL
D/S bed
x Cistern
∆ ∆
∆ ∆ ∆ ∆ ∆
B1 ∆
∆ ∆ ∆
U/S TEL
D/S bed
x Cistern
∆ ∆
∆ ∆ ∆ ∆ ∆
B1 ∆
∆ ∆ ∆
-227-
Irrigation and Drainage Engineering
-228-
Regulating Structure
Solution:
Step 1: Design of Crest
Length of the crest = D/S bed width of channel = 1.2m
Since rectangular crest is provided. The discharge formula is given by
1
Q = Cd 2g L H3/2
H 6
Bt For Cd = 0.415 the equation becomes;
1
Q = 1.84 L H3/2
H 6
Bt
Here, Q = 1.8 cumecs.
L = 1.2m
For initial assumption top width B = 0.5m
Now H5/3 = 0.7263
H= 0.825m say 0.83m
Discharge 1.8
Now approach velocity Va = = = 0.91 m/sec
area (1.2 × 0.929 + 1 × 0.929 2)
Va2/2g = 0.0422m
U/S TEL = U/S FSL + Va2/2g = 106.997 + 0.0422 = 107.039m
RL of crest = U/S TEL – H = 107.039 – 0.825 = 106.214m
Height of crest above U/S floor = 106.214 – 106.068 = 0.146m
Adopt crest width at top Bt = 0.55 d
Where d = height of crest above D/S bed = 106.214 – 105.318m = 0.896m
Now top width Bt = 0.55 0.896 = 0.52m
Keep 0.55m width of the crest.
h + d 0.825 + 0.896
Thickness at base B1 = = = 0.86m
G 2
Step 2: Design of cistern
Length of cistern Lc = 5 H × HL
Where, H = Head over the crest + V2/2g = 0.825m
HL = U/S FSL – D/S FSL = 106.997 – 106.247= 0.75m
Now length of cistern Lc = 4.0m
Adopt length of cistern Lc = 4.5m
1 1
Now, Depth of cistern x = (H × HL)2/3 = (0.825 × 0.75)2/3 = 0.181m
4 4
-229-
Irrigation and Drainage Engineering
Now, minimum length of impervious floor to be provided on the D/S of the crest wall
Theoretically, there is no need of U/S floor (2.876 – 5.5 = –2.624m), but necessary to provide nominal
length of U/S floor. For safety due to surface flow condition, provide U/S floor Length = 2m.
– The uplift pressure under the U/S floor will be counterbalanced by the weight of water
and hence no thickness is required. However, provide a minimum thickness of 0.3m.
– For other points the minimum vertical ordinate between the Bligh’s HGL and floor level
gives the uplift pressure.
– Thus maximum unbalanced head under the D/S toe of the crest wall
= 0.181 +
106.214 – 105.318
10.86 × 5.5 = 0.635m
h 0.635
Now, required thickness t = = = 0.5125
G – 1 2.24 – 1
Adopt 0.52m thick cement concrete floor over laid by 0.2m brick pitching.
-230-
Regulating Structure
107.039
106.068 106.247
0.896
105.318
0.181
∆ ∆ ∆ ∆ ∆
∆ ∆
0.5 B1 ∆ ∆ ∆
∆
0.75
2.0 0.86 4.5
2.86 5.5
All dimensons are in m
-231-
Irrigation and Drainage Engineering
-232-
Regulating Structure
118.30 0.88
1 117.456 HL D/S TEL
D1 = 1.8
116.5 116.8
2.456
1:3 1:8
115.00
0.30 114.7
∆ 0.7
∆ 0.4 ∆ ∆ ∆
∆ ∆
1 B1 ∆ ∆ ∆
∆
1.5
6
7 8
All dimensons are in m
-233-
Irrigation and Drainage Engineering
Exercise
12. Design the floor on the basis of Bligh’s theory taking coefficient of creep = 10. Check the design by
Khosla’s theory and modify the design if necessary. Safe exit gradient may be taken as 1/5. Sketch
the longitudinal section of fall.
-234-
Cross-
Cross-Drainage Structure
C HA P T ER
8 Cross-Drainage Structures
In an irrigation project, when the network of canals (main canals, branch canals, distributaries etc.) are
provided, then canals may have to cross the natural drainages like rivers, streams, drains valley and other
canals at different points within the commanded area of the project. The crossing of the canals with such
obstacles cannot be avoided. So, suitable structures must be constructed at the crossing point for the easy
flow of water of the canal and drainage in the respective directions. These structures are known as cross
drainage structures. They are generally very costly, and should be avoided if possible by changing the
canal alignment and/or by diverting the drains. The nature of cross drainage works may be different at
different places. Sometimes, the bed level of canal may be below the bed level of drainage and
sometimes, it may be higher than that of the drainage. The bed level of canal and drainage may be nearly
same also. So the structures are different at different places and the designations of the structures also are
different. The details of these various structures will be dealt in this chapter.
• The watershed or ridge canal do not have cross drainages. But in actual orientation of the canal
network, this ideal condition may not be available and the obstacles like natural drainages may
be present across the canal. So, the cross drainage works must be provided for running the
irrigation system.
• At the crossing point, the water of the canal and the drainage may get intermixed. So for the
smooth running of the canal with its design discharge the cross drainage works are required.
• The site condition of the crossing point may be such that without any suitable structure, the
water of the canal and drainage cannot be diverted to their natural directions. So the cross
drainage works must be provided to maintain their natural direction of flow.
Based on the relative bed levels, maximum water levels and relative discharges of the canals and
drainages the cross drainage works may be of the following types for 3 cases.
-235-
Irrigation and Drainage Engineering
Case I: Irrigation Canal Passes Over the Drainage
1. Aqueduct
An aqueduct is a cross-drainage structure constructed where the drainage flood level is below the
bed of the canal. Small drains may be taken under the canal and banks by a concrete or masonry
barrel (culvert), whereas in the case of stream crossings it may be economical to flume the canal
over the stream. In this case, the drainage water passes clearly below the canal.
Canal FSL
HFL
River bed
2. Siphon Aqueduct
In a hydraulic structure where the canal is taken over the drainage, but the drainage water cannot
pass below the canal freely. It flows under siphonic action and designed for total head loss through
inverted siphon. So it is known as siphon aqueduct. This structure is suitable when the bed level of
canal is below the highest flood level of the drainage.
Canal FSL
U/S HFL D/S HFL
Canal Bed level
The hydraulic structure in which the drainage is taken over the irrigation canal is known as super
passage. The structure is suitable when the bed level of drainage is above the full supply level of the
canal. The water of the canal passes clearly below the drainage.
-236-
Cross-
Cross-Drainage Structure
HFL stream
Bank of canal
F.S.L
Canal
Canal Canal
Canal
Case III: Drainage and canal intersection each other at the same level.
1. Level crossing
Level crossing facilities are provided when both the drain and the canal run at more or less the same
level. This is more frequently used if the drain flows for a short period (e.g. flash floods in the
drain); in addition, the mixing of the drain flows to canal may be acceptable (if drain is siltless).
The plan layout of a level crossing with two sets of regulators, one across the drain and the other
across the canal, is shown in figure 8.5. Normally, the canal regulator regulates its flow with the
drain regulator kept closed. Whenever the flash floods occur, the canal gates are closed and drainage
gates opened to let the flood flow pass.
-237-
Irrigation and Drainage Engineering
Drainage
(river)
Crest top level at cancal FSL
Drain regulator
HFL = 210
2.5m
From figure and given data; canal bed level is much above than HFL of drainage, than aqueduct is
appropriate for cross drainage structure.
-238-
Cross-
Cross-Drainage Structure
8.3 Design of Siphon Aqueduct
Depending upon the cross – section of the canal over the barrel or (culvert), the aqueducts or siphon
aqueducts are classified into the following three types:
Type I Aqueduct
In this type of aqueduct (or siphon aqueducts) the cross – section of the canal is not changed. The original
cross – section of the canal with normal side slopes is thus retained. The length of the barrel through
which the drainage passes under the canal is a maximum in this type of structures, because the width of
the canal section is maximum. In this type of structures the canal wings are not required. This type is
suitable when the width of the drainage is small (say less than 2.5 m). If the section is changed, the cost of
canal wings would be large in comparison to the saving resulting from decreasing the length of culvert.
Road
FSL
∆ ∆ ∆ ∆ ∆ ∆
HFL
Length of barrel
Drainage
∆
∆
∆ ∆ ∆ ∆ ∆ ∆
HFL
Length of barrel
Drainage
-239-
Irrigation and Drainage Engineering
Type III aqueduct
In this type of aqueduct (or syphon aqueduct), the entire earth section of the canal is discontinued and
replaced by a concrete or masonry through over the drainage [Figure. 8.8].This type of structure is
generally suitable when the width of the drainage is very large (say more than 15 m), so that the cost of
the trough and canal wing walls is less in comparison to the saving resulting from decreasing the length of
barrel. In this type of structure, the canal can be easily flumed, which further reduces the length of the
drainage barrel.
Road
∆ ∆ ∆
∆ ∆
∆ ∆
∆ ∆ ∆
HFL
Length of barrel
Drainage
-240-
Cross-
Cross-Drainage Structure
Size of barrel:
After having fixed the waterway the size of barrels is to be fixed. In the case of an aqueduct, the canal
trough is carried clear above the HFL and hence the height of openings is automatically fixed. In the case
of a siphon aqueduct, the required area of waterway is obtained by dividing the fixed discharge by the
permissible velocity of flow through the barrels. The velocity of floor through the barrels is normally
limited to 2 to 3 m/sec. higher velocities may cause quick abrasion of the barrel surfaces by rolling grit
and will result in high afflux upstream of the siphon aqueduct thus requiring higher and longer marginal
banks to avoid the flooding of the country side. The total area divided by the number of spans gives the
area required by each span. Knowing the width of span and the shape of the opening, the required depth
of the opening can be determined which will fulfill the area required of the span. The span to be provided
depends entirely on structural and economic considerations. For instance where foundations are costly
fewer piers or longer spans are provided.
From the canal bed level, deducting the thickness of the culvert or barrel roof plus the depth of the
opening, the level of the floor of the barrel is obtained. Further in the case of siphon aqueduct it is
desirable to leave some clear headway between the bed of the drain on the downstream side of the
crossing and underside of the culvert or barrel roof. This headway is desirable to minimize the blocking
of culverts or barrel by silt rolling along the bed of the drain and it should be either 1m or half the height
of culvert or barrel, whichever is less.
Design a Canal water way
In the case of siphon aqueduct the canal is flumed i.e. the canal waterway is contracted, to economize the cost
of cross drainage works. The flumed portion or the trough is gradually connected to the normal section with
smooth transition wings at both ends. The contraction of canal waterway although reduces the barrel length s or
the width of the works but it involves the provision of extra transition wings. As such the canal waterway
should be flumed to such an extent that the cost of the works as a whole is minimum.
The fluming or the contraction of the canal waterway should be done in such a way that the velocity in
the trough is not more than 3 m/sec and the flow remains subcritical to avoid the possibility of hydraulic
jump forming in the trough. The approach or contraction transition should not be steeper than 300 which
corresponds to a splay of 2:1 and the departure or expansion transition should not be steeper than 22.50
which corresponds to a splay of 3:1. The transitions consist of curved and flared wing walls so that there
is minimum loss of head and the flow is streamlined.
Design of transition
The transitions can be designed according to two different conditions as indicated below.
1. Design of transitions when the water depth remains constant.
2. Design of transitions when the water depth varies.
Design of transitions when the water depth remains constant:
In the case the water depth in the transition and the trough remain constant the following two
methods may be adopted for the design of transitions.
(i) Mitra’s hyperbolic transition
For water depth to remain constant in the transition and the trough, A.C. Mitra proposed
hyperbolic transition which is given below.
Bc Bf Lf
Bx =
Lf Bc - (Bc - Bf)x
-241-
Irrigation and Drainage Engineering
Where, Bc and Bf are bed width of normal canal and flumed section respectively.
Bx be the bed width at a distance x from the flumed section.
Lf be the total length of the transition.
(ii) Chaturbedi’s semi cubical parabolic transition.
R.S. Chaturvedi on the basis of his experiments proposed the following equation for semi –
cubical parabolic transitions when water depth remains constant.
3
Lf Bc3/2 Bf 2
x = 3/2
Bc - Bf3/2 Bx
Choosing various convenient values of Bx, the corresponding distance x can be computed.
Design of flumed section
As shown in figure 8.10(a) the contraction transition starts at section 1 – 1 and ends at section 2 – 2. The
flumed section continues from section 2 – 2 to section 3 – 3. The expansion transition starts from section
3 – 3 and ends at section 4 – 4. From section 4 – 4 the channel flows in its normal cross section and the
conditions at this section are completely known. Let D and V with appropriate subscripts refer to depths
and velocities at the various sections. The design is done in the following steps.
Step 1: Let the bed level and cross section of the canal at section 4 – 4 completely known.
Water surface elevation at 4 – 4 = Bed level at section 4 – 4 + D4
V 42
TEL at section 4 – 4 = Water surface elevation at 4 – 4 +
2g
Step 2: Between sections 3 – 3 and 4 – 4 there is energy loss due to expansion and due to friction. The
V32 – V42
energy loss due to expansion may be taken as 0.3
2g . The energy loss due to friction
is generally small and may be neglected.
Since trough dimensions at section 3 – 3 are known, V3 is known.
V32 – V42
Elevation of TEL at section 3 – 3 = Elevation at section 4 – 4 + 0.3
2g
V 32
Water surface elevation at section 3 - 3 = Elevation of TEL at section 3-3 –
2g
Bed level at section 3 – 3 = Water surface elevation at section 3 - 3 – D3
Step 3. Between sections 2 – 2 and 3 – 3 the channel flows in a trough of constant cross – section and
there is uniform flow. The only loss in the trough is therefore friction loss HL which can be
computed by Manning’s equation as indicated below.
1 2/3 1/2
V= R S
n
1
1 2/3 HL 2
V= R
n L
V2 n2 L
HL =
R4/3
-242-
Cross-
Cross-Drainage Structure
Elevation of TEL at section 2 – 2 = Elevation of TEL at section 3 – 3 + HL
V 22
Water surface elevation at section 2 – 2 = Elevation of TEL at section 2 – 2 -
2g
Bed level at section 2 – 2 = Water surface elevation at section 2 - 2 – D2
Step 4: Between sections 1 -1 and 2 – 2 there is energy loss due to contraction as well as due to
V22 – V12
friction. The energy loss due to contraction may be taken as 0.2
2g . The energy loss
due to friction is generally small and may be neglected.
V22 – V12
Elevation TEL at section 1 – 1 = Elevation of TEL at 2 – 2 + 0.2
2g
V 12
Water surface elevation at section 1 – 1 = Elevation of TEL at section 1 – 1 -
2g
Bed level at section 1 – 1 = Water surface elevation at section 1 – 1 – D1
Head loss through siphon barrels
In the case of siphon aqueducts and siphon the head loss through the siphon barrels may be calculated by
using Unwin’s formula which is as follows.
L V 2 V a2
h = 1 + f1 + f2 – . . . 8.1
R 2g 2g
Where h = head loss through the siphon barrel in m, which is equal to the difference between water levels
upstream and downstream of siphon barrels
L = length of the barrel in m
R= hydraulic mean radius of the barrel in m
V= velocity of flow through the barrels in m/sec
Va = velocity of approach in m/sec which is generally neglected
f1 = coefficient for loss of head at entry, which may be taken as 0.505 for an unshaped mouth of
the same cross – sectional area as the barrel and 0.08 for bell mouth and
LV2
f2 = coefficient such that the loss of head in the barrel due to friction is given by f2
2gR
-243-
Irrigation and Drainage Engineering
As stated earlier the velocity of flow through the siphon barrel is limited to 2 to 3 m/sec. Thus knowing the
velocity of flow the head required to generate the same velocity can be found from equation 8.1. The high flood
level of the drain downstream of the work remains unchanged even after the construction of the work, but on the
upstream side the high flood level increase by the amount of afflux or the total head loss as given by equation 8.1.
Uplift pressure on the underside of the trough (on the barrel roof)
When water is flowing through the siphon barrel and the water level on the downstream side at the barrel
is higher than the underside of the trough (or the barrel roof), uplift pressure is exerted on the underside of
the trough (or the barrel roof). At the downstream end of the barrel the uplift pressure on the underside of
the trough is equal to the difference between the downstream water level and the level of the underside to
the trough. At any other point along the barrel, the uplift pressure is given by the ordinate between the
hydraulic gradient line and the underside of the trough. The afflux having been calculated by Unwin’s
formula the hydraulic gradient line can be drawn as shown in figure below. The maximum uplift pressure
occurs on the underside of the trough at the upstream end of the barrel. The uplift pressure would be
maximum when the highest flood is passing through the barrel and there is no water in the trough at that
time. Another critical condition to be considered for the design of the trough bed (or barrel roof) is when
the trough is running full with dead weight of trough but there is no uplift from the barrel.
0.4m
U/S TEL Entry loss Friction loss
U/S HFL D/S TEL
Exit loss
Max uplift HGL
D/S HFL
D/S Bed
∆ ∆
∆ ∆ ∆ ∆ ∆
∆
The thickness of the slab forming the trough bed (or the barrel roof) required to counter balance the uplift
(i.e. for the first condition noted above) is generally less than what is required to support the load of
trough water (i.e. for the second condition noted above). However, in some case the thickness of the slab
required to counterbalance the uplift may exceeds the thickness required to support the water load. In
each of these two cases if the slab is designed to balance the uplift or the water load by gravity only i.e.
providing thick slab, which is usually undesirable because it leads to lowering of the levels of both the
underside of the trough bed (or the barrel roof) and the barrel floor which in turn results in increasing the
uplift on the trough bed as well as on the barrel floor.
As such one of the alternatives would be to provide a reinforced concrete slab with reinforcement at the
bottom to take the water load of the trough and the reinforcement at the top to resist uplift by bending. It
may however be noted that since a part of the uplift is resisted by gravity (i.e. by the self-weight of the
slab) only the remainder of the uplift after deducting the part counter balanced by gravity is to be resisted
-244-
Cross-
Cross-Drainage Structure
by bending. Hence the reinforcement at the top of the slab is to be provided only for the remainder of the
uplift. Another alternative may be to provide the thickness of the slab to support the water load in the
trough by gravity and to provide reinforcement only at the top of the slab to resist the remainder of the
uplift by bending. In both these cases it would, however, be necessary to anchor the slab through the pier
to the bottom floor by steel bolts to provide the necessary end reactions for upward bending. A better
alternative may be to provide R.C.C. box culvert.
Example 8.2:
Canal Stream
Solution:
Here; canal bed level 200.00 m is slightly below the HFL (200.50 m) and the HFL is below the FSL
of canal (202.00 m), hence a siphon aqueduct is required.
Q 500
Height of siphon barrel required = = = 2.747m
clear waterway × velocity 13 × 7 × 2
-245-
Irrigation and Drainage Engineering
Step 2: Design of canal waterway
Normal bed width of canal = 25 m
Since the drainage width is large (106m at the crossing) it is economical to flume (concrete, n
= 0.014) the canal.
Adopt a maximum flume ratio of 0.5. Therefore the flumed width of canal (trough) = 0.5 × 25 = 12.5m.
Provide a splay of 2:1 in contraction and a splay of 3:1 in expansion. (Hinds, 1928)
(25 – 12.5) × 2
Length of transition in contraction = = 12.5m
2
(25 – 12.5) × 3
Length of transition in expansion = = 18.75m
2
2 3
Flume (trough)
Bx
Bf = x Bf = 12.5m B0
2 3
Average side Average side
splay 1:2 splay 1:3
1 4
(a)
202.044m
202.032m 202.032m 202.015m
202.029m
201.959m 201.959m 202.0m
200.029m
199.959m 199.959m 200.0m
(b)
Figure 8.10: Flumed section with transition at different section
-246-
Cross-
Cross-Drainage Structure
Referring to Figure 8.10 (a), the following results can be obtained to maintain a constant flow
depth of 2.0 m (full supply depth). The calculations are achieved from section 4 – 4 and
proceed towards section 1 – 1 as tabulated below.
Section
4–4 3–3 2–2 1–1
Width (m) 25.00 12.5 12.50 25.0
2
Area of flow (m ) 56.00 25.00 25.00 56.00
2
(By + zy )
Velocity (m/sec) 0.536 1.2 1.2 0.536
Q/A
Velocity head 0.015 0.073 0.073 0.015
(m)
V2/2g
Loss (m) Expansion loss *Friction loss = Contraction
= 0.017 0.0004 loss
= 0.012
R L of canal bed 200.00 201.959 – 2 = 201.959 – 2 = 202.029 – 2 =
(m) 199.959 199.959 200.029
Flow depth (m) 2 2 2 2
RL of water 200.00 + 2= 202.032 – 0.073 202.032 – 0.073 202.044 – 0.015
surface (m) 202.00 = 201.959 = 201.959 = 202.029
RL of TEL (m) 202.00 + 0.015 202.015+0.017 202.032 + 0.0004 202.032 + 0.012
= 202.015 = 202.032 = 202.032 = 202.044
*Friction loss is calculated below
V2n2L 1.22 × 0.0162 × 106
HL = 4/3 = = 0.0004
R 294/3
A 2 × 12.5
R= = = 29
P 2 × (2 + 12.5)
Step 4: Design of Transition
For a constant depth of flow the transition may be designed such that the rate of change of
velocity per meter length of transition is constant. This approach yields the bed width of the
transition at a distance x from the flume section as
B0BfLf
Bx = Mitra’s hyperbolic equation .......... 8.2
Lf B0 – x (B0 - Bf)
Where B0 = Bed width at original section = 25m
Bf = Bed width of flumed channel section = 12.5m
Lf = length of transition = 12.5m for contraction and 18.75 for expansion transition.
Bx= bed width at any distance x from the flumed section.
-247-
Irrigation and Drainage Engineering
For Contraction transition:
3906.25
Bx =
312.5 - x (25 - 12.5)
X 0 2 4 6 8 10 12.5
Bx 12.5 13.586 14.88 16.44 18.38 20.833 25
For expansion transition:
5859.375
Bx =
468.75 - x (25 - 12.5)
X 0 4 8 12 16 18.75
Bx 12.5 13.99 15.88 18.38 21.80 25
Step 5: Design of Trough
The trough shall be divided into two equal compartments of 6.25m wide, separated by 0.3 m
thick partition. The entire trough (flume section) can be designed as a monolithic concrete
structure. Provide side wall and a bottom slab of about 0.4m (to be fixed by the usual structural
design methods).
Overall length of barrel = 12.5 + 0.3 + 2 × 0.40 = 13.60m.
FSL = 202.00m
U/S HFL = 200.723m 0.4m 0.4m D/S HFL = 200.50m
6.25m 6.25m
0.4m 199.60m
1:3 13.60m 1:5
∆ ∆ ∆ ∆
∆ ∆ 1m ∆ ∆
-248-
Cross-
Cross-Drainage Structure
Step 7: Uplift pressure on roof barrels
RL of bottom of trough = RL of canal bed – slab thickness = 200 – 0.40 = 199.60m
V2
The entry loss at the barrel = 0.5 = 0.102m
2g
Therefore the pressure head inside the barrel just downstream of its entry = 200.723 – 0.102 –
199.60= 1.021m of water × 9.81 = 10.01 KN/m2.
RCC Slab should be designed by providing bottom reinforcement for dead weight of trough
slab + 2 m of water load and by providing top reinforcement for uplift of 10.01 KN/m2 minus
dead weight of trough slab.
Exercise
1. The cross drainage structure across an irrigation channel has following data:
i. Discharge of canal = 30 cumecs
ii. Bed width of canal =20m
iii. Full supply depth of canal =1.6m
iv. Bed level of the canal =260.00m
v. Side slope of canal =1.5:1 (H:V)
vi. High flood discharge of drainage = 450 cumecs
vii. High flood level of drainage =261.00 m
viii. Bed level of drainage =258.00m
ix. General ground level =260.00m
Design the drainage waterway, canal waterway and find the bed levels and FSL at four different
sections of the canal Trough
2. Following data are obtained at the crossing of a canal and a drainage:
Canal Stream
3
Discharge (m /sec) 20 200
Bed level 150.0 148.5
Canal FSL 151.5
Bed width 12.00
Canal side slopes 1.5:1 (H:V)
Stream HFL 150.7
The general terrain level is150.0 m.
Design the following components of siphon aqueduct.
i. Drainage waterway ii. Canal waterway
iii. Transition iv. Uplift
3. Explain with sketch aqueduct, siphon aqueduct, siphon and super passage.
4. What is level crossing? Write down the suitability of inlet and out structure in canal irrigation
system.
5. Which cross drainage structure is suitable and appropriate in Hills of Nepal?
-249-
Irrigation and Drainage Engineering
CHAPTER
-250-
Water Logging and Drainage
-251-
Irrigation and Drainage Engineering
-252-
Water Logging and Drainage
-253-
Irrigation and Drainage Engineering
9.3 Drainage
Irrigation and drainage are two face of the same coin. Surface irrigation is a boon only if it is practiced
with great care. As stated earlier, only optimum amount of water should be applied to the crop, as per the
requirement of the crop and the properties of the soil. In fact, the root zone of the soil fails to absorb
excess water which may percolate and help in raising the water table. If this gravity water encounter an
impervious stratum and is not drained up properly, then this excess water is harmful to crop yield. It
becomes necessary to remove excess water by draining it out from below the soil. The drained water may
be discharged back either into a river or a canal or some other safe place. Hence, while designing a canal
irrigation network, it is desirable to provide a suitable drainage system, for removing the excess irrigation
water. Thus irrigation and drainage go together. Drainage system is also required for draining out the rain
water and ensures its easy disposal to prevent its percolation.
Drainage system can be classified as:
a. Surface drainage b. Sub – surface drainage
Surface drainage is also called open drainage system while sub – surface drainage as tile – drainage or
underground drainage.
-254-
Water Logging and Drainage
the excess irrigation water. Many a times, the excess irrigation water is neglected and these drains
are designed only for the runoff resulting from the average storms which is neither economical nor
desirable. Manning's equations may be used to obtain design velocity of these drains, keeping the
velocity within the critical velocity, and thereby avoiding silting or scouring. Proper shape is
selected based on available information. Manning's equation may however be used for the design of
shallow as well as deep surface drains.
2. Deep surface drains
The drains, which are large enough to carry the flood water of the catchment area from the shallow
surface drains, and are of sufficient depths to provide outlets even for the underground tile drains, if
provided are called deep surface drains. These drains carry the storm water discharge, drains,
shallow surface drains, and the seepage water coming from the underground tile drains. They are,
therefore, designed for the combined discharge of the shallow surface drains as well as that of the
tile drains. Sub-surface drains are required for soils with poor internal drainage and a high water
table generally, a cunnette of about 0.6 m depth with steeper slope is provided in the center of the
drain bed, so as to carry the seepage water of the underground tile drains. Cunnette is lined so as to
withstand higher flow velocities. The full section of drain is used only during the rainy season when
the cunnette is not able to handle the flow will Manning's equation may be used for estimating
velocity and based on that flow capacity can be determined while designing of deep surface drains.
Different forms of sub-surface drains are described below.
1. Surface inlet
A surface inlet is intake structure constructed to carry the pit water into the sub-surface or tile drain.
A cast iron pipe or a manhole constructed of brick or monolithic concrete, is sufficient and
satisfactory. Basically, it is the facility to remove the surface water from the pot holes depressions,
road ditches, and farmstead. This may also be accomplished by connecting them with the shallow
surface drains called random field drains
2. French drain
When the quantity of water to be removed from the pits or depression is small, a blind inlet may be
installed over the tile drain which is also called French drain. These are constructed by back filling
the trench of the tile drain with graded materials, such as gravel and coarse sand, or with corn cobs,
straw and similar substances, as shown in Figure 9.1.
G.L.
G.L.
Pit water
-255-
Irrigation and Drainage Engineering
Such inlets are not permanently effective. The voids in the backfill of the blind inlet become filled up with
the passage of time, thereby reducing its effectiveness. Even though they are not permanently effective,
they are economical to be installed and do not interfere with the farming operations.
3. Bedding
Bedding is a method of surface which makes use of dead furrows, as shown in Figure 9.2. The area
between the two adjacent furrows is known as a bed. The depth of the bed depends on the soil
characteristics and tillage practices. In the bedded area, the direction of fanning may be parallel or normal
to dead furrows. Tillage practices, parallel to the beds, retard water movement to the dead furrows.
Shallow surface
drainage
-256-
Water Logging and Drainage
-257-
Irrigation and Drainage Engineering
Initial depth Design rainfall per day (P3/3) Discharge (Q) Final water depth
Days (mm) mm (500/3 mm) mm/day (mm)
1 40 166.67 60 146.67
2 146.67 166.67 60 253.33
3 253.33 166.67 60 360.00
4 360.00 - 60 300.00
-258-
Water Logging and Drainage
Our assumption is maximum water level is 300mm which may persist for one day but here 300mm
exceeds for 2 days hence we have to increase design discharge.
Trial 2
Assume Q = 70 mm/day
Initial depth Design rainfall per Discharge (Q) Final water depth
Days (mm) day(P3/3) mm mm/day (mm)
1 40 166.67 70 136.67
4 330.00 - 70 260.00
5 260.00 - 70 190.00
Again maximum water level 300mm exceeds for 1 days hence we have to increase design discharge.
Trial 3
Assume Q= 80 mm/day
Initial depth Design rainfall per Discharge (Q) Final water depth
Days (mm) day(P3/3) mm mm/day (mm)
1 40 166.67 80 126.67
4 300.00 - 80 220.00
5 220.00 - 80 140.00
Here maximum water level 300mm is persist for one day and 200 mm persist for up to 3 days hence
our assumption is meet. Hence the design discharge for design of drainage is 80mm/day.
Here, Area = 40 ha
80 × 10-3 m
Discharge Q = × 40 × 104 m2 = 0.37 m3/sec.
86400 sec
Bed slope = 1:400
Manning’s roughness coefficient = 0.025
Assume, side slope = 1:1
B/D ratio = 3
-259-
Irrigation and Drainage Engineering
P = B +2 D 2 = 5.828D.
R = A/P = 0.686D
Now put the values in Manning’s equation and solve
D = 0.347m
B = 1.042m
Adopt free board = 0.1m
Or alternately we can assume non-silting and non-scouring velocity (depends on type of soil) instead
of B/D ratio.
In this case assume velocity v = 0.8m/sec
Area A= Q/v = 0.463m2
A = BD + zD2 …… (i)
1 2/3 1/2
Calculate R from v = R S
n
R = 0.253m
Now P=A/R = 0.463/0.253= 1.83m
We have, P = B +2 D 2 …….(ii)
Solving (i) and (ii)
B = 1.02m
D = 0.34m
Example 9.2
Determine the drainage rate in l/s/ha required to meet the following condition for healthy growth of
rice paddies in bonded field in Terai of Nepal.
Initial water level in field = 50 mm
Maximum water level is 400mm which may persist up to one day.
Depth in excess of 250mm may persist for up to 2 days
No rain follows the design rainfall for several days.
Neglect ET and deep percolation loss.
Design 3 day rainfall is 400 mm.
-260-
Water Logging and Drainage
Solution:
Q lps per ha 1 2 3 4 5 6 7
Q mm per day
Days 8.64 17.28 25.92 34.56 43.2 51.84 60.48
Initial water depth 50 50 50 50 50 50 50
(mm)
0 Rinfall P3/3
Here from graph, our assumption i.e. maximum water depth 400mm persist up to one day and
250mm may persist for 2 days is met by 5 lps per hectare (43.2 mm per day).
Example 9.3:
How many days the field will be inundated above 200mm depth if a drainage rate of 3 l/s per ha is
maintained by constructing internal drainage system? If three days design rainfall is 300mm. Will
such system cause the depth to exceed 300mm?
-261-
Irrigation and Drainage Engineering
Solution:
Assume initial depth of water= 40mm
Given Q 3 lps/ha
25.92 mm/day
Here data shows that the field inundated above 200mm in 3 days and no any depth exceed 300mm.
Example 9.4:
Determine the drainage rate required to meet the following condition. Maximum yearly precipitation for
three consecutive days = 300mm. The design rainfall is to be taken as 10 year return periods. Initial water
level in field = 40mm. Maximum water level is 300mm which may persist for up to one day and depends
in excess of 200 mm may persist for up to 3 days. Assume other suitable values if necessary.
Solution:
Here, maximum yearly precipitation for three days= 450mm
10 year design yearly precipitation for three days = growth factor x 300 mm
For 10 year return period, growth factor = G= 0.32 ln T + 0.78 = 1.5
Now design rainfall = 300x 1.5 = 450mm
Q lps per ha 5 6 7 8 9
Q mm per day
days 43.2 51.84 60.48 69.12 77.76
Initial water 40 40 40 40 40
depth (mm)
Rainfall P3/3
0 (450/3) (mm)
1 150 146.8 138.16 129.52 120.88 112.24
2 150 253.6 236.32 219.04 201.76 184.48
3 150 360.4 334.48 308.56 282.64 256.72
4 317.2 282.64 248.08 213.52 178.96
5 274 230.8 187.6 144.4 101.2
6 230.8 178.96 127.12 75.28 23.44
-262-
Water Logging and Drainage
From graph and table our assumption i.e maximum water depth 300mm for one day and 200 mm
may persist for 3 days is meet by 8 lps per ha. Hence designed drainage rate is 8 lps per ha.
1. Hills
The internal drainage of rice fields in the hills will vary often take the form of spillage from
terrace to terrace via natural channel through the bunds. In some cases, however, field drains
will be necessary, and these may be designed on the basis of runoff estimated for a water
balance similar to that described for the Terai. The following assumptions are made:
- Initial water level is 40 mm
- Maximum water level is 100 mm.
- No rain follows the design rainfall for several days.
- Losses due to evapotranspiration and deep percolation are replaced by ongoing irrigation
and/or flood inflows during the design rainfall.
The balance may be expressed:
Q = P + 40 – 100 = P – 60
Where, Q is the runoff in mm
P is the design rainfall in mm.
The 24 hrs rainfall with a return period of 10 years is recommended for the design of field
drains in the hills.
9.5.2 External Drainage
External drainage refers to runoff generated outside the irrigation area which presents a danger to the irrigation
scheme. It covers the assessment of design floods for the headworks and the assessment of stream flows, which
must be safely passed through or around the irrigated area, i.e., cross drainages. Peak external drainage rate are
required to design structures to carry runoff safely across or around the irrigated area.
-263-
Irrigation and Drainage Engineering
-264-
Water Logging and Drainage
-265-
Irrigation and Drainage Engineering
1. Natural system
In this system the main/sub main and the connecting laterals are provided in natural courses as
shown in figure 9.5 (a). The natural system is preferred in rolling topography.
2. Grid iron layout
In this system the laterals are provided only on one side of the main / sub main as shown in figure
9.5 (b). This system is used when the land is practically level or where the land slopes away from
the main/ sub main on one side and when the entire area has to be drained.
3. Herringbone pattern
In this system laterals join main / sub main from each side alternately as shown in Figure 9.5 (c). It
is adopted when the main /sub main is laid in a depression. In this case the land along the main / sub
main is double drained which is however, necessary because it is in depression and hence requires
more drainage than the land in the adjacent slopes.
4. Double main system
In this system two separate mains/sub mains with separate laterals for each are provided as shown in
Figure 9.5(d). This system is provided when the bottom of the depression is wide. This arrangement
helps to reduce the length of the laterals and eliminates the break in slope of the lateral at the edge of
the depression.
5. Intercepting drain system
In this system there are no laterals but only a main/ sub main is provided at the toe or the slope as
shown in Figure 9.5 (e). This arrangement is adopted when the hilly land is to be drained.
58
56
54
50
-266-
Water Logging and Drainage
Main or submain
(c) Herringbone pattern (d) Double main system
-267-
Irrigation and Drainage Engineering
Impervious layer
Figure 9.6: movement of water to drain
2. The falling of water table, i.e. draw down will be more near the tile than at the points farther
away Since the quantity of water moving between any two flow lines is the same.
3. Once the saturated soil has drained for a day or two, the resulting water table will be, as shown
in Figure 9.6. With the passage of time, the water level goes on lowering down.
4. With series of tile drains, the sub soil water level directly over the drains, is lower than the
level midway between them as in shown in Figure 9.6.
5. When a filter is provided around the tile drains to surround the drains with more pervious soil,
then the overall draw down will be more.
Ground level
s x
(15 to 45m) Drain
a y b
Impervious startum
-268-
Water Logging and Drainage
⌠ q (s – 2x) dx = ⌠
⌡ y dy
⌡ 2Ks
qd y2
(sx – x2) = + C . . . 9.2
2Ks 2
a2
When x = 0 ; y = a. then C = –
2
-269-
Irrigation and Drainage Engineering
s
Also when x = ; y = b, from equation 9.3
2
4K (b2 – a2)
qd =
s
4K (b2 – a2)
s=
qd
Example 9.5:
In a drainage system closed drains are to be placed with their center 2 m below the ground level to
keep the highest position of the water table 1.7m below the ground level. The impervious stratum is
at a depth of 9.6 m below the ground level. If 1% of the average annual rainfall to be drained in 24
hours and co – efficient of permeability K = 1x 10-5 m/sec. If the average annual rainfall in the area
is 850 mm. find the spacing of drain.
Solution:
4K (b2 – a2)
Spacing s =
qd
K= 1 × 10-5 m/sec
a = 9.6 – 2 = 7.6 m
850 1
1% of average annual rainfall over and area A m2 supply by each drain = ×A×
1000 100
= 85 × 10-4A m3
If s is the spacing between the drain then area A supply by each drain per unit length of the drain is;
A= s × 1 = s
On solving, s = 43.487 m
-270-
Water Logging and Drainage
Exercise 9:
1. What is water logging? Explain causes and preventive measures of water logging.
2. What are the effects of water logging?
3. What is internal drainage and External drainage?
4. Explain about the importance of surface and subsurface drainage in Terai as well as Hills of Nepal.
5. What is surface and subsurface drainage?
6. Explain the importance of remodeling of existing drainage.
7. Write the steps to design surface drainage in the bunded field of Terai.
8. What are the assumptions to design surface drainage in Terai and Hills of Nepal?
9. Design a surface drainage for a field of 50 ha area in Terai with following data. Design maximum
yearly precipitation for three consecutive days = 450mm, longitudinal slope of channel 1:400,
manning roughness coefficient 0.02, permissible velocity is 0.7m/sec. Maximum water level is
300mm which may persist for up to one day and depends in excess of 200 mm may persist for up to
3 days. Assume other suitable values if necessary.
10. How do you determine the spacing of tile drain, explain with derivation.
11. Find the spacing between drains for the following data
• Annual rainfall = 1000 mm
• Height of drains above impervious stratum = 4.5m
• Maximum height of the drained water table above the impervious stratum= 5.0m
• Coefficient of permeability k = 10-6 m/sec.
12. Find the inflow into the drain for the following data:
• Spacing = 13m
• Height of drain above impervious stratum= 4.5 m
• Maximum height of the drained water table above the impervious stratum = 5.0m
• Coefficient of permeability k = 10-6 m/sec
13. The annual rainfall in Biratnagar is 2000 mm. Find the spacing of subsurface drain if 2% of average
annual rainfall is to be drained in 2 days.
Given;
Depth of impervious stratum from the top of soil surface = 12m
Position of drain is 2m below the top soil surface and the depth of highest position of water table
below the top soil surface = 1.5m.
Permeability, K = 1 × 10-4 m/sec.
-271-
Irrigation and Drainage Engineering
Annex I
-272-
Annex
Annex II
-273-
Irrigation and Drainage Engineering
Annex III
-274-
Annex
Annex IV
-275-
Irrigation and Drainage Engineering
Annex V
-276-