Appendix B (Part-2 MEICA Guidelines) - Final (Clean Copy)
Appendix B (Part-2 MEICA Guidelines) - Final (Clean Copy)
Confidential
3
Glossary of Terms
Mizuho Bank, Ltd. as Lead and Financial Adviser
White & Case LLP as Legal Adviser
Advisers
WS Atkins & Partners Overseas and Engineering Consultants as
Technical Adviser
AC Alternating Current
Applicant An individual company or a Consortium of companies experienced in the
wastewater treatment sector
Pre-Qualified Applicant(s) who have fulfilled the eligibility requirements
Bidder set out in this RFQ and are not disqualified in terms of this RFQ and have
been issued a NPQ by the Procurers
BOOT Build, Own, Operate and Transfer
Customer Acceptance Test
CAT
A joint venture, partnership or other combination of international and/or
Consortium
KSA companies jointly participating as an Applicant
CDM Construction Design Management Regulations
cpi Characters per inch
DC Direct Current
DPi Dots per inch
Due Date the deadline for submission of RFP
EICA Electrical Instrumentation Control and Automation
1
LED Light Emitting Diode
LLC Limited Liability Company
LTC Levelized Treatment Cost
LV Low Voltage
MCC Motor Control Centre
MEP Mechanical, Electrical, Process
MEWA Saudi Ministry of Environment, Water and Agriculture
MFEC Minimum Financial Evaluation Criteria
Mg/l Milligram per litre
MOF Ministry of Finance of the Kingdom of Saudi Arabia
MTEC Minimum Technical Evaluation Criteria
MV Medium Voltage
NGR Neutral Grounding Resistance
NPQ Notice of Pre-Qualification
NTP Notice To Proceed
NWC National Water Company
O&M Operation and Maintenance
OP Operator Panel (HMI)
ORP Oxidation Reduction Potential
PABX Private Automatic Branch Exchange
PC Personal Computer
OP Operation Panel
3
Applicability of these Guidelines
MEICA guidelines are to be referred for design, Engineering, Procurement & Construction of Mechanical , Electrical ,
Instrumentation, Control and Automation installations at JA2 ISTP site.
Whereas, if any clauses of these Guidelines conflict with the latest EPC Proposal, the latest proposal data shall be
followed.
In the absence of certain portions of MEICA requirements in EPC Proposal, these MEICA Guidelines shall be referred
for design purpose.
Intent of MEICA guidelines is to construct MEICA assets, which makes the plant complete, integral and without any
conflicts of Design.
Note:The Project company obligation in this guideline will be transferred to EPC contractor.
1 INTRODUCTION
This Appendix sets out the General and Particular Specification for Mechanical, Electrical,
Instrumentation, Control and Automation (MEICA) for the Jeddah Airport 2 Sewage Treatment Plant
(STP) that the Project Company shall comply with. Where the Project Company is providing plant that
is outside of these specification clauses, the same standards and level of quality is to be applied as
detailed in these clauses to that plant.
The Project Company shall comply with the following SWPC standards:
Design Manual for Sewage Treatment Plants (Ministry of Water & Electricity; Feb 2007)
Standard Technical Specification for Sewer Networks (Ministry of Water & Electricity; Sept
2007)
Guide to the design of gravity sewers and manholes (SWPC)
Standard Technical Specifications Water Supply Networks (SWPC)
Saudi Building Code Requirements (SBC)
If there is conflict between the above SWPC standards and the clauses in this appendix B then
this appendix B shall overrule.
This specification has been produced to describe the MEICA works associated with this project see
JA2 RFP Part 2 Technical Specification for the project description.
In general, the Project Company shall carry out the scope of supply in accordance with this
specification and to the satisfaction of the SWPC and shall be responsible for the
technical performance in all respects of the Project Company works and, for the adequacy, stability
and safety of the Project Company’s site operations.
MEICA installations work within the STP shall be designed and carried out by the Project Company in
accordance with the current regulations, specifications and project requirements.
The final agreed specifications may be varied/adjusted to suit accepted proposals from the Project
Company, who shall use these guideline specifications as a basis to develop their own particular
project specifications. These specifications shall apply for the purpose of the bid. In all instances
acceptable best practices and applicable standards should be followed.
(i) A new substation for the site to the Saudi Electricity Companies
requirements, standards and approved layouts for electricity substations and
all other electricity cables, connections and infrastructure necessary for the
supply of electricity to the STP. The Project Company shall be responsible
for all negotiation with the SEC for the capacity and the supply tariff and all
payments for power for the Concession period;
(ii) potable water connections and related infrastructure necessary for the supply
of potable water to the Plant; and
and in all cases, the Project Company shall be responsible for connecting the same to the Utilities
Handover Points.
(b) The Project Company shall ensure that the Utilities Works are carried out:
5
2 APPLICABLE STANDARDS
2.1 Table of Standards
The current editions of the standards, codes and recommendations issued by the following
organizations shall apply for the design, construction, testing and commissioning of the Works.
All items provided by the Project Company shall be designed, supplied and installed in accordance
with the more stringent of the Kingdom of Saudi Arabia standards and international standards (ISO or
similar indicated below), but only to the extent that these international standards are not in conflict
with Saudi Arabian legislative requirements.
7
3 ELECTRICAL DETAILS
The Project Company’s shall provide everything necessary to ensure a fully functional Sewage
Treatment plant for the Concession period. The following sections describe the requirements of the
main expected elements to be featured in the electrical infrastructure. The Project Company shall fully
review all documents and submit their design as part of the tender.
The site power supply shall be backed up by suitably sized standby generators to meet the
requirements of the critical processes and operation and maintenance needs. This will require the
provision of a Power Management System (PMS) that will load shed non-critical plant in the event of
power failure.
(i) maintain the Electricity Delivery Points and Electricity Metering Stations in
accordance with the Law, Good Utility Practice and the requirements of SEC;
(ii) comply with all rules, regulation and requirements of SEC as regards to the
calibration and maintenance of the Electricity Delivery Points and Electricity Metering
Stations; and
(iii) communicate and coordinate with SEC in order to ensure the efficient operation of
the Electricity Delivery Points and Electricity Metering Stations.
The power supply to the STP shall be at Medium Voltage (MV): 13.8 kV, 60 Hz, 3 phases, 3 wires,
and ground/earth.(The origin of the MV supply from existing Influent Pump station switchgear with Single feed
upto 13MVA and coordinated by the Project Company and SEC or NWC/ GACA (Client.
Distribution transformers provided by the Project Company shall provide LV (Low Voltage): 380V,
60 Hz, 3 phase, 4 wire, solidly earthed supplies for the STP plant.
The breakers shall be provided with indicating lamps for all cubicles. This shall include indication for
circuit breaker open position, circuit breaker closed position and circuit breaker tripped on fault
conditions.
Breakers shall be provided with remote operating controls and volt-free contacts for connection to a
remote central control desk and SCADA to provide ‘remote manual’ control and remote monitoring of
each circuit breaker.
Modern powered electronic (numerical) protection relays shall be provided at each circuit breaker to
suit the application and connected load type. A fully graded protection system shall be provided in
accordance with the power system requirements. Circuit breaker control design shall include close
first interlocks, inter-trip receive and trip send functions, trip circuit supervision relay, sync check relay
etc. as required.
In case of dual power supply, the circuit breakers shall also have a mechanical and an electrical
interlock installed across them to ensure they always are operated on a 2 from 3 basis at all times if
this is a requirement of the power system design.
Each circuit breaker shall be supplied complete with a manual spring-charged closing mechanism
having a trip-free feature and complete with on-off indication, DC shunt trip and auxiliary switches.
Automatic tripping of circuit breakers shall operate under fault or under voltage conditions.
Power distribution transformer low voltage windings (380 V) shall be connected to 380V switchboards
and MCCs to feed process equipment and loads at different locations.
All MV switchboards provided shall be capable of continuous operation within the internal
environment over an internal temperature of 5degC to 40degC
For MV switchgear each functional unit shall be constructed to form a rigid, free-standing enclosure
and adjacent enclosures shall be securely bolted together to form a rigid Assembly. The switchgear
sections shall be constructed from steel with a protective painting system giving a life to first
maintenance of at least 25 years.
9
The overall switchgear enclosure shall be to IP41. Internal compartments shall be IP3X.
Busbars shall be hard-drawn, high conductivity tinned copper. The busbars shall be suitably rated and
be capable of carrying the rated short circuit current of the switchgear for 3 seconds, an earth bar
shall run the whole length of the switchboard.
Ratings of current transformers, indicating instruments, electronic protection relays etc. shall be
determined by the Project Company with the approval of the Engineer. All cable entries to panels
shall be from below or rear side of the switchboard.
For all units, mechanical indicators on switches shall show on, off, earth position in Arabic and
English.
Each door to the high voltage switch room(s) shall be provided with a set of safety and warning
notices in Arabic and English with the inscriptions in accordance with statutory requirements approved
by the SWPC Engineer.
Each RMU shall comprise two ring switches and a tee-off vacuum circuit breaker, all mounted within a
common enclosure. Integral earthing switches shall be provided for each ring switch and the
transformer circuit.
The RMU shall be designed for front operation and indication, the RMU shall be suitable for both
indoor and outdoor mounting.
Distribution transformers shall be liquid filled outdoor type, oil immersed and have naturally cooled
radiators.
Each substation shall include two transformers which shall operate as duty and standby units,
providing N+1 redundancy. Each transformer shall be rated to handle 100% of the connected load. All
transformer ratings shall be determined by the Project Company with the approval of the Engineer.
Transformers shall be suitable for operating in the site climatic conditions and this may include sun
canopies to protect the transformers. An assessment shall be carried out by the Project Company and
approval shall be sought from SWPC for any solution that makes the transformers more suitable
for climatic conditions.
3.7 Cabling
All MV and LV cables including accessories such as pot-heads, cable splices, glands or terminals
shall be provided in accordance with the current Regulations of SCECO.
All cabling shall be supplied from SWPC approved suppliers.
All MV power, LV power, control and instrumentation field cables shall be steel wired
armoured (SWA) type.
Cables routed inside buildings and through cable trenches shall be securely mounted on
heavy duty, galvanised steel (or GRP type) cable ladder or cable tray.
Power cables shall be direct buried for outdoor runs with suitable trenching except for road
crossings where HV and LV ducts shall be provided. MV, LV, control and signal cables shall
be segregated for the whole length of the individual runs.
Bending preparation and depth for the cables shall be suitable for the application.
The thermal characteristics of the cable sand used for backfilling shall be suitable for the
cable trenches involved
Cable testing shall be carried out, including insulation, continuity testing and associated
documentation to be provided and recorded on the CMMS.
All HV cables shall be pressure tested prior to commissioning and following repairs or
alterations. The HV cables shall not be energised during the pressure test.
The cable installation design shall utilise ERAC/ETAP (or recognised equivalent) and load flow
models.
If due to working condition e.g. ambient temperature, atmospheric contamination, mechanical stress,
electrical interference, etc. more stringent methods of wiring are required to fulfil particular needs then
the most suitable cables and installation methods shall be used.
Fully detailed Cable Schedules shall be produced for each installation giving detailed information
about cable type, design load, cross-sectional areas and estimated route length. Cable lengths and
ratings of cables shall be appropriately sized. All cable information shall be recorded on the CMMS.
Installation routes and details of the cables shall be provided on drawings and submitted to SWPC
for approval. For any modification required approval must be sought from SWPC. In general, all
required cabling shall be provided and installed as per the approved design.
11
3.9 Distribution Boards (For Building Services)
Each building shall be provided with building services distribution boards, for MEP services (lighting,
small power, HVAC, fire alarm system) The distribution boards shall be supplied and installed in
locations with the approval of the Engineer.
Separate dedicated distribution boards shall be provided for instrumentation and process critical
equipment. Building services distribution boards shall not supply instrumentation.
MCCs supplied shall be totally enclosed, freestanding, sectionalised, multi cubicle type, factory built
assemblies. They shall be equipped as required to provide incomers, bus-couplers, motor starters,
motors drives, feeders and ICA controls for the STP low voltage plant and equipment.
Construction shall be to (or equivalent to) Form 4 (in compliance with BS EN 61439) withdrawable
type.
Low voltage MCCs shall be supplied and installed inside dedicated indoor ‘LV switch rooms’.
Access to the field cable terminations shall be from the ‘rear’ or ‘front and rear’ of the MCC. Cable
entry shall be at the bottom.
All LV switchboards and MCCs provided shall be capable of continuous operation within the internal
environment over an internal temperature of 5degC to 45degC
The overall MCC enclosure shall be to IP54 minimum for non-ventilated equipment and IP41 for
ventilated equipment. Internal compartments shall be IP2X.
An air insulated, enclosed busbar chamber shall run along the length of the MCC/switchboard with an
external copper earth bar. Busbars, neutrals and earth bars shall be hard-drawn, high conductivity
tinned copper. The busbars shall be suitably rated and be capable of carrying the rated short circuit
current of the MCC for 3 seconds.
Circuit breakers rated 800A and above shall be Air type circuit breakers.
Ratings of current transformers, indicating instruments, electronic protection relays etc. shall be
determined by the Project Company with the approval of the Engineer.
Electricity KWH meters are to be provided on the incomers to MCCs and at principal feeders as
required to meet SWPC energy management requirements.
Motors with nameplate ratings 11kW (15 HP) and above shall be provided with reduced voltage
starting e.g. star-delta, soft starter or variable frequency drive Direct On-Line DOL, depending on
All Motors shall have their own individual starter panels for isolation and correct lock-out procedures.
All package equipment shall be supplied with their own local control panels to provide operational
flexibility.
For all units, mechanical indicators on switches shall show on, off etc. in Arabic and English.
Each ‘LV switch room’ door shall be provided with a set of safety and warning notices in Arabic and
English with the inscriptions in accordance with statutory requirements approved by the
SWPC Engineer.
Automatic Power factor correction (PFC) units shall be provided in the MV or LV switch rooms to achieve an
overall power factor of 0.95.
The earthing electrode systems shall consist of interconnected rods and buried tapes, it shall be
designed with multiple electrodes and provided with readily removable test connections to allow for
electrode testing. Double earthing electrode nests shall be installed at a location near to the
Substation that is approved by the SWPC.
Connections to main earth rods shall be installed in a manner that electrode nests shall maintain
earthing even when one is not working or isolated.
A minimum of 4m separation shall be maintained between the MV and LV rod groups. At any location
where the MV earth does not maintain the 4m separation from the LV earth, the MV earth will be
insulated to maintain the electrical isolation between the two systems (if required).
The MV Main Earth Bar shall be connected to MV Main Earth Bars in adjacent substations.
Within each substation, the Main MV Earth Bar and Main LV Earth Bar shall be interconnected if the
earthing system design permits this interconnection. To ensure this arrangement is safe, the ground
potential rise will be calculated as per TES-P-119.10 and confirmed as lower than the acceptable
touch and step voltages within the same standard.
13
Where gates exist in steel fences or the doors of a total enclosure are of sheet steel, particularly if the
fence or door is discontinuous, they shall be bonded on both sides of the gate or door to avoid the
possibility of a potential developing across the gate or door.
Where there are metal structures or fences adjacent to a substation, potential differences may occur
between them and the metal parts of the substation or the fences, which may be within touching
distance. On the other hand, if such structures are bonded, or in contact with the substation
steelwork, then the potential may be carried a considerable distance from the substation, e.g. along
the wires of a fence with wooden posts and create a danger elsewhere. Substations must be
designed and sited to avoid these situations.
The size, type, connection details and installation method of bonding conductors or tapes shall be
designed in accordance with the IEC international Standards.
The lighting installation shall include normal task lighting, maintenance task lighting and emergency
lighting for all indoor areas.
220 V single-phase socket outlets shall be provided in the Administration Building, Personnel Building
and Guard House and in other buildings on a distance as per engineer instruction and at least two in
every room of the Administration Building and Guard House and all plant areas at suitable locations.
380 V three-phase socket outlets shall be provided at least one per plant area where the Project
Company considers these necessary for operation and maintenance purposes. The Project Company
shall prepare detailed layout and installation drawings for approval by the Engineer. Lighting and
small power installations including all equipment and materials such as lighting fixtures, socket
outlets, Lighting Panels with miniature circuit breakers, lighting cables, wires and conduits shall be
provided and installed by the Project Company in accordance with the relevant clauses of the
SWPC General Electrical Specifications.
The fire alarm system shall be a fully addressable open protocol system. The fire alarm system shall
be configured into zones.
Electronic sounders shall be installed to achieve minimum audibility levels of 75dB (A). Audibility shall
be 10dB (A) above background noises where these persist for more than five seconds. Levels shall
be measured with all doors closed. Sounders shall incorporate strobes and be programmable from
the fire alarm panel.
Smoke detectors shall be installed to comply with BS5839 or equivalent specification. Optical smoke
detectors shall have a sensitivity adjustment over a three-step range to allow for variance in ‘air’
condition within any room or area.
Heat detectors shall be the combined fixed high temperature / rate of rise type. Detectors shall
possess a minimum of 6 possible selecting sensing states of operation.
Interface units shall be provided as necessary to ensure operation / shut-down of ancillary items of
equipment / plant etc. in the event of an alarm condition.
A label shall be securely fixed to each device clearly identifying the address notation in line with the
designs schedule of devices.
15
The system shall be wired in MICC cable with a LSF over sheath, or approved equivalent, having and
enhanced circuit integrity when exposed to fire. Cables shall be manufactured to BS 7629 or
equivalent. Cables shall incorporate copper conductors rated at 300/500 volts and coloured red.
Break glass call points shall be provided at all points of egress from the buildings and additionally as
required by search distances.
The Fire Alarm System shall include a function to allow the operation of agreed elements to not be
affected during a fire alarm system test.
The Project Company shall include for the full testing, commissioning, verification, certification and
demonstration/training of the fire alarm system by the specialist fire alarm supplier.
The Project Company shall arrange for a suitable broad band communications network connection
with the regional Communications provider.
The instrumentation and control system shall include the following items as minimum:
New Central Operator Control and Process Monitoring System for the new plant complete
with monitor screens, processors, servers, printers and plotters.
Overvoltage/lightning protection for UPS, PLC and specially, for surge/lightning, exposed
equipment(s).
PLCs, OPs, process and analytical instrumentation as appropriate for the approved design
The central control system to be viewable from SWPC's existing regional SCADA
system
The Central Operator Control and Process Monitoring System shall utilize a purpose designed cable
communications network, and a detailed specification for this network shall be submitted at the time of
Tender for approval by SWPC.
An alternative solution other than the one described can be provided if approved by the SWPC.
The processes involved shall be selected to assist with the design parameters and this may affect the
types of instrumentation and controls involved. Once these are finalised approval must be obtained
from SWPC.
4.1.2 Works Operating Philosophy / setpoints
The systems shall be provided for the automatic operation for the STP and their associated support
and subsidiary plant installations with minimum staffing level.
Plant shift supervisory staff located at specific plant areas within the works.
Plant operating and labouring staff necessary for day to day routine manual operating
tasks, and associated work.
Maintenance personnel necessary for routine day to day and periodic plant maintenance
tasks
Within each plant area, the individual plant installations shall be controlled by their respective local
PLC and OP. The PLC systems shall monitor the operation and shall carry out interactive control
functions between the plant installations within their areas.
All the signals that are required for the process plant safety, operation, plant critical alarm/trips and
controls shall be hard wired between plant installations.
Under abnormal operating conditions or a control system failure, each plant installation shall be
capable of being switched to manual control mode from the local switchboards.
The sub masters shall pass all the information to the master station in the main control room in the
Administration Building.
Under normal conditions, each local PLC shall control the local plant and the master station shall
supervise the whole STP process. All local plant shall work automatically, but it shall allow local "take
over" if necessary. The "takeover" shall be activated by a command or action at the local control
panel.
Control shall revert to automatic by activating a further command at the local control panel. All local
and central control system shall include spare installed capacity of not less than 25% of each input
and output module together with a minimum of 30% spare system logic capacity.
The Project Company shall design, supply and install all equipment in the main control room.
The equipment that is proposed to be installed shall include but not limited to the following:
One (1) Central Operator Control and Process Monitoring System including state of the art
PCs and accessories in accordance with the approval of the Engineer.
One (1) Program Development System including state of the art PCs and accessories in
accordance with the approval of the Engineer.
19
One (1) Calendar clock.
Two (2) set of control room furniture and chair for plant and personnel.
One (1) set of equipment in the Manager's office comprising one (1) PC and accessories in
accordance with the approval of the Engineer.
One (1) UPS system supplied to provide stand-by power for 120 minutes. This equipment
shall be protected against lightning and power surge.
Display screens for all the site video installations
The system shall be based on an interconnected PLC network for control with multiple PCs providing
master station(s) and operator panels (OPs)
The alarm, digital and analogue information from the plant and the digital and analogue commands
from the sub master to the plant shall be displayed at the OPs at the sub masters and transmitted to
the main control room for processing and storage by the master station. This information shall also be
displayed on the monitors in the main control room and on the monitor in the manager's office.
A program development system shall be provided in the main control room. It shall be capable of
amending the system configuration and control database to incorporate planned expansion to the
works and also to take advantage of future technological developments which may take place in the
field of STP applications software.
Adjustable set points to modify the parameters on any item of plant shall be accessed by password
protected User Access levels.
Each sub master station shall consist of a PLC housed in a panel. The OP shall be mounted in the
front door. The panel shall also be equipped with all equipment necessary for the control and
monitoring of the plant for which that Local PLC is responsible. The direct control from the motor
control switchboards/MCC shall be manual only.
Automatic control sequences for plant shall be carried out within the PLCs but under abnormal
operating conditions or a PLC failure, the plant shall be switched to manual control from the relevant
control panel(s) or motor control centre.
An Uninterruptable Power Supply (UPS) system shall be installed to maintain each sub master for 120
minutes under a mains failure condition.
Central master station shall scan the sub masters. Block transfer of data shall be accepted. All alarm
and event time and data recorded at the sub masters shall be transferred to the master station.
Failure of any outstation equipment shall provide an alarm at the sub master and central master but
shall not halt the routine scan. The scan shall step over the failed outstation.
Equipment shall operate over the temperature range +0°C to +55°C with relative humidity at 25°C of
95% non-condensing
Plant signal input/output (I/O) technical requirements:
Digital input
Volt free contact with galvanic isolation on input module
Digital output
Galvanic isolation and to switch up to 2 A at 24 V D.C.
Analogue Input:
4-20 mA or 0-10 V, with common mode noise minimum of 80 dB and series mode
noise of minimum 40 dB. Each input shall be signal isolated.
Analogue Output:
4-20 mA or 0-10 V with linearity ± 0.2 %, with an overload capability of 25%
The mean time between failures shall be stated and shall not be less than 5,000 hours and mean time
to repair shall be stated. Factory Acceptance Tests(FATs), witnessed by the Engineer or his
nominated representatives, shall be included.
The computers shall utilise a real time multi-tasking and networked operating system with a proven
track record in real time control applications.
It is a requirement that the system shall be supported by ‘on line’ configuration and editing of all VDU
mimic displays and database and to create new displays and additional database.
A minimum of two active windows should be displayable concurrently. The system shall be designed
to minimise the operator’s use of the keyboard. All major functions shall be accessible on-screen by
the use of the mouse.
VDU mimics shall display dynamic colour details of flow rates, pressures, motor status, levels, alarms,
electrical power supplies and other general equipment status conditions.
The software shall be fully compatible with the current release Microsoft operating system factory pre-
loaded on all computers.
The system supplier shall demonstrate a track record of having interfaced with SCADA / remote
telemetry equipment (RTU) supplied by reputed manufacturers with open industrial protocol.
User Access
The functions available on the system shall be fully flexible so as to allow users access levels to be
customised by the System Manager to suit individual user requirements.
Access to Management and Engineering levels shall be restricted by user-selectable password. The
security systems shall be based on a set of privileges, which may be granted or denied to individual
users by the System Manager. The following five levels of User Access shall typically be required;
21
- Level 1. Public level - Views Process Overview Screen and Operational
Mimic displays only.
- Level 2. Operator level - Gives Operators access to all Mimic Displays
and Routine Operational Setup Screens.
- Level 3. Supervisor level - Giving Supervisors access to all Mimic
Displays and all Operational Setup Screens.
- Level 4. Engineer level - Giving Engineers access to all Mimic Displays,
all Operational Setup Screens and all Engineering Setup Screens
- Level 5. System Manager Level - Giving System Managers full access to
all Mimic Displays, all User Accounts and all User Password
Configuration Changes, all other Utilities and all Windows Operating
System functions.
As a minimum the Operator, Engineer and System Manager levels of user access shall be utilised for
the System Manager.
When logging in and out a log file shall be recorded and time and date stamped. Log in and out time
and dates will be printed on relevant/configured printer.
The software structure shall be based upon a distributed automation system that can be divided into
three main areas:
1) Operation and monitoring including signalling and reporting
2) Communication between the automation equipment
3) Process automation (measuring, open or closed loop control)
Software Documentation
The configuration documentation shall be produced in accordance with the IEC standards.
The Project Company shall provide a Function Design Specification (FDS) which shall be submitted to
the Engineer for approval before manufacture and purchasing commences. There shall be one (1)
Arabic and one (1) English version.
The following material shall be included as a minimum:
List of Contents
Reference to supporting standards, manuals and specification.
Description of the design and design criteria
Relevant details of associated mechanical and electrical equipment
Functional specification
Complete set of supporting drawings
Design documentation describing all the control programs furnished with the system
Design documentation shall include the following as a minimum:
A flow chart of each program module detailing the flow of control throughout the module.
Analysis of normal control modes in manual, remote and automatic.
Analysis of modes of faults and failure.
Analysis of STP start-up and shutdown procedures.
Hard copy documentation of all configuration data, all user accessible source code i.e.,
control program code, reports etc., and database contents including listings. All program
listing shall be clearly and completely commented so as to convey to the reader a full
understanding of the function of the program.
Calculations
Description of quality control methods and approvals
Outline of test procedures
Program for manufacture, delivery, installation and commissioning
Appendices, as necessary, to include the information for the manufacturer
Literature for each item of equipment supplied
The FDS document shall be on A4 size, numbered sheets bound with covers showing the
Employers name, title of scheme, title of contract, Project Company’s name and reference
number.
All drawings shall be on A3 size sheet and include:
Purchasers Name
Title of Contract
Project Company’s Name
Title of Drawing Number
Date
Author
Signature of Project Company to the effect that the drawing has been checked and approved
by him prior to submission.
Facility must be incorporated to permit easy construction and modification of the display pages by
using a standard library of shapes and symbols. The library shall be added to and modified by the
user as required. The configuration shall be object orientated for ease of use.
The initial application software shall provide for the display pages listed below and any pages
necessary for the system to function as a complete entity.
Mimic displays.
System geographical overviews.
Graphic displays.
Trend displays.
Alarm summary tables with date and time.
Event logs of past 72 hours with date and time.
Hydraulic overview.
23
- Print speed: 300 characters per second.
- Print quality: letter print with optional draft mode.
- Paper feed: adjustable width tractor feed mechanism.
- Paper width: 18 to 38 cm.
- Print pitch: 10 or 12cpi.
- Print width: 132 characters at 10cpi.
- Character set: full ASCII. Noise level: < 50dBA.
Colour Printers
A printer shall be used for the production of colour screen dumps and reports and shall have a
sufficiently sized buffer memory such that system performance will not be degraded when the colour
printer is operational and comply as a minimum with the following:
Paper size: A3 and A4.
Print speed: 6 A4 text sheets per minute.
Print speed: colour graphics, 2 minutes per A4 page at 80% graphics.
Colours: compatible with VDU graphics.
Paper feed: A4 and A3 with auto sheet feeder mechanism and minimum 50 sheets per tray.
Resolution: Minimum 600 DPI.
4.3.6 Reports
A reporting system shall provide the following reports:
Plant Alarm Lists Plant Status Lists
Plant measured Variable Lists
Daily reports and summary daily reports
Weekly reports and summary weekly reports
Monthly reports and summary monthly reports
Yearly reports and summary yearly reports
Maintenance reports and forecasts
It shall be possible for any operator to type a message into the system for use by management or
other shift operators. This message shall be displayed on the monitor and can be directed to the main
printer.
An OP (industrial PC) for the local plant shall be door mounted. Metal wiring plan pockets, size A3
port and a wiring plan shall be mounted on the inside of the front door.
The front door and the swinging frame shall not be hinged on the same side of the cubicle.
All PLC equipment and auxiliary components including but not limited to: processor, I/O cards,
communication cards, fieldbus cards, PLC power supply units, terminals, +25% spare terminals, cable
clamp rails, cable conduits, fuses, relays, etc. shall be mounted on the panel backplate.
Earthing bars for protective earth, shield earthing system and electronic earthing system, etc. shall be
provided.
The front door and the swing frame (if fitted) shall be earth protected. Wires to the front door and the
swing frame shall be protected by flexible cable conduit. All equipment in the PLC panel shall be
permanently labelled, all labels shall be readable without the need to remove any components.
Provision shall also be made to store the system database after amendment or additions have been
made to the system mimics, equipment and alarm lists or applications software.
Maintain an AC output voltage of 220 V ± 2% over the entire range of load, DC voltage and
power factor.
Maintain an output frequency constant within 1 % of nominal.
25
Be capable of continuous operation under the ambient temperature specified.
Maintain an overload of 125% for 10 minutes.
Be equipped with an AC output filter to limit the total harmonic voltage distortion (THD) across
linear loads to 5% over the entire range of load, DC voltage and power factor.
Be equipped with a DC input filter to ensure that the RMS value of the AC voltage does not
exceed 5% of the DC voltage.
Maintain inverter output on loss of mains supply without any interruption.
Provide a volt free alarm contact for:
Charger failure
Inverter failure
Static switch failure Batteries discharging
Provide instrumentation for:
Charger output voltage
Battery current (charge/discharge) Load current
Output AC voltage
Provide indications to show status of the component parts of the system.
The UPS shall be mounted in a adequately ventilated steel cabinet with front access door.
Batteries shall be the nickel cadmium or alkaline type and shall be of adequate capacity to
maintain full operation of the specific load equipment plus 10%, for a period of at least 120
minutes during mains failure assuming a normal charge condition at the start of the mains
failure.
4.10 Instruments
The following sections detail the requirements of instruments that are anticipated to be in the final
design. There may be variations but approval must be obtained from SWPC. Unless stated
all instruments shall be rated to IP67
As a minimum all plant above 45kW, where applicable and within a state of the art manufacturer’s
norm, shall be fitted with:
Below 45kW plant is to be fitted with the maximum level of condition monitoring the plant
manufacturer provides.
The electrode assembly shall be standard wall mounted assembly with quick release facility.
Automatic cleaning and calibration facilities shall also be provided.
The equipment shall operate reliably and within specification throughout the climatic
conditions
The equipment shall be resistant to the presence of Hydrogen Sulphide (H2S).
The Project Company shall state the maximum H2S tolerable level of equipment
The output signal shall be 4-20 mA and the system accuracy shall be within ± 2% of span
between automatic calibration.
The system shall be of the automatic calibration/cleaning type with the facility for manual or
remote automatic initiation with selectable time intervals in the range of 6 to 48 hours.
Volt free alarm contacts to be provided for:
System failed/power failed / Calibration failed
Dissolved oxygen sensor failed / Dissolved oxygen outside control limits
The dissolved oxygen sensor shall be:
Either galvanic (lead anode and silver cathode) or polarographic with gold cathode. A solid
gel electrolyte is preferred in either case in the form of a plug-in cartridge to be exchanged at
12-month intervals with no electrolyte change guarantee.
The cell shall utilize a polyethylene or P.T.F.E. membrane of adequate strength and
robustness to allow the following:
A measurement range of:
0-200% saturation or 0-20 mg/l or 0-100% saturation or 0-10 mg/l
An automatic temperature compensation of between SoC (State of Charge 0%) and 40°C
(100%) shall be provided utilizing an in-built thermistor within the probe.
Power shall be supplied from respective plants UPS.
27
Measuring range: - 0 C to 40°C
The transmitter shall have an output of 4-20 mA or 0 -10 V
The transmitter shall have an accuracy within a 1 % of its operating range, repeatability within
±0.2% of span and a dead band not exceeding 0.2% of span.
The transmitter shall provide a system to indicate sensor failure.
Power shall be supplied from respective plants UPS.
Each installation shall be provided with cleaning equipment. This facility either shall operate
continuously or shall include equipment for intermittent operation.
The flowmeter primary shall incorporate electrode(s) to detect when the pipe is not full. The detector
output shall control circuits within the converter to open circuit the analogue signal and initiate an
indication of the "pipe not full" condition.
The electrode holder shall be of the heavy-duty type and be suitable for mounting in the open, or
within an enclosed tank, and shall be totally enclosed and with environmental protection to IP67 as
appropriate.
Each sensor shall be installed on a robust and rigid structure provided for the purpose under this
Contract. The structure shall include a means of levelling the sensor so that the transmitter beam is
perpendicular to the liquid surface and shall provide a safe and easy access to the sensor for
servicing and maintenance.
Each installation shall be supplied installed complete with a local indicator which
shall be incorporated in the transmitter.
29
4.16 ORP Meter
The ORP meter shall have a redox sensor with PTFE ring diaphragm. It shall be able to operate at a
maximum temperature of 50°C and a maximum pressure of 6 bars. There shall be two (2) line display
with two (2) limit and one (1) alarm contact. Output range shall be based on 0/4 - 20 mA.
3
It shall be able to work in sludge type of liquid with a concentration of 2.5 - 5.0 kg/m at a maximum
temperature of 35°C.
4.17 pH Meter
pH meters shall be able to work at a pH range from 0 to 14. Temperature and pressure ranges shall
O
be 0-50 C and 0- 6 bars respectively. There shall be a ring shaped teflon diaphragm and a platinum
temperature sensor. The pH meter shall have a temperature compensation function. The pH meter
shall be heavy-duty type and manufactured to operate in rough environment.
.
The detectors shall give an audible warning when H2S is present in air above the lower safety limit.
The alarm signal shall also be transmitted to the PLC. If a H2S gas monitor is installed inside a
building where H2S gas might be present, an audio-visual alarm must be installed at all the entry
points to the building.
The incoming and outgoing signals cables from the PLC shall be segregated.
All signal- and control- cable shall be segregated from LV and MV cables.
All multi-pair cables shall include a minimum of 25% spare cores. This spare capacity shall be over
and above any cores that may be required for proposed future installations of extensions. All cores,
including the spare ones, shall be connected to terminals.
4.20.1 Motors
All motors in each plant area where applicable shall at least have the following indications;
Off
Hand/OFF/Auto (and Remote if required)
Running
Standing
Available
Tripped
Fault
Duty/Standby selection
Information that is important for the operation of the plant shall be transferred from the other
equipment.
Status information, alarms and warnings from other installations i.e. transformers, HV -, MV -,
LV-switch boards, heating-, cooling-, ventilation- system, fire alarm, gas alarm etc. shall be
taken care of by the control system.
All status information shall be able to be read on each plant areas Operation Panel and on the
control equipment in the main control room.
All alarms and warnings shall automatically be displayed on each plant areas Operation Panel
and on the control equipment in the main control room.
The Project Company shall prepare a list of alarms, trips and warnings, that shall be
controlled and approved by the Engineer.
The screens cleaning devices shall operate and stop according to the signals from the local control
panel. The time period between the signals shall be determined by experience.
The cleaning devices shall be interlocked by signals from the level indicators, which set the cleaning
devices in operation at a certain head loss through the screens.
The cleaning system shall operate at a pre-set time interval for a pre-set duration. Conveyors,
compactors and wash water feed shall start based on screens operation and stops after a pre-set
time delay.
Each screen, conveyor and compactor shall have a force switch. The screen switches shall stop the
rakes when there is something stuck in the screen and an alarm shall be given. After cleaning the
screen, the cleaning devices shall be restarted from the local control panel.
The conveyor and compactor switches shall stop the equipment and its interrelated screens.
Emergency shutdown switches shall be provided for the screens, conveyors and compactors.
31
4.20.3 Grit Chambers
The travelling bridge and associated pumps shall automatically start based on time sequence
activated by signals from the local control panel. The time period between the start signals and the
number of bridge travels shall be determined by experience.
The grit classifier shall be interlocked to start with the bridge and shall have the same operation
period as the bridge with an additional pre-set period.
Blower room
The blowers for the aeration of the grit chambers shall operate continuously.
If one of the blowers fails, the stand-by unit shall automatically start. After the correction of the fault,
the operator shall manually, on the panel or MCC associated with the blowers, reset the system for
normal operation.
The blower duty cycle shall be alternated once a week to equalize the operating time of each the
blowers.
Motor valves
The motor valves shall be automatically controlled in accordance with the blower configuration and
shall be equipped with position indicators for information and interlocking.
Pressure instruments shall be provided on the air pipes for indication and alarms.
Scum sump
The sump level transmitter shall automatically control the scum pump in accordance with the water
level in the sump. A level instrument shall provide high level indications in the sump and give an
alarm.
The scum mixer shall work continuously.
The recirculation pumps shall be operated in cascade that is controlled by the inlet flow meter in order
to achieve a constant recirculation rate.
In order to keep a preset level of dissolved oxygen in the tanks, each tank shall be equipped with an
oxygen transmitter. These transmitters shall control the motor valves located on respective air-tubes
to maintain the preset level. The dissolved oxygen in the tanks shall be measured and registered.
In each unit, one tank shall be equipped with a temperature transmitter to measure and register the
temperature.
ORP meters and pH meters shall be placed in the necessary locations of the tanks by the approval of
the Engineer.
The tanks shall be equipped with motorized penstocks that shall not be connected to the central
automation system. The penstocks shall be equipped with position indicators.
If one of the pumps fails, the stand-by pump shall automatically start. After fixing the problem, the
operator shall manually, on the OP, reset the system for normal operation.
The pump sump shall be equipped with an alarm and a level switch to stop the pump.
The penstocks in each station shall be equipped with position indicators.
33
4.20.12 Scum sump
The level transmitter, in the scum sump, shall automatically control the scum pump according to the
sludge level in the sump. The level indicator shall be used for high level indication.
4.20.14 UV
Level transmitters shall be installed at the outlet of each UV channel to monitor the level at the outlet.
The level transmitters shall indicate level and initiate alarms indicating flooding due to high levels in
the UV channel.
Mixers
The mixers in the sludge storage tank shall operate continuously.
Diffusers
The oxygen transmitter shall control the air going to the diffusers in the tank. There shall be one (1)
blower in duty and one (1) blower in stand-by status. The blowers shall be duty alternated once a
week to equalize the running times.
If the blower on duty fails, the stand-by unit shall automatically start. After the rectification of the fault,
the operator shall manually, on the OP, reset the system for normal operation.
The sludge pumps and the dosing pumps shall be automatically operated. The belt filter(s) and the
sludge storage tank shall be interlocked so that a pressing cycle cannot be started unless sufficient
amounts of sludge are available in the storage tank.
5 MECHANICAL
The number of process units and equipment shall be in accordance with the process design and
system requirements.
The following requirements shall be considered in the design, equipment supply and system
installation:
all valves and penstocks shall be fitted with rising spindles type;
all package equipment shall be supplied with local, dedicated control panels to enable
operation to be switched from remote to local control;
operational flexibility and interchangeability shall be incorporated in the system design; and
The arrangement of plant and equipment shall be such that sufficient space for its
installation, removal, maintenance and safe operation is provided.
2 stage mechanically cleaned inlet screens i.e. course and fine screens;
35
belt conveyors, screw conveyors or screening trough;
screening press and screening containers;
manual screen for plant bypass;
penstocks /sluice gates; and
drain gate valve
The operation of the conveyor shall be interlocked with the that of the screen. The sequence shall be
adjustable in order to establish the most suitable operating regime.
An additional belt or screw conveyor with a bidirectional motor shall be provided to transfer the
compacted washed screenings to a duty / standby screenings container.
Belt conveyors shall have a minimum belt width of 600 mm and operate at a speed sufficient to
remove the maximum amount of screenings accumulated.
Belt conveyors shall be fitted with stainless steel side plates to ensure that the screenings are
retained on the conveyor and a suitable arrangement shall be made to drain excess water into a
drainage channel.
The entire equipment, including auxiliary components, shall be mounted on and supported by a robust
stainless steel framework,
The machinery shall be equipped with overload protection devices that shall stop the conveyor and
give a fault alarm in the event of overload.
The belt shall be manufactured from 3 ply cotton / nylon mixture and shall have oil resistant rubber
covers on the top and bottom faces with thicknesses of 2.5 mm and 1 mm respectively. The belt shall
be driven by an enclosed motorised conveyor roller.
A counter-balance type belt scraper shall be placed under the driving and tail discharge rollers. The
belt scraper shall have a renewable rubber blade to remove all adherent material
Each conveyor shall be provided with stainless steel chute which shall be designed to prevent
adhesion of screenings to its surface. The chute shall direct screenings from the conveyor into
containers. The belt conveyor shall be enclosed to connect to an odour control system.
Screw conveyors shall comprise an Archimedean shaft mounted screw running in a semi-circular
trough supported by heavy duty self-aligning bearings at the drive end and a bearing strip at the non-
drive end. Suitable bearings shall also be provided at the drive end to minimize axial loading of the
drive gearbox.
Screw blade thickness shall be a minimum 15mm. Screw conveyors shall be fabricated from grade
316L stainless steel, the component parts being bolted together with grade 316L stainless steel
fasteners, all joints being positively sealed with gaskets. The screw shall be designed in accordance
with BS4409.
The screw channel shall be protected by two layers of easily-replaceable differently coloured
hardened wearing surfaces.
The design of all the conveyors shall incorporate electrical switches on all the removable inspection
covers that will stop the conveyor if any of the covers are opened.
The operating sequence of the press shall be interlocked with the automatic operation of the screens.
The sequence shall be adjustable in order to establish the most suitable operating regime.
The compactor shall be of the screw type. The compactor, including feed hopper and framework, shall
be manufactured from stainless steel 316L. The screw channel shall be protected by two layers of
easily-replaceable differently coloured hardened wearing surfaces.
.
The machinery shall be equipped with overload protection devices that stop the conveyor and
screening compactor and gives a fault alarm in the event of overload.
The wash water feed pipe shall be equipped with a solenoid valve and isolation ball valve. The wash
water shall be supplied from the plant wash water system at a pressure between 4 and 6 bar, or as
advised by the screen manufacturer, and will be controlled by a solenoid valve which will be open
when the compactor is in operation and closed when it is not.
37
5.2.4 Screening Containers
Each container shall have sufficient capacity to hold a minimum 5 days screenings and be equipped
with suitable fittings to facilitate handling by a lorry-mounted lifting device. The containers shall be
designed to permit self-dewatering of the screenings. The containers shall be welded and made of
mild steel plate and reinforced to provide a stiff and robust design. The containers shall be painted in
accordance with SWPC standards. Strip of rollers, or similar, shall be fitted to facilitate for easy
removal or replacement.
Penstocks
The penstocks shall be as per BS 7775 / BS EN 1984;
Penstocks shall be made of 316 stainless steel, may be either motor or hand operated. All shall
be equipped with hand wheels and rising spindles and have position indicators;
Penstocks shall be on seating or off seating as necessary; and
Penstocks shall be water-tight in one direction.
Sluice gates
Channels shall be designed to limit velocities during normal flow variations to less than 0.2 m/s. The
retention period shall be based on the size of particle to be removed. All aerated grit removal
facilities shall be provided with adequate control devices to regulate air supply and agitation.
Travelling bridge(s) shall be equipped with submersible pumps for pumping grit from the bottom of grit
chamber(s) to the stainless steel channel(s) and ultimately to grit classifiers.
Bridge(s) shall also carry surface scrapers to remove the scum from 1/3 the length of each line. The
scum shall be collected in outlet box(es).
Travelling bridge(s) shall be designed to carry the submersible pumps and all necessary stainless
steel works for the scum scraper(s). They shall be provided with replaceable rubber lined steel wheels
acting on the steel rails for both driving and guiding. Bridge(s) shall be equipped with any necessary
platforms.
Bridge(s) shall be equipped with an electrically driven traversing gear, furnished with overload
protection devices which. in the event of overload, stop the machinery and give a fault alarm.
Bridge(s) shall be made of coated steel and all material in contact with water, such as channels,
pipes, scrapers, etc., shall be made of stainless steel.
Outer coatings of pipes installed under the ground shall be glass-reinforced bitumen.
Blowers, shall be provided and installed in a separate building close to the grit chamber(s).
Blowers shall be designed to supply sufficient air for the efficient operation of aeration system.
Blowers shall have a safety feature to prevent air backflow due to power loss.
Blowers shall be positive displacement rotary type and be air cooled. They shall be driven by electric
motors and mounted on a steel or cast-iron base plate.
Each blower shall be complete with shock insulation, flexible connectors, suction filters, resonance or
absorption type suction and discharge silencers, safety valves, check-valves, pressure gauges and
thermometers.
The drive between blowers and motors shall be through flexible pin and buffer couplings or of the V -
belt type.
Diffusers shall be tubular type and placed parallel to the longer sides of the chambers. The main
distribution pipes between the blower house and grit chamber, branch pipes, manifold pipes and
diffuser pipes shall be properly sized and selected by the Project Company.
39
Ball valves shall be made of stainless steel.
5.3.8 Containers
Containers shall be designed and constructed as specified in Clause 5.2.4
Pipes, channels and scum outlets, supports and brackets shall be made of stainless steel.
5.4.1 Penstocks
All penstocks, shall be selected by the Project Company areas and be suitable for local environment
in which they are installed.
All penstocks shall be in accordance with the specification outlined in Clause 5.2.5.
5.4.2 Weirs
All weirs and fixings shall be of stainless steel and be carefully sized by the Project Company.
41
Submersible mixers shall be provided and installed in each aeration tank to provide a minimum
horizontal velocity of 0.3 m/sec.
Mixer
General
A. Type: Each mixer shall be submersible with the motor close-coupled, directly connected to
the propeller. Gearbox designs shall not be acceptable. The propeller shall be capable of
handling solids, fibrous materials, heavy sludge, and other matter found in sanitary sewage
applications.
B. Submergence: All components of the mixer, including motor, shall be capable of continuous
underwater operation in both of the following conditions: (1) mixer blade completely
submerged, and (2) mixer blade partly submerged in an unbalanced hydraulic loading
condition. In addition, all components of the mixer, including motor, shall be capable of
continuous operation in air, i.e. completely unsubmerged, for a minimum of 2 hours.
C. Materials: Mixer components in contact with the liquid shall be of Type 316 stainless steel
with smooth surfaces devoid of blow holes and other irregularities. All exposed nuts, bolts,
fasteners, and hardware shall be of Type 316 stainless steel.
D. Propeller: The propeller shall be of Type 316 stainless steel, dynamically balanced, non-
clogging backward curved design. Each blade shall be laser cut and welded to the hub to
ensure that the propeller is properly balanced. The propeller shall be secured to the shaft by
a friction clutch which shall act to prevent damage to the propeller or shaft in the event an
object becomes jammed in the propeller. The shaft shall be Type 420 stainless steel.
E. Bearings: The shaft shall rotate on three permanently lubricated bearings. The outboard,
propeller end, bearing shall be an angular contact bearing. The inboard, motor end, bearings
shall be an angular contact to take up the axial loads and a radial bearing to take up the radial
loads. The bearings shall be pre-loaded by a bearing loading nut located on the motor end of
the shaft in order to reduce shaft deflection and increase bearing and seal life. Mixers without
pre-loaded bearings shall not be accepted. All bearings shall have a minimum L-10 rated life
of 100,000 hours.
Motor
F. General: The multi-pole motor shall be directly connected to the propeller. The motor shall
be a squirrel cage, induction, shell type design, housed in an air filled, watertight chamber.
The motor shall be designed for continuous duty, capable of sustaining a maximum of at least
ten evenly spaced starts per hour. The stator winding shall be insulated with moisture
resistant Class F insulation. The rotor bars and short circuit rings shall be made of
aluminium. Each motor shall be protected with an over temperature and moisture protection
system.
G. Cable: Provide sufficient length of cable to connect to terminal junction box where indicated.
The cable shall be sized according to the NEC and ICEA Standards, suitable for submersible
service. Cable entry seal design shall provide a watertight submersible seal.
Mounting Assembly
H. Each mixer shall be equipped with a mounting assembly and vertical support mast designed
to secure the mixer while in operation. The vertical support mast shall be supported as
appropriate.
I. All components of the mounting assembly including mixer mounting base plate, vertical
support mast, sliding bracket, and fastening hardware shall be Type 316 stainless steel.
J. Each mounting assembly shall be provided with a power crane with stainless steel lifting
cable, securely attached to the mixer with sufficient capacity to raise and lower the mixer
assembly.
The recirculation pumps shall be properly located to avoid extracting air bubbles with the wastewater
from the aeration process.
Submersible recirculation pumps shall be provided and installed in each aeration tank.
The pumps shall be suitable for continuous operation and equipped with VFD motors to allow for flow
rate variation based on process requirements and controlled by equipment specified under the
Electrical Works section.
The motor housing shall be made of cast iron and the propeller blades of stainless steel.
The pumps shall be fixed to pump-diffusers made of stainless steel. These shall be embedded, in the
concrete wall.
The pumps shall be supplied with lifting and guide arrangements for stationary installation. All
supports, brackets and guides shall be made of stainless steel.
The blowers shall be suitable for variable flowrate to supply sufficient air for the efficient operation of
aeration system based on DO levels. The blowers shall have a safety feature to prevent air backflow
due to power loss.
Each blower system shall have an integral means of controlling the air flow. Check valves, couplings,
pressure lubricating system, safety controls and other accessories shall be provided with the blowers.
43
Each blower and its motor shall be mounted on a rigid steel or cast-iron skid. A minimum of or one
standby blower shall be provided and any blower shat be able to feed any diffuser line.
The drive between blowers and motors shall be through flexible pin and buffer couplings or of the V -
belt type.
The blowers shall have inlet silencers and inlet filters that are housed within the acoustic enclosure,
access to the filters will not be hindered by the enclosure. The inlet filters are to be raise off the
ground to reduce moisture and dust to enter the inlet of the blowers, especially during jetting/cleaning
of the surrounding area.
The discharge diffuser shall be mounted directly off the compensator on the blower discharge and
shall be insulated to reduce surface touch temperatures to a safe level. The diffuser is to extend
vertically from the blower.
Each blower shall be complete with shock insulation, flexible connectors, suction filters, resonance or
absorption type suction and discharge silencers, safety valves, check-valves, pressure gauges and
thermometers.
An electrically operated blow-off valve with silencer shall be provided for each blower. It shall be open
when the blower is off-line and close after start-up. The compressed air shall be discharged into the
atmosphere outside of the blower enclosure through the blow-off silencer. There shall be no short-
circuiting between the blow-off valve discharge and air intake.
The acoustic enclosure doors shall open outwards to give clear access, and shall have a quick
release restraining mechanism to hold it in the open position. The acoustic cover shall not obstruct
the changing of filter elements. Extractor fan(s) shall extract the hot air from the acoustic enclosure to
atmosphere. Fresh air shall be supplied into the acoustic enclosure via duct/louvre at the opposite
end of the enclosure from the extractor fan discharge location. It shall be ensured that there shall not
be any short-circuiting between the discharge and the inlet points. The fans shall be thermostatically
controlled.
The main distribution pipes between blower house and aeration tanks, branch pipes, manifold pipes
and diffuser pipes shall be properly sized and selected.
The air distribution pipes between blower house and aeration tanks shall be made of hot dip
galvanized steel but buried sections shall be coated with glass reinforced bitumen.
Air regulating valves shall be installed as required for proper air distribution.
The piping from the butterfly valve to the bottom of the aeration basin shall be stainless steel.
EPDM type diffusers shall be preferred.
Each branch pipe shall be provided with a vacuum-valve downstream the motorized butterfly valve.
Airlines at the end of the lateral pipes shall be inter connected to form a ring main to provide equal
pressure across the system. Also, condensate withdrawal pipes and valves shall be included in the
piping system.
5.5.4 Motorized Butterfly Valves
Each branch pipe shall be provided with one motorized butterfly valve for regulating the amount of air
to each channel.
Each branch pipe shall be blind flanged and equipped with a small ball valve for draining the pipe.
5.5.6 Penstocks
All penstocks, shall be selected by the Project Company areas and be suitable for local environment
in which they are installed.
All penstocks shall be in accordance with the specification outlined in Clause 5.2.5.
Electrically driven traversing gear, powered from the tank centre and fitted with overload protection
devices shall, in the event of overload, stop the machinery and give a fault alarm. The rotating bridge
shall be provided with rubber wheels, complete with sealed for life bearings, acting directly on the
concrete surface for driving
D class coated steel shall be used for the bridge and corrosion resistant material, such as stainless
steel, shall be used for all components in contact with sewage.
Rubber strips fitted to the bottom of the sludge scraper shall be readily removable. A vacuum system
for sludge removal is an acceptable alternative.
The electric driven brushes for cleaning both sides of weir channels shall be operated manually from
the bridge.
45
5.7 Tertiary Disc Filtration
Disc filters suitable for filtering domestic sewage following the secondary treatment stage shall consist
of a series of complete units for installation in concrete tanks with an influent channel and a common
outlet channel. Penstocks shall be placed at the inlet and outlet of each tank for isolation of the disc
filter unit.
Typically, the disc filter assembly shall comprise a centre drum; disc with filter media panels; support
frames; covers for the filter; backwash spray assembly with pumps; drive mechanism; automatic
control system; and other required components for complete functional system.
The disc filter frame shall be made of a corrosion resistant material, such as stainless steel SS316L,
and it shall be possible to detach individual filter discs from the frame. The filter frame shall have
spare attachment points, blinded when not in use, to which spare filter discs could be fitted
The disc filter backwash system shall be designed efficiently to simultaneously backwash the filters
from both sides. The backwash cycle shall be activated by a high-water level in the influent chamber
and backwash shall be returned to the Plant inlet.
47
The discharge pipes and manifold pipes of the submersible return sludge pumps shall be flanged
ductile iron pipe.
5.9.6 Penstocks
A sufficient number of penstocks shall be installed in the pump sump for closing the inlet pipes.
The penstocks shall be made of ductile cast iron and be manually operated with rising spindles. The
penstocks shall comply with section 525 above.
5.9.7 Hoist
One (1) hoist including trolley and runway beam shall be provided and installed for handling of
submersible sludge pumps.
The main distribution pipes shall be made of stainless steel. The manifold pipes for diffusers shall be
made of PVC. Diffusers shall be membrane disc type. Pipe supports and brackets shall be made of
hot dip galvanized mild steel.
5.10.3 Blowers
A sufficient number of blowers, including one (1) stand-by. shall be installed in the sludge dewatering
building or blower house.
49
pipework and valving shall be arranged to accommodate these alternative mixing assembly
locations.
The flooded bottom distribution system shall be mounted on the feed end of the press and shall be
sized to provide an adequate residence time for effective floc formation. The distribution system shall
consist of a lower inlet section or feed hopper, an upper distribution and exit section. All metal parts
of the system shall be constructed of type 316 stainless steel. Sludge shall directly overflow the
hopper onto the full width of the distribution section. The sludge inlet line to the tank shall incorporate
a means of draining the feed hopper. The hopper shall also be provided with a plugged drain
connection. No mechanical or static mixing devices shall be included in the hopper or distributor as
such devices become fouled and require frequent cleaning.
5.11.5 Bearings
Bearings shall be arranged for tapered adapter mounting to the drum and roller shafts. Bearings
shall contain Triple-Check contact seals and shaft mounted splashguards on the shaft side to
provide adequate sealing from moisture and grime. Non-shaft sides of bearing housings shall be
solid. Bearing housings shall have a factory applied black fusion bonded applied nylon coating for
added corrosion resistance. All bearing hardware shall be stainless steel. All roller bearings shall be
main frame mounted and shall be greaseable while the press is in operation.
All roller bearings shall have an L-1O bearing life in excess of 800,000 hours with belts tensioned at
9 kg per linear cm with belts travelling at rated speed. Calculations shall be furnished demonstrating
compliance with these provisions.
5.11.6 Miscellaneous
Each press shall be complete with all intra-unit power and control wiring terminating in a single press
mounted NEMA 4X stainless steel junction box. All wiring shall be run in PVC coated rigid conduit for
added corrosion resistance.
Each press shall be complete with all intra-unit hydraulic system and wash water piping, Filtrate and
wash water drain lines shall be directed to the collection basin beneath the press. All wash-water
supply piping and hydraulic piping shall terminate at their respective single inlet connection.
For maximum corrosion resistance, all miscellaneous parts such as brackets, spacers, etc. shall be
fabricated from type 304 stainless steel, and all guards shall be fabricated from type 304 stainless
steel.
51
The panel shall be preassembled and prewired and shall include all controls necessary for semi-
automatic system operation with provisions also for manual control of individual items when desired.
The system shall include facilities to sample individual as well as combined concentrate from the
dewatering belt filter presses.
The flows from each pipeline of the following systems shall be measured:
sludge feed line;
polymer dosing; and
makeup water.
The pumps shall be of variable speed operation by means of electrical speed control systems. The
speed range shall be sufficient enough to enable the pump output to be increased to its maximum.
A pipeline shall be taken from the wash water supply to a tapping point on the suction of each sludge
pump. Solenoid operated isolating valves shall be included in the individual pump connections so
that at the end of each pumping cycle water shall be used to purge the sludge feed pipework.
Pump flow shall be detected by flow meters in discharge pipework to provide actual flow reading.
Steelwork shall be fabricated from substantial steel sections and plates, welded and bolted together
as appropriate. All steelwork shall be galvanised after fabrication.
An open mesh flooring platform, complete with all necessary supporting steelwork guard railing and a
ship's type ladder shall be installed over the sludge pump wheel to facilitate the operation of the
sludge delivery valves and permit access to the pump well. All steelwork shall be galvanised after
fabrication.
Discharge from the silo shall be through a conical base, into an enclosed screw conveyor. The
conveyor shall pass through the wall of the sludge dewatering house and discharge into the polymer
hopper of the polymer preparation unit. A vibrator shall be fitted to the outside of the silo at the base
to assist the flow of polymer into the screw conveyor inlet.
The mixing tank shall comprise at least three (3) compartments, one (1) mixing, one (1) storage
(aging) and one (1) storage/extraction. The compartments shall be separated by baffles designed to
eliminate the possibility of short circuiting. Mixers shall be provided in each compartment.
The powder feeder shall have a variable output with a range of at least 5 to 1.
Suitable heaters shall be provided in the powder feeding system to prevent condensation.
The tanks shall be manufactured from steel plate and section suitably reinforced, and shall have an
overflow pipe and a valved drainpipe both connected to the floor drainage system.
The speed of the pump shall be varied by means of a manually operated hydraulic variable speed
gearbox directly coupled between the pump and drive motor. The gearbox shall be designed to
operate at between 50% to 100% of mean speed.
A flowmeter shall be installed in the discharge pipework to give actual flow rate reading.
Discharge pipework shall include an in-line mixer and wash-water supply control valve to enable the
flow to be diluted from 0.5% to 0.1 %.
Sludge and concentrate pipework shall be flanged, ductile iron. Polymer dosing pipework shall be
made of PVC. Pipe sections and fittings shall be connected with solvent welded type joints, but
flanged joints must be made at connections to equipment and at intermediate positions for pipework
dismantling and cleaning of blockages.
53
The dewatered sludge storage silos shall be equipped with a load cell and inclined screw conveyors
fixed to the bottom to facilitate loading the predetermined sludge tonnage into trucks.
Electrical and SCADA system rooms shall have proper firefighting system according to NFPA
Standards and in line with Local civil defence requirements.
The pressure gauge, pressure switch and air inlet tapings shall be arranged to be above the possible
maximum level of membrane type diaphragm collector in the vessel. A pressure gauge, which reads
the air pressure in the vessel and thereby indicates the pressure in the system, shall be placed on the
tank.
A manually operated lockable air release valve shall be supplied for the vessel to vent excess
pressure before the system is drained.
Pressure switches shall be robustly constructed and be suitable for the arduous duties involved. They
shall be fully adjustable over their working range together with adjustable differentials.
Factory testing of the vessel shall be carried out in accordance with the BS 5500 and a test certificate
issued. The working and testing pressures shall be stamped clearly and visibly to the outside of the
vessel.
The unit shall be suitably protected against low/ no water in the reservoir.
A centrifugal pump of multi-stage end suction and direct driven type shall be fitted to the unit. The
casings shall be made of close grained cast iron. The parts in contact with rotating units shall be
protected with removable bronze or stainless steel wear rings. The impellers shall be made of bronze
or stainless steel secured by keys to the shaft which, where in contact with the water, shall be
protected by removable bronze or stainless steel sleeves. Water throwers shall be provided to prevent
ingress of water into the bearings.
The pump shall have its electric motor close coupled or shall have a suitable flexible coupling fitted
between the motor and pump spindle.
The pressurized vessel and pumps shall be mounted on a robustly constructed common baseplate.
The unit shall be complete with all necessary sluice and reflux valves. The pipes on the unit shall be
galvanised mild steel and shall be flanged or screwed. However, the termination points of pipes shall
be flanged.
(iii) Pipes and Valves
All associated valves, suction and delivery pipes shall be provided. The delivery pipes within the
station shall be made of galvanised steel and shall extend from the booster unit to an isolating valve
placed very close to the unit. The suction pipework shall be a minimum of 100mm diameter and shall
incorporate a foot valve.
(iv) Pressure Gauges
Pressure and combined gauges shall be provided for the pump and air vessel.
(v) Steelwork
The following steelwork shall be provided and fixed in the station: baseplate for pump and air vessel;
and support brackets of pipes
(vi) Method of Control
All controls necessary to achieve the sequence of events detailed below shall be placed in a control
panel:
both manual and automatic control shall be provided for the Booster Unit. A "Hand-off-Auto"
selector switch shall be provided;
under manual control, starting and stopping of the pump shall be initiated from the control
panel;
automatic control shall be such that the pump will start and stop due to signals coming from
the system pressure switches placed on the booster unit;
failure of the duty pump shall initiate the alarm system and the stand-by pump shall
automatically be selected for duty; and
one (1) float switch for automatic cut-out shall be provided to protect the pump in the event of
low water level in the reservoir.
(vii) Motors
The motor shall be of the squirrel cage type protected to IF.54 and shall be rated at 20 percent above
the calculated maximum power.
55
All items of equipment shall be treated to suit the environment and the minimum design life
specified elsewhere.
Pumps shall be of a non-clogging submersible type suitable for sewage or sludge handling;
Pumps shall be capable of operating continuously at all flow rates within design capacity,
without vibration and shall be designed to have a continuously decreasing head-flow
characteristic to provide stable operation;
pump discharge outlets shall be designed to be flange coupled fastened by stainless steel
bolts fitted with primary locking devices or to seal to duct foot bend counterpart;
Motors shall run smoothly and vibration shall not exceed of 4.5mm/s Rotors shall be balanced
both statically and dynamically. Rotors shall be adjusted for dynamic balance with a tested by
an approved method;
Cables shall be flexible twisted copper wire and shall be thoroughly coated with underwater
grade flexible twisted insulation;
Pump motors shall be designed for continuous duty whilst handling pumped media with a
maximum temperature of 40°C and be capable of up to 10 evenly spaced starts per hour;
Motors and pumps shall be designed and assembled by the same manufacturer. The
combined service factor (combined effect of voltage, frequency and specific gravity) shall be a
minimum of 1.15. The motor shall have a voltage tolerance of plus or minus 10%;
Motors shall be designed for operation at a maximum ambient temperature of 40°C and a
maximum temperature rise of 85°C;
Motors and cable shall be capable of continuous submergence without loss of watertight
integrity according to protection class IF 68 (20 m). The pump shall have a non-overloading
characteristic with the motor not exceeding 90% of its design rating at any point along the
pumping curve;
The oil chamber shall be filled with a medical grade white oil of paraffin. The oil shall be free
from aromatic hydrocarbons, be medically clean and be approved according to FDA 172.878;
Pump and motor shaft shall be the same unit. The pump shaft shall be an extension of the
motor shaft. Couplings shall not be acceptable. The shaft material shall be AISI type 431
stainless steel. The use of stainless steel sleeves will not be considered equal to stainless
steel shafts; and
The impeller shall be capable of handling solids, fibrous materials, heavy sludge and other
matter found in normal wastewater. Whenever possible, a fully vanned, non-vortexing,
impeller shall be used for maximum hydraulic efficiency, thus, reducing operating costs. The
impeller shall be capable of passing min 75 mm diameter solid.
It shall be possible to either easily access the pumps for removal and maintenance (dry well
installation) or withdraw the pumps from a wet well easily. Necessary cranage and easy
chain connection systems for lifting the pumps shall be provided.
Each pump shall be fitted with a non-slam check valve and isolation valve.
As a minimum all plant above 45kW, where applicable and within a state of the art manufacturer’s
norm, shall be fitted with:
57
Water in oil sensors;
Rotation sensors;
Below 45kW plant is to be fitted with the maximum level of condition monitoring the plant
manufacturer provides.
6 DESIGN REQUIREMENTS
6.1 Information Modelling
The Project Company shall comply with the requirement to develop, maintain, update and handover a
3D, fully co-ordinated, information-rich (graphical and non-graphical) model for the Plant.
Information models shall be provided by the Project Company at milestones agreed with the
Employer’s Engineer. These models shall be progressively developed to meet the contract
requirements and fully co-ordinated with all other models produced for the Plant.
The 3D information models shall be submitted to the Employer’s Engineer, along with the 2D
deliverables associated with that model, for review and acceptance.
The Project Company, SWPC and the Employer’s Engineer shall agree on the required Level of
Detail to be included in the Information Models at each stage of the design development.
Drawings:
P&IDs
59