ITP & Checklist FOR Excavation & Backfilling and Compaction
ITP & Checklist FOR Excavation & Backfilling and Compaction
0 Inspection and Test Plan (ITP) For Excavation & Backfilling and Legends
Compaction Works
Contract No.
20230329004 SCOPE OF WORK Horticulture Works for Propagation and Cultivation of plants - Production Nursery for King Salman Park H - Hold Point R - Review Point
Discipline Civil ITP Reference: KSP-NCC-NU1-CMT-CIV-ITP-0003 Rev. No. 00 Date 01-May-23 W - Witness Point S - Surveillance
Material Submittal As per design Prior to start of Approved Shop drawings Approved MAR
1.2 Approval (MAR) Document drawings and Project work(100%) Compliance with Specification Submittal N/A H R R R R N/A
Review Specification
As per design
drawings. Prior to start of Approval on latest revision of Approved Shop
1.3 Shop Drawings Document Project Spec. work(100%) relevant Drawings. drawing N/A H R R R R N/A
Review
As per design
drawings. Compliance with theMaterial
1.4 Method Statement Document Manufacturer / Prior to start of Approval submittal & Specification Approved MES/ N/A H R R R R N/A
Review Supplier KSP-NCC-
work(100%)
recommendation and NU1-CMT-
Project Specification CIV-MES-
0003
2.0 Material Inspection
*Approved stockpile.
* Test report
Material / Product Manufacturer Data Prior to Project Specs / Approved MAR Manufacturer
Storage and Visual Sheet / backfilling /MES / MIR DataSheet and N/A H S S S S N/A
2.2 Handling Inspection (100%) Recommendation
Recommendations /
Project Specs / s
Weather
Changes/Conditions
3.0 Excavation
3.1 Setting out and Level Visual As per approved shop Prior to Setting out and final levels of the As per approved
Inspection/Sur drawing / Approved Excavation excavation shall be in accordance with shop drawing / N/A H W S S S N/A
vey Check method statement (100%) the approved drawings SurveyReport /
IRF
Over excavated area shall be
backfilled in layers with suitable fill
materials or concrete level make up of
any type
*Approved stockpile
4.4 Backfilling for Pipe Visual *Approved Shop Each layer *Main backfill shall be placed and well Approved N/A H W S S S N/A
Trenches Inspection drawings compacted in layers not exceeding Checklist
300 mm thick before compaction.
*Approved Method Heavy compactors shall not be used
Statement until there is 600 mm cover over pipes.
*Each layer of
backfill shall be *Layers shall not exceed 200 mm
inspected & thickness (after compaction) on the
tested as previously occupied areas
specified
*Each embankment layer shall be
tested and approved prior to placing
the following
layer
Excavation
1
Setting Out and Excavation level Shall be as per approved
IFC/SHD Drawing.
2
Over excavated area (if any) backfilled and compacted as
specified
3 Sloping and benching provided as per approved Method
Statement
4 Barricading / Edge Protection Provided
Backfilling and Compaction
5 Only approved materials are delivered and installed.
6 Fill Material placed in layers.
7 Layer thickness as specified.
8 Backfilling done up to required finish level
12 Testing done
14 Testing Passed
Remarks:
Amran Hossain
Name, Initial Name, Initial
and Date and Date