Method Statement For Coring

The document outlines safety procedures for coring walls and slabs. It details the steps to properly set up equipment, mark the coring area, use protective gear, operate the coring machine, and clean up. Personnel roles include the safety officer supervising compliance and the worker commencing work safely.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
54 views

Method Statement For Coring

The document outlines safety procedures for coring walls and slabs. It details the steps to properly set up equipment, mark the coring area, use protective gear, operate the coring machine, and clean up. Personnel roles include the safety officer supervising compliance and the worker commencing work safely.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Method Statement

Coring Works

Page 1 of 4
List of Contents

Section Title Page

1.0 SCOPE OF WORKS 3 of 4

2.0 CONSTRUCTION PROCEDURES 3 of 4

3.0 INSPECTION AND TESTING REQUIREMENTS 3 of 4

4.0 CONFORMANCE CRITERIA 3 of 4

5.0 MATERIALS 4 of 4

6.0 PERSONNEL ROLES AND RESPONSIBILITIES 4 of 4

7.0 ENVIRONMENTAL REQUIREMENTS 4 of 4

8.0 HEALTH AND SAFETY inc. RISK ASSESSMENTS 4 of 4

9.0 PLANT AND EQUIPMENT 4 of 4

10.0 SUB-CONTRACTORS / SUPPLIERS 4 of 4

11.0 STORAGE AND HANDLING 4 of 4

12.0 REFERENCE 4 of 4

13.0 ATTACHMENT 4 of 4

A. MATERIAL SAFETY DATA SHEET (MSDS)


(if applicable)
B. SUPPLIERS CATALOGUES

Page 2 of 4
I. Scope of Works

This document covers only the procedure and safety programs needed on how
to properly chip walls and slabs.

II. Construction Procedures

a. Workers will wear proper PPE before starting.


b. Clean the area before commencing work.
c. Ensure proper lighting at work area.
d. Ensure proper ventilation and air flow at work area.
e. Mark out the position to be cored
f. Ensure that there is no services in-front and behind the location to be cored.
g. Move away or protect thing that is directly underneath the area to be cored.
h. Drill and Install wall/slab anchor.
i. Mount the coring machine stand.
j. Fix the core bit to the machine.
k. Adjust and Center the corebit to the marked position
l. Setup water protection system at front and behind of wall/slab if require.
m. Start the coring machine.
n. Turn on the water system and start coring.
o. Once cored through, stop the motor and water.
p. Remove drill motor and diamond bit.
q. Remove cored concrete core.
r. Clean up area and move to the next location.

III. Inspection and Testing Requirements

Not Applicable

IV. Conformance Criteria

Not Applicable

V. Materials

Complete PPE uniform


Grinder
Chisel
Ball Hammer
Vacuum Cleaner

Page 3 of 4
VI. Personnel Roles and Responsibilities

Safety officer’s responsibility is to ensure that the work activity is in


compliance with the safety standards given at site.

Site supervisor’s responsibilities are to supervise the proper work activities of


the workers and compliance with the safety standards at site.

Worker’s responsibility is to commence work safely and properly. In relation


to this methodology proper chipping must be observed to achieve quality work.

VII. Environmental Requirements

Not Applicable

VIII. Health and Safety inc. Risk Assessments

See attached Risk Assessment table

IX. Plant and Equipment

Not Applicable

X. Sub-Contractor / Suppliers

Not Applicable

XI. Storage and Handling

All items will be stored neatly and properly inside the warehouse. Tools and
equipment will be cleaned before and after use.

XII. Reference

Not Applicable