1. The document provides specifications for submersible pumps to be used for plant room drainage, basement drainage, and sewage lifting. 2. It lists the required flow rates, heads, solid handling capacities, and materials of construction for 3 sets of pumps - one each for plant room drainage, basement drainage, and sewage lifting. 3. It also specifies that the pumps must include auto coupling units, local starter panels, and control panels with level sensors and dry run protection. The control panels must integrate with the building management system.

Uploaded by

Dharam Sharma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
50 views2 pages

Data Sheet R0.xlsx - 1

1. The document provides specifications for submersible pumps to be used for plant room drainage, basement drainage, and sewage lifting. 2. It lists the required flow rates, heads, solid handling capacities, and materials of construction for 3 sets of pumps - one each for plant room drainage, basement drainage, and sewage lifting. 3. It also specifies that the pumps must include auto coupling units, local starter panels, and control panels with level sensors and dry run protection. The control panels must integrate with the building management system.

Uploaded by

Dharam Sharma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

General Checklist for Technical document submission SUMP PUMPS

Rev. - R0 CPWD-TPL-SEC-TDS-PHE-006

Makes Make List of


specified in selected Supporting
S.N BOQ item Approved by Contractor documents
Description of item make list of for submitted in
o number
Tender the project attachment for
approval

1.4 Submersible Pumps:


Submersible Centrifugal Non-clog Drainage Pumps
,installation, testing and commissioning of
submersible pumps As Follows:
, installation, testing and commissioning of continuous duty
Submersible Centrifugal non-clogging or vortex type drainage
pumps complete with 3 phase motor with all necessary
protection and mechanical seal as per manufacturer
standard etc. Pumps set shall have auto coupling
assembly. The installation shall be complete with all
1 necessary indigenous accessories as required to complete the
installation with pressure gauge in the discharge line as per
specification/drawings and as directed by Engineer In
Charge

Contractor shall provide pump lifting arrangement shall


comprise of MS galvanized guide bar & MS assembly with
SS 304 chain with shakle suitable for 2 Nos. submersible
drainage pumps in a sump of overall depth not more than 2.0
m,
1.4.1 1 Set : (1 Duty + 1 Assist)
Total flow rate of system: 10.0 LPS
Flow rate : 5.0 LPS each
Head : 15 Mts
Solid Handling : 25 MM
Location : Plantrooms Grundfos, WILO,
Technical Data
Purpose : Plant Room Drainage Xylem (FLYGT), Wilo
Sheet
MOC : CI -Body, C.I impeller & SS shaft - (420 or EBARA, / Kirloska
431)
1.4.2 1 Set : (1 Duty + 1 Assist)
Total flow rate of system: 10.0 LPS
Flow rate : 5.0 LPS each
Head : 20 Mts
Solid Handling : 25 MM
Location : Basement and trench
Purpose : Basement Drainage for Fire Zone
MOC : CI -Body, C.I impeller & SS shaft - (420 or
431)
In addition to the above description pump shall have
grinder/cutter system to provide high efficiency. After
discharge solid handling shall be not more than 20 mm.
Motor shall have built-in thermal protection against
overheating.
1.4.3 1 Set : (1 Duty + 1 Assist)
Total flow rate of system: 5 LPS
Flow rate : 2.5 LPS each
Head : 20 Mts
Solid Handling : 20 MM
Location : Basement
Purpose : Sewage Lifting
MOC : CI -Body, C.I impeller & SS shaft - (420 or
431)
Cost shall be inclusive of providing auto coupling
unit for Sewage ejector pit (separate item)
Shop drawing for the installation to be approved by
the engineer in charge prior to execution.
Local starter panels of IP55 rating fabricated out of 2mm
thick CRCA sheet with hinged lockable doors,
complete with all required starters of
DOL starter. Pump shall be provided with separate
skid mounted electrical panel of 415V +10%, 50 Hz, 3
Phase AC , for power distribution and control for
equipment listed below with all necessary power &
control circuit breakers, contactors, SPPR, start-
All hardwares required for mounting of panel in wall/floor
shall be included in panel cost itself. All power cables
shall be armoured ,XLPE, coper cable of adequate GSIPL (OEM
size. All control cables shall be armoured PVC coper LEGRAND)
cable. Minimum of 2.5Sq.mm cable shall be used for
Note:- Power at 1 Nos. incomer in the panel and
single point BMS connectivity shall be done by
electrical contractor. The pump panel shall
have RS- 485/Modbus/BACnet over IP/ BACnet
over MSTP port to integrate with Building
Management System without any external
hardware/converter requirement. Technical
Control panel shall comprise of level sensor and pumps
shall have dry run protection with high/ low level alarm.
Pumps shall be supplied with 3 Nos. float switches and
electrical control panels with cables. Each pump shall
have provision for auto/ manual operation in the control