Schedule-Proyek RSIS

This document outlines the BIM activities schedule for the RS Islam Surabaya, Wonokromo project over its 16 month duration from 2022 to 2023. It details 9 phases of BIM work including 3D modeling, shop drawings, clash detection, 4D sequencing, 5D cost estimation, 7D asset data integration, 8D safety analysis, and CDE collaboration tools. Each activity is assigned a responsible party and target start and end dates for completion. The status of each activity is marked as continue, closed, or open.

Uploaded by

dani hamdani
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
38 views

Schedule-Proyek RSIS

This document outlines the BIM activities schedule for the RS Islam Surabaya, Wonokromo project over its 16 month duration from 2022 to 2023. It details 9 phases of BIM work including 3D modeling, shop drawings, clash detection, 4D sequencing, 5D cost estimation, 7D asset data integration, 8D safety analysis, and CDE collaboration tools. Each activity is assigned a responsible party and target start and end dates for completion. The status of each activity is marked as continue, closed, or open.

Uploaded by

dani hamdani
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

SCHEDULE AKTIVITAS BIM

Project Number : 2022800020


Project Name : RS Islam Surabaya, Wonokromo
Duration : 16 Bulan

2022 2023 TARGET


No Aktivitas BIM PIC April Mei Juni Juli Agustus September Oktober November Desember Januari Februari Maret April Mei Juni Juli STATUS
Mulai Selesai
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1. Fase 3D
A. 3D Model Bangunan BIM Modeler C C C 01-Apr-22 30-Sep-22 CONTINUE
B. Shopdrawing BIM Modeler
- Struktur CL CL CL 01-Apr-22 31-Aug-22 CONTINUE
- Arsitek 01-Jul-22 31-Dec-22 CONTINUE
- MEP 01-Aug-22 31-Dec-22 CONTINUE
C. Clash Detection BIM Modeler 01-Sep-22 31-Dec-22 OPEN
D. Render Visualisasi BIM Modeler 01-Nov-22 31-Dec-22 OPEN
E. Building Data Integration BIM Modeler & Proc O O O 01-Apr-22 31-Dec-22 OPEN
2. Fase 4D
A. Sequence Simulation (Metode Pelaksanaan) Scheduler 01-Sep-22 31-Oct-22 OPEN
B. Tracking Progress Scheduler 01-Oct-22 31-Jul-23 OPEN
C. Progress Report + Drone Scheduler & QS 01-Oct-22 31-Jul-23 OPEN
3. Fase 5D
A. Perkiraan Biaya QS 01-Oct-22 30-Nov-22 OPEN
B. Quantity Take Off & Material Take Off QS 01-Nov-22 31-Dec-22 OPEN
C. SPK Opname Mandor Berdasarkan Vol. BIM QS 01-Dec-22 31-Dec-22 OPEN
4. Fase7D
A. Penyusunan Data Asset Procurement 01-Nov-22 31-Dec-22 OPEN
B. Integrasi Data Asset dengan BIM 3D Model BIM Modeler & Proc 01-Nov-22 28-Feb-23 OPEN
C. Integrasi Data BIM dengan Facility Management Software BIM Modeler & Proc 01-Jan-22 31-Mar-23 OPEN
5. Fase 8D
A. Job Safety Analysis HSE 01-Oct-22 31-Jan-23 OPEN
6. Fase CDE (Collaboration)
DITAMBAH TERKAIT APPROVAL PROJECT MEMBER
A. Setup Permission Folder & Approval Workflow DCC C C C 01-Apr-22 31-Jul-23 CONTINUE
B. Approval Shop Drawing BIM Modeler CL CL CL 01-Apr-22 28-Feb-23 CONTINUE
C. Approval Material Procurement 01-Apr-22 28-Feb-23 OPEN
D. Approval Laporan Progress (Penagihan Owner) QS 01-Apr-22 31-Jul-23 OPEN
PCM,PEM,PPM,PFM,SPV,PI,B
E. Penggunaan Issue 01-Apr-22 31-Jul-23 OPEN
IM,SURVEY,QC,HSE
F. Penggunaan RFI PI,BIM 01-Apr-22 30-Jun-23 OPEN
G. Penggunaan Meetings DCC C C C 01-Apr-22 31-Jul-23 CONTINUE
H. Fitur Checklist Pekerjaan Dengan CDE QC,HSE 01-Apr-22 30-Jun-23 OPEN
I. Fitur Asset untuk Procurement Logistik 01-Apr-22 31-Jul-23 OPEN