Lec-01 5fb21ae651a2f
Lec-01 5fb21ae651a2f
DESIGN
Amila Abeysinghe
B.Sc. University of Moratuwa, ACMA, CGMA, MBA, Blue Belt - Lean
• Processing (waste associated with spending more time, effort and resources than was
necessary processing products beyond what was necessary or demanded by the
customer)
• Time spent Waiting (waste associated with an employee or a machine being idle)
• Motion. (This is different to transportation. Motion is looking at the efforts and time
expended by employees on performing their tasks.)
• External Setup: That part of the setup which can be done while the machine is still running, for
example, preparing a die to be used for the next run
• Internal Setup: That part of the setup which must be done while the machine is shut down, for
example, removing or attaching dies
• Rule one – all work shall be highly specified as to content, sequence, timing, and
outcome.
• Rule two – every customer-supplier connection must be direct and there must be an
unambiguous yes or no method of sending requests and receiving responses.
• Rule three – the route for every product and service must be simple and direct.
• Rule four – any improvement must be made in accordance with the scientific method,
under the guidance of a teacher, and at the lowest possible level in the organization.
• ‘just-in-time’ emphasizes the idea of producing items only when they are needed
Necessary
Toyota has developed its production system around eliminating three enemies of
Lean: Muda(waste), Muri (overburden) and Mura (unevenness)
MUDA, waste, can be defined in eight types, 7 defined by Toyota and ‘non utilized skills’. These
are: Defects, Overproduction, Waiting, Non-used Talent, Transport, Inventories, Motion and
Excess processing.
MURI, overburden, When operators or machines are utilized for more than 100% to finish their task,
they are overburdened. This means breakdowns when it comes to machines and absenteeism when
it comes to employees. To optimize the use of machines and make sure they function properly,
preventative- and autonomous maintenance can be implemented.
MURA, unevenness, can be found in fluctuation in customer demand, process times per product or
variation of cycle times for different operators. In production environments with low-volume, high
product variation, flexibility is more important than in high-volume, low-product variation
environments.
Value stream mapping (also known as ‘end-to-end’ system mapping) is a simple but
effective approach to understanding the flow of material and information as a product or
service has value added as it progresses through a process, operation, or supply chain. It
visually maps a product or services ‘production’ path from start to finish.
• Continuous improvement
• Visual management
‘Drum beat’ determines the schedules in non-bottleneck areas, pulling through work
(the rope) in line with the bottleneck capacity, not the capacity of the work center. A
bottleneck should never be allowed to be working at less than full capacity; therefore,
inventory buffers should be placed before it to ensure that it never runs out of work
Step Objective
Identify Identify the current constraint (the single part of the process that limits the rate at which the goal is
achieved).
Exploit Make quick improvements to the throughput of the constraint using existing resources (i.e. make
the most of what you have).
Subordinate Review all other activities in the process to ensure that they are aligned with and truly support the
needs of the constraint.
Elevate If the constraint still exists (i.e. it has not moved), consider what further actions can be taken to
eliminate it from being the constraint. Normally, actions are continued at this step until the
constraint has been “broken” (until it has moved somewhere else). In some cases, capital
investment may be required.
Repeat The Five Focusing Steps are a continuous improvement cycle. Therefore, once a constraint is
resolved the next constraint should immediately be addressed. This step is a reminder to never
become complacent – aggressively improve the current constraint…and then immediately move on
to the next constraint.
6 October 2019 Confidential 22
Lean Philosophy
Questions
QUESTION 1
Explain how JIT operations differ from traditional operations by considering product flow
QUESTION 2
Explain how the ‘Rocks in the Water’ analogy outlines the JIT approach to inventory and
problem exposure.
QUESTION 3
‘Within JIT operations the main sacrifice is capacity utilization’ – explain this statement and
its consequences.
QUESTION 4
Describe the ‘lean’ approach and outline its relationship with JIT.
QUESTION 5
Describe the push and pull with advantages of each concept.
• Liker., K. J. &. Miller. D., 2006. Ther Toyota way fieldbook. 1st ed. New York: McGraw Hill
Education
• Slack, Chambers And Johnston, 2007, Operations Management, 5th Edition, Ft Prentice
Hall.