METHOD STATEMENT – PILE TESTS
Table of Contents
1 INTRODUCTION ..................................................................................................................................... 1
1.1 GENERAL DESCRIPTION ................................................................................................................. 1
1.2 GENERAL ACTIVITIES TO BE EXECUTED ......................................................................................... 1
1.3 EQUIPMENT .................................................................................................................................. 1
1.4 INSPECTION AND TESTING ............................................................................................................ 2
1.4.1 Human resource.................................................................................................................... 2
2 PREVIOUS ACTIVITIES ............................................................................................................................ 3
2.1 PIT, CSL, Welding........................................................................................................................... 3
3 CONCLUSIONS ....................................................................................................................................... 4
Figure Index
Figure 1.Metro Line 1 Project Layout Plan.................................................................................................... 1
1 INTRODUCTION
1.1 GENERAL DESCRIPTION
Every construction project requires a correct materialization of the works to be built, to guarantee the
construction of the conditions designed and verified for the project. This materialization is carried out
through the locations, staking out and topographic controls developed throughout the construction stage,
from the start date of the project to its final delivery.
1.3 EQUIPMENT
The equipment to be used in the development of the project will be the following (among others):
• Data recorders
• Precision level
• Camera
• Hand equipment
• Excavation equipment
• Transmitter and receiver probes
• Recording apparatus
• Depth measuring encoding device
METHOD STATEMENT – PILE TESTS
• PC or laptop
• Accelerometer
• Impact device
• Data storage devices
• Graphical output device
• Liquid penetrant testing materials, removers and developers
• Yokes, permanent magnets, prods, bench unit, UV-A Lamps, etc.
Calibration records will be kept in the project files and will be verified during internal and external audits
carried out during the project.
2 PREVIOUS ACTIVITIES
The Contractor must provide their own source of electric power, required to operate the computing and
other systems, as well as all the civil works needed to execute the main scope of the tests.
• ASTM D 5882
• ASTM D 6760
• AWS D.1.1
• AWS D.1.4
• AWS D.1.1 / ASTM E-165
• AWS D.1.1 / ASTM E-709
At least 7 days after the pile was cast or when the concrete
PIT
has reached 75% of the design strength.
At least 7 days after the pile was cast or when the concrete
Cross-Hole
has reached 75% of the design strength.
At least 7 days after the pile was cast or when the concrete
PIT
has reached 75% of the design strength.
3 CONCLUSIONS
- The methodology and therefore the schedule depends on the fulfillment of the preliminary activities
foreseen.
- The contractor proposes the most practical intervention conditions, based on the previous experiences
of the specialized professionals in each area.
- The document may be updated when the contractor considers improvements in its construction
procedures.