This document provides a method statement for pile tests on the Bogota Metro Line 1 project. It outlines the general activities, equipment, and standards used for pile integrity testing (PIT), cross-hole sonic logging (CSL), and welding inspections. The contractor is responsible for power, civil works, and ensuring personnel are qualified to perform the tests according to industry standards. PIT and CSL will be done at least 7 days after pile installation, while welding inspections occur during driving of bored piles.

Uploaded by

Pao Castillo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
20 views6 pages

22meth 1

This document provides a method statement for pile tests on the Bogota Metro Line 1 project. It outlines the general activities, equipment, and standards used for pile integrity testing (PIT), cross-hole sonic logging (CSL), and welding inspections. The contractor is responsible for power, civil works, and ensuring personnel are qualified to perform the tests according to industry standards. PIT and CSL will be done at least 7 days after pile installation, while welding inspections occur during driving of bored piles.

Uploaded by

Pao Castillo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

PRIMERA LÍNEA DEL METRO DE BOGOTÁ

METHOD STATEMENT – PILE TESTS – PIT, CSL, WELDING

CONTROL DE EMISIONES (ISSUE CONTROL)


REV (ISSUE]) FECHA (DATE) EMITIDO PARA (ISSUED TO)
V0A 11/05/2023

El contenido de este documento no podrá ser divulgado a terceros ya sea en parte o en su totalidad sin autorización escrita de METRO LINEA 1 SAS
The content of this document may not be disclosed to third parties either in part or in full without written authorization from METRO LINEA 1 SAS
未经 METRO LINEA 1 SAS 的书面授权,不得将本文档的内容部分或全部透露给第三方
METHOD STATEMENT – PILE TESTS

Table of Contents
1 INTRODUCTION ..................................................................................................................................... 1
1.1 GENERAL DESCRIPTION ................................................................................................................. 1
1.2 GENERAL ACTIVITIES TO BE EXECUTED ......................................................................................... 1
1.3 EQUIPMENT .................................................................................................................................. 1
1.4 INSPECTION AND TESTING ............................................................................................................ 2
1.4.1 Human resource.................................................................................................................... 2
2 PREVIOUS ACTIVITIES ............................................................................................................................ 3
2.1 PIT, CSL, Welding........................................................................................................................... 3
3 CONCLUSIONS ....................................................................................................................................... 4

Figure Index
Figure 1.Metro Line 1 Project Layout Plan.................................................................................................... 1

Version V0A ML1-DMD-DCC-FR-2021-00008-V2 Pag. 2


SCOPE OF WORKS - PC PILE TRANSPORTATION

1 INTRODUCTION
1.1 GENERAL DESCRIPTION
Every construction project requires a correct materialization of the works to be built, to guarantee the
construction of the conditions designed and verified for the project. This materialization is carried out
through the locations, staking out and topographic controls developed throughout the construction stage,
from the start date of the project to its final delivery.

Figure 1.Metro Line 1 Project Layout Plan

1.2 GENERAL ACTIVITIES TO BE EXECUTED


Considering the GPS established in the design stages, once the PMT is approved for the start of activities,
the project will be staked out and the location of auxiliary boundary markers for construction and tests
will be carried out.

1.3 EQUIPMENT
The equipment to be used in the development of the project will be the following (among others):

• Data recorders
• Precision level
• Camera
• Hand equipment
• Excavation equipment
• Transmitter and receiver probes
• Recording apparatus
• Depth measuring encoding device
METHOD STATEMENT – PILE TESTS

• PC or laptop
• Accelerometer
• Impact device
• Data storage devices
• Graphical output device
• Liquid penetrant testing materials, removers and developers
• Yokes, permanent magnets, prods, bench unit, UV-A Lamps, etc.

1.4 INSPECTION AND TESTING


During the development of the project, the necessary equipment to carry out the tests will be required.
This equipment must be calibrated and/or verified with a properly calibrated standard equipment.

Calibration records will be kept in the project files and will be verified during internal and external audits
carried out during the project.

1.4.1 Human Resources


The personnel that carry out the tests must be qualified to carry out them, with the corresponding
certifications for PIT and Cross-hole tests. For Welding inspections and tests, the personnel must be
certified by the AWS.

Version V0A ML1-DMD-DCC-FR-2021-00008-V2 Pag. 2


METHOD STATEMENT – PILE TESTS

2 PREVIOUS ACTIVITIES
The Contractor must provide their own source of electric power, required to operate the computing and
other systems, as well as all the civil works needed to execute the main scope of the tests.

2.1 PIT, CSL, Welding


The contractor must follow all the guidelines specified on the following standards (current versions):

• ASTM D 5882
• ASTM D 6760
• AWS D.1.1
• AWS D.1.4
• AWS D.1.1 / ASTM E-165
• AWS D.1.1 / ASTM E-709

TYPE OF PILE TEST CONSTRUCTION PHASE

At least 7 days after the pile was cast or when the concrete
PIT
has reached 75% of the design strength.

At least 7 days after the pile was cast or when the concrete
Cross-Hole
has reached 75% of the design strength.

Bored Welding between


During the pile driving on site
pile modules

At least 7 days after the pile was cast or when the concrete
PIT
has reached 75% of the design strength.

Camera inspection During the pile driving on site

Version V0A ML1-DMD-DCC-FR-2021-00008-V2 Pag. 3


METHOD STATEMENT – PILE TESTS

3 CONCLUSIONS

- The methodology and therefore the schedule depends on the fulfillment of the preliminary activities
foreseen.

- The contractor proposes the most practical intervention conditions, based on the previous experiences
of the specialized professionals in each area.

- The document may be updated when the contractor considers improvements in its construction
procedures.