Schedule Pekerjaan Box Culvert Dan Submerge Bridge

The schedule outlines the timeline for completing box culvert and submerged bridge construction from March to April 2022. It is broken into two sections - A for box culvert and B for submerged bridge. The key activities include land clearing, filling sand bags, masonry stone installation, backfilling and compacting, lean concrete pouring, and slab placement. The estimated daily labor requirement ranges from 6 to 12 workers per day depending on the construction phase.

Uploaded by

Restu Dwiyantama
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
101 views

Schedule Pekerjaan Box Culvert Dan Submerge Bridge

The schedule outlines the timeline for completing box culvert and submerged bridge construction from March to April 2022. It is broken into two sections - A for box culvert and B for submerged bridge. The key activities include land clearing, filling sand bags, masonry stone installation, backfilling and compacting, lean concrete pouring, and slab placement. The estimated daily labor requirement ranges from 6 to 12 workers per day depending on the construction phase.

Uploaded by

Restu Dwiyantama
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

SCHEDULE PEKERJAAN BOX CULVERT DAN SUBMERGE BRIDGE

TANGGAL
NO ITEM PEKERJAAN Maret 2022 Apr-22 KETERANGAN
21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
A. BOX CULVERT
1 Land Clearing 1
2 Mengisi Sand Bag 5 6
3 Menyusun Sand Bag 6 6
4 Pasang Masonry Stone 6 5
5 Bacfill and compacted 2
6 Lean Concrete 2
7 Land Clearing 1
8 Menyusun Sand Bag 4
9 Pasang Masonry Stone 4 6
10 Bacfill and compacted 2
11 Lean Concrete 2
12 Pembesian Slab dan Bekisting 2
13 Cor Slab 2
B SUBMERGE BRIDGE
1 Land Clearing
2 Mengisi Sand Bag 6 6 6
3 Menyusun Sand Bag 6 6 10
4 Pasang Masonry Stone 10 10 4
5 Memasang Gabion Matrass 6 12 12 6 6
6 Menyusun U-Ditch 6 6
7 Pasang Masonry Stone untuk Oprit 4
8 Bacfill and compacted 4
9 Lean Concrete 4
10 Land Clearing 1
11 Menyusun Sand Bag 7 8 8 6
12 Pasang Masonry Stone 6 12 6 6
13 Memasang Gabion Matrass 6 6 8
14 Menyusun U-Ditch 4 6 6
15 Pasang Masonry Stone untuk Oprit 6
16 Bacfill and compacted 6
17 Lean Concrete 6
18 Pembesian Slab dan Bekisting 6
19 Cor Slab 6
KEBUTUHAN TENAGA KERJA PERHARI 6 6 6 6 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 6 6 6 6 6 6 6