Report 49°

The document summarizes a simulation of a 149 kWp grid-connected photovoltaic system in Budapest, Hungary. It includes details on the project location and specifications, PV array characteristics, system losses, results of the simulation including annual energy production and performance ratio, and monthly balances of key metrics.

Uploaded by

Mate
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
27 views

Report 49°

The document summarizes a simulation of a 149 kWp grid-connected photovoltaic system in Budapest, Hungary. It includes details on the project location and specifications, PV array characteristics, system losses, results of the simulation including annual energy production and performance ratio, and monthly balances of key metrics.

Uploaded by

Mate
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

Version 7.3.

PVsyst TRIAL
PVsyst - Simulation report
Grid-Connected System

Project: first project


Variant: New simulation variant
No 3D scene defined, no shadings
System power: 149 kWp

PVsyst TRIAL
Budapest/Vecsés - Hungary

PVsyst TRIAL

PVsyst TRIAL
Author

PVsyst TRIAL
Project: first project
Variant: New simulation variant

PVsyst V7.3.4
VC0, Simulation date:
05/11/23 09:08

PVsyst TRIAL
with v7.3.4

Project summary
Geographical Site Situation Project settings
Budapest/Vecsés Latitude 47.44 °N Albedo 0.20
Hungary Longitude 19.26 °E
Altitude 185 m
Time zone UTC+1

Meteo data
Budapest/Vecsés
Meteonorm 8.1 (1991-2006) - Synthetic

System summary

PVsyst TRIAL
Grid-Connected System No 3D scene defined, no shadings

PV Field Orientation Near Shadings User's needs


Fixed plane No Shadings Unlimited load (grid)
Tilt/Azimuth 10 / 49 °

System information
PV Array Inverters
Nb. of modules 324 units Nb. of units 1 unit
Pnom total 149 kWp Pnom total 100 kWac
Pnom ratio 1.490

Results summary
Produced Energy 167945 kWh/year Specific production 1127 kWh/kWp/year Perf. Ratio PR 86.90 %

PVsyst TRIAL
Project and results summary
General parameters, PV Array Characteristics, System losses
Main results
Loss diagram
Predef. graphs
Table of contents
2
3
4
5
6
Single-line diagram 7

PVsyst TRIAL

PVsyst TRIAL
05/11/23 PVsyst Evaluation mode Page 2/7
Project: first project
Variant: New simulation variant

PVsyst V7.3.4
VC0, Simulation date:
05/11/23 09:08

PVsyst TRIAL
with v7.3.4

General parameters
Grid-Connected System No 3D scene defined, no shadings

PV Field Orientation
Orientation Sheds configuration Models used
Fixed plane No 3D scene defined Transposition Perez
Tilt/Azimuth 10 / 49 ° Diffuse Perez, Meteonorm
Circumsolar separate

Horizon Near Shadings User's needs


Free Horizon No Shadings Unlimited load (grid)

PVsyst TRIAL
PV Array Characteristics
PV module Inverter
Manufacturer Generic Manufacturer Generic
Model JAM72-S20-460-MR Model SP-100K-L
(Original PVsyst database) (Original PVsyst database)
Unit Nom. Power 460 Wp Unit Nom. Power 100 kWac
Number of PV modules 324 units Number of inverters 9 * MPPT 11% 1 unit
Nominal (STC) 149 kWp Total power 100 kWac
Modules 18 Strings x 18 In series Operating voltage 200-1000 V
At operating cond. (50°C) Pnom ratio (DC:AC) 1.49
Pmpp 137 kWp No power sharing between MPPTs
U mpp 693 V
I mpp 197 A

PVsyst TRIAL
Total PV power Total inverter power
Nominal (STC) 149 kWp Total power 100 kWac
Total 324 modules Number of inverters 1 unit
Module area 720 m² Pnom ratio 1.49

Array losses
Thermal Loss factor DC wiring losses Module Quality Loss
Module temperature according to irradiance Global array res. 58 mΩ Loss Fraction -0.8 %
Uc (const) 20.0 W/m²K Loss Fraction 1.5 % at STC
Uv (wind) 0.0 W/m²K/m/s

Module mismatch losses Strings Mismatch loss


Loss Fraction 2.0 % at MPP Loss Fraction 0.2 %

IAM loss factor

PVsyst TRIAL
Incidence effect (IAM): User defined profile

0° 30° 50° 65° 70° 75° 80° 85° 90°


1.000 1.000 0.992 0.943 0.898 0.813 0.677 0.426 0.000

PVsyst TRIAL
05/11/23 PVsyst Evaluation mode Page 3/7
Project: first project
Variant: New simulation variant

PVsyst V7.3.4
VC0, Simulation date:
05/11/23 09:08

PVsyst TRIAL
with v7.3.4

Main results
System Production
Produced Energy 167945 kWh/year Specific production 1127 kWh/kWp/year
Perf. Ratio PR 86.90 %

Normalized productions (per installed kWp) Performance Ratio PR

PVsyst TRIAL
Balances and main results

GlobHor DiffHor T_Amb GlobInc GlobEff EArray E_Grid PR


kWh/m² kWh/m² °C kWh/m² kWh/m² kWh kWh ratio
January 30.8 17.86 -0.55 35.7 33.5 4906 4824 0.907

PVsyst TRIAL
February 56.0 24.17 0.94 65.0 62.3 9102 8984 0.927
March 92.0 50.45 5.91 99.5 96.5 13764 13596 0.917
April 129.4 66.86 11.61 135.0 131.3 17816 17609 0.875
May 171.6 71.95 16.62 174.9 170.4 22467 22210 0.852
June 180.7 72.91 20.12 181.7 177.4 23004 22743 0.840
July 180.7 84.52 22.43 182.6 178.1 23046 22782 0.837
August 155.0 75.43 21.98 160.1 156.2 20687 20451 0.857
September 106.3 53.24 16.13 112.9 109.5 14950 14771 0.878
October 71.2 37.43 10.94 80.2 77.3 10869 10729 0.898
November 34.2 19.67 5.74 40.2 37.9 5454 5367 0.896
December 24.8 15.29 0.39 29.0 27.1 3954 3880 0.897
Year 1232.9 589.78 11.08 1296.8 1257.3 170021 167945 0.869

PVsyst TRIAL
Legends
GlobHor Global horizontal irradiation EArray Effective energy at the output of the array
DiffHor Horizontal diffuse irradiation E_Grid Energy injected into grid
T_Amb Ambient Temperature PR Performance Ratio
GlobInc Global incident in coll. plane
GlobEff Effective Global, corr. for IAM and shadings

PVsyst TRIAL
05/11/23 PVsyst Evaluation mode Page 4/7
Project: first project
Variant: New simulation variant

PVsyst V7.3.4
VC0, Simulation date:
05/11/23 09:08

PVsyst TRIAL
with v7.3.4

Loss diagram
1233 kWh/m² Global horizontal irradiation
+5.2% Global incident in coll. plane

-3.04% IAM factor on global

1257 kWh/m² * 720 m² coll. Effective irradiation on collectors

efficiency at STC = 20.71% PV conversion

187423 kWh Array nominal energy (at STC effic.)

PVsyst TRIAL
-1.85% PV loss due to irradiance level

-4.14% PV loss due to temperature

+0.75% Module quality loss

-2.15% Mismatch loss, modules and strings

-0.81% Ohmic wiring loss


172438 kWh Array virtual energy at MPP
-1.19% Inverter Loss during operation (efficiency)
-1.42% Inverter Loss over nominal inv. power
0.00% Inverter Loss due to max. input current
0.00% Inverter Loss over nominal inv. voltage
0.00% Inverter Loss due to power threshold

PVsyst TRIAL 167945 kWh


167945 kWh
0.00%
-0.01%
Inverter Loss due to voltage threshold
Night consumption
Available Energy at Inverter Output
Energy injected into grid

PVsyst TRIAL

PVsyst TRIAL
05/11/23 PVsyst Evaluation mode Page 5/7
Project: first project
Variant: New simulation variant

PVsyst V7.3.4
VC0, Simulation date:
05/11/23 09:08

PVsyst TRIAL
with v7.3.4

Predef. graphs
Daily Input/Output diagram

PVsyst TRIAL

PVsyst TRIAL System Output Power Distribution

PVsyst TRIAL

PVsyst TRIAL
05/11/23 PVsyst Evaluation mode Page 6/7
PVsyst V7.3.4
VC0, Simulation date:
05/11/23 09:08
with v7.3.4