My Project
My Project
CONCLUSION
BIBLIOGRAPHY
introduction
INTRODUCTION
To get this aim of cost, we have the quantity and locality of already accessible supplies
and the amount demanded on top of the participation united accompanied by each ‘sending’.
Definition 1.1
Operations Research (OR) may be defined as the science that aims for the application
of analytical and numerical techniques along with information technology to solve
organizational problems.
Definition 1.2
Linear Programming or Linear Optimization is a process which takes into
consideration certain linear relationships to obtain the best possible solution to a mathematical
model. It includes problems dealing with maximizing profits, minimizing costs, minimal usage
of resources, etc.
Definition 1.3
The cost of transporting one unit of an item from origin 𝑖 to destination 𝑗 is 𝑐𝑖𝑗 and is
known for all combinations (𝑖, 𝑗). Quantity transported from origin 𝑖 to destination 𝑗 be 𝑥𝑖𝑗 .
The objective is to determine the quantity 𝑥𝑖𝑗 to be transported over all routes (𝑖, 𝑗) so
as to minimize the total transportation cost. The supply limits at the origins and the demand
requirements at the destinations must be satisfied.
The above transportation problem can be written in the following tabular form:
Destinations
1 2 3 … n Supply
…
m (𝑥𝑚1 ) (𝑥𝑚2 ) (𝑥𝑚3 ) … (𝑥𝑚𝑛 ) 𝑎𝑚
𝑐𝑚1 𝑐𝑚1 𝑐𝑚3 𝑐𝑚𝑛
Demand 𝑏1 𝒃2 𝒃3 … 𝒃𝑛
Definition 1.4
Definition 1.5
A feasible solution is called a Basic Feasible Solution if it contains not more than
𝑚 + 𝑛 − 1 allocations, where m is the number of rows and n is the number of columns in a
Transportation Problem.
Definition 1.6
Optimal Solution is a feasible solution (not necessarily basic) which optimizes
(minimize) the total transportation cost.
Definition 1.7
The Standard Deviation is defined as the deviation of the values or data from their
average mean. Lower standard deviation will conclude that the values are very close around
their average.
On the other hand, higher values mean the values are far from the mean value. It should
be noted here that the standard deviation value can never be negative.
Definition 1.8
∑𝑛𝑗=1 𝐵𝑗 .
Definition 1.9
The Vogel’s Approximation Method or VAM is an iterative procedure calculated to
find out the initial feasible solution of the transportation problem. Vogel’s Approximation
Method is also called as Penalty Method because the difference costs chosen are nothing but
the penalties of not choosing the least cost routes.
Chapter – 2
UNBALANCED TRANSPORTATION PROBLEM
And
In a transportation problem the sum of all available quantities is not equal to the sum of
requirements that is ∑𝑚 𝑛
𝑖=1 𝑎𝑖 ≠ ∑𝑗=1 𝑏𝑗 , then such problem is called an unbalanced
transportation problem
To modify unbalanced transportation problem
An unbalanced TP may occur in two different forms (I) Excess of availability (II)
Shortage in availability. Now discuss these two cases by considering our usual m-origin, n-
destination TP with the condition that ∑𝑚 𝑛
𝑖=1 𝑎𝑖 ≠ ∑𝑗=1 𝑏𝑗 .
𝑚 𝑛+1
∑ 𝑎𝑖 ≠ ∑ 𝑏𝑗
𝑖=1 𝑗=1
The problem with possess a feasible solution if ∑ 𝑎𝑖 > ∑ 𝑏𝑗 . In the first constraint, the
introduction of slack variable 𝑥𝑖𝑛+1 (𝑖 = 1,2, … , 𝑚) gives
𝑛
𝑚 𝑛 𝑚
∑ [∑(𝑥𝑖𝑗 + 𝑥𝑖𝑛+1 )] = ∑ 𝑎𝑖
𝑖=1 𝑗=1 𝑖=1
𝑛 𝑚 𝑚 𝑚
∑ (∑ 𝑥𝑖𝑗 + ∑ 𝑥𝑖𝑛+1 ) = ∑ 𝑎𝑖
𝑗=1 𝑖=1 𝑖=1 𝑖=1
𝑚 𝑚 𝑛 𝑛
If this excess availability is denoted by 𝑏𝑛+1 the modified general TP can be reformulated as
𝑚 𝑛+1
𝑚 𝑛+1
∑ 𝑎𝑖 = ∑ 𝑏𝑗
𝑖=1 𝑗=1
Now introducing the slack variable 𝑥𝑚+1𝑗 , 𝑓𝑜𝑟 𝑗 = 1,2, … , 𝑛 in the second constrained, we get
𝑛 𝑚 𝑛
∑ (∑(𝑥𝑖𝑗 + 𝑥𝑚+1𝑗 )) = ∑ 𝑏𝑗
𝑗=1 𝑖=1 𝑗=1
𝑛 𝑚 𝑚 𝑛
∑ (∑ 𝑥𝑖𝑗 + ∑ 𝑥𝑚+1𝑗 ) = ∑ 𝑏𝑗
𝑗=1 𝑖=1 𝑖=1 𝑗=1
𝑛 𝑛 𝑚
𝑚+1 𝑛
𝑚+1 𝑛
∑ 𝑎𝑖 = ∑ 𝑏𝑗
𝑖=1 𝑗=1
2.2 Existence of Feasible Solution for Unbalanced TP
A necessary and sufficient condition for the existence of a feasible solution to the
unbalanced transportation problem is
𝑚 𝑛+1 𝑚+1 𝑛
∑ 𝑎𝑖 = ∑ 𝑏𝑗 (𝑜𝑟) ∑ 𝑎𝑖 = ∑ 𝑏𝑗
𝑖=1 𝑗=1 𝑖=1 𝑗=1
Destination
source 𝑫𝟏 𝑫𝟐 𝑫𝟑 … 𝑫𝒋 … 𝑫𝒏 supply
𝑺𝟏 𝑥11 𝑥12 𝑥13 … 𝑥1𝑗 … 𝑥1𝑛 𝑎1
𝑐11
𝑐12 𝑐13 𝑐1𝑗 𝑐1𝑛
𝑺𝟐 𝑥12 𝑥22 𝑥23 … 𝑥2𝑗 … 𝑥2𝑛 𝑎2
𝑐21 𝑐22 𝑐23 𝑐2𝑗 𝑐2𝑛
… …
…
…
…
Destination
source 𝑫𝟏 𝑫𝟐 𝑫𝟑 … 𝑫𝒋 … 𝑫𝒏 𝑫𝒏+𝟏 supply
𝟎𝟏 𝑥11 𝑥12 𝑥13 … 𝑥1𝑗 … 𝑥1𝑛 𝒙𝟏𝒏+𝟏 𝑎1
𝑐11 𝑐12 𝑐13 𝑐1𝑗 𝑐1𝑛 𝒙𝟏𝒏+𝟏
… …
…
…
…
…
𝟎𝒊 𝑥𝑖1 𝑥𝑖2 𝑥𝑖3 … 𝑥𝑖𝑗 … 𝑥𝑖𝑛 𝒙𝒊𝒏+𝟏 𝑎𝑖
𝑐𝑖1 𝑐𝑖2 𝑐𝑖3 𝑐𝑖𝑗 𝑐𝑖𝑛 𝒙𝒊𝒏+𝟏
… …
…
…
𝟎𝒎 𝑥𝑚1 𝑥𝑚2 𝑥𝑚3 … 𝑥𝑚𝑗 … 𝑥𝑚𝑛 𝒙𝒎𝒏+𝟏 𝑎𝑚
𝑐𝑚1 𝑐𝑚2 𝑐𝑚3 𝑐𝑚𝑗 𝑐𝑚𝑛 𝒙𝒎𝒏+𝟏
𝒃𝒏+𝟏 =
𝒎 𝒏
Demand 𝑏1 𝑏2 𝑏3 … 𝑏𝑗 … 𝑏𝑛 𝒎 𝒏
∑ 𝒂𝒊 > ∑ 𝒃𝒋 ∑ 𝒂𝒊 > ∑ 𝒃𝒋
𝒊=𝟏 𝒋=𝟏 𝒊=𝟏 𝒋=𝟏
The 𝑚 × 𝑛 squares are called cells. The transportation cost 𝑐𝑖𝑗 from the 𝑖 𝑡ℎ source to the
𝑗 𝑡ℎ destination is displayed in the lower right side of the (𝑖, 𝑗)𝑡ℎ cell. Any feasible solution is
shown in the table by entering the values of 𝑥𝑖𝑗 in the upper left side of the (𝑖, 𝑗)𝑡ℎ cell.
The various 𝑎𝑖 ’s and 𝑏𝑗 ’s are called rim requirements. The feasibility of a solution can
be verified by summing the values of 𝑥𝑖𝑗 along the rows and down the columns (i.e., 𝑥𝑖𝑗
satisfying the rim conditions).
Any feasible solution for transportation problem must have exactly (𝑚 + 𝑛 −1) non –negative
basic variables (or) allocations.
Unbalanced Transportation Table: (Shortage in availability i.e., ∑ 𝑎𝑖 > ∑ 𝑏𝑗 )
Destination
source 𝑫𝟏 𝑫𝟐 𝑫𝟑 … 𝑫𝒋 … 𝑫𝒏 supply
𝟎𝟏 𝑥11 𝑥12 𝑥13 … 𝑥1𝑗 … 𝑥1𝑛 𝑎1
𝑐11
𝑐12 𝑐13 𝑐1𝑗 𝑐1𝑛
𝟎𝟐 𝑥12 𝑥22 𝑥23 … 𝑥2𝑗 … 𝑥2𝑛 𝑎2
𝑐21 𝑐22 𝑐23 𝑐2𝑗 𝑐2𝑛
… …
…
…
𝟎𝒊 𝑥𝑖1 𝑥𝑖2 𝑥𝑖3 … 𝑥𝑖𝑗 … 𝑥𝑖𝑛 𝑎𝑖
𝑐𝑖1 𝑐𝑖2 𝑐𝑖3 𝑐𝑖𝑗 𝑐𝑖𝑛
… …
…
…
𝟎𝒎 𝑥𝑚1 𝑥𝑚2 𝑥𝑚3 … 𝑥𝑚𝑗 … 𝑥𝑚𝑛 𝑎𝑚
𝑐𝑚1 𝑐𝑚2 𝑐𝑚3 𝑐𝑚𝑗 𝑐𝑚𝑛
𝑚 𝑛
Demand 𝑏1 𝑏2 𝑏3 … 𝑏𝑗 … 𝑏𝑛
∑ 𝑎𝑖 < ∑ 𝑏𝑗
𝑖=1 𝑗=1
Destination
source 𝑫𝟏 𝑫𝟐 𝑫𝟑 … 𝑫𝒋 … 𝑫𝒏 supply
𝟎𝟏 𝑥11 𝑥12 𝑥13 … 𝑥1𝑗 … 𝑥1𝑛 𝑎1
𝑐11
𝑐12 𝑐13 𝑐1𝑗 𝑐1𝑛
𝟎𝟐 𝑥12 𝑥22 𝑥23 … 𝑥2𝑗 … 𝑥2𝑛 𝑎2
𝑐21 𝑐22 𝑐23 𝑐2𝑗 𝑐2𝑛
… …
…
…
𝟎𝒊 𝑥𝑖1 𝑥𝑖2 𝑥𝑖3 … 𝑥𝑖𝑗 … 𝑥𝑖𝑛 𝑎𝑖
𝑐𝑖1 𝑐𝑖2 𝑐𝑖3 𝑐𝑖𝑗 𝑐𝑖𝑛
… …
…
𝑚 𝑛
Demand 𝑏1 𝑏2 𝑏3 … 𝑏𝑗 … 𝑏𝑛
∑ 𝑎𝑖 < ∑ 𝑏𝑗
𝑖=1 𝑗=1
Step 2:
For each row and column reaming under consideration calculate its Standard
1
Deviations (SD). In that rows SD is denoted by 𝜎𝑠𝑖 [= √𝑛 (𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 ] for
row (or) column with the largest SD and allocate maximum possible to the variable
with least unit TC in the selected row (or) column. So as to exhaust either the supply at
particular origin or satisfy demand at a destination.
Step 6:
(I) If one row (column) with non-zero supply (demand) remains uncrossed out,
determine the basic variable in the row(column) by LCM step.
(II) If all the variable in uncrossed out rows and columns have zero supply
(demand), determine the zero basic variables by LCM step.
Step 7:
Given TP is unbalanced TP, there are two cases
(I) ∑ 𝑎𝑖 > ∑ 𝑏𝑗
(II) ∑ 𝑎𝑖 < ∑ 𝑏𝑗
Case(I):
Case (II):
Whenever ∑ 𝑎𝑖 < ∑ 𝑏𝑗 , Introduce a dummy origin (𝑚 + 1)th row in the
transportation table. The unit transportation cost to this dummy origin is 𝑐𝑚+1𝑗
and the value of 𝑐𝑚+1𝑗 = 0 for 𝑗 = 1,2, … , 𝑛. The supply of this dummy origin
is 𝑎𝑚+1 = ∑ 𝑏𝑗 − ∑ 𝑎𝑖 . The unit of amount shafting from (𝑚 + 1)th origin to
𝑗th destination is 𝑥𝑚+1𝑗 = 𝑏𝑗 − ∑𝑚
𝑖=1 𝑥𝑖𝑗 , for 𝑗 = 1,2, … , 𝑛.
Step 8:
The balanced transportation table having at least one basic cell in each
row(column) including dummy row(column) and also the basic cell do not form loop.
Hence the initial basic feasible solution is obtained and the minimum transportation
cost equal to
𝑚 𝑛+1 𝑚+1 𝑛 𝑚 𝑛
Problem 3.2.1
Consider the following transportation problem involving three sources and four
destinations.
Source 𝐷1 𝐷2 𝐷3 𝐷4 supply
𝑆1 6 1 9 3 70
𝑆2 11 5 2 8 55
𝑆3 10 12 4 7 70
Demand 85 35 50 45
Solution:
To find the given problem is balanced or unbalanced transportation problem.
Now, Total no. of supply = ∑𝑖 𝑎𝑖 = 195
Total no. of demand = ∑𝑗 𝑏𝑗 = 215
It seems that total no. of supply and total no. of demand is not equal. Hence, the given
transportation problem is Unbalanced TP.
To change the Unbalanced TP into Balanced TP. Then add a dummy row (𝑆4 )
in the initial transportation table.
Source 𝐷1 𝐷2 𝐷3 𝐷4 supply
𝑆1 6 1 9 3 70
𝑆2 11 5 2 8 55
𝑆3 10 12 4 7 70
𝑆4 0 0 0 0 20
Demand 85 35 50 45 215
(Table 3.1.1)
METHOD 1
To find initial basis feasible solution using Vogel’s approximation or penalty
method as follows:
𝑆1 6 1 9 3 70 2
𝑆2 11 5 2 8 55 3
𝑆3 10 12 4 7 70 3
20
𝑆4 0 0 0 0 20(0) 0
Demand 85(65) 35 50 45
Column 6 1 2 3
difference
(Table 3.1.2)
Source 𝐷1 𝐷2 𝐷3 𝐷4 supply Row
difference
65
𝑆1 6 1 9 3 70(5) 2
𝑆2 11 5 2 8 55 3
𝑆3 10 12 4 7 70 3
Demand 65(0) 35 50 45
Column 4 4 2 4
difference
(Table 3.1.3)
𝑆2 5 2 8 55 3
𝑆3 12 4 7 70 3
Demand 35(30) 50 45
Column 4 2 4
difference
(Table 3.1.4)
Source 𝐷2 𝐷3 𝐷4 supply Row
difference
30
𝑆2 5 2 8 55(25) 3
𝑆3 12 4 7 70 3
Demand 30(0) 50 45
Column 7 2 1
difference
(Table 3.1.5)
𝑆3 4 7 70 3
Demand 50(25) 45
Column 2 1
difference
(Table 3.1.6)
Column - -
difference
(Table 3.1.7)
Source 𝐷4 supply Row
difference
45
𝑆3 7 45(0) -
Demand 45(0)
Column -
difference
(Table 3.1.8)
To find the total cost (IBFS) in the given transportation problem is as follows:
Source 𝐷1 𝐷2 𝐷3 𝐷4 supply
65 5
𝑆1 6 1 9 3 70
30 25
𝑆2 11 5 2 8 55
25 45
𝑆3 10 12 4 7 70
20
𝑆4 0 0 0 0 20
Demand 85 35 50 45 215
(Table 3.1.9)
ITERATION 1
Source 𝐷1 𝐷2 𝐷3 𝐷4 supply
𝑆1 6 1 9 3 70
𝑆2 11 5 2 8 55
𝑆3 10 12 4 7 70
𝑆4 0 0 0 0 20
Demand 85 35 50 45
(Table 3.1.10)
𝑭𝒐𝒓𝒎𝒖𝒍𝒂:
1
𝒔𝒕𝒂𝒏𝒅𝒂𝒓𝒅 𝒅𝒆𝒗𝒊𝒂𝒕𝒊𝒐𝒏 (𝒓𝒐𝒘𝒔) = 𝜎𝑠𝑖 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2
𝑛
1
𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑑𝑒𝑣𝑖𝑎𝑖𝑡𝑜𝑛 (𝑐𝑜𝑙𝑢𝑚𝑛𝑠) = 𝜎𝐷𝑖 = √ 𝑐𝑖𝑗 2
∑(𝑐𝑖𝑗 − ̅̅̅)
𝑚
SD (𝜎𝐷1 ) ⟹
𝐶𝑖𝑗 (𝐶𝑖𝑗 − ̅̅̅̅
𝐶𝑖𝑗 )2
6 0.5625
11 18.0625
10 10.5625
0 45.5625
1 1
𝜎𝐷1 = √ 𝑐𝑖𝑗 2 = √ (74.75) = 4.32
∑(𝑐𝑖𝑗 − ̅̅̅)
𝑚 4
𝝈𝑫𝟏 = 𝟒. 𝟑𝟐
∑𝐶 18
𝐶𝑖𝑗 = 𝑚𝑖𝑗 = 4 = 4.5 , where 𝑚 = 4
̅̅̅̅
1 1
𝜎𝐷2 = √ 𝑐𝑖𝑗 2 = √ (89) = 4.72
∑(𝑐𝑖𝑗 − ̅̅̅)
𝑚 4
𝝈𝑫𝟐 = 𝟒. 𝟕𝟐
9 27.5625
2 3.0625
4 0.0625
0 14.0625
1 1
𝜎𝐷3 = √ 𝑐𝑖𝑗 2 = √ (44.75) = 3.34
∑(𝑐𝑖𝑗 − ̅̅̅)
𝑚 4
𝝈𝑫𝟑 = 𝟑. 𝟑𝟒
3 2.25
8 12.25
7 6.25
0 20.25
∑𝐶 18
𝐶𝑖𝑗 = 𝑚𝑖𝑗 = 4 = 4.5 , where 𝑚 = 4
̅̅̅̅
1 1
𝜎𝐷4 = √ 𝑐𝑖𝑗 2 = √ (41) = 3.20
∑(𝑐𝑖𝑗 − ̅̅̅)
𝑚 4
𝝈𝑫𝟒 = 𝟑. 𝟐𝟎
To find row difference using Standard Deviation
SD (𝜎𝑆1 ) ⟹
𝐶𝑖𝑗 (𝐶𝑖𝑗 − ̅̅̅̅
𝐶𝑖𝑗 )2
6 1.5625
1 14.0625
9 18.0625
3 3.0625
∑𝐶 19
𝐶𝑖𝑗 = 𝑛 𝑖𝑗 = 4 = 4.75 , where 𝑛 = 4
̅̅̅̅
1 1
𝜎𝑆1 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 = √ (36.75) = 3.03
𝑛 4
𝝈𝑺𝟏 = 𝟑. 𝟎𝟑
11 20.25
5 2.25
2 20.25
8 2.25
∑𝐶 26
𝐶𝑖𝑗 = 𝑛 𝑖𝑗 = 4 = 6.5 , where 𝑛 = 4
̅̅̅̅
1 1
𝜎𝑆2 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 = √ (45) = 3.35
𝑛 4
𝝈𝑺𝟐 = 𝟑. 𝟑𝟓
∑ 𝐶𝑖𝑗 33
̅̅̅̅
𝐶𝑖𝑗 = = = 8.25 , where 𝑛 = 4
𝑛 4
1 1
𝜎𝑆3 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 = √ (36.75) = 3.03
𝑛 4
𝝈𝑺𝟑 = 𝟑. 𝟎𝟑
SD (𝜎𝑆4 ) ⟹
𝝈𝑺𝟒 = 𝟎
Source 𝐷1 𝐷2 𝐷3 𝐷4 supply SD row
difference
35
𝑆1 6 1 9 3 70 (35) 3.03
𝑆2 11 5 2 8 55 3.35
𝑆3 10 12 4 7 70 3.03
𝑆4 0 0 0 0 20 0
Demand 85 35 (0) 50 45
ITERATION 2
Source 𝐷1 𝐷3 𝐷4 supply
𝑆1 6 9 3 35
𝑆2 11 2 8 55
𝑆3 10 4 7 70
𝑆4 0 0 0 20
Demand 85 50 45
Table 3.1.12
Column difference using Standard Deviation
𝝈𝑫𝟏 = 𝟒. 𝟑𝟐 𝝈𝑫𝟑 = 𝟑. 𝟑𝟒 𝝈𝑫𝟒 = 𝟑. 𝟐𝟎
6 0
SD (𝜎𝑆1 ) ⟹
9 9
3 9
∑𝐶 18
𝐶𝑖𝑗 = 𝑛 𝑖𝑗 = 3 = 6 , where 𝑛 = 3
̅̅̅̅
1 1
𝜎𝑆1 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 = √ (18) = 2.45
𝑛 3
𝝈𝑺𝟏 = 𝟐. 𝟒𝟓
11 16
2 25
8 1
∑𝐶 21
𝐶𝑖𝑗 = 𝑛 𝑖𝑗 = 3 = 7 , where 𝑛 = 3
̅̅̅̅
1 1
𝜎𝑆2 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 = √ (42) = 3.74
𝑛 3
𝝈𝑺𝟐 = 𝟑. 𝟕𝟒
10 9
4 9
7 0
∑ 𝐶𝑖𝑗 21
̅̅̅̅
𝐶𝑖𝑗 = = = 7 , where 𝑛 = 3
𝑛 3
1 1
𝜎𝑆3 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 = √ (18) = 2.45
𝑛 3
𝝈𝑺𝟑 = 𝟐. 𝟒𝟓
SD (𝜎𝑆4 ) ⟹
𝝈𝑺𝟒 = 𝟎
Source 𝐷1 𝐷3 𝐷4 supply SD row
difference
𝑆1 6 9 3 35 2.45
𝑆2 11 2 8 55 3.74
𝑆3 10 4 7 70 2.45
20
𝑆4 0 0 0 20 (0) 0
Demand 85 (65) 50 45
ITERATION 3
Source 𝐷1 𝐷3 𝐷4 supply
𝑆1 6 9 3 35
𝑆2 11 2 8 55
𝑆3 10 4 7 70
Demand 65 50 45
Table 3.1.13
6 9
11 4
10 1
∑𝐶 27
𝐶𝑖𝑗 = 𝑚𝑖𝑗 = 3 = 9 , where 𝑚 = 3
̅̅̅̅
1 1
𝜎𝐷1 = √ 𝑐𝑖𝑗 2 = √ (14) = 2.16
∑(𝑐𝑖𝑗 − ̅̅̅)
𝑚 3
𝝈𝑫𝟏 = 𝟐. 𝟏𝟔
𝐶𝑖𝑗 (𝐶𝑖𝑗 − ̅̅̅̅
𝐶𝑖𝑗 )2
9 16
SD (𝜎𝐷3 ) ⟹ 2 9
4 1
∑𝐶 15
𝐶𝑖𝑗 = 𝑖𝑗 = = 5 , where 𝑚 = 3
̅̅̅̅
𝑚 3
1 1
𝜎𝐷3 = √ 𝑐𝑖𝑗 2 = √ (26) = 2.94
∑(𝑐𝑖𝑗 − ̅̅̅)
𝑚 3
𝝈𝑫𝟑 = 𝟐. 𝟗𝟒
SD (𝜎𝐷4 ) ⟹
𝐶𝑖𝑗 (𝐶𝑖𝑗 − ̅̅̅̅
𝐶𝑖𝑗 )2
3 9
8 4
7 1
∑𝐶 18
𝐶𝑖𝑗 = 𝑚𝑖𝑗 = 3 = 6 , where 𝑚 = 3
̅̅̅̅
1 1
𝜎𝐷4 = √ 𝑐𝑖𝑗 2 = √ (14) = 2.16
∑(𝑐𝑖𝑗 − ̅̅̅)
𝑚 3
𝝈𝑫𝟒 = 𝟐. 𝟏𝟔
𝑆1 6 9 3 35 2.45
50
𝑆2 11 2 8 55 (5) 3.74 ⟵
𝑆3 10 4 7 70 2.45
Demand 65 50 (0) 45
Source 𝐷1 𝐷4 supply
𝑆1 6 3 35
𝑆2 11 8 5
𝑆3 10 7 70
Demand 65 45
Table 3.1.15
∑𝐶 9
𝐶𝑖𝑗 = 𝑛 𝑖𝑗 = 2 = 4.5 , where 𝑛 = 2
̅̅̅̅
1 1
𝜎𝑆1 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 = √ (4.5) = 1.5
𝑛 2
𝝈𝑺𝟏 = 𝟏. 𝟓
SD (𝜎𝑆2 ) ⟹ 𝐶𝑖𝑗 (𝐶𝑖𝑗 − ̅̅̅̅
𝐶𝑖𝑗 )2
11 2.25
8 2.25
∑𝐶 19
𝐶𝑖𝑗 = 𝑛 𝑖𝑗 = 2 = 9.5 , where 𝑛 = 2
̅̅̅̅
1 1
𝜎𝑆2 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 = √ (4.5) = 1.5
𝑛 2
𝝈𝑺𝟐 = 𝟏. 𝟓
SD (𝜎𝑆3 ) ⟹ 10 2.25
7 2.25
∑𝐶 17
𝐶𝑖𝑗 = 𝑖𝑗 = = 8.5 , where 𝑛 = 2
̅̅̅̅
𝑛 2
1 1
𝜎𝑆3 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 = √ (4.5) = 1.5
𝑛 2
𝝈𝑺𝟑 = 𝟏. 𝟓
Source 𝐷1 𝐷4 supply SD row
difference
35
𝑆1 6 3 35 (0) 1.5
𝑆2 11 8 5 1.5
𝑆3 10 7 70 1.5
Demand 65 (30) 45
ITERATION 5
Source 𝐷1 𝐷4 supply
𝑆2 11 8 5
𝑆3 10 7 70
Demand 30 45
𝝈𝑺𝟐 = 𝟏. 𝟓 𝝈𝑺𝟑 = 𝟏. 𝟓
Column difference using standard deviation
11 0.25
10 0.25
∑𝐶 21
𝐶𝑖𝑗 = 𝑚𝑖𝑗 = 2 = 10.5 , where 𝑚 = 2
̅̅̅̅
1 1
𝜎𝐷1 = √ 𝑐𝑖𝑗 2 = √ (0.5) = 0.5
∑(𝑐𝑖𝑗 − ̅̅̅)
𝑚 2
𝝈𝑫𝟏 = 𝟎. 𝟓
8 0.25
7 0.25
∑𝐶 15
𝐶𝑖𝑗 = 𝑖𝑗 = = 7.5 , where 𝑚 = 2
̅̅̅̅
𝑚 2
1 1
𝜎𝐷4 = √ 𝑐𝑖𝑗 2 = √ (0.5) = 0.5
∑(𝑐𝑖𝑗 − ̅̅̅)
𝑚 2
𝝈𝑫𝟒 = 𝟎. 𝟓
Source 𝐷1 𝐷4 supply SD row
difference
𝑆2 11 8 5 1.5
45
𝑆3 10 7 70 (25) 1.5 ←
Demand 30 45 (0)
ITERATION 6
𝑆2 11 5 −
25
𝑆3 10 25 (0) −
Demand 30 (5)
SD column ↑ 0.5
difference
Table 3.1.18
The highest SD occurs in column 𝐷1 . Allocate maximum possibilities (i.e.) 25 eliminates row
𝑆3 .
ITERATION 7
Demand 5 (0)
SD column 0.5
difference
Hence, we have the following allocations.
Source 𝐷1 𝐷2 𝐷3 𝐷4 supply
35 3
𝑆1 6 5 1 9 3 70
5 50
𝑆2 11 5 2 8 55
25 45
𝑆3 10 12 4 7 70
20
𝑆4 0 0 0 0 20
Demand 85 35 50 45 215
Problem 3.2.2
Consider the following transportation problem involving four sources and three
destinations.
Source 𝐷1 𝐷2 𝐷3 supply
𝑆1 5 6 9 100
𝑆2 3 5 10 75
𝑆3 6 7 6 50
𝑆4 6 4 10 75
Demand 70 80 120
Solution:
To find the given problem is balanced or unbalanced transportation problem.
It seems that total no. of supply and total no. of demand is not equal. Hence, the given
transportation problem is Unbalanced TP.
To change the Unbalanced TP into Balanced TP. Then add a dummy column (𝐷4 ) in
the initial transportation table.
Source 𝐷1 𝐷2 𝐷3 𝐷4 supply
𝑆1 5 6 9 0 100
𝑆2 3 5 10 0 75
𝑆3 6 7 6 0 50
𝑆4 6 4 10 0 75
(Table 3.2.1)
Now, No. of supply = No. of demand. Hence the transportation problem is Balanced TP.
METHOD 1
To find initial basis feasible solution using Vogel’s approximation method or
penalty method as follows:
𝑆1 5 6 9 0 100 5
𝑆2 3 5 10 0 75 3
30
𝑆3 6 7 6 0 50 (20) 6 ←
𝑆4 6 4 10 0 75 4
Column 2 1 3 0
difference
(Table 3.2.2)
𝑆1 5 6 9 100 1
𝑆2 3 5 10 75 2
20
𝑆3 6 7 6 20(0) 1
𝑆4 6 4 10 75 2
Column 2 1 3↑
difference
(Table 3.2.3)
Source 𝐷1 𝐷2 𝐷3 supply Row
difference
𝑆1 5 6 9 100 1
70
𝑆2 3 5 10 75 (5) ← 2
𝑆4 6 4 10 75 2
Demand
70 (0) 80 100
Column
difference 2 1 1
(Table 3.2.4)
𝑆1 6 9 100 3
𝑆2 5 10 5 5
75
𝑆4 4 10 75 (0) ← 6
Demand 80 (5) 100
Column 1 1
difference
(Table 3.2.5)
Source 𝐷2 𝐷3 supply Row
difference
𝑆1 6 9 100 3
5
𝑆2 5 10 5 (0) ← 5
Demand 5 (0) 100
Column 1 1
difference
(Table 3.2.6)
Column −
difference
(Table 3.2.7)
To find the total cost (IBFS) in the given transportation problem is as follows:
Source 𝐷1 𝐷2 𝐷3 𝐷4 supply
100
𝑆1 5 6 9 0 100
70 5
𝑆2 3 5 10 0 75
20 30
𝑆3 6 7 6 0 50
75
𝑆4 6 4 10 0 75
(Table 3.2.8)
The transportation cost (IBFS) is
= (3 × 70) + (5 × 5) + (9 × 100) + (4 × 75) + (6 × 20) + (0 × 30)
= 1,555
Hence, the total transportation cost (IBFS) is 1,555
METHOD 2
To find initial basis feasible solution using Standard Deviation method as follows:
ITERATION 1
Source 𝐷1 𝐷2 𝐷3 𝐷4 supply
𝑆1 5 6 9 0 100
𝑆2 3 5 10 0 75
𝑆3 6 7 6 0 50
𝑆4 6 4 10 0 75
𝑭𝒐𝒓𝒎𝒖𝒍𝒂:
1
𝒔𝒕𝒂𝒏𝒅𝒂𝒓𝒅 𝒅𝒆𝒗𝒊𝒂𝒕𝒊𝒐𝒏 (𝒓𝒐𝒘𝒔) = 𝜎𝑠𝑖 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2
𝑛
1
𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑑𝑒𝑣𝑖𝑎𝑖𝑡𝑜𝑛 (𝑐𝑜𝑙𝑢𝑚𝑛𝑠) = 𝜎𝐷𝑖 = √ 𝑐𝑖𝑗 2
∑(𝑐𝑖𝑗 − ̅̅̅)
𝑚
To find column difference using Standard Deviation:
SD (𝜎𝐷1 ) ⟹
𝐶𝑖𝑗 (𝐶𝑖𝑗 − ̅̅̅̅
𝐶𝑖𝑗 )2
5 0
3 4
6 1
6 1
∑𝐶 20
𝐶𝑖𝑗 = 𝑚𝑖𝑗 = 4 = 5 , where 𝑚 = 4
̅̅̅̅
1 1
𝜎𝐷1 = √ 𝑐𝑖𝑗 2 = √ (6) = 1.22
∑(𝑐𝑖𝑗 − ̅̅̅)
𝑚 4
𝝈𝑫𝟏 = 𝟏. 𝟐𝟐
∑𝐶 22
𝐶𝑖𝑗 = 𝑚𝑖𝑗 = 4 = 5.5 , where 𝑚 = 4
̅̅̅̅
1 1
𝜎𝐷2 = √ 𝑐𝑖𝑗 2 = √ (5) = 1.12
∑(𝑐𝑖𝑗 − ̅̅̅)
𝑚 4
𝝈𝑫𝟐 = 𝟏. 𝟏𝟐
∑𝐶 35
𝐶𝑖𝑗 = 𝑚𝑖𝑗 = 4 = 8.75 , where 𝑚 = 4
̅̅̅̅
1 1
𝜎𝐷3 = √ 𝑐𝑖𝑗 2 = √ (10.75) = 1.64
∑(𝑐𝑖𝑗 − ̅̅̅)
𝑚 4
𝝈𝑫𝟑 = 𝟏. 𝟔𝟒
SD (𝜎𝐷4 ) ⟹
𝝈𝑫𝟒 = 𝟎
To find Row Difference using Standard Deviation:
SD (𝜎𝑆1 ) ⟹
𝐶𝑖𝑗 (𝐶𝑖𝑗 − ̅̅̅̅
𝐶𝑖𝑗 )2
5 0
6 1
9 16
0 25
∑𝐶 20
𝐶𝑖𝑗 = 𝑛 𝑖𝑗 = 4 = 5 , where 𝑛 = 4
̅̅̅̅
1 1
𝜎𝑆1 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 = √ (42) = 3.24
𝑛 4
𝝈𝑺𝟏 = 𝟑. 𝟐𝟒
∑𝐶 18
𝐶𝑖𝑗 = 𝑛 𝑖𝑗 = 4 = 4.5 , where 𝑛 = 4
̅̅̅̅
1 1
𝜎𝑆2 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 = √ (51) = 3.57
𝑛 4
𝝈𝑺𝟐 = 𝟑. 𝟓𝟕
∑ 𝐶𝑖𝑗 19
𝐶𝑖𝑗 = 𝑛 = 4 = 4.75 , where 𝑛 = 4
̅̅̅̅
1 1
𝜎𝑆3 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 = √ (30.75) = 2.77
𝑛 4
𝝈𝑺𝟑 = 𝟐. 𝟕𝟕
1 1
𝜎𝑆4 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 = √ (52) = 3.61
𝑛 4
𝝈𝑺𝟒 = 𝟑. 𝟔𝟏
𝑆1 5 6 9 0 100 3.24
𝑆2 3 5 10 0 75 3.57
𝑆3 6 7 6 0 50 2.77
75
𝑆4 6 4 10 0 75 (0) 3.61 ⟵
Source 𝐷1 𝐷2 𝐷3 𝐷4 Supply
𝑆1 5 6 9 0 100
𝑆2 3 5 10 0 75
𝑆3 6 7 6 0 50
Demand 70 5 120 30
Table 3.2.11
Row difference using Standard Deviation
SD (𝜎𝐷1 ) ⟹
𝐶𝑖𝑗 (𝐶𝑖𝑗 − ̅̅̅̅
𝐶𝑖𝑗 )2
5 0.1089
3 2.7889
6 1.7689
∑𝐶 14
𝐶𝑖𝑗 = 𝑚𝑖𝑗 = 3 = 4.67 , where 𝑚 = 3
̅̅̅̅
1 1
𝜎𝐷1 = √ 𝑐𝑖𝑗 2 = √ (4.6667) = 1.25
∑(𝑐𝑖𝑗 − ̅̅̅)
𝑚 3
𝝈𝑫𝟏 = 𝟏. 𝟐𝟓
𝐶𝑖𝑗 (𝐶𝑖𝑗 − ̅̅̅̅
𝐶𝑖𝑗 )2
SD (𝜎𝐷2 ) ⟹
6 0
5 1
7 1
∑𝐶 18
𝐶𝑖𝑗 = 𝑚𝑖𝑗 = 3 = 6 , where 𝑚 = 3
̅̅̅̅
1 1
𝜎𝐷2 = √ 𝑐𝑖𝑗 2 = √ (2) = 0.82
∑(𝑐𝑖𝑗 − ̅̅̅)
𝑚 3
𝝈𝑫𝟐 = 𝟎. 𝟖𝟐
9 0.4489
10 2.7889
6 5.4289
∑𝐶 25
𝐶𝑖𝑗 = 𝑚𝑖𝑗 = 3 = 8.33 , where 𝑚 = 3
̅̅̅̅
1 1
𝜎𝐷3 = √ 𝑐𝑖𝑗 2 = √ (8.6667) = 1.70
∑(𝑐𝑖𝑗 − ̅̅̅)
𝑚 3
𝝈𝑫𝟑 = 𝟏. 𝟕𝟎
Source 𝐷1 𝐷2 𝐷3 𝐷4 Supply SD row
difference
𝑆1 5 6 9 0 100 3.24
70
𝑆2 3 5 10 0 75 (5) 3.57 ⟵
𝑆3 6 7 6 0 50 2.77
ITERATION 3
Source 𝐷2 𝐷3 𝐷4 Supply
𝑆1 6 9 0 100
𝑆2 5 10 0 5
𝑆3 7 6 0 50
Demand 5 120 30
Table 3.2.13
SD (𝜎𝑆1 ) ⟹
𝐶𝑖𝑗 (𝐶𝑖𝑗 − ̅̅̅̅
𝐶𝑖𝑗 )2
6 1
9 16
0 25
∑𝐶 15
𝐶𝑖𝑗 = 𝑛 𝑖𝑗 = 3 = 5 , where 𝑛 = 3
̅̅̅̅
1 1
𝜎𝑆1 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 = √ (42) = 3.74
𝑛 3
𝝈𝑺𝟏 = 𝟑. 𝟕𝟒
∑𝐶 15
𝐶𝑖𝑗 = 𝑛 𝑖𝑗 = 3 = 5 , where 𝑛 = 3
̅̅̅̅
1 1
𝜎𝑆2 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 = √ (50) = 4.08
𝑛 3
𝝈𝑺𝟐 = 𝟒. 𝟎𝟖
𝐶𝑖𝑗 (𝐶𝑖𝑗 − ̅̅̅̅
𝐶𝑖𝑗 )2
SD (𝜎𝑆3 ) ⟹ 7 7.1289
6 2.7889
0 18.6667
∑𝐶 13
𝐶𝑖𝑗 = 𝑛 𝑖𝑗 = 3 = 4.33 , where 𝑛 = 3
̅̅̅̅
1 1
𝜎𝑆3 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 = √ (28.6667) = 3.09
𝑛 3
𝝈𝑺𝟑 = 𝟑. 𝟎𝟗
𝑆1 6 9 0 100 3.74
5
𝑆2 5 10 0 5 (0) 4.08 ⟵
𝑆3 7 6 0 50 3.09
Source 𝐷3 𝐷4 Supply
𝑆1 9 0 100
𝑆3 6 0 50
Demand 120 30
Table 3.2.15
∑𝐶 15
𝐶𝑖𝑗 = 𝑚𝑖𝑗 = 2 = 7.5 , where 𝑚 = 2
̅̅̅̅
1 1
𝜎𝐷3 = √ 𝑐𝑖𝑗 2 = √ (4.5) = 1.5
∑(𝑐𝑖𝑗 − ̅̅̅)
𝑚 2
𝝈𝑫𝟑 = 𝟏. 𝟓
SD (𝜎𝐷4 ) ⟹
𝝈𝑫𝟒 = 𝟎
Row difference using Standard Deviation
9 20.25
0 20.25
∑𝐶 9
𝐶𝑖𝑗 = 𝑛 𝑖𝑗 = 2 = 4.5 , where 𝑛 = 2
̅̅̅̅
1 1
𝜎𝑆1 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 = √ (40.5) = 4.5
𝑛 2
𝝈𝑺𝟏 = 𝟒. 𝟓
6 9
0 9
∑𝐶 6
𝐶𝑖𝑗 = 𝑖𝑗 = = 3 , where 𝑛 = 2
̅̅̅̅
𝑛 2
1 1
𝜎𝑆3 = √ ∑(𝑐𝑖𝑗 − ̅̅̅)
𝑐𝑖𝑗 2 = √ (18) = 3
𝑛 2
𝝈𝑺𝟑 = 𝟑
Source 𝐷3 𝐷4 Supply SD row
difference
30
𝑆1 9 0 100 (70) 4.5 ⟵
𝑆3 6 0 50 3
SD column 1.5 0
difference
Table 3.2.16
ITERATION 5
𝑆1 9 70 −
50
𝑆3 6 50 (0) −
SD column 1.5 ↑
difference
Table 3.2.17
Demand 70 (0)
SD column −
difference
Table 3.2.18
Source 𝐷1 𝐷2 𝐷3 𝐷4 supply
70 30
𝑆1 5 6 9 0 100
70 5
𝑆2 3 5 10 0 75
50
𝑆3 6 7 6 0 50
75
𝑆4 6 4 10 0 75
= 1465
3.3 Results and discussions
After obtaining an optimum solution by the proposed “Standard Deviation Method
(SDM)”, the obtained result is compared with the results obtained by Vogel’s Approximation
Methods (VAM) is shown in Table 3.3.1
As can be shown from Table 3.3.1, the SDM offers a better first fundamental feasible solution
in comparison to the outcomes produced by the conventional method VAM. The effectiveness
of SDM has also been examined through the resolution of several unbalanced transportation
issues are cost-minimized, and it is discovered that the SDM method produces the greatest
results overall.
ConClusion
CONCLUSION
The information supplied in this study and covered above provides an IBFS of the
unbalanced TP. According to the problem used to explain this method, SDM requires fewer
calculations and provides the best possible answer when compared to VAM. SDM gives an
immediate optimal solution or a better optimal solution with the fewest possible iterations to
the unbalanced transportation issue. The technique presented here guarantees a very good
solution to identify the IBFS of an unbalanced TP. Finally, it can be asserted that the SDM, by
assuring minimal transportation costs, may offer a wonderful First Basic Feasible Solution.
This will assist individuals who desire to maximise their profit while reducing their
transportation costs in achieving their objectives.
bibliography
BIBLIOGRAPHY