SR Task Report

The document provides a status update of various construction activities taking place across 16 different areas of a site from January 23rd to February 3rd. It details the start and end dates, current status, and any remarks for tasks such as reinforcement, shuttering, casting, plastering, and application of primers and waterproofing across collection tanks, oil chambers, control rooms, and other infrastructure. Many activities were completed on schedule but some remain pending, including road work, drain work, shed construction, and various fabrication tasks.

Uploaded by

Mobish Thomas
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
26 views

SR Task Report

The document provides a status update of various construction activities taking place across 16 different areas of a site from January 23rd to February 3rd. It details the start and end dates, current status, and any remarks for tasks such as reinforcement, shuttering, casting, plastering, and application of primers and waterproofing across collection tanks, oil chambers, control rooms, and other infrastructure. Many activities were completed on schedule but some remain pending, including road work, drain work, shed construction, and various fabrication tasks.

Uploaded by

Mobish Thomas
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 6

Started Date End Date Status Status

Sr.No Location and activity 27-01-2023 Remark 28-01-2023


1 Collection tank
Reinforcement of 3rd lift 23-01-2023 24-01-2023 Completed Completed
Fixing of Puddle flange 24-01-2023 24-01-2023 Completed Completed
shuttering of 3rd lift 25-01-2023 27-01-2023 Completed Completed
casting of 3rd lift 28-01-2023 28-01-2023 Completed Completed
Shuttering last 700 mm
fixation of insert plate
De-shuttering
Cleaning
Fixation of platform
Void filling
External plaster
Epoxy water proofing

2 Oil and Grease Chamber


Reinforcement of column 23-01-2023 23-01-2023 Completed Completed
shuttering of column 23-01-2023 24-01-2023 Completed Completed
Casting of column 25-01-2023 25-01-2023 Completed Completed
De-shuttering of column 27-01-2023 27-01-2023 Completed Completed
shuttering of slab 27-01-2023 27-01-2023 Completed Completed
Reinforcement of slab 27-01-2023 27-01-2023 Completed 1/28/2023 Completed
casting of slab 28-01-2023 28-01-2023 Completed Completed
casting of step- slab Completed Completed
Vertical steel binding Completed Completed
Shuttering of single pouring
De-shuttering
Cleaning
Erection of ladder
Void filling
External plaster
Epoxy water proofing

3 MBR Chamber
Reinforcement of 2nd lift 23-01-2023 23-01-2023 Completed Completed
Fixing of Puddle flange 24-01-2023 24-01-2023 Completed Completed
shuttering of 2nd lift 24-01-2023 25-01-2023 Completed Completed
casting of 2nd lift 25-01-2023 25-01-2023 Completed Completed
De-shuttering of 2nd lift 27-01-2023 28-01-2023 Completed Completed
Reinforcement of 3rd lift 27-01-2023 27-01-2023 Completed Completed
Fixing of Puddle flange 27-01-2023 27-01-2023 Completed Completed
shuttering of 3rd lift 28-01-2023 28-01-2023 Completed Completed
casting of 3rd lift 28-01-2023 28-01-2023 Completed Completed
Shuttering last 300 mm 29-01-2023 29-01-2023 Completed Completed
fixation of insert plate 30-01-2023 30-01-2023 Completed Completed
De-shuttering 01-02-2023 01-02-2023 Completed Completed
Plastrering of external wall 02-03-2023 Started
Cleaning 03-02-2023 Started
Fixation of platform Pending
Void filling Pending
External plaster Pending
Epoxy water proofing Pending

4 Equalisation tank
Plastering of outside wall 20-01-2023 23-01-2023 Completed Completed
Cleaning of inside of tank 25-01-2023 25-01-2023 Completed Completed
Core cutting of holes 26-01-2023 26-01-2023 Completed Completed
Application of Epoxy 24-01-2023 28-01-2023 Pending Pending

5 Intermediate tank
Core cutting 26-01-2023 26-01-2023 Completed Completed
Fixing of Remaing rungs Pending Pending
Application of Epoxy Pending Pending

6 Aeration tank
Plastering of outside of wall 19-01-2023 26-01-2023 Completed Completed
Placing of aeration tank platform 24-01-2023 24-01-2023 Completed Completed
Application of Epoxy 24-01-2023 28-01-2023 Started Started

7 Sludge Holding tank


Plastering of outside wall 27-01-2023 02-03-2023 Completed Completed
Application of Epoxy 24-01-2023 28-01-2023 Pending Pending
Fixing of platform & ladder 28-01-2023 28-01-2023 Pending Pending

8 Control & Panel room


Starter 28-01-2023 28-01-2023 Completed Completed
Masonry 29-01-2023 30/02/2023 Completed Completed
Casting of lintel 02-02-2023 02-02-2023 Completed Completed
Masonry 02-03-2023 Started Started
External Plaster 01-02-2023 Started Started
Internal Plaster 02-02-2023 Started Started
Door & Window
Flooring
Platform slab
Plumbing work
Electrification work

9 Road work 27-01-2023 Pending Pending


Void filling
Levelling & Compaction
Steel binding
VDF

10 Drain work Pending Pending


Slope verification
Excavation
PCC
Fixation of Hume pipe
Chambers and trench

11 Shed & pipe-rack Pedestal 27-01-2023 27-01-2023 Pending Pending


Excavation Pending Pending
Cleaning Pending Pending
PCC Pending Pending
Shuttering & Steel binding Pending Pending
Fixation of J-bolt and base plate Pending Pending
Casting Pending Pending

12 Fabrication work
Platform of Sludge holding tank 18-01-2023 22-01-2023 Completed Completed
Application of primer on Sludge 24-01-2023 24-01-2023
holding tank Completed Completed
column of the sheds 22-01-2023 27-01-2023 Completed Completed
Application of primer on column of 27-01-2023 30/01/2023
shed Completed Completed
Casting of shed column pedestal Pending Pending
Eracation of shed column Pending Pending

13 Site cleaning 28-01-2023 Pending Pending


14 Sump excavation 27-01-2023 28-01-2023 Completed Completed
15 Earth Pit Pending Pending
16 FRP chamber cover Pending Pending
17 Retaining wall Pending Pending
18
Remark