MEC 604 Linear Progrmming UNIT I
MEC 604 Linear Progrmming UNIT I
…..Eq (2)
…..Eq (3)
The cost of shipping a unit from the ith origin to the jth
destination is known for all combinations of origins and
destinations.
Steps Involved:
The total amount of raw material available per day for both products is
15751b. The total storage space for all products is 1500 ft2, and a
maximum of 7 hours per day can be used for production.
Developing LP Model (3)
Example Problem
All products manufactured are shipped out of the storage area at the end
of the day. Therefore, the two products must share the total raw material,
storage space, and production time. The company wants to determine
how many units of each product to produce per day to maximize its
total income.
Solution
• The company has decided that it wants to maximize its sale income,
which depends on the number of units of product I and II that it
produces.
• Therefore, the decision variables, x1 and x2 can be the number of units
of products I and II, respectively, produced per day.
Developing LP Model (4)
• The object is to maximize the equation:
Z = 13x1 + 11x2
subject to the constraints on storage space, raw materials, and
production time.
• Each unit of product I requires 4 ft2 of storage space and each unit of
product II requires 5 ft2. Thus a total of 4x1 + 5x2 ft2 of storage space is
needed each day. This space must be less than or equal to the
available storage space, which is 1500 ft2. Therefore,
4X1 + 5X2 1500
• Similarly, each unit of product I and II produced requires 5 and 3 1bs,
respectively, of raw material. Hence a total of 5xl + 3x2 Ib of raw
material is used.
Developing LP Model (5)
• This must be less than or equal to the total amount of raw material
available, which is 1575 Ib. Therefore,
5x1 + 3x2 1575
• Prouct I can be produced at the rate of 60 units per hour. Therefore, it
must take I minute or 1/60 of an hour to produce I unit. Similarly, it
requires 1/30 of an hour to produce 1 unit of product II. Hence a total of
x1/60 + x2/30 hours is required for the daily production. This quantity
must be less than or equal to the total production time available each
day. Therefore,
x1 / 60 + x2 / 30 7
or x1 + 2x2 420
• Finally, the company cannot produce a negative quantity of any
product, therefore x1 and x2 must each be greater than or equal to zero.
Developing LP Model (6)
• The linear programming model for this example can be summarized as:
…..Eq (4)
Graphical Solution to LP Problems (1)
Graphical Solution to LP Problems (2)
• An equation of the form 4x1 + 5x2 = 1500 defines a straight line in the
x1-x2 plane. An inequality defines an area bounded by a straight line.
Therefore, the region below and including the line 4x1 + 5x2 = 1500 in
the Figure represents the region defined by 4x1 + 5x2 1500.
• Same thing applies to other equations as well.
• The shaded area of the figure comprises the area common to all the
regions defined by the constraints and contains all pairs of xI and x2
that are feasible solutions to the problem.
• This area is known as the feasible region or feasible solution space.
The optimal solution must lie within this region.
• There are various pairs of x1 and x2 that satisfy the constraints such as:
Graphical Solution to LP Problems (3)
• Trying different solutions, the optimal solution will be:
X1 = 270
X2 = 75
• This indicates that maximum income of $4335 is obtained by producing
270 units of product I and 75 units of product II.
• In this solution, all the raw material and available time are used,
because the optimal point lies on the two constraint lines for these
resources.
• However, 1500- [4(270) + 5(75)], or 45 ft2 of storage space, is not used.
Thus the storage space is not a constraint on the optimal solution; that
is, more products could be produced before the company ran out of
storage space. Thus this constraint is said to be slack.
Graphical Solution to LP Problems (4)
• If the objective function happens to be parallel to one of the
edges of the feasible region, any point along this edge between
the two extreme points may be an optimal solution that
maximizes the objective function. When this occurs, there is no
unique solution, but there is an infinite number of optimal
solutions.
The total amount of raw material available per day for both products is
15751b. The total storage space for all products is 1500 ft2, and a
maximum of 7 hours per day can be used for production. The company
wants to determine how many units of each product to produce per
day to maximize its total income.
The Simplex Method (4)
Solution
Step 1: Convert all the inequality constraints into equalities by
the use of slack variables. Let:
…..Eq (4)
The Simplex Method (5)
…..Eq (5)
The Simplex Method (6)
…..Eq (6)
Substituting this equation into Eq. (5) yields the following new
formulation of the model.
…..Eq (7)
The Simplex Method (8)
From Eq. (C2), x2 can take on the value (5/3 )(315) = 525 if
x1 = S2 = 0
…..Eq (9)
…..Eq (5)
In any
iteration, a
variable that
has a
nonzero
value in the
solution is
called a
basic
variable.
Simplex Tableau for Maximization (2)
Step III: Identify the variable, called the leaving variable, which
will be changed from a nonzero to a zero value in the next
solution.
Simplex Tableau for Maximization (3)
Step IV: . Enter the basic variables for the second tableau. The
row sequence of the previous tableau should be maintained,
with the leaving variable being replaced by the entering variable.
Simplex Tableau for Maximization (4)
…….Eq. (1)
…….Eq. (2)
…….Eq. (3)
Complications in Simplex Method (8)
…….Eq. (4)
From Eq. (3):
Complications in Simplex Method (9)
…….Eq. (5)
Equality Constraint
An equality constraint has the following general form:
Equality Constraint
Because xj’ and xj’’ can have any nonnegative values their
difference (xj’ –xj’’) can have any value (positive or negative).
After substitution, the simplex method can proceed with just
nonnegative variables.
Complications in Simplex Method (13)
Degenerate Solution
If the number of basic variables is fewer than the number of
constraints in a solution, the solution is said to be degenerate.
A zero constant term for one or more basic variables in any
iteration of the simplex solution would be a clear indication of a
degenerate solution.
The normal simplex procedure cannot solve a degenerate
problem.
Advanced methods are available to solve degenerate problems.
Complications in Simplex Method (14)
Let y1, y2 and y3 represent the unit price of each unit of storage
space, raw materials, and production time, respectively.
The unit prices are in fact the income values of each unit of
resource to the N. Dustrious Company.
There are available 500 ft2 of storage space, 1575 lb of raw
materials, and 420 minutes of production time per day.
Thus the total income value (P) of all the available resources
may be expressed as follows :
P = 1500y1 + 1575y2 + 420y3
The objective of the problem is to minimize P subject to the
condition that the N. Dustrious Company will earn at least as
much income as when it operates the production facility itself.
Duality (3)
In addition, the unit prices y1, y2 and y3 must all be greater than
or equal to zero.
Duality (4)
…….Eq. (1)
The primal problem can now take the following standard form:
Duality (9)