ATL GI For Small Commercial Development
ATL GI For Small Commercial Development
Prepared for
CITY OF ATLANTA, GEORGIA
DEPARTMENT OF WATERSHED MANAGEMENT
APRIL 2014
Prepared by
AMEC Environment & Infrastructure
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Contents
1. Introduction and Approach...............................................................................................1
Background and Purpose ............................................................................................... 1
What are Small Commercial Green Infrastructure Practices? ......................................... 1
The Challenges of Applying GI Practices on Small Commercial Sites ............................ 2
2. Overview of the Manual ...................................................................................................4
3. Small Commercial Development Stormwater Management Procedures and
Requirements ..................................................................................................................5
General Requirements ................................................................................................... 5
Applicability .................................................................................................................... 5
Stormwater Concept Plan ............................................................................................... 6
4. Concept Plan Development .............................................................................................8
Concept Plan Step 1: Identify Site Constraints and Opportunities................................... 8
Concept Plan Step 2: Appropriate Selection and Application of GI Practices .................. 8
Concept Plan Step 3: Prepare Conceptual Site Layout Incorporating GI Practices ........10
Concept Plan Step 4: Schedule and Attend Stormwater Concept Plan and
Consultation Meeting .........................................................................................12
5. Design Process .............................................................................................................13
Standardized Design Criteria for 1 Inch RRv Capture on Small Commercial Sites ........13
Credits and Incentives ...................................................................................................13
Stormwater Design Step 1: Determine RRv Required for 1-Inch Rainfall Event .............13
Stormwater Design Step 2: Identify and Select Combination of GI Practices .................14
Stormwater Design Step 3: Size Selected GI Practice to Meet RRv Required ...............14
Stormwater Design Step 4: Calculate RRv Provided .....................................................15
Stormwater Design Step 5: Prepare Runoff Reduction Supplemental Design (if
necessary) .........................................................................................................15
Stormwater Design Step 6: Develop a Landscape Plan .................................................15
6. Plan Submittal Process .................................................................................................16
7. Green Infrastructure Practice Design Guidelines ...........................................................17
Bioretention
Infiltration Trenches
Bioswales
Permeable Pavement
Stormwater Planters
Subsurface Infiltration
Rainwater Harvesting/Cisterns
Green Roofs
Page i
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Tables
Table 1. Green Infrastructure on Small Commercial Sites: Challenges and Solutions ............... 3
Table 2. Appropriate GI Practice Selection by Contributing Drainage Area ............................... 9
Figures
Appendixes
Page ii
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page iii
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
In order to mitigate these impacts, the City of Atlanta requires, in accordance with Chapter 74, Article X,
Post-Development Stormwater Management, that stormwater management measures be utilized on
commercial sites for:
Reducing runoff and mimicking pre-development hydrology are two of the primary goals of a sustainable
stormwater management program. Managing individual, small storm events on small commercial sites
can help capture “first flush” pollutants and provide opportunities for reducing runoff volume.
The Post-Development Stormwater Management Ordinance adds a Runoff Reduction requirement that
promotes the use of Green Infrastructure (GI). The term “Runoff Reduction” means the interception,
evapotranspiration, infiltration, or capture and reuse of stormwater runoff. In the City of Atlanta, the
stormwater management system must be designed to reduce the volume of runoff generated by the first
1 inch of rainfall through the use of GI Practices. This volume must be retained on site and is not allowed
to run off.
To achieve these goals, the City of Atlanta requires stormwater management on small commercial
development and redevelopment properties, by including stormwater Better Site Design practices,
protecting natural areas and green space, reducing impervious cover, and leveraging existing natural
features for stormwater management use.
The City acknowledges that comprehensive GI stormwater design on small commercial sites can be
challenging. This document presents guidelines for selecting and installing the appropriate GI stormwater
management measures when developing or redeveloping a small commercial site that will create or
replace more than 500 square feet, but less than 5,000 square feet, of impervious surface.
Small commercial GI site design distributes appropriate GI Practices such as bioretention, infiltration
trenches, bioswales, permeable pavement, stormwater planters, subsurface infiltration, rainwater
harvesting/cisterns, and green roofs into the site landscape and infrastructure and interconnects them to
address the required Runoff Reduction volume. Figure 1 shows a comparison of traditional and GI
stormwater practices at a small commercial site.
Page 1
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page 2
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Challenge Solution
GI can compete for space Be creative with the site layout by incorporating GI within site landscape and
with a variety of existing parking. Utility-specific horizontal and vertical setbacks should be met.
utilities and infrastructure. When encroachment is unavoidable, additional protection or encasement of the
utility or protection of the infrastructure may be warranted. Construction
sequencing should be planned to minimize disruption of utility service.
Challenge Solution
Urban soils are often highly Many GI Practices are required to include a specified soil mix and integrate an
compacted and nutrient- underdrain system. Soil amendments can also be added to the in situ soils if
deficient, and limit the deemed necessary.
growth of plants and Soil can be tilled or excavated if more favorable conditions are identified deeper
infiltration of stormwater. within the soil profile.
Challenge Solution
Concentrated runoff and It is important for the design to incorporate energy dissipation and pre-treatment
potentially high sediment practices that will capture/collect sediment to prevent clogging.
loads can be expected in Highly tolerant and hardy plants should be selected.
ultra-urban environments.
Routine maintenance must be specified and provided.
Challenge Solution
Highly polluted runoff from Specify a lined stormwater planter, bioretention, green roofs, and/or rainwater
urban sites may infiltrate harvesting, which rely on evapotranspiration and reuse rather than infiltration.
into subsoils. Segregate the most polluted runoff and treat with special practices—both
structural and nonstructural (for example, special drains and spill cleanup
practices).
Challenge Solution
Small commercial sites will Bioretention areas in parking lots can typically deliver required stormwater
be limited in space to meet management and use plants that meet the 10% tree planting and landscaping
multiple zoning, landscape, requirement in accordance with the City’s Tree Ordinance (Sec. 158-30).
parking, and stormwater Permeable pavement can function both as a parking area and a stormwater
requirements. management facility, offering a space-saving solution on expensive real estate.
Challenge Solution
Urban GI is often subject to To address public visibility, a routine maintenance plan is required to keep GI
higher public visibility, Practices free of trash and debris.
greater trash loads, Signage is also recommended for GI Practices to educate and increase public
pedestrian use, vandalism, awareness.
and vehicular loads.
Low-stature plants and a more formalized planting plan can be used to blend
practices into surrounding landscapes.
Low fences, grates, or other measures can be installed to prevent damage from
traffic and pedestrians.
Challenge Solution
GI stormwater practices GI Practices can cost less to install and maintain than traditional stormwater
are perceived to be more practices. For example, cisterns can reduce the need for irrigation and even
expensive than traditional potable water. Native drought-tolerant plants can also eliminate the use of
stormwater practices. potable water and fertilizers. Often, less storm pipe, curb, and gutter are
needed in design.
Challenge Solution
Changing regulations This manual was created to help simplify and streamline the design process
require creative methods to and take the uncertainty out of the design.
reduce the volume of runoff
leaving the site.
Page 3
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
This guideline is meant to complement the use of the Georgia Stormwater Management Manual
Volume 2 (Blue Book) and the Coastal Stormwater Supplement (CSS). The CSS may be used to design
GI in lieu of this document, but must be used for sites that propose more than 5,000 square feet of
impervious area. The CSS describes a set of runoff reduction credits that can be applied to appropriate
site design conditions. These credits may be challenging to achieve for small commercial sites covered by
this document. In cases where such credit approaches could apply, they will be allowed in accordance
with guidance contained in the CSS.
Page 4
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Applicability
Establish: (1) if the site is exempt from stormwater requirements, (2) if this Small Commercial
Development Manual applies, or (3) if a full design submittal must be prepared following the Blue Book
and the CSS.
Page 5
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page 6
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page 7
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Constraints Include:
Opportunities Include:
• Modification of existing on-site elements Example Opportunities
such as landscape islands to function as
GI Practices
• Existing pervious or impervious areas on
site that can be restored or retrofitted
• Potential stormwater management
locations/ opportunities
• Prospective GI Practices to be utilized
• Treat an equivalent area of existing paved
surface runoff in lieu of new impervious
surface if drainage patterns allow
Page 8
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Not all GI Practices are suitable to accept runoff from all types of surfaces. See Table 2 for a summary of
acceptable conditions. Recommended drainage area size and specific ratios are addressed for each
practice in the individual GI Practice Design Guidelines found in Section 7, Green Infrastructure Practice
Design Guidelines, of this document.
As a rule of thumb, capture of the runoff from a 1-inch rainfall requires approximately 8 cubic feet of
storage per 100 square feet of contributing impervious drainage area.
Pre-Treatment
Each of the GI Practices requires some form of pre-treatment to prevent sediment, non-stormwater
pollutants, and trash from entering and/or clogging the system. The main goal of pre-treatment is to
capture floatables, debris, grease, oils, silt, and sediment where they can be easily cleaned through
regular maintenance, and before they can clog the system or pass underground. Some GI Practices
noted in Table 2 include pre-treatment filtering as part of the design, while others require additional
measures. If additional measures are warranted, proprietary mechanical GI Practices such as inlet sumps
or catch basin inserts can be employed upstream of the GI Practice to protect the long-term performance
of the practice. These require additional cost and long-term maintenance considerations.
Practice Requires
Loose Gravel or
(High Sediment
Pre -Treatment
Dumpster Pad
Pre-Treatment
Exposed Soil
Potential)**
Landscape
Pavement
Stabilized
Grass /
Recommended Size of
Roof
GI Practice Based on
GI Practice Contributing Area *
5% to 10% of Contributing
Bioretention Area
Infiltration 5% of Contributing Area
Trenches
5% of Contributing Area
Bioswales
Permeable
Pavement 25% of Contributing Area
Stormwater
Planter 5% of Contributing Area
Subsurface 5% to 10% of Contributing
Infiltration Area
Rainwater
Harvesting No Restriction
Page 9
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
1. Divert offsite drainage around the perimeter of the site or safely through the site to the maximum
extent practical.
2. Identify opportunities for Better Site Planning and Design Practices as defined in Chapter 7 of the
CSS, emphasizing design that minimizes disturbance to existing trees where practical.
3. Make full use of the site, integrating GI elements into landscaping areas, buffers, walkways, and
parking lots while adequately addressing appropriate protection of utilities and utility trenches
from the influence of storage inundation.
4. Use a combination of recognized GI Practice types including soil restoration, downspout
disconnection, and filter strips to intercept runoff near its source and provide filtering and
infiltration.
5. Eliminate storm pipes, manholes, and inlet structures in favor of interconnected bioretention cells,
curb turnouts, and permeable pavement where practical to provide collection, conveyance, and
pre-treatment.
6. Provide distributed storage and conveyance using bioswales in combination with appropriately
graded subsurface stone media or chamber reservoirs and underdrains.
7. Incorporate multiple routes for runoff to get into the integrated stormwater system and/or backup
routing when possible (for example, use both permeable pavement and curb turnouts to transport
stormwater to a yard inlet).
8. Avoid designs that place GI Practices at the bottom of dry detention ponds that provide volumetric
storage and may compromise the performance when inundated.
9. Reduce outflow volume, designing GI Practices to maximize evapotranspiration near the surface
and infiltration in suitable soils.
10. Provide overflow energy dissipation or bypass routing for runoff from storm events beyond design
sizing to avoid the potential for the GI Practice to be washed out.
11. Provide overflow connection to the existing drainage system, confirming that discharge does not
create adverse impacts downstream and that overflow routing has been provided.
Page 10
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page 11
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Concept Plan Step 4: Schedule and Attend Stormwater Concept Plan and
Consultation Meeting
It is highly recommended to schedule the stormwater consultation meeting prior to rezoning or planning
approval; however, this meeting must take place prior to the submittal of a building or land disturbance
permit application. Contact the Site Development office, 404-330-6249, to schedule a meeting time. A
copy of the Stormwater Concept Plan and Consultation Meeting Record form has been provided in
Appendix E.
Submittal Requirements
Required Concept Plan submittal information includes:
• Existing conditions
• Proposed limits of clearing and proposed impervious surfaces
• Soil infiltration rate information from soil surveys, on-site soils analysis, or infiltration test—
infiltration testing is required for previously developed or graded sites or sites with urban soil
types
• Natural Resources Inventory
• Stormwater management concept narrative that identifies Better Site Design Practices and
Techniques in accordance with Chapter 7 of the CSS
o Conservation of natural resources and features
o Lower-impact site design techniques
o Reduction of impervious cover
o Use of natural features for stormwater management
o Use of integrated GI Practices
• Conceptual Site Plan
Page 12
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
5. DESIGN PROCESS
Standardized Design Criteria for 1 Inch RRv Capture on Small Commercial
Sites
The Post-Development Stormwater Management Ordinance requires that stormwater management
systems be designed to capture the volume of runoff generated by the first 1 inch of rainfall through the
use of GI Practices. This volume, the RRv, must be retained on-site and is not allowed to run off.
RRv is calculated using the following formula from Section 5.2 of the CSS:
RRv = [(P)(Rv)(A)] / 12
Where:
RRv = runoff reduction volume (acre-feet)
P = target runoff reduction rainfall (inches)
Rv = volumetric runoff coefficient = 0.05+0.009(I)
A = site area (acres)
12 = unit conversion factor (inches/foot)
Where:
I = site imperviousness (%)
For small commercial sites, the RRv requirement has been simplified to pertain only to the 1 inch of
rainfall from the added and/or replaced impervious surface. It does not require consideration of runoff
from the overall site. This simplification applies only to small commercial sites creating, adding, and/or
demolishing and replacing between 500 and 5,000 square feet of impervious surface. Note that this is not
simply a net addition of impervious surface; rather, it can include impact to existing imperviousness.
Applicants have the choice to meet this requirement by following the practices in this document, or by
using the Blue Book and the CSS to design an appropriate stormwater management plan. Applicants are
strongly encouraged to utilize Better Site Design techniques outlined in Section 6 of the CSS to address
overall site conditions. When placing and sizing GI Practices, the designer must consider the total
impervious area draining to the practice to ensure appropriate functionality and long-term success.
A. Calculate created, added, and/or demolished and replaced impervious surface area from
proposed design plans.
B. If the applicable impervious surface is less than 500 square feet or exceeds 5,000 square feet,
this manual does not apply; instead, a full design submittal must be prepared following the Blue
Book and the CSS.
C. Identify the RRv Required from Figure 5 using the calculated impervious surface area.
Page 13
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
D. If the impervious area draining to the GI Practice exceeds 5,000 square feet, or if a more detailed
result is desired, the RRv Required can be calculated by using the following formula:
Area of contributing impervious surface × 0.08
Figure 5. RRv Required (in cubic feet) for 1 Inch of Rainfall for Small Commercial Sites in
Atlanta
A. Meet the intent and locations of practices proposed at the Stormwater Concept Plan Meeting
B. In combination, can meet RRv Required storage requirements based on Figure 5, GI Practice
sizing tables, and any allowable volume reduction credits
C. Stay within the contributing drainage area limits from Table 2
Page 14
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
B. Using proposed design plans, calculate the impervious area and delineate the flow path of runoff
from created, added, and/or demolished and replaced impervious surface area to each planned
GI Practice.
C. Confirm that contributing drainage areas to each of the GI Practices do not exceed those noted in
Section 3, Concept Development, Table 2.
A. Confirm that soil depth of the GI Practice is appropriate for selected vegetation.
B. Verify that vegetation can tolerate anticipated level of ponding in GI Practices.
Page 15
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
The plan submittal must include a clear delineation of contributing runoff areas and flow paths to each GI
Practice, with specific design details including site-specific contours, invert elevations, and cross sections
for each GI Practice.
Specific instructions should be included on the plans to avoid compaction of GI installations during
construction.
Page 16
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
• Bioretention
• Infiltration Trenches
• Bioswales
• Permeable Pavement
• Stormwater Planters
• Subsurface Infiltration
• Rainwater Harvesting/Cisterns
• Green Roofs
Page 17
SMALL COMMERCIAL GUIDE
CITY OF ATLANTA, GEORGIA
DEPARTMENT OF WATERSHED MANAGEMENT
BIORETENTION
A bioretention area is a planted landscape area designed to
receive and infiltrate or filter runoff. Bioretention systems are
flexible, adaptable, and versatile stormwater management
facilities that are effective at reducing runoff rates and pollutant
loads for highly urban development and redevelopment sites.
Because its shape is flexible, bioretention can be adapted to a
site by lowering conventional raised landscape areas to be able
to receive runoff. Bioretention areas typically consist of a flow
inlet structure, a pretreatment element, a temporary ponding area
with overflow, an engineered soil mix planting bed, vegetation,
and an outflow regulating structure (for example, an upturned
underdrain).
Location
Bioretention areas can be planted to be
When possible, place bioretention in areas of the site that: aesthetically pleasing and look like ‘typical’
landscape areas.
Have the most permeable soils.
Receive stormwater runoff primarily from impervious surfaces.
Are in parking lot landscape islands, small pockets of open areas, or side yard buffer areas.
Are 2 feet above the seasonally high water table, outside the public right of way unless appropriate
maintenance agreement is completed, and away from underground utility lines, septic fields, and
steep slope edges.
Are 10 feet from building foundations or public roadway subgrade unless the design includes
proper waterproofing techniques (such as an impermeable liner).
Page BioR-1
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Design
General
Bioretention storage includes up to three storage components (see detail on pages BioR-6 and -7):
ponded surface storage, storage within the bioretention soil, and (optionally) stone storage below
the bioretention soil (not shown). The size of the bioretention practice will vary depending on the
impervious surface draining to it, the design ponding depth above the soil, and the depth of the
amended soil and optional stone.
The geometric design of urban bioretention is flexible and is usually dictated by other site elements
and location constraints such as buildings, sidewalk widths, utility corridors, and retaining walls.
The surface area of the practice depends on the storage volume needed, but the loading ratio of
the impervious drainage area to the bioretention surface area should generally not exceed 10:1 to
20:1.
For sloped sites, verify that the bottom of bioretention areas is at a constant elevation or that
storage calculations take into consideration reduced storage due to slope. Use of bioretention
areas in series with appropriately designed staged overflows can maximize storage on sloped
sites.
Use of the upturned underdrain pipe as shown in Appendix B, Supplemental Green Infrastructure
Practice Details, will allow for a 100% RRv credit to be taken for the storage volume within the
bioretention practice even though an underdrain is provided.
Step-by-Step Sizing
1. Verify the RRv Required (in cubic feet) for the site as outlined in Section 5, Design Process.
2. Determine the total bioretention surface area (in square feet) by summing each area identified on
the concept plan.
3. The storage volume for bioretention is made up of two or three components calculated individually
and then summed: surface storage, bioretention soil storage, and (optionally) storage in a deeper
stone layer.
4. Use Table A and the surface area determined in Step 2 to find the surface storage volume for the
intended design ponding depth. Alternatively, calculate the storage volume from the Step 2 surface
area total by multiplying depth by surface area. The maximum allowable ponding depth for
bioretention is 12 inches.
BIORETENTION TABLE A
Bioretention Surface Storage Volumes (cubic feet)
Bioretention Typical
5x10 5x15 5x20 5x30 10x10 10x15 10x20 10x30 10x40 10x50 10x60 10x70 10x80 20x20 20x30 20x40 30x30
Dimensions (feet)
surface area (square feet) 50 75 100 150 100 150 200 300 400 500 600 700 800 400 600 800 900
Surface Storage at 6"
25 38 50 75 50 75 100 150 200 250 300 350 400 200 300 400 450
Depth (cubic feet)
Surface Storage at 9"
38 56 75 113 75 113 150 225 300 375 450 525 600 300 450 600 675
Depth (cubic feet)
Surface Storage at 12"
50 75 100 150 100 150 200 300 400 500 600 700 800 400 600 800 900
Depth (cubic feet)
Use the typical dimensions or surface area determined in Step 2 and Table B to find the storage
volume in the bioretention soil. Interpolate as necessary.
Page BioR-2
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
BIORETENTION TABLE B
Bioretention Soil Storage Volumes for all Infiltration Rates (cubic feet)
100% RRv Credit by Volume
Bioretention Typical
5x10 5x15 5x20 5x30 10x10 10x15 10x20 10x30 10x40 10x50 10x60 10x70 10x80 20x20 20x30 20x40 30x30
Dimensions (feet)
surface area (square feet) 50 75 100 150 100 150 200 300 400 500 600 700 800 400 600 800 900
Soil Storage at 18" Depth
24 36 48 72 48 72 96 144 192 240 288 336 384 192 288 384 432
(cubic feet)
Soil Storage at 24" Depth
32 48 64 96 64 96 128 192 256 320 384 448 512 256 384 512 576
(cubic feet)
Soil Storage at 36" Depth
48 72 96 144 96 144 192 288 384 480 576 672 768 384 576 768 864
(cubic feet)
note: table assumes a void ratio of 0.32
5. If additional stone storage is provided below the bioretention soil, see the Supplemental Stone
Storage Volume table in the Subsurface Infiltration Practice Design Guidelines. This storage
volume is added as the third component of the bioretention practice storage volume.
6. Combine the bioretention RRv storage volumes (surface storage plus bioretention soil storage plus
stone storage, if applicable) with the RRv for other BMPs as outlined in Section 5, Design Process,
and proceed with Design Process Step 4 summing treatment volumes to attain the RRv Provided.
Page BioR-3
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Ensure that the bottom of the bioretention practice is not compacted during construction, or is roto-
tilled to a depth of 6 inches to counteract compaction prior to bioretention soil placement. Tilling
3 inches of sand into the bottom is another acceptable method of counteracting compaction.
Outflow-Regulating Structure
Because of inconsistent infiltration on smaller commercial sites, incorporate an upturned underdrain
system that consists of washed gravel and perforated pipe (see typical detail) to provide an easier way
to tie into the existing stormwater infrastructure and additional storage and increased infiltration. The
design should include:
4- to 6-inch diameter perforated PVC pipe (AASHTO M252)
Upturned solid pipe 12 to 18 inches below the bottom of the soil surface
Vegetation
Vegetation commonly planted in bioretention areas includes native trees, shrubs, and other herbaceous
vegetation. When developing a landscape plan, choose vegetation that can stabilize soils and tolerate the
design stormwater runoff rates and volumes. Vegetation used in bioretention areas should be able to
tolerate both wet and dry conditions. Use of non-clay-backed sod on any grassed bioretention side slopes
is required instead of seeding.
Develop a specific landscape/planting plan for each bioretention area.
See Appendix D for a recommended plant list and example planting plans.
Maintenance
Routine operation and maintenance is essential to gain public acceptance of highly visible urban
bioretention areas and ensure properly functioning. A legally binding Inspection and Maintenance
agreement shall be completed. A sample Inspection and Maintenance Checklist is included in this
document.
Perform weeding, pruning, fertilizing, and trash removal as needed to maintain appearance.
Water the plants during drought conditions as necessary.
To ensure proper performance, check that stormwater infiltrates properly into the soil within
48 hours after a storm.
If excessive ponding time is observed on the surface or within the clean-out, undertake corrective
measures such as inspection for soil compaction and underdrain clogging.
A healthy and properly maintained bioretention area. The pretreatment area and overflow structure have been
properly maintained and are clear of debris.
Page BioR-4
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Example
A typical small commercial parking lot consisting of a “mounded” landscape island planted with turf
grass.
A small commercial parking lot utilizing the landscape island as a bioretention system.
Page BioR-5
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page BioR-6
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page BioR-7
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Inspector:
Date: Time:
Weather: Rainfall over previous 2-3 days?
Bioretention Location:
Bioretention Components:
Maintenance Inspection
Items Inspected Checked Needed Frequency
DEBRIS CLEANOUT Y N Y N
Bioretention and contributing areas clean of debris. Monthly
No dumping of yard wastes into bioretention. Monthly
Litter (trash, debris, etc.) have been removed. Monthly
VEGETATION
Page BioR-8
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
COMMENTS:
Dimension on as built:
Maintenance required as detailed above? Y/N Compliance with any other required conditions? Y / N
Comments:
Inspector’s signature:
Engineer/Agent’s signature:
Page BioR-9
SMALL COMMERCIAL GUIDE
CITY OF ATLANTA, GEORGIA
DEPARTMENT OF WATERSHED MANAGEMENT
INFILTRATION TRENCHES
Infiltration trenches are gravel-filled holding areas that receive,
store, and infiltrate stormwater runoff from roofs, driveways,
parking lots, and other contributing site surface areas. The
runoff is temporarily stored as it passes through the surrounding
stone bedding and infiltrates into the adjacent subsoil. An
overflow mechanism (surcharge pipe, connection to larger
infiltration area, etc.) is typically provided to ensure that excess
runoff is safely and efficiently conveyed to downstream
drainage systems or receiving waters.
Location
Choose a location keeping these factors in mind:
o Favorable infiltration areas on the site
o Areas that drain stormwater runoff primarily from
An Infiltration Trench can fit into tight
impervious surfaces spaces that are typical of small commercial
sites. Photo courtesy of:
o Small pockets of open areas, side yard buffer http://www.portlandoregon.gov/bes/article/
areas, and landscape beds 202883
o Level area to ensure that runoff is evenly distributed over the surface area
o Possible conflicts with site or building utilities
o Aesthetic considerations
Locate the infiltration trench 2 feet above the seasonally high water table; outside the public right-
of-way unless an appropriate maintenance agreement is completed; and away from utility lines,
septic fields, and steep slopes.
For sloped sites, verify that the bottom of the infiltration trench is at a constant elevation or that
storage calculations consider the reduced storage due to the sloped trench.
Terraced infiltration trenches in series with appropriately designed staged overflows can
maximize storage on a sloped site.
Infiltration trenches should be located at least 5 feet from building foundations and 10 feet from
buildings with basements and property lines; and away from potable water wells or public
roadway subgrade unless the design includes proper waterproofing techniques (such as an
impermeable liner).
Subsurface soils need to be appropriately loosened and tilled to enhance infiltration
characteristics.
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Design
General
The size of the infiltration trenches will vary, depending on the impervious surface draining to it
and the depth of the stone.
The actual geometric design of an infiltration trench is usually dictated by other site elements
such as buildings, sidewalk widths, utility corridors, and retaining walls.
As a rule of thumb, shallow infiltration trenches with a large surface area will perform better (and
require less maintenance) than a deep infiltration trench with a small surface area.
Surface area depends on storage volume, but should generally not exceed a maximum loading
ratio of 5 to 10% of the drainage area.
For sloped sites, verify that the bottom of the infiltration trench is at a constant elevation or that
storage calculations consider the reduced storage due to the sloped trench.
o Use of terraced infiltration trenches in series with appropriately designed staged overflows
can maximize storage on a sloped site.
The design should include appropriate pretreatment, such as:
o Vegetated filter strip with a minimum 10-foot length
o Vegetated buffer if the trench receives runoff from multiple directions
o Sediment forebay or similar sedimentation chamber
o Oil and grit separator if runoff is from highly polluted, urban hotspot areas
Exit velocities from pretreatment must be non-erosive and discharge to stone for the 2-year,
24-hour storm event
The infiltration trench design should include:
o Storage in an excavated trench backfilled with coarse washed stone, river rock, or pea
gravel, and lined with filter fabric on sides
o Filter layer composed of 3/8-inch pea gravel or sand separating the native soils and stone
storage
o One or more observation well consisting of 4-inch to 6-inch PVC pipe that extends to the
bottom of the infiltration trench
o Overflow relief drain
o Surface overflow routing
The infiltration trench specifications should meet the following requirements:
o Fully drains within 48 hours
o Depth is a maximum of 5 feet
o Bottom slope of trench is flat across its width and length or appropriately staged storage
overflow weirs have been designed
o Overflow channel to safely pass flows that exceed the storage capacity of the trench
Step-by-Step Sizing
1. Establish the RRv Required (in cubic feet) for the contributing impervious area using Figure 5 in
Section 5, Design Process.
2. Determine the dimensions and depth of the proposed infiltration trench.
3. Confirm the site infiltration rates per infiltration testing parameters in Appendix C.
4. Use the dimensions determined in Step 2, and Table A for infiltration rates greater than 0.25 inch
per hour or Table B for infiltration rates less than 0.25 inch per hour to find the storage volume
provided in the stone.
INFILTRATION TRENCH TABLE A
Stone Storage Volumes for Infiltration Rates greater than 0.25 inches/hour or with Upturned Underdrain (cubic feet)
100% RRv Credit by Volume
Infiltration Trench Typical
3x10 3x20 3x30 3x40 3x50 5x10 5x20 5x30 5x40 5x50 5x60 5x70 5x80 5x90 5x100 8x100 10x100
Dimensions (feet)
surface area (square feet) 30 60 90 120 150 50 100 150 200 250 300 350 400 450 500 800 1000
Stone Storage at 18" Depth
18 36 54 72 90 30 60 90 120 150 180 210 240 270 300 480 600
(cubic feet)
Stone Storage at 24" Depth
24 48 72 96 120 40 80 120 160 200 240 280 320 360 400 640 800
(cubic feet)
Stone Storage at 36"
36 72 108 144 180 60 120 180 240 300 360 420 480 540 600 960 1200
Depth (cubic feet)
Stone Storage at 48"
48 96 144 192 240 80 160 240 320 400 480 560 640 720 800 1280 1600
Depth (cubic feet)
Stone Storage at 60" Depth
60 120 180 240 300 100 200 300 400 500 600 700 800 900 1000 1600 2000
(cubic feet)
note: table assumes a void ratio of 0.40
INFILTRATION TRENCH TABLE B
Stone Storage Volumes for Infiltration Rates less than 0.25 inches/hour (cubic feet)
50% RRv Credit by Volume
Infiltration Trench Typical
3x10 3x20 3x30 3x40 3x50 5x10 5x20 5x30 5x40 5x50 5x60 5x70 5x80 5x90 5x100 8x100 10x100
Dimensions (feet)
surface area (square feet) 30 60 90 120 150 50 100 150 200 250 300 350 400 450 500 800 1000
Maintain
Routine operation and maintenance is essential to ensure proper functioning of infiltration trenches. The
following items should be included in the overall maintenance plan, and a legally binding Inspection and
Maintenance agreement shall be completed. A sample Inspection and Maintenance Checklist is included
in this document.
Routinely inspect and clean out gutters and catch basins to reduce sediment load to infiltration
trenches.
Clean intermediate sediment trap sumps, replace filters, and otherwise clean pretreatment areas
in directly connected systems. At minimum, cleaning should occur quarterly.
Routinely examine to ensure that inlet and outlet devices are free of debris and operational.
After storm events, evaluate the drain-down time of the infiltration trenches by measuring the
standing water in the observation well to ensure the drain-down time of 48 hours or less.
Examples
Capped
Observation
Well
1
Sand Bottom
3
2
Figures depicting: (1) a subsurface infiltration facility cross section, (2) a facility
during construction, and (3) a facility after construction is complete. Photos
courtesy of: http://www.csc.temple.edu/t-vssi/BMPSurvey/delaware_countycc.htm
and http://www.esf.edu/ere/endreny/GICalculator/InfiltrationIntro.html
INTEGRITY OF SYSTEM
COMMENTS:
Dimension on as built:
Maintenance required as detailed above? Y / N Compliance with other required conditions? Y/N
Comments:
Inspector’s signature:
Engineer/Agent’s signature:
BIOSWALES
A bioswale is a vegetated, open, conveyance channel,
filled with an engineered soil mix and planted with a
combination of grasses and other herbaceous plants,
shrubs, or trees. Bioswales are essentially linear
bioretention areas that are designed to capture and
temporarily store runoff in the amended soils and
provide infiltration and water quality treatment. Check
dams maximize these functions by creating ponding
areas where settling and infiltration can occur.
Commercial facilities often have landscaped or
grassed areas that can also serve as drainage
pathways and infiltration areas. A bioswale is a
practical replacement for stormwater conveyance by
roadway median strips and parking lot curb and gutter. Terraced bioswale accepts runoff from roof drains.
Grade control structures allow infiltration
Klaus Building - Georgia Tech – Atlanta, Georgia
Location
Bioswales should be located in areas with slopes about 0.5%, but steeper areas can be terraced
to provide staged conveyance.
A minimum of 2 feet is required between the bottom of the practice and the seasonally high water
table.
The practice can be utilized within parking lot islands, median strips, and side yard buffer areas.
Locate the practice at least 5 feet from building foundations, and 10 feet from buildings with
basements and property lines; outside the public right of way unless an appropriate maintenance
agreement is completed; and away from utility lines, septic fields, and steep slopes.
Curb cut entrance to bioswale. Photo courtesy of Bioswales can function as a substitute for parking lot
www.americanforests.org. curb and gutter systems.
Page BioS-1
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Design
Bioswales can include up to three storage components, depending on the design: ponded surface
storage, storage within the bioswale soil, and optional stone storage below the bioswale soil (not
shown in the attached detail). The dimensions of the bioswale practice will vary, depending on the
impervious surface area draining to it, the length of the conveyance across the site, the ponding
depth above the soil, and the depth of the amended soil and optional stone.
If bioswales are the principal conveyance from the site, they should be sized to convey peak
discharge runoff from the contributing area without eroding the bioswale.
Consider the site’s natural topography when choosing the location for the bioswale. Runoff from
impervious areas should be easily directed to the practice. The recommended drainage area to a
bioswale is 5% of contributing drainage area.
Investigate the feasibility of infiltration according to conditions in the area proposed for the
bioswale.
The actual geometric design of bioswales is usually dictated by other site elements such as
buildings, sidewalk widths, utility corridors, and retaining walls.
o Typical dimensions for a bioswale should be 2 to 8 feet wide with 3:1 (H:V) side slopes
(maximum 2:1).
Pretreatment is preferred and can extend the life of the bioswale. For sizing and design
information see Appendix B, Supplemental Green Infrastructure Practice Details. The following
forms of pretreatment and energy dissipation are recommended:
o Grass filter strip
o Forebay
o River cobble diaphragm or drop inlet with thick filtering vegetation
The slope along the length of the bottom of the bioswale should not exceed 0.5%. If the slope is
greater than 0.5%, then lined check dams or a series of terraced subsoil steps should be used to
make the effective slope 0.5% or less, to allow for maximum infiltration.
Bioswale systems consist of:
o An open conveyance channel
o A filter bed of engineered soil mix that is a minimum of 36 inches deep. Engineered soil shall
consist of the following:
Texture: Sandy loam or loamy sand
Sand Content: 60%–70% clean, washed sand (dry weight basis)
Clay: not greater than 10% (dry weight basis)
Topsoil: 8%–12% (dry weight basis)
Compost: 5%–10% (dry weight basis)
Infiltration Rate: 0.5 inch/hour minimum, preferred 1-2 inch/hour
o Gravel and optional perforated pipe underdrain system (see typical detail).
o A ponded depth of 9 inches or less is recommended (maximum 12 inches) with a drain time
less than 48 hours.
Bioswales must:
o Hold and slowly convey the design storage (1 inch) without erosion
o Safely convey the overbank flood protection rainfall event (for example, a 25-year, 24-hour
event) or have a flow splitter to divert excess runoff around the practice
Page BioS-2
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Step-by-Step Sizing
1. Verify the RRv Required (in cubic feet) for the site as outlined in Section 5, Design Process, of
this document.
2. Determine the total bioswale surface area (in square feet) by summing each area identified on the
concept plan.
The storage volume for bioswales can consist of multiple components calculated individually and
then summed: surface storage, bioswale soil storage, and (optional) storage in a deeper stone
layer.
3. Confirm the site infiltration rates per infiltration testing parameters in Appendix C.
4. Use Table A and surface area determined in Step 2 to find the surface storage volume for the
intended design ponding depth. Alternatively, calculate the storage volume from the Step 2
surface area total by multiplying depth by the surface area. The maximum allowable ponding
depth for bioswales is 12 inches.
BIOSWALE TABLE A
Bioswale Surface Storage Volumes (cubic feet)
Bioswale Typical
3x10 3x20 3x30 3x40 3x50 5x10 5x20 5x30 5x40 5x50 5x60 5x70 5x80 5x90 5x100 8x100 10x100
Dimensions (feet)
surface area (square feet) 30 60 90 120 150 50 100 150 200 250 300 350 400 450 500 800 1000
Surface Storage at 6"
15 30 45 60 75 25 50 75 100 125 150 175 200 225 250 400 500
Depth (cubic feet)
Surface Storage at 9"
23 45 68 90 113 38 75 113 150 188 225 263 300 338 375 600 750
Depth (cubic feet)
5. Optional use of the upturned pipe underdrain as shown in Appendix B, Supplemental Green
Infrastructure Practice Details, will allow a 100% RRv credit to be taken for the storage volume
within the bioswale practice for soils with less than 0.25 inch/hour infiltration.
6. Use the typical dimensions or surface area determined in Step 2 and Table B for infiltration rates
greater than 0.25 inch/hour or a bioswale with an upturned underdrain pipe. Use Table C for
infiltration rates less than 0.25 inch/hour with an underdrain to find the storage volume in the
bioswale soil. Interpolate as necessary.
BIOSWALE TABLE B
Bioswale Soil Storage Volumes for Infiltration Rates greater than 0.25 inches/hour or with Upturned Underdrain (cubic feet)
100% RRv Credit by Volume
Bioswale Typical
3x10 3x20 3x30 3x40 3x50 5x10 5x20 5x30 5x40 5x50 5x60 5x70 5x80 5x90 5x100 8x100 10x100
Dimensions (feet)
surface area (square feet) 30 60 90 120 150 50 100 150 200 250 300 350 400 450 500 800 1000
Page BioS-3
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
BIOSWALE TABLE C
Bioswale Soil Storage Volumes for Infiltration Rates less than 0.25 inches/hour (cubic feet)
50% RRv Credit by Volume
Bioswale Typical
3x10 3x20 3x30 3x40 3x50 5x10 5x20 5x30 5x40 5x50 5x60 5x70 5x80 5x90 5x100 8x100 10x100
Dimensions (feet)
surface area (square feet) 30 60 90 120 150 50 100 150 200 250 300 350 400 450 500 800 1000
Soil Storage at 18" Depth
7 14 22 29 36 12 24 36 48 60 72 84 96 108 120 192 240
(cubic feet)
Soil Storage at 24" Depth
10 19 29 38 48 16 32 48 64 80 96 112 128 144 160 256 320
(cubic feet)
Soil Storage at 36" Depth
14 29 43 58 72 24 48 72 96 120 144 168 192 216 240 384 480
(cubic feet)
note: table assumes a void ratio of 0.32
7. If additional stone storage is provided below the bioswale soil, see the Supplemental Stone
Storage Volume table in the Subsurface Infiltration Practice section. This storage volume is
added as the third component of the bioswale practice storage volume.
Combine the bioswale RRv storage volumes (surface storage plus bioswale soil storage plus stone
storage, if applicable) determined above with other GI Practices as outlined in Section 5, Design Process,
and proceed with Design Process Step 4, summing treatment volumes to attain RRv Provided.
Vegetation
Vegetation commonly planted in bioswale areas includes native trees, shrubs, and other herbaceous
vegetation. When developing a landscape plan, choose vegetation that can stabilize soils and tolerate the
design stormwater runoff rates and volumes. Vegetation used in bioswale areas should be able to tolerate
both wet and dry conditions. Use of non-clay-backed sod on any grassed bioswale side slopes is required
instead of seeding.
Maintain
Routine operation and maintenance is essential to gain public acceptance of highly visible urban bioswale
areas and ensure properly functioning. A legally binding Inspection and Maintenance Agreement shall be
completed. A sample Inspection and Maintenance Checklist is included in this document.
Perform weeding, pruning, fertilizing, and trash removal as needed to maintain appearance.
Water the plants during drought conditions as necessary.
To ensure proper performance, check that stormwater infiltrates properly into the soil within
48 hours after a storm.
If excessive ponding time is observed on the surface or within the clean-out, undertake corrective
measures such as inspection for soil compaction and underdrain clogging.
Page BioS-4
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Examples
.
Page BioS-5
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
BEFORE: A typical small commercial parking lot consisting of a “mounded” landscape island planted
with turf grass.
AFTER: A small commercial parking lot island converted to a bioswale utilizing sheet flow from
impervious surface to a filter strip.
Page BioS-6
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page BioS-7
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page BioS-8
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page BioS-9
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page BioS-10
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Inspector:
Date: Time:
Weather: Rainfall over previous 2-3 days?
Swale Location:
Bioswale Components:
Maintenance Inspection
Items Inspected Checked Needed Frequency
DEBRIS CLEANOUT Y N Y N
Swale and contributing areas clean of debris. Monthly
No dumping of yard wastes into swale. Monthly
Litter (trash, debris, etc.) have been removed. Monthly
VEGETATION
Page BioS-11
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
COMMENTS:
Dimension on as built:
Maintenance required as detailed above? Y/N Compliance with other conditions? Y/N
Comments:
Inspector’s signature:
Engineer/Agent’s signature:
Page BioS-12
SMALL COMMERCIAL GUIDE
CITY OF ATLANTA, GEORGIA
DEPARTMENT OF WATERSHED MANAGEMENT
PERMEABLE PAVEMENT
Permeable pavement provides the structural support of
conventional pavement, but allows stormwater to drain directly
through the load-bearing surface into the underlying stone base
and soils, intercepting and reducing stormwater runoff. During a
rain event, stormwater flows through the porous surface, drains
into the crushed stone sub-base beneath the pavement, and
remains stored until stormwater can infiltrate into the soil or
outlet through the underdrain. There are permeable varieties of
asphalt, concrete, and interlocking pavers. Permeable
pavement systems are suitable for any type of small Permeable paver parking stalls add variety to
commercial development. They are especially well-suited for parking lot landscape. English Park, Atlanta
parking lots, walkways, and sidewalks. Proper training of
owners, users, and maintenance staff will help to prolong the life of the permeable pavement.
Location
The location of this GI Practice is most often dictated by site design factors including building
location, drive entrances, internal circulation, and landscaping requirements. Choose a location
keeping these factors in mind:
o Areas with lower traffic volumes such as parking spaces are preferable.
o Permeable pavement is most appropriate for areas that are relatively flat (generally less than
a 5% slope).
o Avoid areas with drainage from adjacent erodible areas with the potential for heavy sediment
loads.
o Place in an area not likely to receive runoff from dumpster pads, materials storage, or
process areas.
o Do not use this practice where hazardous materials are handled or stored.
Locate the bottom of the pavement section 2 feet
above the seasonally high water table, outside the
public right of way unless an appropriate maintenance
agreement is completed (see Appendix E, Sample
Forms), and away from utility lines, septic fields, and
steep slopes.
Provide proper waterproofing techniques (such as an
impermeable liner) for permeable pavement located
next to buildings; otherwise, permeable pavement
shall be located 10 feet from building foundations. Permeable concrete used in a roadway
application. Felder Avenue, Atlanta
Page PP-1
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Design
General
Key elements of the design include:
o A permeable surface with a high infiltration rate
o Bedding material, if required by manufacturer’s
recommendations
o An open-graded, aggregate base choker or filter
course, used to stabilize the stone surface for
the pavement material
o A stone sub-base suitable for design traffic loads
o An uncompacted, level sub-grade (to allow
infiltration of stormwater)
o Positive overflow to prevent system flooding
Infiltration tests are required (two per GI Practice).
Required surface area depends on the desired storage volume, but should generally not exceed
a maximum loading ratio of 25% of the contributing drainage area.
Permeable pavement can be used on most travel surfaces with slopes less than 5%.
The depth of the stone sub-base should be designed based on stormwater management
objectives, total drainage area, traffic load, and soil characteristics. At a minimum, the gravel and
perforated underdrain system shall be sized to meet traffic loading requirements for the selected
permeable material.
For sloped sites, verify that the bottom of the stone sub-base is at a constant elevation or that
storage calculations consider reduced storage due to the sloped bottom.
o Use of staged storage cells in series with appropriately designed staged overflows can
maximize storage on a sloped site.
Step-by-Step Sizing
1. Establish the RRv Required (in cubic feet) for the contributing impervious area using Figure 5 in
Section 5, Design Process.
2. Determine the dimensions and depth of the proposed infiltration trench.
3. Confirm the site infiltration rates per infiltration testing parameters in Appendix C.
Page PP-2
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
4. Use the dimensions determined in Step 2, and Table A for infiltration rates greater than 0.25 inch
per hour, or Table B for infiltration rates less than 0.25 inch per hour to find the storage volume
provided in the stone.
PERMEABLE PAVEMENT STONE STORAGE TABLE A
Stone Storage Volumes for Infiltration Rates greater than 0.25 inches/hour (cubic feet)
100% RRv Credit by Volume
Stone Storage Typical
5x10 5x15 5x20 5x30 10x10 10x15 10x20 10x30 10x40 10x50 10x60 10x70 10x80 20x20 20x30 20x40 30x30
Dimensions (feet)
surface area (square feet) 50 75 100 150 100 150 200 300 400 500 600 700 800 400 600 800 900
PEMEABLE PAVEMENT STONE STORAGE TABLE B
Stone Storage Volumes for Infiltration Rates less than 0.25 inches/hour (cubic feet)
50% RRv Credit by Volume
Stone Storage Typical
5x10 5x15 5x20 5x30 10x10 10x15 10x20 10x30 10x40 10x50 10x60 10x70 10x80 20x20 20x30 20x40 30x30
Dimensions (feet)
surface area (square feet) 50 75 100 150 100 150 200 300 400 500 600 700 800 400 600 800 900
Stone Storage at 12" Depth
10 15 20 30 20 30 40 60 80 100 120 140 160 80 120 160 180
(cubic feet)
Stone Storage at 18" Depth
15 23 30 45 30 45 60 90 120 150 180 210 240 120 180 240 270
(cubic feet)
Stone Storage at 24" Depth
20 30 40 60 40 60 80 120 160 200 240 280 320 160 240 320 360
(cubic feet)
Stone Storage at 36" Depth
30 45 60 90 60 90 120 180 240 300 360 420 480 240 360 480 540
(cubic feet)
Stone Storage at 48" Depth
40 60 80 120 80 120 160 240 320 400 480 560 640 320 480 640 720
(cubic feet)
note: table assumes a void ratio of 0.40
Pretreatment
Contributing drainage areas should have proper pretreatment design to filter debris and sediment
that may clog the permeable pavement system. Appropriate pretreatment measures can be found
in Appendix B, Supplemental Green Infrastructure Practice Details, and include:
o A grass filter strip
o Forebay
o A river cobble diaphragm or thick filtering vegetation
Page PP-3
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Outflow-Regulating Structure
Because of inconsistent infiltration conditions on smaller commercial sites, incorporate an
upturned underdrain system that consists of washed gravel and perforated pipe (see Appendix B,
Supplemental Green Infrastructure Practice Details) to provide an easier way to tie into the
existing stormwater infrastructure and additional storage and increased infiltration. The design
should include:
o Aggregate: 8-inch layer ASTM D448 Size No. 57 washed stone and should be separated by
a thin 2- to 4-inch layer of choker stone (ASTM D 448 size No. 8, 3/8-inch to 1/8-inch or
ASTM D 448 size No. 89, 3/8 inch to 1/16 inch)
o Perforated pipe: 4- to 6-inch perforated PVC (AASHTO M 252), 3/8-inch perforation spaced
6 inches on center, minimum slope of 0.5% (no sock pipes shall be permitted)
o Nonwoven separation geotextile utilized on the side surface interfaces ONLY
Upturned “S” solid underdrain pipe below the bottom of the surface may be used to receive full
RRv credit.
Native soils along the bottom of the permeable pavement system should be tilled or scarified to 3
to 4 inches prior to placement of choker stone.
No mulch or landscaping material shall be stored on the pavement areas.
Pavement should be tested after construction for adequate infiltration.
o Make sure the permeable pavement surface is even, runoff evenly spreads across it, and the
storage bed drains within 48 hours.
Maintain
Permeable pavement systems require regular maintenance to extend their life. A legally binding
Operation and Maintenance Agreement should be created. A sample Inspection and Maintenance
Checklist is included in this document.
Pavement should be inspected to ensure it is clear of sediment and debris post-construction,
annually, and after large storm events.
Vacuum-sweep the permeable pavement surface annually.
Dirt and sediment that is ground in repeatedly by tires can lead to clogging. Trucks or other heavy
vehicles should be prevented from tracking or spilling dirt onto the pavement.
Inspect for deterioration or spalling annually and rehabilitate the system per O&M guidelines.
All construction or hazardous materials carriers should be prohibited from entering a permeable
pavement lot.
During winter, abrasives such as sand or cinders shall not be applied on or adjacent to the
permeable pavement.
Salt is not recommended for use as a de-icer on permeable pavement. Nontoxic, organic de-icers
applied either as blended, magnesium chloride-based liquid products or as pretreated salt are
preferable. De-icing materials should be used in moderation.
Page PP-4
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Fine aggregate allows water to infiltrate in gaps Permeable asphalt (first developed in the 1970s)
between interlocking pavers. Pavers are well-suited to consists of standard bituminous asphalt in which
plazas, patios, and small parking areas where fines have been screened and reduced, allowing
aesthetics are important. Photo courtesy of water to pass through small voids. Photo courtesy of
www.nrdc.org. www.socwisconsin.org.
Page PP-5
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Examples
Page PP-6
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page PP-7
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page PP-8
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Inspector:
Date: Time:
Weather: Rainfall over previous 2-3 days?
Page PP-9
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
COMMENTS:
Dimension on as built:
Maintenance required as detailed above? Y/N Compliance with other conditions? Y/N
Comments:
Inspector’s signature:
Engineer/Agent’s signature:
Page PP-10
SMALL COMMERCIAL GUIDE
CITY OF ATLANTA, GEORGIA
DEPARTMENT OF WATERSHED MANAGEMENT
STORMWATER PLANTERS
Stormwater planters are contained landscape areas
designed to receive stormwater runoff from paved
surfaces. Stormwater planters consist of a planter
box that can either be lined or unlined, filled with an
engineered soil mix and planted with trees,
perennials, and shrubs. The top of the soil in the
planter is lower in elevation than the surrounding
pavement to allow runoff to flow into the planter. An
underdrain is used when necessary to route excess
runoff to the storm drain system. Stormwater
planters manage stormwater by providing storage,
infiltration, and evapotranspiration of runoff.
Page SP-1
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
roadway subgrade unless the design includes proper waterproofing techniques (such as an
impermeable liner).
Subsurface soils need to be appropriately loosened and tilled to enhance infiltration
characteristics.
Proper waterproofing techniques or an impermeable liner are necessary for planters located next
to buildings, in highly urban areas within utility easements, in soils with poor infiltration rates, in
areas with a high water table, and above contaminated soils.
o Infiltration is not appropriate for sites with contaminated soils, because it could impact pollutant
migration.
Design
General
The geometric design of subsurface infiltration
is usually dictated by other site elements such
as buildings, sidewalk widths, utility corridors,
and retaining walls.
Key elements of the design include:
o An inlet or opening in the curb to direct
stormwater into the planter
o Concrete or prefabricated walls that form
the vertical sides of the planter
o Planter bioretention soils of an
appropriate depth to support planned
landscape plants and/or trees. The
minimum depth is 24 inches, and
36 inches is required where trees are specified.
o A stone drainage bed for stormwater storage and infiltration, separated from the bioretention
soil above and the subgrade below with a choker stone course or filter fabric.
o An uncompacted, level sub-grade (to allow infiltration of stormwater)
o Overflow outlet to prevent system flooding
o Underdrain or upturned overflow pipe in poor soil conditions
o Impermeable liner in conditions that do not allow for infiltration.
o Optional check dams for sloped beds
Waterproofed or lined planters will receive credit for 50% of the storage provided to meet the
RRv.
The length of flow path of the contributing drainage area should be less than:
o 150 feet for pervious drainage areas
o 75 feet for impervious drainage areas
If flow path length cannot be met, then bioretention is recommended.
Step-by-Step Sizing
1. Verify the RRv Required (in cubic feet) for the site as outlined in Section 5, Design Process.
Page SP-2
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
2. Determine the total planter surface area (in square feet) by summing each area identified on the
concept plan.
Storage Volume for planters is made up of two or three components calculated individually and
then summed: surface storage, planter soil storage, and (optionally) storage in a deeper stone
layer.
3. Confirm the site infiltration rates per infiltration testing parameters in Appendix C.
4. Use Table A and the surface area determined in Step 2 to find the surface storage volume for the
intended design ponding depth. Alternatively, calculate the storage volume from the Step 2
surface area total by multiplying depth times surface area. The maximum allowable ponding
depth for planters is 12 inches.
STORMWATER PLANTER TABLE A
Planter Surface Storage Volumes (cubic feet)
Planter Typical Dimensions
5x10 5x15 5x20 5x30 10x10 10x15 10x20 10x30 10x40 10x50 10x60 10x70 10x80 20x20 20x30 20x40 30x30
(feet)
surface area (square feet) 50 75 100 150 100 150 200 300 400 500 600 700 800 400 600 800 900
Surface Storage at 6"
25 38 50 75 50 75 100 150 200 250 300 350 400 200 300 400 450
Depth (cubic feet)
Surface Storage at 9"
38 56 75 113 75 113 150 225 300 375 450 525 600 300 450 600 675
Depth (cubic feet)
Surface Storage at 12"
50 75 100 150 100 150 200 300 400 500 600 700 800 400 600 800 900
Depth (cubic feet)
5. Optional use of the upturned pipe underdrain as shown in Appendix B, Supplemental Green
Infrastructure Practice Details, will allow for 100% RRv credit to be taken for the storage volume
within the planter practice for soils with less than 0.25 inch/hr infiltration or for planters with an
impermeable liner.
STORMWATER PLANTER TABLE B
Planter Bioretention Soil Storage Volumes for Infiltration Rates greater than 0.25 inches/hr or with Upturned Underdrain
(lined or unlined)
100% RRv Credit by Volume
Planter Typical Dimensions
5x10 5x15 5x20 5x30 10x10 10x15 10x20 10x30 10x40 10x50 10x60 10x70 10x80 20x20 20x30 20x40 30x30
(feet)
surface area (square feet) 50 75 100 150 100 150 200 300 400 500 600 700 800 400 600 800 900
6. To find the storage volume in the planter bioretention soil, use the typical dimensions or surface
area determined in Step 2 and Table B for infiltration rates greater than 0.25 inch/hour or a
planter with an upturned pipe underdrain, or Table C for infiltration rates less than 0.25 inch/hour
without an underdrain or with an impermeable liner. Interpolate as necessary.
Page SP-3
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
STORMWATER PLANTER TABLE C
Planter Bioretention Soil Storage Volumes for Infiltration Rates less than 0.25 inches/hr or with Impermeable Liner (cubic feet)
50% RRv Credit by Volume
Planter Typical Dimensions
5x10 5x15 5x20 5x30 10x10 10x15 10x20 10x30 10x40 10x50 10x60 10x70 10x80 20x20 20x30 20x40 30x30
(feet)
surface area (square feet) 50 75 100 150 100 150 200 300 400 500 600 700 800 400 600 800 900
Soil Storage at 24" Depth
16 24 32 48 32 48 64 96 128 160 192 224 256 128 192 256 288
(cubic feet)
Soil Storage at 36" Depth
24 36 48 72 48 72 96 144 192 240 288 336 384 192 288 384 432
(cubic feet)
Soil Storage at 48" Depth
32 48 64 96 64 96 128 192 256 320 384 448 512 256 384 512 576
(cubic feet)
note: table assumes a void ratio of 0.32
7. If additional stone storage is provided below the bioretention soil, see the Stone Storage Volume
table in the Subsurface Infiltration Practice Section. This storage volume is added as the third
component of the stormwater planter practice storage volume.
8. Combine the stormwater planter RRv storage volumes (surface storage plus planter soil storage
plus stone storage, if applicable) determined above with other practices as outlined in Section 5,
Design Process, and proceed with Design Process Step 4 summing treatment volumes to attain
the RRv Provided.
Inlet/Flow-Regulating Structures and Pretreatment Elements
Specific inlet types and energy dissipation upstream of
the planter area are recommended to filter out
sediment, trash, floatables, and pollutants.
The following inlet types are recommended.
For sizing and design information see
Appendix B, Supplemental Green
Infrastructure Practice Details.
o Sheet flow off a depressed curb with a
3-inch drop
o Curb cuts into the planter area
o Grates or trench drains that convey flows
across a sidewalk from the curb or
downspouts Stormwater planters can be integrated into a highly
urban area and provide aesthetic appeal.
The following forms of pretreatment and
energy dissipation are recommended. For
sizing and design information see Appendix B, Supplemental Green Infrastructure Practice
Details.
o Grass filter strip
o Forebay
o River cobble diaphragm or thick filtering vegetation
Temporary Surface Storage (Ponding)
Surface ponding depth can range from 6 inches to 12 inches (9 inches is suggested).
A maximum drain-down time of 48 hours is required for the planter.
In areas with steeper slopes, the addition of a check dam works to slow the runoff which allows
increased infiltration. Check dams can be placed in series to increase their effectiveness.
Page SP-4
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Allow a minimum 2 inches of freeboard between the elevation of the maximum ponding depth and
top of planter.
If a liner is used, only 50% RRv credit will be provided for surface ponding storage.
Engineered Soil Mix Planting Bed
Use an appropriate mulch layer (2 to 4 inches of fine, shredded hardwood) and avoid lighter
mulch material that may float. Pea gravel can be used as an alternative to mulch.
Install an appropriate engineered soil mix at a minimum depth of 18 inches for plants and a
minimum of 3 feet for trees. Protect soil from being compacted by construction traffic during or
after placement. Alternate engineered soil mixes will be considered with appropriate tests and
documentation.
o Texture: Sandy loam or loamy sand
o Sand Content: 60%–70% clean, washed sand (dry weight basis)
o Clay: Not greater than 10% (dry weight basis)
o Topsoil: 8%–12% (dry weight basis)
o Compost: 5%–10% (dry weight basis)
o Infiltration Rate: 0.5 inch/hour minimum, preferred 1-2 inch/hour
Protect the bottom of the planter from compaction during construction, or till soils to a depth of
6 inches to counteract compaction prior to planter soil placement. Tilling 3 inches of sand into the
bottom is another acceptable method of counteracting compaction.
Outflow-Regulating Structure
Because of inconsistent infiltration on smaller commercial sites, incorporate an upturned underdrain
system that consists of washed gravel and perforated pipe to provide a way to tie into the existing
stormwater infrastructure and additional storage and increased infiltration. The design should include:
4- to 6-inch-diameter, perforated PVC pipe (AASHTO M252)
Upturned solid pipe 12 to 18 inches below the bottom of the soil surface
Engineering considerations shall be provided to prevent stormwater backup on streets.
Vegetation
Vegetation commonly planted in stormwater planter areas includes shrubs, herbaceous vegetation, and
sometimes native trees. When developing a landscape plan, choose vegetation that will be able to
stabilize soils and tolerate the stormwater runoff rates and volumes that will pass through.
See Appendix D, Planting List and Example Planting Plans, for a recommended plant list and appropriate
selection criteria based on GI Practice and soil depth.
Maintain
Routine operation and maintenance is essential to gain public acceptance of highly visible urban
stormwater planter areas and ensure proper functioning. A legally binding Inspection and Maintenance
Agreement shall be completed. A sample Inspection and Maintenance Checklist is included in this
document.
Page SP-5
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Weeding, pruning, and trash removal should be done as needed to maintain aesthetics for
community acceptance.
During drought conditions, it may be necessary to water the plants, as would be the case with any
landscaped area.
To ensure proper performance, inspectors should check that stormwater infiltrates properly into
the soil within 48 hours after a storm.
If excessive ponding is observed, corrective measures include inspection for soil compaction and
underdrain clogging.
Page SP-6
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Examples
Page SP-7
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page SP-8
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page SP-9
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page SP-10
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page SP-11
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page SP-12
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page SP-13
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Sample Stormwater Planter Inspection and Maintenance Checklist
Inspector:
Date: Time:
Weather: Rainfall over previous 2-3 days?
Bioretention Location:
Planter Components:
Maintenance Inspection
Items Inspected Checked Needed Frequency
DEBRIS CLEANOUT Y N Y N
Planter area and contributing draining areas clean of debris. Monthly
No dumping of yard wastes into planter. Monthly
Litter (trash, debris, etc.) have been removed. Monthly
VEGETATION
Page SP-14
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
COMMENTS:
Dimension on as built:
Maintenance required as detailed above? Y / N Compliance with any other required conditions? Y / N
Comments:
Inspector’s signature:
Engineer/Agent’s signature:
Page SP-15
SMALL COMMERCIAL GUIDE
CITY OF ATLANTA, GEORGIA
DEPARTMENT OF WATERSHED MANAGEMENT
SUBSURFACE INFILTRATION
Subsurface infiltration facilities are underground holding
areas that receive, store, and infiltrate stormwater runoff
from impervious areas. These systems include modified
French drains (MFD), dry wells, subsurface stone galleries,
and other open-bottom chamber products. They differ from
infiltration trenches because runoff enters the facility
through inlets, roof leaders, a pretreatment system, or
other directly piped connections rather than through a
surface conveyance. The runoff is temporarily stored as it
passes through the surrounding stone bedding and
infiltrates into the adjacent subsoil. An overflow mechanism
(surcharge pipe, connection to larger infiltration area, etc.)
is provided to ensure that excess runoff is safely and
A modified French drain can be added to
efficiently conveyed to downstream drainage systems or
a small commercial site to blend into the
receiving waters. This section focuses on MFD and dry wells overall site plan.
as the most appropriate solutions for small commercial sites.
MFDs are shallow trench excavations filled with stone that are designed to intercept and temporarily store
stormwater runoff until it infiltrates into the soil. They are particularly well-suited to receive rooftop runoff,
but can also be used to receive stormwater runoff from other small, impervious areas. They are
essentially infiltration trenches but with the runoff
introduced via a perforated pipe set into the upper portion
of the gravel.
Location
For small commercial sites, the type of subsurface infiltration chosen will depend on drainage
patterns and available space.
They should be designed so that the top of the MFD or dry well is as close to the surface as possible
to reduce digging needed to facilitate maintenance access.
Subsurface soils must not be compacted. Once the area is excavated, subsoils need to be loosened
and tilled to a depth of 6 inches.
Page S-Inf-1
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
MFD trenches and dry wells should be located at least 5 feet from building foundations and 10 feet
from buildings with basements and property lines.
The top end of the MFD can be next to the building in order to connect to downspouts, but should
slope away from the building.
To reduce the chance of clogging, MFDs and dry wells should drain only impervious areas, and runoff
should be pretreated with at least one of the pretreatment details found in Appendix B, Supplemental
Green Infrastructure Practice Details.
MFDs and dry wells should not be located beneath an impervious (paved) surface, in an area with a
water table or bedrock less than 2 feet below the trench bottom, over other utility lines, or above a
septic field.
Subsurface stone galleries and chambers can be installed under parking lots and other developed
areas. It is important to provide adequate access to the system through manholes for maintenance
and observation.
The downstream end of the MFD pipe must daylight more than 10 feet from the property line. This
can be done with a riser and upflow drain if necessary.
Page S-Inf-2
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Design
General
To prevent clogging, appropriate pretreatment including sediment trap sumps, catch basin
inserts, basket and in-line leaf strainers, or other available pre-manufactured filtering units should
be provided to minimize the quantity of sediment that reaches the system. Follow the
manufacturer’s specifications where available.
A sediment sump or vault chamber sized to have 1 cubic foot of storage per 100 feet of
impervious area draining to it should be placed at the inlet of the subsurface infiltration practice.
The bottom of the system should be flat or gently sloping toward the downstream end to provide
uniform infiltration across the subsoil interface.
Riprap, plunge pools, pads, or other energy dissipaters should be placed at the end of the outlet
for surface overflow discharges.
Runoff in excess of the design volume should be diverted around the practice or alternatively, in
the case of MFDs, to a downstream overflow to avoid damage to the practice.
Subsurface infiltration may include stone storage galleries, perforated high-density polyethylene
pipe, dry well structures, or other proprietary manufactured systems.
Gravel should be angular, washed, and uniformly graded No. 57 stone (0.75-inch to 1.75-inch
diameter).
Subsurface stone galleries and MFDs must not be deeper than they are wide.
Dry wells must be surrounded by a zone of angular, washed, and uniformly graded No. 57 stone.
The slope of the MFD pipe should be between 0.5% and 6%. It can be serpentine or multi-
pronged if sufficient slope is available.
MFD gravel depths should be at least 18 inches and no more than 36 inches.
Chambers associated with subsurface stone galleries should meet the following requirements:
o Minimum 3,000-psi structural reinforced concrete may be used in non-traffic areas.
o All joints should be constructed with water stops.
o Cast-in-place walls must follow structural retaining wall design procedures.
o Maximum depth from finished grade to the chamber’s invert should not exceed 20 feet.
If proprietary manufactured systems are used, provide manufacturer’s specifications, details, and
sizing information indicating that the system can meet the RRv Required for the site.
Systems must meet structural requirements for minimum cover, overburden support, and traffic
loading for anticipated surface use without compacting subsoils. Additional aggregate may be
required for structural support.
Adequate maintenance access points should be provided for all systems at the inlet pipe and
outflow structures.
o Vaults with widths of 10 feet or less should have removable lids.
Step-by-Step sizing
1. Establish the RRv Required (in cubic feet) for the contributing impervious area using Figure 5 in
Section 5, Design Process.
2. Determine the dimensions and depth of the proposed subsurface infiltration practice.
a. Length × width × depth for MFDs and stone galleries
Page S-Inf-3
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
b. Diameter, perimeter stone storage width, and depth for dry wells
3. Confirm the site infiltration rates per infiltration testing parameters in Appendix C.
4. For MFDs, use the dimensions determined in Step 2 above. Then refer to Table A for infiltration
rates greater than 0.25 inch per hour or Table B for infiltration rates less than 0.25 inch per hour
to find the storage volume provided in the MFD stone.
5. For stone storage galleries use the dimensions determined in Step 2 above. Then refer to
Table C for infiltration rates greater than 0.25 inch per hour or to Table D for infiltration rates less
than 0.25 inch per hour to find the storage volume provided in the stone.
6. For dry wells, use Table E for infiltration rates greater than 0.25 inch per hour or Table F for
infiltration rates less than 0.25 inch per hour.
7. For chamber systems, provide manufacturer’s sizing calculations indicating that RRv Required
has been met.
MFD STORAGE TABLE A
Stone Storage Volumes for Infiltration Rates greater than 0.25 inches/hour (cubic feet)
100% RRv Credit by Volume
MFD Typical Dimensions
3x10 3x20 3x30 3x40 3x50 5x10 5x20 5x30 5x40 5x50 5x60 5x70 5x80 5x90 5x100
(feet)
surface area (square feet) 30 60 90 120 150 50 100 150 200 250 300 350 400 450 500
MFD STORAGE TABLE B
Stone Storage Volumes for Infiltration Rates less than 0.25 inches/hour (cubic feet)
50% RRv Credit by Volume
MFD Typical Dimensions
3x10 3x20 3x30 3x40 3x50 5x10 5x20 5x30 5x40 5x50 5x60 5x70 5x80 5x90 5x100
(feet)
surface area (square feet) 30 60 90 120 150 50 100 150 200 250 300 350 400 450 500
Page S-Inf-4
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
STONE GALLERY STORAGE TABLE C
Stone Storage Volumes for Infiltration Rates greater than 0.25 inches/hour (cubic feet)
100% RRv Credit by Volume
Stone Gallery Typical
10x10 10x20 10x30 10x40 10x50 10x60 20x20 20x30 20x40 30x30
Dimensions (feet)
surface area (square feet) 100 200 300 400 500 600 400 600 800 900
Stone Storage at 24"
80 160 240 320 400 480 320 480 640 720
Depth (cubic feet)
Stone Storage at 36" Depth
120 240 360 480 600 720 480 720 960 1080
(cubic feet)
Soil Stone at 48" Depth
160 320 480 640 800 960 640 960 1280 1440
(cubic feet)
Stone Storage at 60" Depth
200 400 600 800 1000 1200 800 1200 1600 1800
(cubic feet)
note: table assumes a void ratio of 0.40
STONE GALLEREY STORAGE TABLE D
Stone Storage Volumes for Infiltration Rates less than 0.25 inches/hour (cubic feet)
50% RRv Credit by Volume
Stone Gallery Typical
10x10 10x20 10x30 10x40 10x50 10x60 20x20 20x30 20x40 30x30
Dimensions (feet)
surface area (square feet) 100 200 300 400 500 600 400 600 800 900
Page S-Inf-5
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
DRY WELL STORAGE TABLE E
Storage Volumes for Infiltration Rates greater than 0.25
inches/hour (cubic feet)
100% RRv Credit by Volume
Tank inside diameter
24 36 48 60 72 84 96
(inches)
Storage at 18" Depth
8 15 25 37 51 67 86
(cubic feet)
Storage at 24" Depth
11 20 33 49 68 90 115
(cubic feet)
Storage at 36" Depth
16 30 49 73 102 135 172
(cubic feet)
Storage at 48" Depth
21 41 66 97 135 180 230
(cubic feet)
Storage at 60" Depth
27 51 82 122 169 224 287
(cubic feet)
Diameter of Dry Well plus stone perimeter must exceed depth
Storage Volume assumes 12 inch stone perimeter for full depth of Dry Well
DRY WELL STORAGE TABLE F
Storage Volumes for Infiltration Rates less than 0.25
inches/hour (cubic feet)
50% RRv Credit by Volume
Tank inside diameter
24 36 48 60 72 84 96
(inches)
Storage at 18" Depth
4 8 12 18 25 34 43
(cubic feet)
Storage at 24" Depth
5 10 16 24 34 45 57
(cubic feet)
Storage at 36" Depth
8 15 25 37 51 67 86
(cubic feet)
Storage at 48" Depth
11 20 33 49 68 90 115
(cubic feet)
Storage at 60" Depth
13 25 41 61 85 112 144
(cubic feet)
Diameter of Dry Well plus stone perimeter must exceed depth
Storage Volume assumes 12 inch stone perimeter for full depth of Dry Well
Page S-Inf-6
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Maintenance
Routine operation and maintenance is essential to ensure proper functioning of subsurface infiltration
systems. A legally binding Inspection and Maintenance Agreement shall be completed. A sample
Inspection and Maintenance Checklist is included in this document. The following items should be
included in the overall maintenance plan:
Routinely inspect and clean out gutters and catch basins to reduce sediment load to the
infiltration system.
Clean intermediate sump boxes, replace filters, and otherwise clean pretreatment areas in
directly connected systems. At a minimum, cleaning should occur quarterly.
Routinely examine the practice to ensure that inlet and outlet devices are free of debris and
operational.
After storm events, evaluate the drain-down time of the subsurface infiltration system to ensure
the drain-down time of 48 hours or less.
Page S-Inf-7
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Examples
Non-woven
Geotextile
Fabric
Page S-Inf-8
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
NON-WOVEN
GEOTEXTILE FABRIC,
TOP AND SIDES ONLY
Page S-Inf-9
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Inspector:
Date: Time:
Weather: Rainfall over previous 2-3 days?
Page S-Inf-10
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
COMMENTS:
Dimension on as built:
Comments:
Inspector’s signature:
Engineer/Agent’s signature:
Page S-Inf-11
SMALL COMMERCIAL GUIDE
CITY OF ATLANTA, GEORGIA
DEPARTMENT OF WATERSHED MANAGEMENT
Location
Pick a location keeping these factors in mind:
o Ease in connecting roof drains
o Overflow to downslope areas
o Level area for placement of the cistern or tank
o Location relative to intended water uses
o Possible conflicts with site or building utilities
o Electrical connections, if applicable
o Emergency ingress/egress
o Leaf screen option
o Location of hoses or other water distribution components
o Aesthetic considerations
Ensure adequate space is provided for appropriate foundation and structural support for the
cistern or tank structure.
Choose an adequate discharge location and overflow route to a vegetated landscaped area or
additional GI Practice.
Page RH/C-1
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Design
General
Rainwater harvesting is most effective when designed to meet a specific water reuse demand.
Multiple devices can be used to increase available storage and simplify routing for reuse. Devices
should be of the appropriate type and have sufficient capacity for the intended application as
noted:
o Rain barrel (50–150 gallons)
o Cistern (500–7,000 gallons)
o Larger aboveground tank (3,000–12,000 gallons)
Prepare a rainwater reuse schedule to confirm that the practice:
o Is appropriately sized to meet the demand for reuse type.
o Allowed by City code.
o Sufficiently draws down stored water to maintain available storage between storm events.
o Accommodates variation in demand as a result of season or high/low use periods.
Select one or more pretreatment options.
Pretreatment of water entering the
cistern will remove debris, dust, leaves,
and other material. Some pretreatment
options are illustrated on the cistern
typical detail.
Fully cover water storage to avoid
potential mosquito breeding.
Storage tank material should be made of
material that is appropriate for
application and sealed with a water safe,
non-toxic substance. Typically a
commercial design intended for cistern
use is chosen. Screens are an acceptable form of pretreatment for
rainwater harvesting systems. Photo courtesy of
For indoor reuse applications follow www.treehugger.com.
appropriate codes and:
o Provide proper signage distinguishing nonpotable water from potable water
o Use appropriate plumbing fittings, backflow prevention, and pumps
o Incorporate appropriate filtration and treatment if reuse application connects to nonpotable
indoor water system
Install a bypass/overflow system to accommodate the conveyance of runoff when the system is
full.
Account for bypass and overflow runoff volumes in overall site design.
Page RH/C-2
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Step-by-Step Sizing
1. Determine the RRv Required (in cubic feet) for the contributing impervious area using Figure 5 in
Section 5, Design Process, of this document. A rule of thumb is that you will need 0.6 gallon per
square foot to meet the 1-inch rainfall requirement.
2. Convert RRv Required in cubic feet to gallons using the formula:
RRv Required × 7.48
3. Increase the storage volume by 25% to provide contingency in case the tank does not completely
empty between storm events.
4. If a device cannot hold the full RRv and contingency volume, one alternative is to divert overflow
to another GI Practice such as a filter strip or rain garden.
Maintain
Routine operation and maintenance is essential to ensure proper functioning rainwater harvesting
systems.
Page RH/C-3
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Example
A cistern intercepts downspout runoff, and outlets to the adjacent landscape area
Page RH/C-4
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page RH/C-5
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page RH/C-6
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Inspector:
Date: Time:
Weather: Rainfall over previous 2-3 days?
Page RH/C-7
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
COMMENTS:
Dimension on as built:
Maintenance required as detailed above? Y/N Compliance with other conditions? Y/N
Comments:
Inspector’s signature:
Engineer/Agent’s signature:
Page RH/C-8
SMALL COMMERCIAL GUIDE
CITY OF ATLANTA, GEORGIA
DEPARTMENT OF WATERSHED MANAGEMENT
GREEN ROOFS
A green roof is a system consisting of waterproofing material,
growing medium, and vegetation, and is used in place of a
traditional roof as a way to limit impervious site area and
manage stormwater runoff. Green roofs capture and
temporarily store runoff within the growing medium, promoting
retention and evapotranspiration of precipitation. The majority
of green roofs can be classified as intensive or extensive.
Intensive green roof systems have a thick layer of engineered
soil (12 to 24 inches) that supports a diverse plant community
that may even include trees. Extensive green roof systems
typically have a much thinner layer of engineered soil (2 to
6 inches) that supports a plant community composed primarily
of drought-tolerant vegetation, such as sedums and succulent
plants. In either case, the design should be self-sustaining. City Hall Green Roof. Atlanta, Georgia
Location
Green roofs are best suited for flat roofs. The maximum acceptable pitch for a conventional green
roof is 25%.
Example applications include: new or existing rooftops, rooftop pavilions, parking decks, and
storage sheds.
Systems can be designed to provide partial or full roof coverage and access to rooftop building
utilities.
The system should be placed in a location where it can be easily accessed for maintenance.
The system should be placed in a location where the overflow can be connected to building
drainage piping.
Inspect the roofing membrane and components, and verify that the system conforms to the
specifications of the green roof provider.
Design
General
Green roofs must be designed in accordance with the ASTM International Green Roof Standards
and applicable city, state, and federal building codes. The structural support must be sufficient to
hold the additional weight of the green roof, which is typically an additional 15 to 30 pounds per
square foot of load for an extensive system with a 4-inch growing medium. Because of these
loading requirements, more options are available for new buildings; however, retrofits are
possible. A licensed professional structural engineer should be involved with the design of a
green roof to ensure that the roof has sufficient structural capacity.
Page GR-1
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Step-by-Step Sizing
1. Determine the RRv Required (in cubic feet) for the contributing impervious area using Figure 5 in
Section 5, Design Process. The contributing impervious area should be limited to the area of the
green roof. The green roof should not accept additional contributing drainage.
2. A typical green roof has been shown to reduce runoff by 0.4 inch of rainfall per 1 inch depth of
soil media. For a roof with 3 inches of soil or more, RRv Required for the green roof area will be
met. RRv Provided can be calculated by:
RRv Provided (cubic feet) = (green roof area × green roof soil depth (inches) × 0.4)
12
Page GR-2
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
3. Table A shows the results of this calculation for a 100-square-foot section of green roof. The
numbers can be extrapolated to determine the RRv Provided for any multiple of 100 square feet.
For example, the RRv Provided calculation for a 400-square-foot roof with 6 inches of soil would
be:
4 × 20 cubic feet = 80 cubic feet
4. A minimum depth of 4 inches of soil is recommended to provide contingency in case the growing
medium does not completely dry between storm events.
5. As an alternative, for green roofs with 3 inches or more of
soil depth, the area of the green roof can be deducted
from the impervious surface added or modified to
determine RRv Required in Section 5, Design Process, of
this document.
6. If the green roof does not meet the RRv Required for the
impervious surface added or modified, one alternative is
to divert overflow to another GI Practice, such as a
cistern.
Vegetation
Vegetation commonly planted on extensive green roofs
includes sedums and succulents. To ensure diversity and
viability, half of the plants should be sedum varieties and
include at least four different species. The remaining
plants should be herbs, meadow grasses, or meadow
flowers, depending on the desired appearance. For
intensive green roofs, qualified professionals should
identify plants that will tolerate the harsh growing
conditions found on rooftops and will be capable of
thriving in a limited-moisture rooftop environment.
Page GR-3
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Maintain
A legally binding Inspection and Maintenance Agreement shall be completed. A sample Inspection
and Maintenance Checklist is included in this document. Routine operation and maintenance is
essential to gain public acceptance of visible urban green roofs and ensure properly functioning
systems.
Green roofs are prone to volunteer weed growth. Weeding, pruning, and trash removal should be
performed as needed to maintain the aesthetics.
During drought conditions, it may be necessary to water the plants, as with any landscaped area.
To ensure proper performance of the engineered soil mix, inspectors should check to make sure
that the stormwater infiltrates properly into the soil within 48 hours after a storm.
If excessive ponding is observed, corrective measures include inspection for soil compaction and
drainage layer clogging.
Inspect drain inlet pipes for leaks and clogs. Clear when soil substrate, vegetation, debris, or
other materials clog the drain inlet.
Inspect the roof for leaks and structural deficiencies, and repair as necessary.
Page GR-4
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Example
Page GR-5
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page GR-6
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page GR-7
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page GR-8
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Inspector:
Date: Time:
Weather: Rainfall over previous 2-3 days?
INTEGRITY OF BIORETENTION
Page GR-9
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
COMMENTS:
Dimension on as built:
Comments:
Inspector’s signature:
Engineer/Agent’s signature:
Page GR-10
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
The example site is an existing commercial site (outlined in red in Figure A-1) that is entirely covered with
impervious surfaces, including a building and parking area. The soil conditions are Type C with a water
table that is 4 feet or greater below the surface. Proposed site impacts include a building addition, a
partial pavement replacement, and circulation improvements along with reconfiguration of parking.
(Note: This manual applies because the net impacted impervious area is less than 5,000 square feet.)
Page A-1
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
STORMWATER DESIGN STEP 1: Determine RRv Required for a 1-Inch Rainfall Event
a. Calculate net of created, added, and/or demolished and replaced impervious surface area from
design plans.
The impacted impervious surface for the example site is shown on Figure A-2 and calculated in
Table A-1.
b. If the applicable impervious surface is less than 500 square feet or exceeds 5,000 square feet, this
manual does not apply. Instead, a full design submittal must be prepared following the Blue Book
and the CSS.
From Table A-1, the net impacted impervious surface falls within the range of this manual.
c. Identify RRv Required from Figure A-3 (Section 5, Figure 5) using the calculated impervious
surface area.
Figure A-3. RRv Required for 1 Inch of Rainfall for Sizing Example
Page A-2
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
b. In combination, can meet RRV Required storage requirements based on Figure A-3, GI
Practice sizing tables, and any allowable volume reduction credits.
The practices identified in Figure A-4 were selected from the GI Practice Design Guidelines in
Section 7 of this manual and were reviewed by City staff at the required Stormwater Concept Plan
meeting. For this site, other combinations of alternatives would also work. These were selected to
demonstrate a variety of practices.
GI Practice 1 = 10-foot by 20-foot (equivalent) bioretention area within the proposed parking lot
island. GI Practice 1 will have 6 inches of surface ponding storage and 18 inches
depth of amended soil.
GI Practice 2 = 20-foot by 40-foot permeable paver area with 12 inches of stone depth providing
storage, infiltration, and pre-filtration for the downstream infiltration trench.
GI Practice 3 = 5-foot by 40-foot infiltration trench with no anticipated surface ponding and 18 inches
of stone storage.
The sizes proposed for these practices are preliminary based on what works efficiently within the site
layout. Final sizing to confirm that, in combination, they meet the RRv Required (370 cubic feet) will
be the result of an iterative process in Step 4.
c. The surface type of the contributing drainage area is appropriate for the selected practice per
Table 2 in Section 4.
For this example, GI Practice 1, Bioretention, receives runoff from pavement and the stabilized
landscape island area. GI Practice 2, Permeable Paver Parking, receives runoff from pavement area.
GI Practice 3, Infiltration Trench, receives runoff from the building addition roof and the adjacent
grass area. Table A-2, derived from Section 4, Table 2, confirms that the selections are appropriate.
(high sediment
Pre -Treatment
Pre-Treatment
Dumpster pad
exposed soil
landscape
Pavement
stabilized
potential)
Recommended Size of
Grass /
GI Practice Based on
Roof
Contributing Area
GI Practice (%)
Bioretention 5 to 10
Infiltration
5
Trench
Permeable
Pavement 25
Page A-3
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
STORMWATER DESIGN STEP 3: Size the Selected GI Practices to meet RRv Required:
a. Finalize the design layout and the GI Practice geometries (from Section 7 of this manual) that
can be used to meet the RRv required from concept plan.
See Figure A-4 for preliminary GI practice dimensions for use in this step.
b. Using proposed design plans, calculate the impervious area and delineate the flow path of
runoff from created, added, and/or demolished and replaced impervious surface area to each
planned GI Practice.
Figure A-5 shows the surface drainage area routed to each GI Practice. The areas are listed in
Table A-3.
Page A-4
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
c. Confirm that contributing drainage areas to each of the GI Practices do not exceed those
noted in Section 4, Concept Development, Table 2.
For this example, the contributing drainage areas have been confirmed to be within acceptable
design parameters as shown in Table A-3.
Page A-5
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
GI Practice 2 Permeable Paver Parking (found in the Permeable Pavement Practices Design
Guideline)
PERMEABLE PAVEMENT STONE STORAGE TABLE B
Stone Storage Volumes for Infiltration Rates less than 0.25 inches/hour (cubic feet)
50% RRv Credit by Volume
Stone Storage Typical
5x10 5x15 5x20 5x30 10x10 10x15 10x20 10x30 10x40 10x50 10x60 10x70 10x80 20x20 20x30 20x40 30x30
Dimensions (feet)
surface area (square feet) 50 75 100 150 100 150 200 300 400 500 600 700 800 400 600 800 900
Stone Storage at 12" Depth
10 15 20 30 20 30 40 60 80 100 120 140 160 80 120 160 180
(cubic feet)
Stone Storage at 18" Depth
15 23 30 45 30 45 GI Practice
60 2
90 120 150 180 210 240 120 180 240 270
(cubic feet)
Stone Storage at 24" Depth
20 30 40 60 40 60 80 120 160 200 240 280 320 160 240 320 360
(cubic feet)
Stone Storage at 36" Depth
30 45 60 90 60 90 120 180 240 300 360 420 480 240 360 480 540
(cubic feet)
Stone Storage at 48" Depth
40 60 80 120 80 120 160 240 320 400 480 560 640 320 480 640 720
(cubic feet)
note: table assumes a void ratio of 0.40
GI Practice 3 Infiltration Trench (found in the Infiltration Trench Practices Design Guideline)
INFILTRATION TRENCH TABLE B
Stone Storage Volumes for Infiltration Rates less than 0.25 inches/hour (cubic feet)
50% RRv Credit by Volume
Infiltration Trench Typical
3x10 3x20 3x30 3x40 3x50 5x10 5x20 5x30 5x40 5x50 5x60 5x70 5x80 5x90 5x100
Dimensions (feet)
surface area (square feet) 30 60 90 120 150 50 100 150 200 250 300 350 400 450 500
Cubic Feet of Stone
9 18 27 36 45 15 30 45 60 75 90 105 120 135 150
Storage at 18" Depth
GI Practice 3
Cubic Feet of Stone
12 24 36 48 60 20 40 60 80 100 120 140 160 180 200
Storage at 24" Depth
Cubic Feet of Stone
18 36 54 72 90 30 60 90 120 150 180 210 240 270 300
Storage at 36" Depth
Cubic Feet of Stone
24 48 72 96 120 40 80 120 160 200 240 280 320 360 400
Storage at 48" Depth
Cubic Feet of Stone
30 60 90 120 150 50 100 150 200 250 300 350 400 450 500
Storage at 60" Depth
note: table assumes a void ratio of 0.40
b. If RRv Provided above is greater or equal to RRv required from Step 1, proceed with site
design and Plan Submittal Process
RRv Provided is the total of all of the individual GI Practice storage volumes from the sizing tables. The
total for this example is 416 cubic feet as shown in Table A-4. RRv Provided is greater than or equal to
RRv Required (416 cubic feet ≥ 370 cubic feet). This confirms that the storage provided by this example
is acceptable.
Storage Volume
GI Practice (cubic feet)
1 Bioretention island 6″ surface ponding 100
1 Bioretention island soil storage 96
Permeable paver parking with 12″ stone storage
2 160
depth
3 5′ x 40′ Infiltration Trench with 18” stone depth 60
TOTAL RRv Provided 416
Page A-6
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Because RRv Provided exceeds RRv Required, the designer has the option to repeat the sizing process
with reduced GI practice dimensions or to proceed with site design and the plan submittal process. For
this example, the length of the infiltration trench is reduced to 20 feet, resulting in 20 cubic feet of storage
and a revised RRv Provided of 376 cubic feet. See Table A-5. The designer must confirm that
contributing area requirements remain valid. For this example, the surface area was not altered, and the
areas listed in Table A-3 remain valid.
INFILTRATION TRENCH TABLE B
Stone Storage Volumes for Infiltration Rates less than 0.25 inches/hour (cubic feet)
50% RRv Credit by Volume
Infiltration Trench Typical
3x10 3x20 3x30 3x40 3x50 5x10 5x20 5x30 5x40 5x50 5x60 5x70 5x80 5x90 5x100
Dimensions (feet)
surface area (square feet) 30 60 90 120 150 50 100 150 200 250 300 350 400 450 500
Cubic Feet of Stone
9 18 27 36 45 15 30 45 60 75 90 105 120 135 150
Storage at 18" Depth
GI Practice 3-revised
Cubic Feet of Stone
12 24 36 48 60 20 40 60 80 100 120 140 160 180 200
Storage at 24" Depth
Cubic Feet of Stone
18 36 54 72 90 30 60 90 120 150 180 210 240 270 300
Storage at 36" Depth
Cubic Feet of Stone
24 48 72 96 120 40 80 120 160 200 240 280 320 360 400
Storage at 48" Depth
Cubic Feet of Stone
30 60 90 120 150 50 100 150 200 250 300 350 400 450 500
Storage at 60" Depth
note: table assumes a void ratio of 0.40
Storage Volume
GI Practice (cubic feet)
1 Bioretention island 6″ surface ponding 100
1 Bioretention island soil storage 96
Permeable paver parking with 12″ stone storage
2 160
depth
3 5′ x 20′ Infiltration Trench with 18” stone depth 30
REVISED RRv Provided 386
c. If, during this step, the site constraints do not allow enough volume capture and storage
space to meet RRv Required, then determine the remaining runoff reduction volume:
This step not necessary because the RRv Provided is greater than RRv Required.
d. Sites not able to provide adequate volume to meet RRv required need to meet additional Water
Quality measures under Design Step 5.
This site exceeds the RRv Required and no additional measures will be employed. Proceed to
Stormwater Design Step 6: Develop a Landscape Plan (not included in this sizing example).
Page A-7
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page B-1
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Group A: Soils having a high infiltration rate (low runoff potential) when thoroughly wet. These consist
mainly of deep, well-drained to excessively drained sands or gravelly sands. These soils
have a high rate of water transmission.
Group B: Soils having a moderate infiltration rate when thoroughly wet. These consist chiefly of
moderately deep or deep, moderately well-drained or well-drained soils that have
moderately fine texture to moderately coarse texture. These soils have a moderate rate of
water transmission.
Group C: Soils having a slow infiltration rate when thoroughly wet. These consist chiefly of soils
having a layer that impedes the downward movement of water, or soils of moderately fine
texture or fine texture. These soils have a slow rate of water transmission.
Group D: Soils having a very slow infiltration rate (high runoff potential) when thoroughly wet. These
consist chiefly of clays that have a high shrink-swell potential, soils that have a high water
table, soils that have a claypan or clay layer at or near the surface, and soils that are
shallow over nearly impervious material. These soils have a very slow rate of water
transmission.
Soil Type A B C D
Typical Infiltration Rate Range
> 0.4 0.15–0.4 0.05–0.15 < 0.05
(inches/hour)
Site Soils
Well-drained A and B soils provide the best opportunity for infiltration and successful long-term
performance of all types of GI Practices.
Type C soils can be tilled to improve initial infiltration, and the use of bioretention with appropriate
deep-root plants has proven successful in these conditions.
Sites with D soils, a high water table, or bedrock near the surface should use GI Practices for
filtering and storing runoff. Infiltration may be applied in D soils with appropriately documented
infiltration testing.
Page C-1
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Infiltration Testing
Because it is important to establish the infiltrative
performance of the soils at the location and interface of
the bottom of the GI Practice with the subgrade, on-site
testing is required to obtain the infiltration rates to be
used in the design calculations. A variety of field tests
exists for determining the infiltration capacity of a soil.
Laboratory tests are not recommended, because a
homogeneous laboratory sample does not represent
field conditions.
Double-ring infiltrometer test: A double-ring infiltrometer test estimates the vertical movement of
water through the bottom of the test area. The outer ring helps to reduce the lateral movement of
water to the soil from the inner ring. The results from this test, generally reported in centimeters
per second (cm/sec) or inches per hour (in/hour), are appropriate for use in the GI Practice sizing
tables provided in the Design Guidelines.
Percolation test: A percolation test allows water movement through both the bottom and sides of
the test area. For this reason, the measured rate of water level drop in a percolation test must be
adjusted to account for the exfiltration occurring through the side interface of the test area.
The final percolation rate should be adjusted for each test according to the following formula.
Geotechnical investigations may include laboratory test results for permeability (K), which is
typically reported in cm/sec. This information can be used for conceptual design and sizing of GI
Practices, but field testing should be completed for final design calculations.
If additional geotechnical investigations are not performed for the project, or if results do not
indicate the seasonal high groundwater elevation, a hole must be excavated to a minimum of
2 feet below the bottom interface of the GI Practice with the subgrade to confirm that the
seasonal high groundwater elevation or bedrock is not within 2 feet of the bottom of the GI
Practice.
Page C-2
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Introduction
Landscaping is a critical element to improve both the function and appearance of GI Practices. Vegetation
should be selected based on soil depth, sun exposure, water tolerance, salt tolerance, and other
environmental conditions. This Appendix provides general landscape guidance, plant selection guidance
for effective stormwater GI Practices, and two example bioretention parking lot island planting plans.
The successful growth of plants, shrubs, and trees in GI practices is highly dependent on the soil depth.
The following table provides the appropriate soil depth and plant type for GI practices.
The planting plan shall include a sequence of construction, a description of the contractor's
responsibilities, a planting schedule and installation specifications, initial maintenance requirements, and
a warranty period stipulating requirements for plant survival.
Recommended Plants
Bioretention, Planters, and Bioswales
Plants for bioretention and other GI practices must be able to tolerate both wet and dry conditions. This
list, while not exhaustive, includes many plants that will tolerate conditions in bioretention areas. The
plants in this list have different preferences for both moisture and light, as shown in the columns labeled
“Moisture” and “Sun.” Additionally, most of these plants are native to Georgia and thus contribute the
added benefit of providing habitat and food for native pollinators and wildlife. Plants that are not native to
Georgia are marked with an asterisk (*). At the end of this Appendix are two example planting plans for
bioretention parking lot islands.
Key
Height: Typical height range for mature plants
Moisture: The amount of soil moisture that plants will tolerate is defined as follows:
Page D-1
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page D-2
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page D-3
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Infiltration Trenches
Infiltration trenches can be designed with a grass cover to aid pollutant removal and prevent clogging.
The sand filter or trench is covered with permeable topsoil and planted with grass in a landscaped area.
Properly planted, these facilities can be designed to blend into natural surroundings.
Grass should be capable of withstanding frequent periods of inundation and drought. Vegetated filter
strips and buffers should fit into and blend with surrounding area. Native grasses are preferable, if
compatible.
Design Constraints
Do not plant trees or provide shade within 15 feet of an infiltration or filtering area or where leaf
litter will collect and clog infiltration area.
Do not locate plants in areas that block maintenance access to the facility.
Sod areas with heavy flows that are not stabilized with erosion control matting.
Divert flows temporarily from seeded areas until stabilized.
Planting on any area requiring a filter fabric should include material selected with care to ensure
that no tap roots will penetrate the filter fabric.
Page D-4
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Note1: These grasses are sod forming and can withstand frequent inundation, and are thus ideal for the
swale or grass channel environment. Most are salt-tolerant as well.
Note 2: Where possible, one or more of these grasses should be in the seed.
Note 3: In areas that need immediate stabilization, sod should be used.
Page D-5
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page D-6
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page D-7
City of Atlanta, Georgia
Green Infrastructure Practices for Small Commercial Development
Page E-1
Projects Requiring a Stormwater
Consultation Meeting
The following projects are required to have a Consultation Meeting with Site Development staff to
review the Stormwater Concept plan, prior to submittal of the BB / LD permit application:
Commercial Projects
New developments that add any impervious surface OR disturb
more than one acre of land.
Redevelopment projects that add or replace more than 500 square
feet of impervious surface OR disturb more than one acre of land.
Demolition Projects that leave more than 500 square feet of
impervious surface in place.
Residential Projects
Projects reviewed for Preliminary Plat approval.
New Multi-family, Townhome, Apartment, Subdivision (not
individual lots), and Condo developments.
NOTES
Call 404-330-6249 or email [email protected] to schedule a Consultation Meeting.
Visit www.AtlantaWatershed.org/greeninfrastructure for more information regarding the
Stormwater Concept Plan and Consultation Meeting.
If the proposed project is exempt from the Post-Development Stormwater Management Ordinance,
Section 74-504 (d), no consultation meeting is necessary.
The construction of a new home on an individual lot must manage the first 1.0” of runoff onsite;
however, no consultation meeting is necessary prior to permit application. See the above
website for additional information on Green Infrastructure on residential lots.
New Developments take place on parcels that are wooded or have never been developed.
Redevelopment projects occur on sites that are currently developed or have previously been
developed.
Once the Consultation Meeting takes place, the Applicant will be given a copy of the Meeting
Record to include as part of the BB / LD application packet.
For applicable developments (see below), a stormwater concept plan and consultation meeting is required early in the design
process. The project’s engineer and Site Development staff shall discuss the post-development stormwater management
measures necessary for the proposed project and to assess constraints, opportunities and ideas for better site design, green
infrastructure and runoff reduction techniques early in the design process. This consultation meeting shall be held prior to
submittal of an application for a building permit (BB) or land disturbance permit (LD).
Per the City of Atlanta’s Post Development Stormwater Management Ordinance, the project’s engineer must present a
Stormwater Concept Plan to Site Development Staff for the following activities:
• New commercial development (Greenfield) that involves the creation of any impervious cover;
• Commercial redevelopment that includes the creation, addition, or replacement of 500 square feet of impervious cover
or more;
• Commercial development or redevelopment that disturbs one acre of land or more; and,
• Commercial demolition projects that leave in place more than 500 square feet of impervious cover.
For more information regarding the applicability and exemptions of the City’s Post Development Stormwater Management
ordinance, see Chapter 74-Environment, Article X. Section 74-504 of the city code.
The Stormwater Concept Plan should include the following:
_____ Project description;
_____ A preliminary survey showing the following:
_____ Property lines, existing conditions, general topography, general soil conditions, easements, and adjacent rights-
of-way;
_____ Location of all state waters, wetlands, applicable buffers, and floodplains;
_____ Any critical areas of the site which may affect the control of stormwater during and post-construction (steep slopes,
eroded areas, buffers, invasive species, existing stormwater infrastructure, undersized culverts, floodplains, wetlands,
etc.);
_____ A conceptual grading plan;
_____ Location and limit of proposed structures, land disturbing activities, demolition, and impervious surfaces;
_____ Infiltration rates shall be determined by soil surveys, on-site soil analysis, double-ring infiltrometer or percolation test.
If a site has been previously developed or graded or contains urban soil types, a double-ring infiltrometer or percolation
test is required. The test locations must be in the region where infiltration practices are proposed at the appropriate
depth; and,
_____ Preliminary selection and location of proposed structural stormwater controls; location of existing and proposed
conveyance systems such as grass channels, swales, and storm drains; flow paths; relationship of site to upstream and
downstream properties and drainages; and preliminary location of proposed stream channel modifications, such as
bridge or culvert crossings.
NOTE: Signature on this document does NOT constitute design approval, nor is it intended as a comprehensive list of all
issues. Signature authorizes applicant to proceed with application for a land development/building permit. Issues
identified must be addressed prior to plan approval by Site Development.
FOR ADMINISTRATIVE USE ONLY
Issues Discussed Potential Opportunities and Comments
o Stream buffer _____________________________________________________________________________
o Wetland _____________________________________________________________________________
o Floodplain _____________________________________________________________________________
o Easement _____________________________________________________________________________
o Steep slope _____________________________________________________________________________
o RR limitations _____________________________________________________________________________
o Other _____________________________________________________________________________
Engineer’s Certificate
Green Infrastructure Practices
I, ________________________________, a registered professional engineer in the State of Georgia,
hereby certify with my signature and seal, that the Green Infrastructure (Runoff Reduction) practices
located at the following address,___________________________________________, as permitted
under Building Permit #_________________, have been constructed in conformance with the approved
plans and specifications.
Professional
Seal
Signature
Date
City of Atlanta’s Engineer’s Certification for Green Infrastructure Practices ‐ Revised 6/10/14
CITY OF ATLANTA
DEPARTMENT OF WATERSHED MANAGEMENT
STORMWATER AS BUILT SURVEY REQUIREMENTS
From Section 74-519 (b) of the City of Atlanta Code of Ordinances, “Upon completion of a project, and prior to final inspection
pursuant to section 74-43(f) or issuance of a certificate of occupancy, the applicant or responsible party…is required to submit an
electronic format as determined by the department of watershed management, and a paper format of the actual "as built" plans for
any stormwater management facilities or practices after final construction is completed. The plan must show the as built
configuration for all stormwater management facilities and practices and must be certified by a professional engineer.”
A paper copy of this survey and attached “Engineer’s Certificate” will be given to the Environmental Compliance Inspector of the
given site, and an electronic copy (.pdf) of each will be emailed to [email protected].
It shall be at all times the responsibility of the engineer of record to accurately model and report the conditions on the site, AFTER
CONSTRUCTION. All labeling shall be consistent with the approved hydrology study and maintenance agreement.
All as built drawings must be georeferenced to the US State Plane coordinate system, NAD 83, GA West Zone, US Survey Feet.
All drawings must contain two reference pins (i.e. property corners).
Section 74-513 (b) of the Post-Development Stormwater Management Ordinance states that “If any of the stormwater runoff
volume generated by the first 1.0” of rainfall cannot be reduced or retained on the development site, due to site characteristics
or constraints…the remaining volume shall be increased by a multiplier of 1.2 and shall be intercepted and treated in one or
more stormwater management practices that provide at least an 80 percent reduction in total suspended solids.”
If reducing the entire 1.0” volume onsite is not feasible, the Design Professional must provide the following documentation:
1) Soil investigation report (which includes double-ring infiltrometer or percolation tests) demonstrating that onsite soils
are not suitable for infiltrating the required volume within a 48-hour time period. The test locations must be in the
region where stormwater management practices would be utilized at the appropriate depths. Evidence of a high water
table, surface bedrock, contaminated soils, or the presence of a High Risk Operation or Hotspot (as defined in Section
74-503) may be included in this report.
2) A written analysis signed and sealed by the Design Professional stating the amount of volume that cannot be reduced
onsite, the total volume of Water Quality to be provided instead (1.2 multiplier), and site specific reasoning and
supportive evidence for not providing the runoff reduction volume. This analysis must demonstrate that incorporating
runoff reduction practices to comply with the ordinance is an extreme economic hardship or physical impossibility due
to the configuration of the site or to irreconcilable conflicts with other City requirements. Certain practices, such as
green roofs and rainwater harvesting techniques, do not require infiltration into subsurface soils, but rather rely on
evapotranspiration and reuse. An estimated cost comparison of said runoff reduction practices compared to the
proposed Water Quality practices must be included to demonstrate an economic hardship.
3) A conceptual site plan in accordance with Section 74-510 of the ordinance.
The above documentation must be submitted with this form during the Stormwater Concept Plan consultation meeting or during
permit review. If development plans change significantly between the consultation meeting and permit review, an updated
justification will be required. Site Development plan review staff will decide whether the submitted justification warrants
approval. This decision may be appealed in writing to Lowell Chambers, Director of Site Development, or to Margaret Tanner,
Deputy Commissioner of the Office of Watershed Protection. Decision of said appeal shall be made within one week of
receiving the attached form and documentation.
□ Approved
______________________________________________________________________________________________________________________________
□ Denied ___________________________________________________________________________________________
_____________________________________________________________________________________________________
WHEREAS, the Owner desires to make certain improvements to the property and obtain a
building permit from the City for such improvements; and
WHEREAS, the improvements the Owner desires to make to the property include a storm
water management facility consisting of ________________________________________________ ,
further described on Exhibit “B”, attached hereto and made a part hereof by reference; and
WHEREAS, the City requires the execution of a Stormwater Management Inspection and
Maintenance Agreement in accordance with City Code Section 74-511 prior to and as a condition of
receiving a permit for the improvements included on the plans prepared by
_____________________________________________________ and dated ___________________ ,
said plans incorporated by reference into this Agreement, as maintained in the records of the City.
THEREFORE, in order for the City to issue a building permit to the Owner, the Owner agrees
for him/her self(s), his/her agents, his /her assigns and successors in title to the property, to the
following:
1) To indemnify the City of Atlanta, its officers, agents, and employees, successors and assigns
from any damages or claims for damages arising out of a) the construction or use of the
stormwater management facility as shown on the above referenced plans, b) the additional
runoff or discharge of storm water from the property caused by the improvements to the
property, or c) any up-stream or down-stream adverse impacts due to structural, design,
installation, maintenance or any other failure of the stormwater facility.
2) To file and record the executed agreement and all the exhibits in the Fulton or DeKalb County
Courthouse. The agreement is a permanent covenant running with the land and shall be binding
upon the successors in title of the Owner.
3) To own, operate, and maintain the stormwater facility in good order and repair, as designed and
permitted and not to encroach upon, diminish, or alter the stormwater management facility
without first obtaining an appropriate building permit from the City for any subsequent
modifications.
4) To provide an annual inspection and maintenance report to the City to ensure continuing
Revised 12/15/2011
proper performance of the stormwater management facility as designed. The inspection and the
report will be performed and attested to by a qualified professional having certified Level II
Georgia Soil and Water Conservation Commission Specialist standing and shall conform to
the format shown in Appendix E of the Georgia Stormwater Management Manual. Any
deficiencies noted in either operation or maintenance of the facility(s) must be included in the
report along with the proposed remedies required and a time table for their implementation. If
portions of the property are subsequently sold or otherwise transferred to new ownership,
legally binding arrangements must be made to pass the inspection and maintenance
responsibility to the appropriate successors in title. These arrangements must designate for each
portion of the site the party to be responsible for its inspection and maintenance. A copy of the
report must be submitted to the City of Atlanta, Department or Watershed Management and
will be due annually on the date specified by the Department.
The Owner, in conjunction with this Agreement and in accordance with Section 74-517 of the
City Code, acknowledges that the City may enter the Property at reasonable times and in a
reasonable manner for the purpose of inspection. The Owner further acknowledges that that if
the Owner fails or refuses to meet the requirements of this agreement, the City may, after
appropriate notice, enter the property to correct a violation of the design standards or
maintenance requirements by performing the necessary work to place the facility in proper
working condition. When the City must perform such repairs or improvements, all costs for
work associated with bringing the stormwater management facility back to good order and
repair shall be at the Owner’s sole cost and expense.
The rights and obligations granted herein shall run with the land and shall be binding upon the
Owner, its successors and assigns.
IN WITNESS WHEREOF, the Owner has caused this Stormwater Management Facility
Inspection and Maintenance/ Indemnification Agreement to be duly executed under seal,
this______day of_________, 2________
OWNER
_______________________ By: _____________________________
Unofficial Witness
_________________________________
(Print)
_______________________
Notary Public Its: ______________________________
My commission expires: (Title of authorized representative)