0% found this document useful (0 votes)
26 views

Chapter 6 Scheduling CPM PERT

This document discusses project scheduling and management techniques like the critical path method (CPM) and program evaluation and review technique (PERT). It explains that a project involves a set of related tasks that must be completed to finish the project. It also describes how to break a project down into a work breakdown structure and develop a network diagram to show the sequential relationships between activities using nodes and arrows. The network diagram is then used to schedule the project and identify the critical path.

Uploaded by

nescafe ok
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
26 views

Chapter 6 Scheduling CPM PERT

This document discusses project scheduling and management techniques like the critical path method (CPM) and program evaluation and review technique (PERT). It explains that a project involves a set of related tasks that must be completed to finish the project. It also describes how to break a project down into a work breakdown structure and develop a network diagram to show the sequential relationships between activities using nodes and arrows. The network diagram is then used to schedule the project and identify the critical path.

Uploaded by

nescafe ok
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 32

Scheduling

Project Management-CPM/PERT

1
Project
 A project is composed of Jobs, Activities, Functions
or Tasks that are related to one to the other in some
manner, and all of these should be completed in order
to complete the project.

Main Objectives of a Project


 The project should be completed with a minimum of
elapsed time.
 It should use available manpower and other resources
as carefully as possible, without delay.
 It should be completed with a minimum of capital
investment, without delay. 2
Characteristic of a project
 An unique, one-time operational activity or
effort.
 Requires the completion of a large number of
interrelated activities.
 Established to achieve specific objective.
 Resources, such as time and/or money, are
limited.
 Typically has its own management structure.
 Requires leadership.
3
Examples
 constructing houses, factories, shopping malls,
athletic stadiums or arenas.
 developing military weapons systems, aircrafts,
new ships.
 launching satellite systems.
 constructing oil pipelines.
 developing and implementing new computer
systems.
 planning concert, football games, or basketball
tournaments.
 introducing new products into market.

4
What is project management?
 The application of a collection of tools and
techniques to direct the use of diverse resources
towards the accomplishment of a unique,
complex, one time task within time, cost and
quality constraints.
 Its origins lie in World War II, when the military
authorities used the techniques of operational
research to plan the optimum use of resources.
 One of these techniques was the use of
networks to represent a system of related
activities. 5
Project Management Process

 Project Planning
 Project Scheduling
 Project Controlling

6
Work breakdown structure
 A method of breaking down a project into individual
elements ( components, subcomponents, activities and
tasks) in a hierarchical structure which can be scheduled
and given cost.
 It defines tasks that can be completed independently of
other tasks, facilitating resource allocation, assignment
of responsibilities and measurement and control of the
project.
 It is foundation of project planning.
 It is developed before identification of dependencies
and estimation of activity durations.
 It can be used to identity the tasks in the CPM (Critical
Path Method) and PERT (Project Evaluation and
Review Technique).
7
Project Planning
 Resource Availability and/or Limits
 Due date, late penalties, early completion
incentives.
 Budget
 Activity Information
 Identify all required activities.
 Estimate the resources required (time) to
complete each activity.
 Immediate predecessor(s) to each activity needed
to create interrelationships.

8
Project Scheduling and Control Techniques

 Gantt Chart
 Critical Path Method (CPM)
 Program Evaluation and Review Technique
(PERT)

9
Project Network
 Network analysis is the general name given to certain specific
techniques which can be used for the planning, management and
control of projects.

 Use of nodes and arrows


 Arrows  An arrow leads from tail to head directionally.
 Indicates ACTIVITY, a time consuming effort that is
required to perform a part of the work.
 Nodes  A node is represented by a circle.
 Indicates EVENT, a point in time where one or more
activities start and/or finish.

10
 Activity
 A task or a certain amount of work required in the
project.
 Requires time to complete.
 Represented by an arrow.
 Dummy Activity
 Indicates only precedence relationships.
 Does not require any time of effort.

11
Project Network
 Event
 Signals the beginning or ending of an activity.
 Designates a point in time.
 Represented by a circle (node).
 Network
 Shows the sequential relationships among activities
using nodes and arrows.
Eve
nt
Eve Activity Eve
Eve nt nt
nt

Eve
nt

Fig: Network Diagram


Event
The commencement or completion of an activity is called as an
EVENT.
Representation of Events

Circular Square Rectangular Oval

Specifying the Events


Tail Event : Marks the beginning of an activity.
Head Event: Marks the ending of an activity.
Dual Role Event : Head event to some activity and tail event to other.
activity.
Activity Activity Activity Activity
10 10 10

Tail Event Head Event Dual Role Event

13
Example
2
D
A

1 B 3 E 5
C F

Event 1: Tail Event for Activities A and B


Event 2: Head Event for Activity A, Tail Event for Activity D
Event 3: Head Event for Activity B, Tail Event for Activities
C and E
Event 4: Head Event for Activity C, Tail Event for Activity F
Event 5: Head Event for Activities D, E, F

14
Successor Events
The event or events that follow another event.
Immediate Successor Events
The event or events that immediately follow another event without any
intervening ones.
Predecessor Events
The event or events that occur before another event.
Immediate Predecessor Events
The event or events that immediately come before another event without any
intervening ones. 2

1 3 5

Example;

Events 2, 3, 4 and 5 are Successor events to 1 4


Events 2, 3 and 4 are Immediate successor events to
1
Events 1, 2, 3 and 4 are predecessor event to 5
Events 2, 3 and 4 are Immediate Predecessor event
to 5 15
Activity
An Activity is the actual Performance of a task.
Representation and Identification
Representation of Activity

2 Activity (2,3) 3
Identification of Activity
5 Activity P 6

Install Machine
2 3 Description of Activity
[Activity (2,3)]

16
Parallel Activity
Those activities which can be performed simultaneously and independently to each other.
Serial Activity
Those activities which are to be performed one after the other, in succession.

P Q
3 3
B Excavate Concrete
Foundations Foundations

Parallel Activities Serial Activities

Activities A and B are parallel Activities P and Q are serial activities.


activities since they can taken up Activity Q cannot be started, unless
concurrently and executed activity P is completed.
simultaneously.
Activity P is known as Preceding Activity, while
Activity Q is known as Succeeding Activity, in
relation to each other.

17
Dummy
A dummy is a type of operation in the network which neither requires any time nor any
resources, but is merely a device to identify a dependence among operations.

A B
1 2 3 Set 1

4 C 5 D 6 Set 2

Set 1: A. A wait for delivery of new machine.


B. Installing new machine.
Set 2: C. Removing Existing machine.
B. Disposal of existing machine.
Activities A and B of set 1 and C and D of Set 2 are to be performed
serially.
Both the sets are performed simultaneously.
However, from practical considerations, activity D of set 2 cannot be
performed unless activity A of set 1 is completed.
Hence a dummy link is used, joining node 2 to node 5, indicating that
activity D cannot be started unless event 2 is over.
18
Network Diagram
Activity-On-Node (AON)
Nodes represent activities, and arrows show
precedence relationships.
AOA Project Network for House

3
Lay Dummy
foundation
2 0 Build Finish
3 1 house work
1 2 4 6 7
Design house Order and 3 1
and obtain receive Select 1 1 Select
financing materials paint carpet
5

19
Activity-On-Arrow (AOA)
Arrows represent activities and nodes are events for
points in time.

AON Project Network for House


Lay foundations Build house
2 4
Finish work
2 3
7
Start 1 1
3
Design house and 6
3
obtain financing 5 1
1
1 Select carpet
Order and receive
Select paint 20
materials
Situations in Network Diagram
B
A
A must finish before either B or C can start.

C
A
C Both A and B must finish before C can start.
B

A
C Both A and C must finish before either of B or D
can start.
B
D

A
B
A must finish before B can start.
Dummy Both A and C must finish before D can start.

C
D 21
Example
Draw the network for a project having four activities labeled A, B, C and D, and
related as below:
1) Activity A and Activity B can be done concurrently
2) Activity A is the immediate predecessor of activity C, and so is the
relation between B and D
3) Accomplishment of C and D marks the completion of the project.
2
A C

1 4

B D
3

22
CPM Calculation
Path
 A connected sequence of activities leading
from the starting event to the ending event.
Critical Path
 The longest path (time); determines the
project duration.
Critical Activities
 All of the activities that make up the
critical path.
Forward Pass
 Earliest Start Time (ES)
 earliest time an activity can start.
 ES = maximum EF of immediate predecessors.
 Earliest finish time (EF)
 earliest time an activity can finish.
 earliest start time plus activity time.
 EF= ES + Time
Backward Pass
Latest Start Time (LS)
Latest time an activity can start without delaying critical path
time.
LS= LF - Time
Latest finish time (LF)
Latest time an activity can be completed without delaying
critical path time.
24
LS = Minimum LS of immediate predecessors
CPM analysis
 Draw the CPM network.
 Analyze the paths through the network.
 Determine the float for each activity.
 Compute the activity’s float.
 Float = LS - ES = LF - EF
 Float is the maximum amount of time that this activity
can be delayed in its completion before it becomes a
critical activity, i.e., delays completion of the project.
 Find the critical path is that the sequence of activities and
events where there is no “slack” i.e.. Zero slack
 Longest path through a network.
 Find the project duration is minimum project completion
time.
25
CPM Example:
CPM Network
f, 15

g, 17 h, 9
a, 6
i, 6

b, 8

d, 13 j, 12

c, 5
e, 9

26
f, 15
g, 17 h, 9
a, 6
i, 6
b, 8
d, 13 j, 12
c, 5
e, 9 EF= ES + LS= LF -
Time Time
Activity Time Immediate Earlier Start Earlier Latest Latest Float ( LS-
predecessor (ES) Finish Start finish ES = LF-EF)
(EF) (LS) (LF)
a 6 0 6 3 9 3
B 8 0 8 0 8 0
C 5 0 5 7 12 7
D 13 b 8 21 8 21 0
E 9 c 5 14 12 21 7
F 15 a 6 21 9 24 3
G 17 a 6 23 10 27 4
H 9 f 21 30 24 33 3
I 6 g 23 29 27 33 4
J 12 d,e 21 33 21 33 0 27
Critical Path
f, 15

g, 17 h, 9
a, 6

i, 6

b, 8
d, 13
j, 12

c, 5

e, 9

28
Activity Immediate Duration
Example Predecessors
a --- 2
b --- 5
c --- 4
d b 5
e a 7
f a 3
g b 3
h c,d 6
i c,d 2
j e 5
k f,g,h 4
l f,g,h 3
m i 12
29
n j,k 8 29
Example
• The network for a certain project is shown in the figure
below along with the estimated time of completion of each
activity marked. Compute the activity times and float for
each activity. Locate the critical path on the network.

2 D 8 K 9 M
2 20 20 10
A
36 E J9 L
10 8
1 B 3 C 4 I 7
4 2 9
F 15
5 H9

G4
6

30
Critical Path

2 D 8 K 9 M
2 20 20 10
A
36 E J9 L
10 8
1 B 3 C 4 I 7
4 2 9
F 15
5 H9

G4
6

31
Example
Activity Immediate Duration
Predecessors
a --- 5
b --- 4
c a 3
d a 4
e a 6
f b,c 4
g d 5
h d,e 6
i f 6
j g,h 4 32

You might also like