Project selection and portfolio management are important processes for companies. [1] Screening models can help senior management select successful projects from a pool of opportunities. [2] Companies should use approaches like checklists, scoring models, profile models, or financial models to evaluate projects objectively. [3] Portfolio management ensures a company's collection of projects align with its strategic goals and available resources.

Uploaded by

Kenny Mak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
37 views15 pages

2 - Continued Project Selection

Project selection and portfolio management are important processes for companies. [1] Screening models can help senior management select successful projects from a pool of opportunities. [2] Companies should use approaches like checklists, scoring models, profile models, or financial models to evaluate projects objectively. [3] Portfolio management ensures a company's collection of projects align with its strategic goals and available resources.

Uploaded by

Kenny Mak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 15

Project Selection and

Portfolio Management

3-1
Selecting a Project

3-2
Apple Dilemma
• How Apple needs to select projects/products.
• How in your view Apple should make this
decision?
• What criteria should they use? And why?

3-3
How to Select Projects
• Having infinite resources allow us to take every opportunity
• Screening models should help Senior Management pick winners
from a pool of projects.
• Realism: reflect organisational objectives.
• Capability: allow the company to deal different types of projects
and allow the company to use them as wide as possible
• Flexibility: can be easily modified when the environment
changes, adding more criteria for example (Loose Fit).
• Ease of use: can be used by people in different parts of the
organisation, it should be easily understood.
• Cost effectiveness: not expensive to use otherwise people may
not used it, cost of obtaining information should be low
• Comparability; broad enough to be applied to multiple projects
and allows comparisons between alternatives.
3-4
Screening & Selection Issues
• Screening models are numeric or nonnumeric and should have:
• The Factors that need to be considered in evaluating project
alternatives are numerous
1. Risk – unpredictability to the firm
– Technical, financial, safety, legal, quality/reputation…
2. Commercial – market potential
– ROI, Payback period, market share, initial cash investment,
ability to generate future business
3. Internal operating – changes in firm operations
– Training needs, recruitment needs, changing the physical
environment, changes to manufacturing or service
operations
4. Additional–impact on image, patent, strategic fit, etc.
3-5
Approaches to Project Screening
• All models only partially reflect reality and have
both objective and subjective factors imbedded

1. Checklist model

2. Simplified scoring models

3. Profile models

4. Financial models

3-6
1. Checklist Model
A checklist is a list of criteria applied to possible
projects.

 Requires agreement on criteria

 Assumes all criteria are equally important

Checklists are valuable for recording opinions and


encouraging discussion

3-7
2. Simplified Scoring Models
Each project receives a score that is the weighted sum of its grade
on a list of criteria. Scoring models require:

 Assign importance weights to each criterion, rely on collective


group judgment

 Assign score values to each criterion in terms of its rating for each
project

 Multiply importance weights by scores to arrive at weighted score


for each criteria for each project

 Add the weighted scores to arrive at an overall project score.


3-8
Project criteria Importance Score (B) Weighted
weight (A) score (AxB)
Project Alpha cost 3 3 9
Profit potential 2 2 4
Risk 4 2 8
Duration 1 1 1

Total weighted 22
score

3-9
3. Profile Models
Show risk/return options for projects.
X6
Maximum Criteria
Desired Risk X2
X4 X5 selection as
R axes
i X3
s X1
k Efficient Frontier
Rating each
Minimum project on
Return
Desired Return criteria

3-10
Advantages and Disadvantages
• Profile model gives managers an opportunity to
map out potential returns while considering the
risks that comes with every choice.
• However it limits the decision makers to a small
number of criteria, two, risk and return.
• Values need to be attached to risk which tend not
to be quantified
3-11
4. Financial Models
Based on the time value of money principal

• Payback period
• Net present value (NPV)
• Internal rate of return

3-12
Choosing a Project Selection Approach
• Failure in this area can be due to:
1. Not being objective
– Sacred cows and senior managers projects are pushed to
the front and financially “tweaked”.

2. Some models maybe more appropriate to certain


companies and certain projects.
• Making a good project selection is a crucial step to
ensuring good project management downstream.

3-13
Project Portfolio Management
PPM is the systematic process of selecting, supporting, and managing
the firm’s collection of projects.
Projects should share a common strategic purpose and the same
scarce resources
The challenge is to balance between long term objectives and short
term needs and constraints. Senior Managers should ask:
• What projects the company should fund?
• Does the company have the resources to support them?
• Do these projects reinforce future strategic goals?
• Does this project make good business sense?
• Is this project complementary to other company projects?
3-14
Portfolio Management Tasks
• Decision making: Proceeding in a particular strategic direction
is influenced by market conditions, capital availability,
perceived opportunity and acceptable risk.

• Prioritization: based on cost, opportunity, top management


pressure, risk, strategic fit, desire for portfolio balance.

• Review: projects that satisfy the company priorities

• Realignment: when a new project is added to a portfolio the


company needs to examine whether that has an impact on
the attainment of the strategic goals.

3-15