Proposal

KSA Handling Services submitted a proposal to Vannacore, Inc. for ground clearing and other services. The proposal includes clearing 21,800 sqm of circular ground over 10 days for 85,000 pesos. It also includes road repair, trucking services, landscaping, and carpentry works over 48 days for a total of 231,000 pesos. The proposal requires 29 workers for 7 days to complete 100% of the ground clearing and tab cleaning. It provides a detailed budget breakdown and list of suppliers.

Uploaded by

Melvin Betonio
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
83 views5 pages

Proposal

KSA Handling Services submitted a proposal to Vannacore, Inc. for ground clearing and other services. The proposal includes clearing 21,800 sqm of circular ground over 10 days for 85,000 pesos. It also includes road repair, trucking services, landscaping, and carpentry works over 48 days for a total of 231,000 pesos. The proposal requires 29 workers for 7 days to complete 100% of the ground clearing and tab cleaning. It provides a detailed budget breakdown and list of suppliers.

Uploaded by

Melvin Betonio
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 5

GROUND CLEARING PROPOSAL FOR VANNACORE, INC.

DATE APRIL 7, 2023

TO VANNACORE, INC.
Linek, Nalus, Kiamba, Sarangani

FROM KSA HANDLING SERVICES


Fatima, Uhaw, General Santos City

RE PROPOSED BUDGET FOR GROUND CLEARING AND OTHER SERVICES TO RENDER AT VANNACORE, INC
LOCATED AT LINEK, NALUS, KIAMBA SARANGANI

WORK / JOB DISCRIPTIONS RATE DURATION AMOUNT

CLEARING AND CIRCULAR P


GROUND MOWERING
21 800sqmtrs CIRCUL PACKAGE 10 WORKING DAYS 85,000.00
8 400 Sqmtrs CIRCUL
2 1500 Sqmtrs RECT

MAIN ROAD REPAIR AND G PACKAGE 10 WORKING DAYS 70,000.00


TRUCKING SERVICES 3,000/DAY 10 WORKING DAYS 30,000.00
MAIN OFFICE LANDSCAPIN PACKAGE 3 WORKING DAYS 30,000.00
WAREHOUSE CLEARING PACKAGE 5 WORKING DAYS 60,000.00
CARPENTRY WORKS
6 MODULES OF ROOTS 5,000/SHED 10 WORKING DAYS 30,000.00
1 CENTRIFUGAL MOTO 7,000/SHED 3 WORKING DAYS 7,000.00
2 SMALL DISTRIBUTIO 2,000/SHED 2 WORKING DAYS 4,000.00
231,000.00
THIS PROPOSAL WAS MADE UPON THE REQUEST OF THE COMPANY
THE RATE WAS BASED ON THE ACTUAL AND PRESENT SITUATION DURING THE OCULAR INSPECTION DATE
AND MAY SUBJECT FOR ANY CHANGES AS DAYS GOES BY.
O RENDER AT VANNACORE, INC.

STATUS

ONGOING MOWERING

DAILY RATE

ONGOING
RENDERED 3 DAYS
DONE
NOT YET STARTED

DONE
ONGOING
ONGOING

G THE OCULAR INSPECTION DATED APRIL 2, 2023.


JOB ORDER WORKERS

MOWER 3
TAB CLEANING 5
CARPENTRY 3
CARPENTRY LABOR 3
CIRCULAR GRASS CLEARING 3
ROAD REPAIR LABORER 5
WEEDING 5
LANDSCAPING 2
29

GAS 80 LITERS
OIL 2LITERS
ASSORTED PLANTS
MOWER RENTALS 3
BOLDERS/GRAVEL/SOIL 8 LOADS
HAULING CAR RENTAL 1

20% ADMIN FEE


TOTAL PROPOSED BUDGET
NOTE: 7 WORKING DAYS WITH 29 MANPOWER FOR 100% COMPLETION ON G
EXCEPT FOR ROAD REPAIRS
RATE # OF DAYS TOTAL

500 7 10,500.00
350 7 12,250.00
550 7 11,550.00
350 7 7,350.00
350 7 7,350.00
350 7 12,250.00
350 7 12,250.00
500 7 7,000.00
80,500.00

63/LITER 7 5,040.00
168/LITER 7 336.00
10,000.00
300/Day 7 6,300.00
800/LOAD 6,400.00
3000/Day 3 9,000.00
37,076.00 117,576.00
23,515.20
141,091.20
ANPOWER FOR 100% COMPLETION ON GROUND CLEARING AND TAB CLEANING

OR NUMBER DATE AMOUNT TOTAL

YANNI HARDWARE 589 04/04/2023 2,340.00


RME 317 11/14/22 670.00
RME 210 2/31/23 4,460.00
RME 209 3/30/23 9,325.00
RME 203 11/16/22 480.00
RME 202 10/27/22 2,220.00
RME 201 10/27/22 3,140.00
22,635.00

SMH ENTERPRISES 5761 4/4/2023 642.00

COCO LUMBER 3955156 3/4/2023 20,224.00


6/4/2023 6,400.00
ATF 27307 3/31/23 50.00
BLACK POTS 4/4/2023 400.00
SOC 12612 5/4/2023 192.00
TRIPLE K 5769 2/4/2023
TRIPLE K 5806 5/4/2023
TRIPLE K 5819 6/4/2023
-
MOTOLANE 7730 3/4/2023
MOTOLANE 7729 3/4/2023
MOTOLANE 7742 4/4/2023
-
BAUTISTA GAS 131137 5/4/2023 500.00
51,043.00