BoQ-Beam Retrofitting Works LandT

This document is a bill of quantities (BOQ) for strengthening work at the Warangal Super Speciality Hospital. It includes 7 items: [1] Providing a steel cuplock system and support system for structural elements, [2] Supporting structural elements temporarily during repair work, [3] Conducting reinforcement scans, applying alloy strips and laminates to beams, [4] Installing carbon fiber laminates on beams, [5] Installing carbon fiber laminates on bottom of beams, [6] Strengthening structural elements with fiber wrapping, and [7] Applying fireproofing material. The document provides descriptions, quantities, units, rates and amounts for each work item.

Uploaded by

Abhijit Karpe
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
303 views2 pages

BoQ-Beam Retrofitting Works LandT

This document is a bill of quantities (BOQ) for strengthening work at the Warangal Super Speciality Hospital. It includes 7 items: [1] Providing a steel cuplock system and support system for structural elements, [2] Supporting structural elements temporarily during repair work, [3] Conducting reinforcement scans, applying alloy strips and laminates to beams, [4] Installing carbon fiber laminates on beams, [5] Installing carbon fiber laminates on bottom of beams, [6] Strengthening structural elements with fiber wrapping, and [7] Applying fireproofing material. The document provides descriptions, quantities, units, rates and amounts for each work item.

Uploaded by

Abhijit Karpe
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

BOQ for the strengthening work for Warangal Super Speciality Hospital

Sr. No. Description Qty Unit Rate Amount Remarks


1 Providing & erecting sturdy steel cuplock system as per manufacturers specifications including
necessary support system comprising of a combination of anchorage system and coupling
QRO m 1000
arrangements to and from the adjoining structure, supports etc.till completion of work activity
etc. complete. Material-L&T Scope. Installation-Vendor's scope
Supporting the structural element temporarily using heavy-duty flat-headed steel props of
minimum capacity 3 Ton and having height upto the bottom of the structural element erected
vertically in plumb, braced horizontally and diagonally at center with each other using 40 Nb steel
We are considering
2a. pipes and supporting a continuous 4" x 3" wooden runner just below the structural element, resting QRO m 1000
Horseen Make
on a wooden block to support the structure provisionally during repair and jacketing, etc. and
maintaining them in position till required as directed by the consultant (mode of measurement per
floor per prop per rep). Material-L&T Scope. Installation-Vendor's scope
Breaking, Removing of brickwork/ water proofing/ floor finish if required (Including plaster chipping
2b. within the brick area, tiles) work by low impact Hammer, Breaker without damaging the structure. QRO m 1000
Material-L&T Scope. Installation-Vendor's scope
Advanced 3D Reinforcement Scanning of RCC element:
Conducting adequate no's. of 300mm deep scan passes (concrete penetrating radar
scans) to detect the steel reinforcement or prestressing cables in existing RCC elements by using
3a.
ground/ Wall penetrating radar system to avoid the damages to the main bars during drilling for
inserting bolts etc. complete. using Hilti PS300/PS1000 machine/equivalent make, with
localisation accuracy of ±10 mm 3
Application of structural grade adhesive putty in between near surface high strength (450MPa)
3b. alloy strips and concrete surface with necessary surface cleaning filling of the gaps etc (Material
Make : SRMPL : SRM SA/ Equivalent Make) We are considering
380 m 4500 1710000
Providing, transporting, lifting, cutting in 100mm wide- & 12 mm thick SRM HS Plates (High strength Horseen Make
alloy strips of minimum 450MPa) of required length, including surface preperation for alloy
3c. plate, including fixing inposition on beams by maintining proper alignment as per detailed
drawing etc complete (Bolts to be paid under separte item). (Material Make : SRMPL : SRM HS
Plates/ Equivalent Make)
3d. Providing, Supplying, transporting, drilling holes upto 18 mm dia, 100mm depth by rotary hammer
drill, dust removing.
(i) 16 mm dia mechanical anchor (5.8 grade & above), up to 85 mm embedded/ up to18 mm
dia hole. (Material Make :Wurth / Klimas / SRMPL/Equivalent Make)
Installation of Laminates on top of beams
Providing and applying the marked application area with surface primer compatible with
proposed FRP laminate system and allowing it to cure as per manufacturers specification. Based on
4 drawings, the precured FRP elements are to be trimmed to the required application / working
lengths and applied with even and laminar layer of structural grade, non sag, epoxy adhesive and
placed in position as per manufacturers specification. Clearing of the spilled over epoxy from sides of
laminate and filling of gaps of upto 2 mm thick if any, etc complete. Note: Single and continous
laminate to be used for application i.e., lapping not allowed (Rate including wastages if any).
SRM C/Equivalent make Lam 100 x 5 Carbon Laminate NPS, with characteristic tensile strength of We are considering
225 m 5500 1237500
atleast 1500MPa, Ef > 140GPa, Transverse flexural strength of atleast 70MPa with inter laminar shear Horseen Make
4a.
strength of atleast 65MPa, fiber volume fraction of 65%, made under strict quality controlled
thermoset epoxy resin pultrusion process
Non prestress Anchor system : Providing and fixing in position suitably designed, system
compatible non corrosive aluminium alloy end anchor plate of H9 Grade of required size with M12
4b.
to M16 point anchorage including structural grade,
non sag, epoxy adhesive, compatible mechanical anchors as per manufacturers specifications.
(i) SRM AP H9NP 250x150x12(or Equivalent make)
(ii) SRM AP H9NP 350x150x12(or Equivalent make)
BOQ for the strengthening work for Warangal Super Speciality Hospital
Sr. No. Description Qty Unit Rate Amount Remarks
5 Installation of Laminates on bottom of beams
SRM C Lam 100 x 5 Carbon Laminate NPS (or Equivalent make), with characteristic tensile strength
We are considering
of atleast 1500MPa, Ef > 140GPa, Transverse flexural strength of atleast 70MPa with inter laminar 775 m 4100 3177500
5a. Horseen Make
shear strength of atleast 65MPa, fiber volume fraction of 65%, made under strict quality controlled
thermoset epoxy resin pultrusion process
PosiTest AT-M with 50mm C1583 Kit (or Equivalent make): Carrying out Pull-Off Adhesion Testing
with Automatic Adhesion Testers confirming to ASTM C1583 (tensile strength of concrete overlays).
6a. Including using 50mm C1583 Kit, ideal for measuring the tensile strength of concrete surfaces and
concrete repairs and overlay material. To be conducted on each beam on vertical surfaces where
wrapping is to be performed. 2 tests per beam.
Application of structural grade putty to builtup the surface with necessary surface cleaning filling of
6b.
the gaps etc (Material Make : SRMPL/Equivalent Make)
Strengthening structural elements with non metallic composite fiber wrapping system
comprise of fiber sheet and compatible saturant, by dry/wet layup system including, Surface
preparation: Grinding/ moulding concrete substrate, cleaning it with wire brush removing oil,
laitance if present, rounding sharp edges to min 25 mm radius etc. complete. Profiling:
Applying compatible primer on prepared substrate, Filling the holes and uneven surface with We are considering
thixotropic putty with Compatible flat metal pointless spreader etc. complete Wrapping: 810 sqm 5200 4212000
Horseen Make
6c. Wrapping the fiber sheet to structural element at desired orientation using Compatible flexible
spring type steel core oscillate tool to avoid any air voids etc. repeat the same procedure for multiple
layers(if any) with the interval of 8 hrs. Sand pasting on outer most wrap: Applying second coat of
saturant after min. 12 hrs, rectify air voids if any paste the river sand on it to make surface rough to
take any further finishes (Mode of measurement: surface area of Fiber sheet Consumed and
not surface area of RCC elements, overlaps to be measured seperately) Material make :
SRMPL/Equivalent Make
(i) SRM-C-WRAP UD900 Uni-directional carbon fiber wrap
Providing and fixing of cabon anchors SRM C Anchors , 75 mm embedment, 150 mm flay with
minimum 8 petals at 300 mm c/c or required spacing including drilling of holes, cleaning of dust
6d.
with air blowers, fixing of anchor with epoxy saturant, adhesive or putty and allowing it to cure in
position.
Providing and applying pre packed cementitious fire proofing material for 2 hours fire rating 640 sqm 2250 1440000
over strengthened area at a
7
thickness of upto 25mm for structural members. Material make: Carboline/Sika/SRMPL/Equivalent
Make
Total Amount Excluding Taxes: 1,17,77,000.00