PSM 1 Question and Answers
PSM 1 Question and Answers
You are responsible for achieving maximum business value for the project, and represent
the Voice of the Customer. What role do you play in this project?
Answer : B
Explanation:
The Product Owner is the person responsible for achieving maximum business value
for the project. He or she is also responsible for articulating customer requirements
and maintaining business justification for the project. The Product Owner represents
the Voice of the Customer.
Answer : D
Reference:
https://pmstudycircle.com/2015/01/a-short-guide-to-expected-monetary-value-emv/
Peter is a Scrum Master on a software development project for a premier chain of hospitals. It
is his responsibility to conduct Daily Standups. Which of the following is not a question
answered by the Scrum Team during the Daily Standups?
Answer : D
Reference:
https://www.mountaingoatsoftware.com/agile/scrum/meetings/daily-scrum
A. The iterative nature of Scrum with its rapid turnaround time and feedback cycles
allows for early detection of failures.
B. Risks can be managed only at the project level, even if they are related to or
originate in portfolios or programs.
C. Risk Burndown Charts aye an important tool for communicating information
related to risks to the Stakeholders.
D. Risk is largely minimized in Scrum due to the flexibility in adding or modifying
requirements at any time in the project lifecycle.
Answer : B
Reference:
http://blog.scrumstudy.com/how-scrum-framework-minimizes-risks-threats-in-projects-2/
Which of the following is a responsibility of the Scrum Master in the context of change in
Scrum?
A. Eliminating all changes that may affect the quality of deliverables and processes
B. Facilitating identification of Change Requests by the Scrum Team and their
assessment and prioritization by the Product Owner.
C. Providing requests for changes in a project.
D. Approving changes that are amended, removed, or added according to project
requirements, and communicating the same to the Scrum Team.
A. Ð’
B. В, С, and D
C. Ð’ and D
D. A and Ð’
Answer : C
Reference:
http://blog.scrumstudy.com/responsibilities-of-various-scrum-roles-in-an-organization/
Answer : B
On a hydroelectric power project, damage to life and property due to floods and landslides
has been identified as a potential risk. Which of the following Risk
Assessment Techniques can be used by the Scrum Team to assess the potential risk, and its
impact on project objectives?
Answer : A
Reference:
https://scrumstudy.wordpress.com/2014/08/27/scrum-master-how-are-risks-assessed-in-a-
scrum-project/
The Chief Scrum Master is a part of the Scrum Core Team that assembles to retrospect the
project and to identify, document, and internalize the lessons learned.
There are various tools to Retrospect Project during the Retrospect Project Meeting. Which of
the following tools can be used in this process?
A. Gap analysis.
B. SWOT analysis.
C. Proof of Concept.
D. Speed Boat.
Answer : D
Reference:
http://blog.scrumstudy.com/retrospect-scrum-project-the-lessons-to-be-learnt/
Answer : B
Explanation:
Primary objectives of Retrospect Sprint meeting are to identify three specific things:
1. Things the team needs to keep doing: best practices
2. Things the team needs to begin doing: process improvements
3. Things the team needs to stop doing: process problems and bottlenecks
4. These areas are discussed and a list of Agreed Actionable Improvements is created.
Reference:
http://blog.scrumstudy.com/all-about-retrospect-sprint-meeting/
The Scrum Master is attending a meeting in which the Scrum Team is estimating the effort
required to develop the functionality described in each User Story. The team wants to adopt
an estimation technique through which they will be able to quickly estimate a large number
of User Stories. Which of the following techniques do you think they should adopt?
A. Planning Poker.
B. Wideband Delphi.
C. Affinity Estimation.
D. Relative Sizing.
Answer : C
Explanation:
Affinity estimation is a technique used to quickly estimate a large number of User Stories.
Using sticky notes or index cards or tape, the team places User Storied on a wall or other
surface, in order from small to large. For this, each team member begins with a subset or User
Stories from the overall Prioritized Product
Backlog to place by relative size. This initial placement is done in silence. Once everyone has
placed their User Stories on the wall, the team reviews all the placements and may move User
Stories around as appropriate. The second part of the exercise involves discussion. Finally,
the Product Owner will indicate some sizing categories on the wall. These categories can be
small, medium or large, or they may be numbered using story point values to indicate relative
size. The team will then move User Stories into these categories as the final step in the
process. Some key benefits of this approach are that the process is very transparent, visible to
everyone, and is easy to conduct.
Reference:
http://blog.scrumstudy.com/estimation-techniques-in-scrum/
You are a Scrum Master on a project that is preparing to begin its first Sprint. You explain to
the Scrum team the concept of Daily Standup Meetings. You include all of the following
points in your introduction to the Daily Standup Meeting, EXCEPT:
Answer : B
Reference:
https://www.mountaingoatsoftware.com/agile/scrum/meetings/daily-scrum
The Scrum framework, being an Agile iterative process, inherently minimizes risk. Many
Scrum practices facilitate effective management of risk. Choose the option that is NOT a
correct pairing of a Scrum characteristic with its role in minimizing risk:
Answer : D
Reference:
http://blog.scrumstudy.com/how-scrum-framework-minimizes-risks-threats-in-projects/
Gregory is the Scrum Master on a project to create automated devices for the health industry.
He advocates that every member of the Scrum Team should actively participate in team
building activities, estimation meetings, and in Daily Standups. He looks to give more
responsibility to team members. Which of the following theories does Gregory seem to
subscribe to?
A. Theory X
B. Theory Y
C. Maslow's hierarchy of needs
D. Win/Win Conflict Resolution
Answer : C
Reference:
https://medium.com/serious-scrum/we-dont-let-the-teams-self-organise-fd27807d8e15
A large software company has 8 Scrum teams with each team having a Scrum Master. After
the Daily Standup everyday with their respective teams, all Scrum
Masters meet for a Scrum of Scrums. What are they likely to do during this meeting?
Andy, a Scrum Master, is helping his team draft a Sprint Backlog. In which of the following
phases would this Scrum process be in?
A. Initiate
B. Plan and Estimate
C. Implement
D. Review and Retrospect
Answer : B
Ans-B
2. Which of the following is a responsibility of the Scrum Master in the context of change
in Scrum?
A. Eliminating all changes that may affect the quality of deliverables and processes
B. Facilitating the identification of Change Requests by the Scrum Team and their
assessment and prioritization by the Product Owner.
C. Providing requests for changes in a project.
D. Approving amended, removed, or added changes according to project requirements and
communicating to the Scrum Team.
Ans-B
Ans-A
A. A, B, C, D
B. A, C, D
C. A, D
D. A, B
Ans-B
Ans-C
6. Which one of the following is NOT traditionally an activity of the Scrum framework?
A. Sprint planning
B. Sprint review
C. Sprint retrospective
D. Weekly inspection
Ans-D
Ans- C
A. A sprint is a condensed amount of time where developers work as many hours as they
need to finish the work assigned to them.
B. A sprint is a pre-specified amount of time in which the developer’s team works at a
sustained pace to complete a chosen set of items from the Product Backlog.
C. A sprint is a fixed amount of time set aside for the team to run tests and resolve any
outstanding bugs right before the product ships
D. A sprint is a pre-specified period during which team members choose individual items
from the product backlog to work on. A new article is brought into the sprint as each
item is completed.
Ans- B
Ans- B
10. How can software development projects be executed by implementing the Scrum
Framework?
Ans- C
Ans-B
12. Which of the following best describes the approach for determining the Sprint length?
Ans-D
13. What should the developers do if the product owner is repeatedly too busy to be
available?
A. Continue the work, record the assumptions and ask the customer later for input
B. Send the customer a written warning that the end product will be completed on time
but may not meet their needs
C. Allow the Business Analyst to take on the role of Proxy Product Owner
D. Draw the problem to the attention of the Scrum Master
Ans-D
Ans- B
Ans-D
Ans-D
17. What are the two primary artifacts of a sprint planning meeting, and what is the
related commitment?
Ans-A
18. Which of these statements best describes the Agile approach to teamwork?
A. The team should plan to work overtime regularly throughout the project
B. The team should expect to work longer hours towards the end of the project to deliver
all that was committed to
C. The team should strive for a sustainable pace that they can maintain potentially for a
long time
D. The team will regularly need to work many hours overtime but can compensate for this
during periods of less intensity
Ans-C
19. Who ultimately decides when the team has enough work for the sprint in planning?
A. The ScrumMaster
B. The product owner
C. The team Developers
D. The product owner, ScrumMaster, and team vote to determine when the sprint backlog
is full
Ans-C
A. Task focused
B. Process-oriented
C. Supportive
D. Disengaged
Ans-C
Ans-B
22. The “ MoSCoW “ technique is a popular prioritization technique, where the "M" stands
for ...
A. May have
B. Major
C. Must Have
D. Mandatory
Ans- C
Ans- B
Ans- A
25. Once an Agile project is underway, what should the approach to planning be?
Ans-A
26. What does Scrum advise a team to do with the product backlog items it chooses to
bring into the sprint?
A. The team should break each product backlog item into work items that preferably take
no more than a day.
B. The product owner assigns each product backlog item to the specialist best suited to
carry the work.
C. The team asks the ScrumMaster to research the product backlog items and decide who
should work on each one.
D. The team doesn't do anything with the product backlog items. Scrum doesn’t use tasks
or task lists.
Ans-A
27. As per Scrum, which one of the following is an essential feature of the daily stand-up
(daily Scrum) meeting?
A. The meeting should ensure that it is clear to all which team members are not performing
B. All Developers participate every day and are willing to help each other in completing the
work of the Sprint
C. Everyone is required to report how much time was spent on each work item
D. No one is allowed to leave the stand-up meeting until all problems raised have been
solved
Ans-B
28. How could the maintainability of the developing product be improved in a team?
Ans-D
Ans-C
Ans- D