MSDB Preparing Manual and Installation Iss2
MSDB Preparing Manual and Installation Iss2
Installation Manual
1 Document Symbols ........................................................................................ 4
2 Safety .............................................................................................................. 5
2.1 Distribution rules ..................................................................................................................................... 5
3 Technical Data ................................................................................................ 6
3.1 Standards ................................................................................................................................................... 6
3.2 Dimensions & weights .............................................................................................................................. 7
4 Installation Procedure ................................................................................... 8
4.1 Procedure for preparing a Lucy Electric MSDB for manual handling and installation. ....................... 8
4.1.1 Procedure to strip down the Lucy Electric MSDB (before mounting) ..................................................................8
4.2 Procedure to mount the Lucy Electric MSDB ........................................................................................ 10
4.3 Cabling preparation for the Lucy Electric MSDB .................................................................................. 10
4.3.1 General Cabling Notes ...........................................................................................................................................11
4.3.2 Cable preparation ..................................................................................................................................................11
4.3.3 SNE installations ....................................................................................................................................................11
4.3.4 CNE installations ....................................................................................................................................................12
4.3.5 1J And 2J Cable installations .................................................................................................................................13
4.3.6 Additional Information For 2J Configuration ......................................................................................................14
4.3.7 Connection of outgoing 100A Service ways ........................................................................................................14
4.4 Recapitulation of the salient installation points: ................................................................................. 16
4.5 SWA gland sizes ..................................................................................................................................... 16
This manual was produced in April 2017 and applies to the LV MSDB range.
Due to Lucy Electric’s policy of continuous research and development, Lucy Electric reserves the right to change
the design and specification of its products without prior notice or liability.
This document (LIP10-034 Issue 1) supersedes LIP09-085 and LIP10-032, which have been withdrawn.
DANGER: failure to follow this instruction will result in death or serious injury.
WARNING: failure to follow this instruction may result in death or serious injury.
Installers of this equipment must have experience and expertise with LV equipment.
To minimise the risk of personal injury or equipment damage, this manual must be read carefully prior to
installation.
This manual MUST be readily available whenever the unit is handled or during installation.
A copy will be found in every new MSDB procured and must be carefully read and complied with.
If this equipment has incurred damage prior to installation, contact the manufacturer and/or supplier
immediately.
• Before commencing any work, ensure that the necessary safety precautions, risk
assessments and safety documents are in place.
• Installation must be carried out observing the appropriate Operational Safety Rules.
In all instances risk assessments should be undertaken prior to undertaking any new activity where potential
hazards are concerned. This is particularly important in order to identify the necessity for specific PPE, that
may be required and that cannot be avoided even with safe systems of work in place.
Appropriate PPE must be worn when performing any form of switching operation in order to comply with
company safety procedures.
3.1 Standards
MSDB complies with the following standards:
IP Rating BS EN 60529
1J Type 2J Type
* Doors, fuse handles, connectors, miscellaneous fixings, shrouds and covers have been removed as detailed in
Section ’4.1.1 Procedure to strip down the Lucy Electric MSDB (before mounting)’ on page 8
Safety notice: This equipment must be installed by competent personnel in full conformity with the latest
edition of local and National Wiring Regulations currently in force and the Electricity at Work Regulations.
Full PPE must be worn at all times. Note that this operation necessarily involves the intervention of two
persons in order to comply with Health and Safety Manual Handling requirements.
• All work MUST be carried out in accordance with current issued Company Safety Rules.
• This installation procedure MUST NOT be carried out with the cable live.
• Make sure that the site is safe and work in accordance with your on-site risk assessment.
• If in doubt about any aspect of your work, contact your supervisor.
• When installing an MSDB the unit needs to be a minimum of 400mm from floor level (with the
duct lining up with the cable entry). Where the duct does not line up with the cable entry, this
height will need to be increased significantly. The actual height will be dependent upon the size
of the cable and the amount of misalignment. The maximum bending radius of 12x the cable
diameter must not be exceeded.
• DO NOT disassemble the factory made busbar or terminal block connections thereto (exception:
CNE link between the neutral and earth bars). They have been factory tightened to a specific
torque and should not be disturbed.
4.1.1 Procedure to strip down the Lucy Electric MSDB Note: The weight of the unit as detailed in “3.2
(before mounting) Dimensions & weights” on page 7 can be
achieved by following operations.
1 : Remove the nut and bolt which maintain the 2 : With the doors opened and the weight relieved
doors in the closed position and disconnect the from the hinges, pinch the two hinge spring pins
door earth equipotential conductors which are and lift the doors clear.
secured by M6 nuts.
5 : Using the appropriate screwdriver, unscrew the 6 : Slide out the solid and perforated gland plates
single captive screw retaining the insulated and set aside.
connector cover in place and set aside all the
covers.
• There is a choice of three phase connector mounting positions allowing different conductor
routes to give the optimum result for any given cable lay.
• When making off the conductors, always avoid delta up situations as this hinders correct
seating of the grey connector shrouds due to the protruding shear bolt stubs.
• On 4C SNE installations, always commence by positioning the neutral conductor as flatly as
possible along the length of its channel. This is to ensure that thee is clearance between it and
any phase connects that may be situated above it.
• Any crossing of the cores must take place as close as possible to the cable crutch to avoid a
build-up of cores which would prevent the lowermost grey connector shroud from locating
properly.
• Only commence the shearing off of the connector bolt heads once all the conductors are located
and loosely tightened in their respective connectors. This avoids the risk of connections
loosening due to adjacent conductors being manipulated during the jointing process.
• In the event that meter tails are terminated in the cabinet, ensure that both the phase and
neutral conductors pass through the same aperture in the MSDB casing.
4.3.2 Cable preparation
1 : Strip out all redundant cable tapes and wadding, consolidate the strands of the copper earth conductor and
offer up the cable to the cabinet.
2 : Perform a preliminary assessment of the routes the individual conductors will have to take and plan
accordingly to avoid unnecessarily tight bends which are likely to induce stress to the assembly.
4.3.3 SNE installations
1 : Remove the link between the neutral and earth 2 : Position the short neutral connector upstand in a
terminal bars by rotating the link away as vertical orientation on the neutral busbar, insert
shown. the bolt through the busbar and with the plain
Note: Depending on the variant chosen, the neutral and spring washers in place, tighten to a torque
and earth terminal bars may be located either at the of 45Nm. Attach the neutral connector to the
top or bottom of the unit. upstand and tilt slightly downwards to avoid
having a double set in the conductor.
Neutral Connector
Earth
Connector
4.3.4 CNE installations
1 : Make sure that the link is in place between the 2 : Select the optimum orientation for the brass
neutral and earth bars and securely tightened neutral earth terminal, secure it to earth busbar
(28Nm). (28Nm torque) and terminate the neutral earth
conductor via the shear head bolt.
2J Type 1J Type
Shown below is an example of how the 2J MSDB can be cabled using 4C SNE cable. Determine the
best possible conductor routing that suits the given cable lay before commencing work.
Making Off The Neutral Making Off The Brown Phase
2 : When all the phase conductors are set and in position in their connectors, verify that conductor secondary
insulation is not in contact with any exposed metalwork of opposite polarity and shear off the connector
bolts.
3 : The next sequence is a reversal of section 4.1.1. 4 : Cabinets are fitted with an external earth bar
Remove all cabling debris that may be present in having two M12 nuts/bolts for connection to the
the cabinet. Replace and secure all previously DNO earth. Once the termination has been
removed screens and covers ensuring that they completed, DNO sealing wires can be put in place
seat correctly. Reinstall the doors and attach the preventing the earth from being disconnected.
earth leads to their studs.
The cabinet is prepared for attachment to the wall in exactly the same manner as 1J units by removing
doors, fuse handles and phase shrouds. There are four M8/M10 wall fixing points with keyhole slots as per
the 1J unit although they are spaced further apart to reflect the extra width of the 2J units.
Observe the same cabling methodology as previously stated for the 1J in relation to core routing and
conductor orientation in terminals. When installing the neutral terminal in 4c configurations, do not omit
to tighten all the setscrews on the short terminal upstand if this has been disturbed.
4.3.7 Connection of outgoing 100A Service ways
1 : Slacken the thumbscrews and extract the main J 2 : Similarly remove the 100A Service way fuse
type fuse handles, if these have not already been handles in the adjoining compartment, if not
removed. already removed.
6 : Re-instate all previously removed covers, shields and fuse handles equipped with their appropriate fuses.
Ensure cabinet is ready for putting into service and check Customer polarity.
1 : Conduct a risk assessment and ensure that there is adequate manpower to lift the units into position. Close
attention should be paid to compliance with the Manual Handling Operators Regulations (SI 1992/2793).
Weights range from 42kgs to 82kgs fully equipped with doors and fuse handles attached.
2 : Remove doors, shields, fuses etc. to lighten the unit prior to manhandling to the installed position.
3 : Using the fixing centre tape provided, mark the wall at the height that will allow the correct cable bend
radius for the cable being used.
4 : Drill the mounting surface and install the appropriate fixing devices.
5 : Bring the (lightened) unit to the wall and affix.
6 : Trial fit all the cores before commencing the shear-off operation.
7 : Sectorial aluminium conductors should be laid delta down in the phase and neutral connectors to keep
shear-off bolt stub protrusions to a minimum.
8 : Execute any core cross overs as close as possible to the cable point of entry in to the cabinet.
9 : Replace the doors, door earth leads and all previously removed covers and shields. Ensure that the circuit
identification labels are filled in and securely attached. Check that the cable glands are correctly fitted.
10 : Access to the outgoing Service ways and J fuses may be restricted through the use of DNO safety padlocks
in the respective door tabs.
Lucy Electric UK Limited Lucy Electric Arabia Co. Ltd Lucy Asia Pacific Sdn. Bhd
Howland road, Thame, Oxfordshire, OX9 Novotel Business Centre, PO Box 35340 Unit 17-05-06, Level 17
3UJ, United Kingdom. Dammam 31488, Saudi Arabia. PJX-HM Shah Tower,
Tel: +44 (0) 1844 267 267 Tel:+96 6138 147 910 No16A Jalan Persiaran Barat, 46050
Fax: +44 (0) 1844 267 223 Fax: +96 6138 147 914 Petaling Jaya, Selangor, Malaysia
E-mail: [email protected] E-mail: [email protected] Tel: +603 74910700
Aftersales: Fax: +603 79316923
[email protected] E-mail: [email protected]
Lucy Middle East F.Z.E. Lucy Electric South Africa (Proprietary) Limited Lucy Electric (Beijing) Co. Ltd
PO Box 17335, Jebel Ali, Dubai, Unit 12 & 13,Block C, Honeydew Bussiness Park, 1503 Room 1122, Tower A, Gateway
United Arab Emirates. Citrus Street, Laser Park, Honeydew, 2170, South Square, No. 18 Xiaguangli, North
Tel: +9714 812 9999 Africa. Road East Third Ring, Chaoyang
Fax: +9714 812 9900 Postal Address: P.O. Box 1078, Honeydew. Distric, Beijing, China. 100027
E-mail: [email protected] Tel: +27 11 0257490 Tel: +86-(0)10 59231176
Aftersales: [email protected] Fax: +27 11 7943277 Fax: +86-(0)10 59231177
E-mail: [email protected] E-mail: [email protected]
Lucy Electric Thailand Limited Lucy Electric India Private Ltd
388 Exchange Tower, 37th Flr Unit 3702 F-10, MIDC
Sukhumvit Road, Klongtoey Sub district Ambad
Klongtoey District, Bangkok, 10110 Nasik 422010, India.
Thailand Tel: +91 253 2381603
Tel: +66 (02) 663 4290 Fax: +91 253 2381247
Fax: +66 (02) 663 4293 E-mail:[email protected]
E-mail: [email protected]
www.lucyelectric.com