Admin and Control Building Schedule
Admin and Control Building Schedule
November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022
Mode 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 31 5 10 15 20 25 2 7 12 17 22 27 1 6 11 16 21 26 1
1 Admin and Control Building 151 days Dec 1 '21 Apr 30 '22
2 Ground Floor North Zone 11 days Dec 1 '21 Dec 11 '21
3 ground floor casting 3 days Dec 1 '21 Dec 3 '21
4 toilet room casting 7 days Dec 1 '21 Dec 7 '21
5 column to 1st floor 7 days Dec 5 '21 Dec 11 '21
6 Ground Floor South Zone 15 days Dec 1 '21 Dec 15 '21
7 column to 1st floor 5 days Dec 1 '21 Dec 5 '21
8 staircase core to 1st floor 15 days Dec 1 '21 Dec 15 '21
9 1st Floor CCR Zone 27 days Dec 12 '21 Jan 7 '22
10 scaffolding and formwork for postension slab 7 days Dec 12 '21 Dec 18 '21
11 rebar and postension system installation, slab casting 8 days Dec 19 '21 Dec 26 '21
12 column to upper 1st floor and roof 10 days Dec 29 '21 Jan 7 '22
13 1st Floor Admin Zone 35 days Dec 19 '21 Jan 22 '22
14 scaffolding and formwork for postension slab 6 days Dec 19 '21 Dec 24 '21
15 rebar and postension system installation, slab casting 15 days Dec 27 '21 Jan 10 '22
Project: Admin and Control bui Split Inactive Task Duration-only Finish-only Progress
Date: Dec 2 '21 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress