0% found this document useful (0 votes)
19 views

Admin and Control Building Schedule

This document outlines a construction project timeline with 30+ subtasks for building an admin and control building over 151 days from December 2021 to April 2022. Key milestones include ground floor construction from December 1-15, 2021; first floor construction from December 12, 2021 to January 22, 2022; roof construction from January 8 to March 3, 2022; and architectural, mechanical, electrical and panel installation work from February 25 to April 30, 2022. The project aims to complete structural work, mechanical and electrical systems installation, interior finishing and commissioning by the end of April 2022.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
19 views

Admin and Control Building Schedule

This document outlines a construction project timeline with 30+ subtasks for building an admin and control building over 151 days from December 2021 to April 2022. Key milestones include ground floor construction from December 1-15, 2021; first floor construction from December 12, 2021 to January 22, 2022; roof construction from January 8 to March 3, 2022; and architectural, mechanical, electrical and panel installation work from February 25 to April 30, 2022. The project aims to complete structural work, mechanical and electrical systems installation, interior finishing and commissioning by the end of April 2022.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Task Name Duration Start Finish

November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022
Mode 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 31 5 10 15 20 25 2 7 12 17 22 27 1 6 11 16 21 26 1
1 Admin and Control Building 151 days Dec 1 '21 Apr 30 '22
2 Ground Floor North Zone 11 days Dec 1 '21 Dec 11 '21
3 ground floor casting 3 days Dec 1 '21 Dec 3 '21
4 toilet room casting 7 days Dec 1 '21 Dec 7 '21
5 column to 1st floor 7 days Dec 5 '21 Dec 11 '21
6 Ground Floor South Zone 15 days Dec 1 '21 Dec 15 '21
7 column to 1st floor 5 days Dec 1 '21 Dec 5 '21
8 staircase core to 1st floor 15 days Dec 1 '21 Dec 15 '21
9 1st Floor CCR Zone 27 days Dec 12 '21 Jan 7 '22
10 scaffolding and formwork for postension slab 7 days Dec 12 '21 Dec 18 '21
11 rebar and postension system installation, slab casting 8 days Dec 19 '21 Dec 26 '21

12 column to upper 1st floor and roof 10 days Dec 29 '21 Jan 7 '22
13 1st Floor Admin Zone 35 days Dec 19 '21 Jan 22 '22
14 scaffolding and formwork for postension slab 6 days Dec 19 '21 Dec 24 '21
15 rebar and postension system installation, slab casting 15 days Dec 27 '21 Jan 10 '22

16 column to roof 7 days Jan 13 '22 Jan 19 '22


17 staircase core to roof floor 10 days Jan 13 '22 Jan 22 '22
18 Roof Floor 55 days Jan 8 '22 Mar 3 '22
19 scaffolding and formwork for postension slab 20 days Jan 8 '22 Jan 27 '22
20 rebar and postension system installation, slab casting 15 days Jan 28 '22 Feb 11 '22

21 remove scaffolding 14 days Feb 18 '22 Mar 3 '22


22 Archi.,Building Services, Panel Installation in CCR & 65 days Feb 25 '22 Apr 30 '22
DCS Room
23 M&E 1st Fixed above ceiling 28 days Feb 25 '22 Mar 24 '22
24 Blockwall installation 21 days Feb 25 '22 Mar 17 '22
25 Plastering 16 days Mar 9 '22 Mar 24 '22
26 Ceiling installation 21 days Mar 14 '22 Apr 3 '22
27 Panel support installation 37 days Mar 25 '22 Apr 30 '22
28 Panel and Cable trayinstallation, Tempo.A/C installation 37 days Mar 25 '22 Apr 30 '22

29 Raised floor installation 37 days Mar 25 '22 Apr 30 '22


30 ELECTRICAL WORKS 1 day? Nov 22 '21 Nov 22 '21
31 Lighting system Ground floor
32 Lighting system 1st floor
33 Communication system
34 Fire Alarm system
35 HVAC system

Task Project Summary Manual Task Start-only Deadline

Project: Admin and Control bui Split Inactive Task Duration-only Finish-only Progress
Date: Dec 2 '21 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1

You might also like