Contract Time Extension
Contract Time Extension
Code: DPWH-BOC-TVA-F001
Bureau of Construction Revision No.: 01
CONTRACT TIME EXTENSION AUDIT CHECKLIST Date: January 10, 2023
Annex C (Conformance with Existing Laws/Policies) Page No.: 1 of 1
CHECK IF THE FOLLOWING ARE IN ACCORDANCE WITH THE EXISTING LAWS, RULES AND REGULATIONS, AND
DEPARTMENT POLICIES AND ISSUANCES
MAX. COMPLIANCE ACTUAL
REQUIREMENTS REMARKS
SCORE YES NO N/A SCORE
1 There is legal basis in the issuance of Suspension Order
based on the circumstances cited in RA 9184 and other 30
laws and Department Policies
2 Compliance of Time Extension 25
a. The number of pre-determined unworkable calendar
days is considered in the computation of Time
Extension
b. The activities affected fall within the critical path of
the construction schedule*
10
c. The CTE is approved by the authorized DPWH
5
Officials
d. The contractor has no fault in the extension of
10
contract time
3 Compliance with Time Frame in the
Processing/Preparation
20
a. Processing is consistent with the DOTs Time Frame
(Letter Request of the Contractor to DOTs to 10
Processing and Approval
b. The notices of the contractor is consistent with
Section 10.1 Annex E of the Revised IRR of RA 9184 5
Maximum Score 95
*except for items that are parallel activities but
affects the duration of the project
a. Barangay Resolution 15
b.
c.
d.