Mohsin Javed has prepared an action plan as a trainee E&I engineer with 11 items to complete various documentation, inspection, and maintenance tasks for the E&I department. Several items are already completed, including preparing equipment drawings and wiring diagrams, assessing the lightning protection system, and reviewing maintenance documentation. Other items are in progress, such as incorporating generator warmup procedures into the PM plan and inspecting distribution boards. Remaining items that have not yet started include cable sizing calculations and preparing maintenance procedures and standards. Mohsin is working with field mentors to complete routine maintenance activities and assignments on an ongoing basis.

Uploaded by

mohsin awan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views2 pages

Action Plan (Mohsin Javed Trainee Engineer E & I)

Mohsin Javed has prepared an action plan as a trainee E&I engineer with 11 items to complete various documentation, inspection, and maintenance tasks for the E&I department. Several items are already completed, including preparing equipment drawings and wiring diagrams, assessing the lightning protection system, and reviewing maintenance documentation. Other items are in progress, such as incorporating generator warmup procedures into the PM plan and inspecting distribution boards. Remaining items that have not yet started include cable sizing calculations and preparing maintenance procedures and standards. Mohsin is working with field mentors to complete routine maintenance activities and assignments on an ongoing basis.

Uploaded by

mohsin awan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Action Plan

Mohsin Javed
Trainee E & I Engineer

Serial # Description Status from Field Target Completion Date Progress Mentor Remarks
(Complete/In Progress/Not Yet Started)

Review & Preparation of all the E & I Department Documentation.


Equipment Details.
SLDs
Panels Wiring Diagrams
PM Plans.
Checklists. Reviewed the SLDs & verification with field equipments to finalize the whole
1 Logs sheets. Completed In first Routa facility SLD with proper details.
Tripping Sheets
Equipment & panels Rating, Taggings.
Cable Schedule
History logs.
MSIs.

2 Preparation of SLDs for Each DB on field Completed 10-May-23 Completed all SLDs in AUTOCAD as per original format
DOL Wiring diagram for Diesel Loading pump completed
3 Preparation of Wiring Diagrams for DOLs & VFDs Completed 15-May-23 VFD Panel A completed

4 Lightening Protecton system Assessment at Halini Completed 15-May-23 Completed as per NFPA 780 Standard\ Reviewed and finalized

Diesel Genset Warmup Activity


Monthly PM is being carried out after and warmup activiity is being performed
5 Incorporating Diesel Genset Warmup Activity at No Load fortnightly in PM Plan In Progress 9-May-23
Preparation of Warmup Checklist too.

Camp History log to log all the issues & troubleshooting procedure with actual
Review of Camp Maintenance Documentation
Caravan Inspection Plan reason.
Caravan Inspection Plan follow up.
6 Camp Air Conditioning system Maintenance Plan & last Service Tagging Completed In first Routa
Follow up of AC Conditioning PMs.
Last Service Tag & Next service Tag on Each AC will be displaced.
Caravan Inspection Checklists.
Preparing the PM Plan for caravans with proper schedule
Caravan Breaker Tagging.

Inspection of All Field DBs


Cable Dressing & Tagging
Proper cable Termination & Glanding.
Inspection of DBs in progress
Individual Breaker Tagging & Rating labels
7 Proper Earthing Connections Completed In 2nd Rota Tagging is in progress on each breaker.
DBs History log to maintain record of previous issues for troubleshooting purpose. SLD & Breaker Details will be displayed on Each DB.
Earth Pits Resistance Record.
Electrical Cable Meggering Results

Arrangment of All the relavent docuements to critical equipments.


OEM manual.
Serivice Manual In Progress In
Troubleshooting Proceudures etc
Parts Manuall

8 Lux Metering on field Not Yet Started As per the availability of LUX meter

9 Electrical Cable Sizing Not Yet Started 2nd Routa Reviewing the Cable schedule to check the lengths of laid cables
Breaker Ratings Calculation & Sizing
Preparation of E & I Department MSI & Procedures
Review of Existing MSIs
Earth Pits Meggering & Maintenance Procedure
Electrical Cable Meggering Procedure.
Electrical Motors Meggering & insulation test Procedure
Electrical Motor Maintenance & Troubleshooting
Direct online Starter Maintained & Troubleshooting
Variable Frequency Drives Troubleshooting & maintained Procedure
10 Calibration of Fields instrumentations Not Yet Started 1st Routa
Maintenance of UPS system
Procedure for Inspection & Maintenance of Distribution Boards
Procedure for Inspection, Troubleshooting & Maintenance of Wellhead Solar Panels
Procedure for Inspection & Maintenance of Circuit Breakers
Procedure for Troubleshooting & Maintenance of Gas Detectors
Procedure for Troubleshooting & Maintenance of Flame Detectors
Procedure for Troubleshooting & Maintenance of PLC
MSI & Procedure as per the equipment's

Routine Maintenance activities.


Any Troubleshooting or any requirement based on the field operation.
11 In Progress On Going
PM/CM Activities.
Assignments Assigned by field Mentors