Tri Jaya BILL OF QUANTITY
FABRIKASI MEKANIKAL INDUSTRI 7-Dec-22
Jl. Raya Sidorejo 69 Krian Sidoarjo Telp. 081 357877600
e-mail :
[email protected] NO : QUO-2206-033
NO DESCRIPTION QTY UNIT UNIT PRICE INSTALATION PRICE TOTAL (IDR)
Pekerjaan Pembuatan Air Hood
Air hood
Ukuran : 3000x1700x1000mm, dia. 340mm,
Tebal : 2mm carbon steel
Air Hood 476 2 pcs IDR 12,090,000 IDR 24,180,000
Flange : 5mm carbon steel
Pembuatan By CV Tri Jaya
Air hood
Ukuran : 4000x600x1500mm
Tebal : 2mm carbon steel
Air Hood 340 2 pcs IDR 22,971,000 IDR 45,942,000
Flange : 5mm carbon steel
Pembuatan By CV Tri Jaya
Pekerjaan Pembuatan Support Air Hood & Pipa
Air Pipe, Square (340x340mm) to round (dia.340mm),
Tebal : 2mm carbon steel
Air Hood 340 Support 4 Meter IDR 2,170,000 IDR 8,680,000
Flange : 5mm carbon steel
Pembuatan By CV Tri Jaya
Air Pipe, dia. 340mm,
Tebal : 2mm carbon steel
Pipa DN 340 15 Pcs IDR 1,054,000 IDR 15,810,000
Flange : 5mm carbon steel
Pembuatan By CV Tri Jaya
Air Pipe, dia. 530mm
Tebal : 2mm carbon steel
Pipa DN 530 30 Meter IDR 1,782,500 IDR 53,475,000
Flange 5mm carbon steel
Pembuatan By CV Tri Jaya
Air Pipe, dia. 480mm
Tebal : 2mm carbon steel
Pipa DN 480 2 Meter IDR 1,751,500 IDR 3,503,000
Flange : 5mm carbon steel
Pembuatan By CV Tri Jaya
Silencer and hood,dia.600mm
Silincer Dn 600 Bahan : Mild steel/Baja Lunak 2 pcs IDR 25,296,000 IDR 50,592,000
Pembuatan by CV Tri Jaya
Pekerjaan Pembuatan Pipa two Way
Pipe two-way, dia. 480mm and dia. 340mm,Deg:30°
Tebal : 2mm carbon steel pcs
Pipa Two Way 480 1 IDR 3,255,000 IDR 3,255,000
Flange : 5mm carbon steel
Pembuatan By CV Tri Jaya
Pipe two-way, dia. 530mm,480mm,340mm, Deg:30°
Tebal : 2mm carbon steel
Pipa Two Way 530 - 1 1 set IDR 3,828,500 IDR 3,828,500
Flange : 5mm carbon steel
Pembuatan By CV Tri Jaya
Pipe two-way, dia. 530mm and dia. 340mm, Deg:30°
Tebal : 2mm carbon steel
Pipa Two Way - 2 1 pcs IDR 3,596,000 IDR 3,596,000
Flange : 5mm carbon steel
Pembuatan By CV Tri Jaya
Pipe elbow, dia. 340mm, Deg:60°
Tebal : 2mm carbon steel
Pipa Elbow 340 -1 4 pcs IDR 1,116,000 IDR 4,464,000
Flange : 5mm carbon steel
Pembuatan By CV Tri Jaya
Pipe elbow, dia. 340mm, Deg:90°
Tebal : 2mm carbon steel
Pipa Elbow 340 - 2 3 pcs IDR 1,674,000 IDR 5,022,000
Flange : 5mm carbon steel
Pembuatan By CV Tri Jaya
Pipe elbow, dia. 530mm, Deg:90°
Tebal : 2mm carbon steel
Pipa Elbow 530 7 set IDR 2,867,500 IDR 20,072,500
Flange : 5mm carbon steel
Pembuatan By CV Tri Jaya
Pekerjaan Pembuatan Valve
Air butterfly valve, dia.340mm
Tebal : 2mm carbon steel
Valve - 1 5 pcs IDR 930,000 IDR 4,650,000
Flange : 5mm carbon steel
Pembuatan By CV Tri Jaya
Air butterfly valve, dia.530mm
Tebal : 2mm carbon steel
Valve - 2 2 pcs IDR 1,255,500 IDR 2,511,000
Flange : 5mm carbon steel
Pembuatan By CV Tri Jaya
Pekerjaan Pembuatan Support Pipa dan Dust Collector
Support Pipa 8 Pcs IDR 4,000,000 IDR 32,000,000
Support Dust Collector 2 Pcs IDR 13,000,000 IDR 26,000,000
Jasa Install total & Mobilitas 1 Set IDR 160,000,000 IDR 160,000,000
Biaya Pembuatan Panel 1 Set IDR 47,039,375 IDR 47,039,375
Biaya Sewa Tempat Tinggal 1 Bulan IDR 2,000,000 IDR 2,000,000
TOTAL IDR 516,620,375