Well Foundations
Well Foundations
The following are the advantages of well foundations over other types of deep foundations
such as pile foundations:
1. The effect of scour can be better withstood by a well foundation because of its large
cross-sectional area and rigidity.
2. The depth can be decided as the sinking progresses, since the nature of the strata can
be inspected and tested, if necessary, at any desired stage. Thus, it is possible to
ensure that it rests upon a suitable bearing stratum of uniform nature and bearing
power.
3. A well foundation can withstand large lateral loads and moments that occur in the
case of bridge piers, abutments, tall chimneys, and towers; hence it is preferred to
support such structures.
4. There is no danger of damage to adjacent structures since sinking of a well does not
cause any vibrations.
The elements of a well foundation are: (i) Cutting edge (ii) Curb (iii) Concrete seal or Bottom
Plug (iv) Steining (v) Top Plug, and (vi) Well Cap.
i. Cutting Edge: The function of the cutting edge is to facilitate easy penetration or sinking
into the soil to the desired depth. As it has to cut through the soil, it should be as sharp as
possible, and strong enough to resist the high stresses to which it is subjected during the
sinking process. Hence it usually consists of an angle iron with or without an additional
plate of structural steel. It is similar to the sharp-edged cutting edge of a caisson shown
in Fig.
ii. Steining: The steining forms the bulk of the well foundation and may be constructed with
brick or stone masonry, or with plain or reinforced concrete occasionally. The thickness
of the steining is made uniform throughout its depth. It is considered desirable to provide
vertical reinforcements to take care of the tensile stresses which might occur when the
well is suspended from top during any stage of sinking.
iii. Curb: The well curb is a transition member between the sharp cutting edge and the thick
steining. It is thus tapering in shape. It is usually made of reinforced concrete as it is
subjected to severe stresses during the sinking process.
iv. Concrete Seal or Bottom Plug: After the well foundation is sunk to the desired depth so
as to rest on a firm stratum, a thick layer of concrete is provided at the bottom inside the
well, generally under water. This layer is called the concrete seal or bottom plug, which
serves as the base for the well foundation. This is primarily meant to distribute the loads
on to a large area of the foundation, and hence may be omitted when the well is made to
rest on hard rock.
v. Top Plug: After the well foundation is sunk to the desired depth, the inside of the well is
filled with sand either partly or fully, and a top layer of concrete is placed. This is known
as ‘top plug’. The sand filling serves to distribute the load more uniformly to the base of
the well, to reduce the stresses in the steining, and to increase the stiffness of the well
foundation. However, as this adds to the weight and load transmitted to the foundation
stratum, the engineer has to consider the desirability or otherwise of providing the sand
filling from the point of view of bearing power and settlement. The top plug of concrete
serves to transmit the loads to the base in a uniform manner.
vi. Well Cap: The well cap serves as a bearing pad to the superstructure, which may be a
pier or an abutment. It distributes the superstructure load onto the well steining
uniformly.
Sinking of Wells
If the river bed is dry, the cutting edge over which the well curb is to be built is placed at the
correct position after excavating the bed for about 150 mm for seating. If there is water, with
a depth upto 5 m, a sand island is created before placing the curb. The size of the island
should be large enough to accommodate the well with adequate working space all round In
case the depth of water is more than 5 m, it is more economical to build the curb on the bank
and float it to the site.
Wooden sleepers are usually inserted
below the cutting edge at regular
intervals to distribute the load evenly
on the soil. The shuttering of the well
curb is erected—the outer one with
steel or wood and inner with brick
masonry. The reinforcements for the
curb are then placed in position, the
vertical bars projecting about 2 m
above the top of the curb. Concreting
of the curb is done in continuous
operation. After the curb is cured and allowed to cure for at least seven days, the shuttering
may be removed as also the sleepers.
The Steining is constructed with a height of 1.5 m at a time and sinking done after allowing at
least 24 hours for setting. Once the well has acquired a grip of about 6 m into the ground, the
steining can be raised 3 m at a time. The height of any lift is restricted such that the well does
not lose stability.
The sinking process is commenced after the curb is cast and the first stage of steining is ready
after curing. The material is excavated from inside manually or mechanically. Manual
dredging is feasible when the depth of water inside the well is not more than 1 m. An
automatic grab operated by diesel winches is used when the depth of water is more. Blasting
with explosives is used when weak rock is encountered.
The well should be sunk straight and vertical at the correct position. It is not an easy task to
achieve this objective in the field. Sometimes the well tilts onto one side or it shifts away
from the desired position.
Tilts and shifts must be carefully noted and recorded. Correct measurement of tilt is an
important observation in well sinking. It is difficult to specify permissible values for tilts and
shifts. IS:3955-1967 recommends that tilt should be generally limited to 1 in 60. The shift
should be restricted to one percent of the depth sunk. In case these limits are exceeded,
suitable remedial measures are to be taken for rectification.
The following remedial measures may be taken to rectify tilts and shifts:
A well foundation should be sunk below the maximum scour depth such that there is
adequate lateral stability. The depth of the bottom of the well below the maximum scour level
is known as the ‘Grip Length’. Thus, one of the important factors governing the depth of a
well foundation is the criterion of the minimum grip length necessary to provide adequate
lateral stability, besides the other factor of placing the bottom on a stratum with sufficient
bearing power.
For the first criterion, it is necessary to obtain the depth of scour from hydraulic
consideration. The scour depth can be ascertained by one of the following approaches:
a. Actual sounding at or near the proposed site immediately after a flood, at any rate
before there is any time for silting up appreciably.
b. Theoretical methods taking into account the characteristics of flow like the direction,
depth, and velocity, and those of the river bed material.
In case the first approach of taking soundings is not feasible, the second approach may be
used and the normal depth of scour may be calculated by Lacey’s formula:
( )
1. Define: (i) well steining; (ii) Grip length (iii) Kentledge. (December 2009)
2. What are the various components of a well foundation and what are their uses? (May
2009)
3. What is grip length of a well? What are the considerations in the determination of the
grip length? (July 2008)
4. What are the problems associated with well sinking? Mention any two methods [with
sketches] of rectifying the same. (May 2007)
5. Define and explain the ‘grip length’ of a well foundation(December 2006)
6. Explain Sand island method of construction of well foundation
7. What are the various components of well foundation? What are their uses?
8. Explain the procedure for construction and sinking of wells [with the help of sketches]
9. Briefly explain the causes and remedies for tilts and shifts in well foundations.
10. What are the problems encountered in the sinking of wells foundations?
11. What are the precautions to be taken to prevent tilt and shifts in a well foundation
12. Sketch and describe the various components of a well foundation including the
functions of each.