Civil Engineering
Civil Engineering
Civil Engineering
Construction
Planning & Management
Well Illustrated Theory with
Solved Examples and Practice Questions
Note: This book contains copyright subject matter to MADE EASY Publications, New Delhi. No part of this book may be reproduced,
stored in a retrieval system or transmitted in any form or by any means. Violators are liable to be legally prosecuted.
Construction
Planning & Management
Contents
CHAPTER
01
Project Management and Network Theory
1.1 Introduction
Project is a temporary endeavour undertaken to provide a unique product, service or result. A project
involves series of activities which consumes resource and time.
Objectives of a Project:
• It should be completed in minimum time with minimum capital investment.
• It should use available manpower and other resources optimally.
1.2.2 Scheduling
Scheduling is the allocation of resources such as time, material, space, equipment and human and
technological effort.
It involves:
1. Finalizing the planned functions mechanically.
2. Assigning starting and completion dates to each activity to proceed in a logical sequence and in a
systematic manner.
2 Civil Engineering MPSC
1.2.3 Controlling
Controlling involves:
1. Determination of deviations from basic plan and their effects on the project.
2. Replanning and rescheduling of activities to compensate for the deviations which is called “updating”.
It should be noted that planning and scheduling are accomplished before the actual project
starts while controlling is operative during execution of the project.
The method of planning and controlling that was originally developed was called Project Planning
Do
and Scheduling (PPS). PPS was later on converted into Critical Path Method (CPM), so the CPM
You
involves the deterministic approach and is used for the repetitive types of projects.
Know
1. Lack of degree of details: Only major activities are shown in bar chart and sub-activities can not
be separated out. Hence effective control over the activities in big projects can not be achieved.
2. A bar chart does not show progress of work and hence it can not be used as a control device.
3. A bar chart is unable to depict interdependencies of various activities clearly.
4. Bar charts are not useful in the projects where there are uncertainties in determination of estimation of
time required for completion of various activities such as in R&D projects.
5. Bar chart can not distinguish between critical and noncritical activities and hence resource smoothening
and resource levelling can not be done.
Bar chart diagrams are useful for only smaller and simpler conventional projects, especially construction
and manufacturing projects, in which time estimates can be made with fair degree of certainty.
Construction Planning & Management Project Management ...
3
• In linked bar chart, auticities are linked with Fig. Mile-stone chart
arrows and liners, indicating require and order
of auticities.
Do you know? Controlling can be better achieved with the help of milestone charts, but still activity
interrelationship and accountability of time uncertainty can not be depicted which can be overcome in network
technique.
A
ity
tiv
Ac
Activity B
10
Ac
Tail Event tivi
t yC
(C)
Ac
tivi
ty A
Activity B
20
C Head Event
ity
tiv (C)
Ac
1 3 4 5
1 2 5
Do you know? It should be noted there can be only one tail event and one head event in a project.
1.5.2 Activity
Activity is actual performance of a job. It requires time and resources for its completion.
Following are examples of an activity:
1. Excavate trench
2. Mix concrete
3. Prepare budget
In A-O-A system (Activity On Arrow network system), activity is represented by arrows between
Do
You events while in A-O-N (Activity On Node system), activities are represented by nodes. In
Know A-O-N system, events have no places.
A B
1 2 3 A B
AON
A-O-A
B D
i
A, B, C are concurrent activities and terminates at same node ‘i ’ such activities are independent of
each other.
6 Civil Engineering MPSC
A C
i
As soon as event ‘i’ reached, activity B, C and D can be simultaneously started. Such activities (B,
C, D) are also parallel activities.
2. Serial activities: The activities which can be started one after another and are dependent on each
other are called as serial activities.
B D
i
1.5.3 Dummy
• A dummy is a type of operation which neither requires time nor any resource, but it denotes
dependency among the activities.
• It is represented by dashed arrow.
In the figure shown below, a dummy activity is shown.
B Dummy
activity
Dummy
1 2 1
B
2
B
(a) Ambiguous Representation (b) Grammatically Clean Representation
A C
B D
• Dummies are used to show predecessor relation but if that relation is already established
Do
in the network, then that dummy is redundant and has to be removed.
You
Know • If dummy is only incoming/outgoing arrow to/from a node then it can be remove provided
there is no logical or grammatical error.
1 2 7 8
4 6
Example -1.1 A project consist of 10 activities as detailed below draw an arrow diagram
representation of the project
Job activity A B C D E F G H I J
Immediate
– A A A B C D D E, F, G H, I
predecessor
Solution :
The network:
E
3
B
A C F I J
1 2 4 6 7 8
D
5
G
A B A B
C C
Wrong Right
2. Dangling error: Project is complete only when all its activities are complete but the duration of
activity ‘R ’ has no effect on the project time as shown in figure.
3
T
Q
P S U 5
1 2 4
R
To avoid dangling error, the network must be examined in such a manner that all events except initial
and final events must have at least one activity entering and one activity leaving them.
Construction Planning & Management Project Management ...
9
3. Wagon wheel er errr or: As shown in figure, each of the activities P, Q and R cannot start until all the
three activities A, B and C are completed. But in reality, this may not be the situation. There is no
error visible in the construction of diagram but logical error has crept into it.
A P
B Q
C R
D
dotted arrow.
4. A dummy activity must necessarily be E
introduced in every network. F
Which of the above statements are correct?
(a) 1, 2 and 3 (b) 1 and 3 4 10 14 20 29
Time in days
(c) 2, 3 and 4 (d) 1 and 2
10 Civil Engineering MPSC
given by (d)
D B
(a) F.W. Taylor
(b) Henry Gantt
(c) M.R. Walker Q.10 Consider the AON diagram below:
(d) J.E. Kelley What is the minimum number of dummy arrows
[ESE-1995] required for conversion into AOA diagram?
Q.6 Grantt charts indicate
B G
(a) comparison of actual progress with the
reheduted progress
(b) balance of work to be done A C F H
(c) progressive cost of project
(d) inventory costs [ESE-1997]
5
A C
Q.14 List the following processes in their correct 11. (c) 12. (b) 13. (d) 14. (d) 15. (c)
sequence, from earliest to latest, in project
implementation planning :
1. Project duration
2. Resource histogram
3. Standardized input/performance for each
5. (a)
activity including alternatives
4. WBS The concept of functional organisation was given
5. Resource optimization considering by F.W. Taylor, who recommended the
constraints appointment of specialists at important positions.
6. Activities and their inter-relationships Functional organisation allows decision to be
Select the correct answer using the code given decentralised since issues are assigned to
below: specialists or units, giving them the responsibility
(a) 2, 1, 3, 5, 6 & 4 (b) 2, 6, 3, 5, 1 & 4 of implementing, equating, or controlling the given
(c) 4, 1, 3, 5, 6 & 2 (d) 4, 6, 3, 5, 1 & 2 procedures or goals.
[ESE-2014]
6. (a)
Q.15 Consider the following tasks: Bar chart gives comparison of actual progress to
1. Placing of reinforcement (P ) for roof slab the scheduled progress.
cannot start before bending of reinforcement
(B ) and erection of framework (E ). 9. (b)
2. As soon as placing of reinforcement is As per the question activity C is only dependent
finished correcting (C ) will follow. The correct on activity A and activity D is depending on
activity on arrow diagram representing the activity A and B both. Therefore,
above task is Option (a) is wrong because according to network
B P C shown, C is also dependent on B which is not
(a)
correct.
E
Option (c) is wrong because head of the arrow is
towards left of activity A.
12 Civil Engineering MPSC
B
P C
1 2 4 6 8 E
5