Pda (Contoh)
Pda (Contoh)
Prepared by,
NZA QS CONSULT
NO. 18, JALAN RENANG 13/26,
SEKSYEN 13,
40100 SHAH ALAM
SELANGOR DARUL EHSAN
MAY 2023
SUMMARY OF DEVELOPMENT COST
GFA(M2) #REF!
Amount Total Amount COST/M2
Item Description (RM) (RM) (RM)
2.3 Drainage
2.5 Sewerage
BLOK PENGINAPAN
ITEM DESCRIPTION UNIT RATE GFA : 1,892 20,365
QTY AMOUNT cost/m2 cost/Sqft
SECTION I - BUILDING WORKS
A WORK BELOW LOWEST FLOOR FINISH
Pad Footing
a. Concrete Grade 30 (300mm thk) m3 400.00 214 85,614.42 45.25 4.20
b. 6mm-32mm diameter reinforcement kg 6.00 44,519 267,116.99 141.18 13.12
c. Formwork m 20.00 115 2,294.86 1.21 0.11
Ground Beam
a. Concrete Grade 30 (300mm thk) m3 400.00 428 171,228.84 90.50 8.41
b. 6mm-32mm diameter reinforcement kg 6.00 89,039 534,233.98 282.36 26.23
c. Formwork m 20.00 229 4,589.72 2.43 0.23
C UPPER FLOOR
Rc Slab
a. Concrete Grade 30 (300mm thk) m3 400.00 127 50,756.88 26.83 2.49
b. 6mm-32mm diameter reinforcement kg 6.00 26,394 158,361.47 83.70 7.78
c. Formwork m2 20.00 59 1,172.30 0.62 0.06
D ROOF
a. Metal Deck Roofing With Acessories m2 150.00 1,892 283,800.00 150.00 13.94
b. Steel Structure (20kg/m2) kg 15.00 37,000 555,000.00 293.34 27.25
BLOK PENGINAPAN
ITEM DESCRIPTION UNIT RATE GFA : 1,892 20,365
QTY AMOUNT cost/m2 cost/Sqft
SECTION I - BUILDING WORKS
F EXTERNAL WALL
a. 150mm thk half brickwall m2 50.00 1,611 80,540.40 42.57 3.95
G INTERNAL WALL
a. 150mm thk half brickwall m2 50.00 1,434 71,683.40 37.89 3.52
H DOORS
a. SD: Double Leaf Equal Swing 982.8 No. 1,500.00 2 3,000.00 1.59 0.15
b. SD: Double Leaf Swing 982.8 No. 1,500.00 4 6,000.00 3.17 0.29
c SD: Double Leaf MS Grille 982.8 No. 1,500.00 1 1,500.00 0.79 0.07
d. SD: Single Leaf (Bilik/Office) 982.8 No. 1,500.00 28 42,000.00 22.20 2.06
e. SD: Single Leaf Toilet Pegawai 982.8 No. 1,500.00 19 28,500.00 15.06 1.40
f. SD: Single Leaf Toilet Cubicle 982.8 No. 1,500.00 8 12,000.00 6.34 0.59
g SD: Single Leaf Toilet Louvers 982.8 No. 1,500.00 8 12,000.00 6.34 0.59
h Fire Door 1092 No. 2,500.00 2 5,000.00 2.64 0.25
J WINDOWS
a. Anodised aluminium casement window c/w 6mm thk
clear tinted glass
1200 x 2100mm No. 1,320.00 20 26,400.00 13.95 1.30
600 x 2100mm No. 660.00 12 7,920.00 4.19 0.39
1800 x 2100mm No. 1,980.00 16 31,680.00 16.74 1.56
600 x 600mm No. 180.00 24 4,320.00 2.28 0.21
K FLOOR FINISHES
Internally:
a. Homogenous Tiles m2 - - - -
b. Homogenous Floor m2 120.00 1,532 183,840.00 97.17 9.03
c. Genlanggang ( Sepak Takraw & Badminton) m2 65.00 318 20,670.00
BLOK PENGINAPAN
ITEM DESCRIPTION UNIT RATE GFA : 1,892 20,365
QTY AMOUNT cost/m2 cost/Sqft
SECTION I - BUILDING WORKS
L WALL FINISHES
Internally:
a. Plaster and paint to brickwall m2 8.00 2,478 19,820.54 10.48 0.97
b. Ceramic Tiles (Toilet) m2 110.00 195 21,437.24 11.33 1.05
Externally:
a. Plaster and paint to brickwall m2 12.00 2,049 24,584.45 12.99 1.21
Sub total 65,842.23 34.80 3.23
M CEILING FINISHES
Internally:
a. Cellular Fibre Ceiling m2 70.00 1,892 132,440.00 70.00 6.50
Externally
a. Metal Ceiling m2 400.00 42 16,600.00 8.77 0.82
N SANITARY FITTINGS
a. Pedestal Water closet w.c No. 2,100.00 15 31,500.00 16.65 1.55
b. Squatting Water closet w.c No. 1,100.00 2 2,200.00 1.16 0.11
c. Hand bidet No. 500.00 17 8,500.00 4.49 0.42
d Wash Hand Basin with rc top No. 3,800.00 10 38,000.00 20.08 1.87
e. Wash Hand Basin wall mounted No. 900.00 13 11,700.00 6.18 0.57
f. Extra Large Wash Basin No. 685.50 10 6,855.00 3.62 0.34
g. Kitchen Basin (Double) No. 1,052.00 2 2,104.00 1.11 0.10
h. Mirror (500mm x 800mm) No. 500.00 23 11,500.00 6.08 0.56
j. Shower No. 431.00 17 7,327.00 3.87 0.36
k. Toilet roll holder No. 300.00 17 5,100.00 2.70 0.25
l. Tap No. 300.00 41 12,300.00 6.50 0.60
m. Floor trap No. 250.00 44 11,000.00 5.81 0.54
n. Counter Top No. 3,500.00 9 31,500.00 16.65 1.55
p. Plumbing LS - 462,500.00 244.45 22.71
q. BWIC LS - 10,000.00 5.29 0.49
Sub total 652,086.00 344.65 32.02
Sub total - - -
4 WATER RETICULATION
4.1 Water Piping Works
HDPE Pipes Diameter 150mm m 1,500 250.00 375,000.00
4.3 Water Reticulation Accessories like air valve, scour valve, pressure reducing valve, LS 0.00
pressure control valve, butterfly valve, sampling point, fire hydrant, precast concrete
chamber ( assume 10%)
Meter no 150 1,500.00 225,000.00
Hydrant no 150 2,500.00 375,000.00
Air Valve no 150 1,500.00 225,000.00
Scour Valve no 150 1,500.00 225,000.00
4.4 Connection/Hot Tapping LS 10,000.00
1,435,000.00
5 SEWERAGE
5.1 Sewerage Reticulation Pipes (for depth 1.2m to 6.0m)
Vitrified clay pipes (VCP)diameter 150mm m 40 250.00 10,000.00
5.2 Sewerage Manhole (1.5m c/c) nos 10 5,000.00 50,000.00
5.3 Connection to main LS 1 10,000.00 10,000.00
5.4 STP (45PE) LS 1 120,000.00 120,000.00
190,000.00
6 FENCING
6.1 Anti Climb Fencing m 865 500.00 432,500.00
6.2 Entrance Gate no. 1 15,000.00 15,000.00
Notes:
1) The preliminary cost estimate is based on current prevailing market rates and subject to
confirmation by the Project QS. The prelimnary cost estimate shall be further confirmed during
detailed design. It shall be used for budgetary purposes only.
2) Cost estimate is excluding contribution fees to authorities.
4) Cost estimate excluding additional authorities requirement imposed during submission.
5) Earthwork quantities calculated based on assuming the platform is ready and only minor trimming with in site.
6) Cost estimate is based on raw quantity without any mark up in quantity.
7) Sewer connection is assume at Entrance og RMAF based on assumption and will be determine
later
8) costing for water reticulation works is assume based on the best case scenario which is no
upgrading works for SYABAS pipe is required and proposed tapping point is at development
boundary