DQS256 Lecture On Cost Analysis Notes
DQS256 Lecture On Cost Analysis Notes
By,
SITI SARAH MAT ISA
1
Introduction
Definition of cost analysis
Purpose of cost analysis
Objectives / uses of cost analysis
Buildings ALLOWED for cost analysis
Preparation of cost analysis
Principles of analysis
FAQ
6/15/2023 2
The cost analysis of construction project
could provide the QS useful information of
cost data
The cost analysis provides a yardstick for the
client and design team.
The success of cost planning and cost control
system depends on the proper use of cost
information
6/15/2023 3
The systematic breakdown of cost of a
building into various ELEMENTS which are
meaningful to client and members of the
design team to assist in the preparation of
cost plans for future projects.
6/15/2023 4
➢ To reveal the cost relationship
between various sections/
elements of a building which are
meaningful to both client and
design team.
➢ To allow the costs of two or
more buildings to be compared
6/15/2023 5
Appreciation – enables clients and designers to know and
appreciate how the cost is distributed among the elements
and compared to the overall cost of the building
Judgement – able to determine which elements have
disproportionate cost when consider in relation to
efficiency and quality. Therefore, enable client and
designer to develop idea as to how costs can be
allocated to obtain a more balanced design
6/15/2023 7
DESIGN PROCESS TERMINOLOGY
Cost Control
(Estimates can occur at any stage of this process)
Cost Planning
Tender
Cost Check awarded
R.I.B.A.
A B C D E F G H J K L M Management
OUTLINE SCHEME DETAIL PRODUCTION BILLS OF TENDER PROJECT SITE Handbook
INCEPTION FEASIABILITY COMPLETION FEEDBACK
PROPOSAL DESIGN DESIGN INFORMATION QUANTITIES ACTION PLANNING OPERATIONS Terminology
Pilot
Outline Details Record Drawings
Design Plans Detail
Design
Drawing
Scheme Production Contract
Design Plans Information Drawings
Drawings
6/15/2023 8
➢ The cost analysis is prepared by examining
the information of a project which has been
constructed in which the bills of quantities
have been priced by the successful
contractor.
➢ Technically, it’s worthwhile to analyse the
actual costs (final account) rather than based
on projected costs (accepted tender sum/
contract sum).
➢ However, in practice, cost analysis is
normally prepared based on data collected
from an accepted tender.
6/15/2023 9
A) The cost analysed are the Client’s Cost on
the accepted Tender sum
B) The cost analysed are the Contractor’s
Costs on the Final Account
C) The cost analysed are the Client’s Costs on
the Final Account
6/15/2023 10
There are several reasons as to why the cost analysis
is not prepared based on the ‘actual’ cost
6/15/2023 11
12
6/15/2023 13
Total sum of money allocated to
this part of a building
6/15/2023 14
◦ Cost of a particular element
divided by the gross floor area
(GFA).
Cost/m2 GFA =Total cost of element
GFA
◦ Provide the elemental cost
contribution to the overall rate
per m2 GFA for the project.
6/15/2023 15
◦ Total quantity of the element
expressed in units appropriate to
the element concerned
◦ You can refer to the table in the
ECA manual page 8-9
Issue:
Can I extract the EUQ directly from the BQ?
6/15/2023 16
◦ The Element Total Cost will be
divided with EUQ
EUR = Total cost of element
EUQ
◦ Hence, the Element unit RATE
which when multiplied by the
element unit quantity (EUQ) will
give the total cost of the element.
6/15/2023 17
The proportional relationship
between an element and the GFA.
Also known as cost factor.
Calculated by dividing the net area
of element (EUQ) with GFA to three
decimal places
= EUQ
GFA
6/15/2023 18
6/15/2023 19
The ECA has been well known to provide a
very useful cost information especially in
the process of cost planning for future
project
However, the cost obtained from the ECA is
insufficient to determine the actual cost of
proposed project
It must consider the condition and the
details of the proposed project, the quality
and quantity of works involved as compared
to previous project
20
Information YOU WILL require:
Standard form of Elemental Cost Analysis prepared
by the Building Cost Information Centre of Royal
Institution of Surveyors Malaysia (RISM)
Form 1, 2 & 3. (Jangan ubah atau tambah ikut
sesuka hati kamu)
➢FORM 1: Project information
➢FORM 2: Summary of element cost with
preliminaries and contingencies shown
separately
➢FORM 3: A brief specification in elemental
format.
6/15/2023 21
Information YOU WILL require:
▪ Tender Report
▪ Drawing – plan & elevations ( Architecture
Drawing)
▪ Contract Documents/Accepted tender
documents
▪ Manual for the preparation of ELEMENTAL
COST ANALYSIS.
6/15/2023 22
Bills of Quantities (with quantities)
▪ Most preferred to use BQ with quantities
▪ The BQ should be prepared in an elemental
format.
▪ BQ items must be allocated to more
appropriate element (please refer manual)
▪ Prime cost sum need to be allocated to their
respective elements (allowed & tendered),
e.g., Electrical Installation, Lift Installation
▪ Unusual or difficult items in the BQ, should be
included with the more appropriate element.
6/15/2023 23
Contingencies - should be omitted from
the analysis; why?
6/15/2023 24
25
A building within a project should be
analyzed separately
6/15/2023 26
Chose only one building for ECA
preparation
6/15/2023 27
Information must be provided to assist the
preparation of estimates based on
abbreviated measurements.
Information such as drawings and specification
need to be provided
6/15/2023 30
Comprise five sections:
◦ Introduction
◦ Principles of analysis
◦ Instructions
◦ Definitions of terms
◦ List & Contents of elements
Standard form of Elemental Cost Analysis
Form 1: Project Information and the information of
analysed building
Form 2 : A Breakdown Summary of Cost Element
Form 3 : Brief Specification
6/15/2023 31
Sources:
FORM 1 Accepted tender/contract
documents, tender reports
Project title and drawing (plan &
Client elevations)
Location
Tender date
Project details
Contract type Purpose:
Contract particulars To inform the user about
Market conditions the nature of the project
Competitive tender list and its price level
Design/Shape information To allow the user make
Brief cost information necessary adjustment to
cater for time, location,
type of contract, market
and size factors
6/15/2023 32
Form 1
33
Plan of building Elevation of the bldg
20m
(-2) 35m
40m (+6)
(+3) 15m
Sources:
FORM 2 Accepted tender/
contract documents,
Summary of elements costs drawing (plan &
List of element elevations)
Total cost of element
Cost per square metre GFA Purpose:
Element unit quantity Can be used to prepare
Element unit rate realistic estimates,
Element unit ratio per metre budget and cost plan
square GFA for new project
Reinforced concrete To allow useful cost
Reinforcement comparative study to
Formwork ensure the design does
P.C sum: allowed & tendered. not exceed the
estimated budget
35
Form 2
36
Sources:
Accepted
Form 3 – tender/contract
Brief specification – documents, Contract
Briefly describe the Drawing (plan &
various components in elevation)
each elements, the Purpose:
types and quality of Provide overall picture
materials used for of the standard and
each part of building quality of the building
which is useful for
making comparative
study
37
Form 3
38
GFA Area from drawings
Total cost of element Cost extract from Bills of
EUQ (except finishes, Quantities
fittings & finishings, Area measured from
services). drawings
Finishes, fittings &
finishings, services Area & quantities
Volume of reinforced extract from Bills of
concrete Quantities
Weight of reinforcement
Area of formwork
Information Sources
39
Assignment ECA Report (in PDF format)
This report shall comprise the following:
Preliminary notes/ Introduction of ECA,
introduction to analysed project
ECA Form 1
ECA Form 2
ECA Form 3
Working sheet – e.g. dimension papers to
calculate the GFA, usable area, ancillary area,
circulation area and internal division area
Any calculation related (ex: EUQ or ext. works
and preliminaries)
Attachments/Appendix
Drawings – plan & elevation of single building, roof plan.
Summary cost of Building Elements and Final Summary of
Contract Sum
Other information if necessary 40
Can I analyse :
◦ terrace/link/semi-detached
building?
◦ shop-office?
◦ shop house?
◦ alteration works?
◦ refurbishment works?
6/15/2023 41
If a project comprise more than one building,
how do l show the cost of preliminaries and
external works , since both is for the whole
project?
6/15/2023 42
Preliminaries for single building can be
calculated as follows:
6/15/2023 43
Project
Preliminaries =RM50,000
Total Building Cost = RM1,000,000
% of preliminaries = RM50,000 x 100 = 3.0%
RM1,000,000
Single building
Cost of single building = RM350,000
Preliminaries = RM350,000 x 5% = RM17,500.00
6/15/2023 44
Contingencies for single building can be
calculated as follows:
6/15/2023 45
Cost of single building x value of project site work
Total building cost*
6/15/2023 46
Project
Contract Sum = RM1,000,000 (excluding contingencies &
site work)
Site work =RM25,000
Total building cost = RM1,000,000 – RM25,000
% of site work= RM25,000 x 100 = 2.564%
RM975,000
Single building
Cost of single building = RM350,000
Site work= RM350,000 x 2.564% = RM8,974.00
6/15/2023 47
Cost of single building x value of project drainage
Total building cost*
6/15/2023 48
Can I analyse
building when the
construction project
has already been
completed?
YOU CAN
But completed not more
than 2 years
6/15/2023 49
I do not have the
complete resources
to prepare my ECA
because I work in a
contractor’s
company. Could l
seek external
resources?
6/15/2023 50
◦ Could I analyse building Preferably use
that used Summary of project that used
Tender and Schedule of
BQ?
Rate (contract based on
drawing & specification)? Otherwise, time
consuming.
Might be difficult
for you.
6/15/2023 51
◦ Could I use cost No….you can not.
analysis forms specially
developed by my
employer?
DON’T BE LAZY……,
INDUSTRIAL TRAINING IS MAKING YOU A
BETTER PERSON
6/15/2023 52
LEARNING PROCESS NEVER END
6/15/2023 53