CHP 2. Contract Costing Sums
CHP 2. Contract Costing Sums
A construction company undertook a contract at an estimated price of Rs. 108 lakh, which includes
a budgeted profit of Rs. 18 lakh. The relevant data for the year ended 31-3-2018 are as under :
('000)
Materials issued to site 5,000
Direct wages paid 3,800
Plant hired 700
Site office costs 270
Materials returned from site 100
Direct expenses 500
Work certified 10,000
Progress payment received 7,200
A special plant was purchased specifically for this contract at 8,00,000 and after use on this
contract till the end of 31-3-2018 it was valued at 5,00,000. The cost of materials at site
at the end of the year was estimated at 18,00,000. Direct wages accrued as on 31-3-2018 was 1,10,000.
Required :
Prepare the Contract Account for the year ended 31st March, 2018 and compute the
profit to be taken to the Profit and Loss Account.
Solution 1:
Working Notes:
= 92.59 %
2. Since the percentage of Contract completion is more than 90% therefore the profit to be taken to
Profit and Loss Account can be computed by using the following formula.
00 since certification. The value of the material used since certification is Rs. 4,160.
Contract Account 51 for the year ended 31st March, 2013
The contract a/c shows a loss and hence the total amount of loss is transferred to the profit and loss a/c in accordance with th
c in accordance with the convention of conservatism.
M/s. Rajendra constructions obtained a contract to build a Fly-over Bridge at a contract price of Rs:
150 lacs. The contractee agrees to pay 90% of value of the work done as certified by the architect
immediately on receipt of the certificate and to pay the balance on completion of the contract. The
contractor commenced the work on 1st May 2013 and it is estimated to be completed by 31st
December, 2014. The actual expenditure upto 31st March, 2014 and subsequent estimated
expenditure upto 31st December, 2014 is furnished below :-
ill 18
Estimated Expenditure
Actual Expenditure from
Particulars
upto 31-3-2.14 1-4-2014 to 31-
12-2014
Direct Materials 3,350,000 2,800,000
Indirect Materials 560,000 700,000
Direct Wages 842,000 795,000
Sub Contract Charges 98,000 52,000
Architect's Fees 184,000 284,000
Administrative Overheads 650,000 450,000
Special Equipment Charges 486,000 254,000
Supervision Charges 10,000 p.m. 12,000 p.m.
Establishment Charges 8,000 p.m. 9,000 p.m.
* Other details : Actual (RS) Estimated (RS)
Cash Received 6,750,000 8,250,000
Closing Material at site 410,000 -
Uncertified Work 180,000 -
Certified Work (Cumulative) 7,500,000 15,000,000
A special machinery costing Rs: 13,40,000 was bought for the contract and the estimated scrap value
of the machinery at the end of the contract would be Rs: 1,40,000. It is decided that the Profit to be
taken credit for should be that proportion of the estimated net profit to be realized on completion of
the contract which the certified value of work as on 31st March, 2014 bears to the total contract
price. Maintain 2% provision for contigencies on total cost of contact (excluding such provision for
contingencies).
You are required to prepare the Contract Account for the period ending 31st March, 2014 and show
your calculation of the Profit to be credited to the Profit and Loss Account for the period ended 31st
March, 2014.
IN THE BOOKS OF RAJENDRA CONSTRUCTION COMPANY
Contact Account (Fly over Bridge) for the period ended 31-03-2014
Particulars Amount
To Direct Materials 3,350,000
To Indirect Materials 560,000
To Direct Wages 842,000
To Sub Contract Charges 98,000
8,770,000
1 MONTH = 6600000
By Contractee 15,000,000
13092000
261840
15,140,000
Illustration 14
The Jai Hind Construction Company undertook the construction of a building at a contract price of
Rs. 2,00,00,000.
The date of commencement of contract was 1st May 2013.
The following cost information is given for the period ended 31st March 2014 :
1. Direct Materials sent to the site - 5,000 tons @ Rs. 1.50 per kg.
2. Indirect Materials Rs. 6,50,000.
3. Direct Labour - 12,000 Mandays @ Rs. 180 per manday.
4. Indirect Labour charged at 7.5% of Direct Labour.
5. Sub contract charges charged at 15% of Indirect Materials.
6. Direct Materials Returned to stores 20 tons.
7. Direct Materials Lost in an accident 5 tons.
8. Supervision charges paid Rs. 8,000 per month.
9. Administrative overheads incurred Rs. 12,000 per month.
10.Architect Fees charged at 2% of Work Certified.
11. Plant and Machinery installed at site on the date of commencement of contract at a cost of
Rs. 15,00,000. Which is to be depreciated @ 12% p.a. under original cost method.
12.Cash received from contractee Rs. 1,26,00,000 which is equal to 90% of Work Certified.
13.Direct Material at site as on 31st March 2014 - 15 tons.
14.Cost of work done but not certified was Rs. 2,04,500 on 31st March 2014.
You are required to prepare a Contract Account for the period ended 31st March, 2014 in the books
of Jai Hind Construction Company and show what profit or loss should be taken into account for the
period ended 31st March, 2014.
tract price of
14000000 (1500000*12%*(11/12))
165000
14 in the books
account for the
Working Notes :
1. Direct Materials Rate per kg ` 1.50 i.e. rate per ton ` 1,500 (as one ton is equal to 1000 kgs.)
2. Profit = 2/3 x Notional Profit x Cash Received/Work Certified
2/3 x 30,30,000 x 90/100
= Rs. 1818000
14,264,500 14,264,500
To Profit and Loss A/c 1,818,000 To Notional Profit c/d 3,030,000
To Reserve 1,212,000
3,030,000 3,030,000
0.7 ((2/3)*3030000*(12600000/14000000))
(12600000/14000000)) 1818000
Illustration 45
Mr. Vivek undertook a contract for the construction of building on 1st January, 2013, the contract
price being Rs. 15,00,000.
The following details are available for the year 2013 :
Rs.
Materials purchased 2,40,000
Materials issued from stores 3,00,000
Labour employed on site 90,000
Plant installed on site 1,20,000
Direct Expenses 60,000
Proportionate establishment charges 15,000
Cash received (80% of work certified) 6,00,000
Work un-certified 1,50,000
Materials returned to stores 15,000
Materials in hand at the end 6,000
Wages outstanding 18,000
Direct expenses accrued 24,000
Prepare the Contract Account and show the amount that would appear in the Balance Sheet. A part
of plant costing Rs. 20,000 was stolen at the beginning of the year and the Insurance Co. paid
Rs. 12,000. Plant is depreciated @ 20% p.a.
the contract
2,40,000
3,00,000
90,000
1,20,000
60,000
15,000
6,00,000
1,50,000
15,000
6,000
18,000
24,000
e Sheet. A part
Contract Account
1,021,000
To Profit and Loss A/c 82,133 To Notional Profit c/d
To Reserve 71,867
154,000
Balancesheet
Liabilities Rs. Assets
154,000
Rs.
6000
80,000
750,000
150,000
986,000
71,867
914,133
600,000
314,133
120,000
20,000
100,000
20,000
80,000
o Profit and Loss Account :
1,500,000
750,000
600,000
82133
the Costing P & L A/c (and not the Contract A/c. The
d to be out of common plant.
A firm of contractors commenced three contracts viz. A,B,C on 1st April,2012, on 1st October,2012 & 1st January,2013 respec
Particulars Contract A Contract B Contract C
Contract Price 800,000 250,000 250,000
Materials issued 144,000 58,000 20,000
Wages paid 220,000 112,400 14,000
Direct expenses paid 10,400 3,600 1,400
Plant installed 40,000 16,000 12,000
Materials at siteat the year end 8,000 4,000 2,000
Wages Outstanding 6,800 3,600 1,600
Work certified (% of contract price) 50% 64% 14.40%
Cash Received 75% 75% 75%
Work uncertified 12,000 8,000 2,100
Direct expenses prepaid 1,200 400 200
The plants are installed on respective dates of the contracts and depreciation is to be provided at 10% p.a.
Prepare Contract Accounts A,B & C and show the calculation of profit transferred to Profit and Loss Account.
16000*10%*6/12=800
12000*10%*3/12 300
12 & 1st January,2013 respectively. The following particulars about above three contracts are obtained for the year ended 31st March,201
Working Note:
1) % of Work Certified is 50% for contract A.
PROFIT transf to P&L A/c = 36,000*2/3*75% = Rs. 18000.
2) As there is loss in contract B , whole loss will be transferred to P&L A/c.
3) As the % of work certified is (14.4%) for contract C which is less than 25%, the whole notional profit will be treated as reser
A B C
Siddesh Construction company has undertaken three contracts during the year and the following particulars are available as o
All contracts were commenced during the current year. Total Depreciation on plants amounted to
11,200 and allocate the same to all contracts in the ratio of work certified.
Prepare Contract Accounts. Show the calculation of profit transferred to Profit and Loss Account.
ng particulars are available as on 31-12-2014.
Solution 24:
Contract Account
Working Note:
=1/3 X =2/3 X
Notional Notional
Profit X Profit X
Cash/ Cash/
Work Work
D. Ratio of Applied Certified Certified
= 1/3 X =2/3 X
75000 X 100000 X
320000/4 375000/
00000 500000
Trial Balance
Particulars
Land and Building
Bank Balance
Contract A/c:
Material
Plant
Wages
Expenses
The contract price is ` 5,00,000. It began on 1st January 2013. Out of the plant and material charged
to the contract, plant costing 4,000 and materials costing 6,000 were destroyed by an accident.
On 31-12-2013 plant costing 10,000 was returned to store, the value of materials on site was
5,000 and the cost of work done but not certified was 10,000. Depreciate plant at 10% p.a. and 2% land and building.
Prepare Contract A/c after taking 2/3 profit on cash basis to profit and loss A/c and balance sheet as on 31-12-2013.
Amount Particulars Amount
64,000 Capital 100,000
18,000 Sundry Creditors 12,000
Cash Received 270,000 300000
100,000 (90% of work certified)
40,000
150,000
10,000 -
382,000 382,000
Solution 46:
To Depreciation 1,280
(Building)
0
34,440
As per TB 40,000
Less:
Lost 4,000
Returned 10,000 14,000
26,000
Depreciation @ 10% 2,600
23,400
Rs.
4,000
6,000
9,000
338,400
357,400
57,400
0
57,400
Rs.
62,720
45,440
9,000
18,000
-
135,160
Rs.
34,440
-
34,440
Jai hind construction limited obtained the contract to construct a housing complex for RS.300
lakh. The contractee
The work agreedon
was commenced to1pay
st 90% of
august theand
2010 workcompleted
certified immediately
on 31st marchupon theA receipt
2012. machineof
costing RS.30, 00,000 was specially bought for use on contract and it would fetch RS.3, 00,000
3/31/2011
Particulars
RS
Monetary Information :
Wages 1,050,000
Indirect Materials 1,830,000
Direct Expenses 395,000
Office Expenses 579,000
Price per ton of Steel 42,000
Price per Brick 8
Scrapped Value of Bricks -
Work Certified (Cumulative) 12,000,000
Work unCertified 500,000
Quantitative Information :
Steel - Purchased (Ton) 105
Returned (Ton) 4
Lost in Accident (Ton) -
Sold (Ton) -
Bricks - Purchased Nos. 120,000
Returned Nos. 3,000
Lost in Accident Nos. 1,500
Prepare contract accounts for the year ended 31-3-2011 and 31-3-2012.
g complex for RS.300
ly
rchupon theA receipt
2012. machineof
uld fetch RS.3, 00,000
3/31/2012
RS
1,980,000
3,140,000
680,000
864,000
44,000
9
32,000
30,000,000
-
120
3
5
3
150,000
2,000
-
Jai Hind Construction Ltd.
Contract A/c for the year ended 31st March, 20
Particulars Amount Amount
To Materials :
-Steel Purchases 4,410,000
Less: Returns -168,000 4,242,000
-Bricks Purchases 960,000
Less: Returns 24,000 936,000
To Wages 1,050,000
To Direct Expenses 395,000
To Indirect Expenses 1,830,000
To Office Expenses 579,000
To Depreciation on
Machinery 1,080,000
To Notional Profit : 2,400,000
P & L A/c 720,000
Reserve 1,680,000
12,512,000
1. 2011
Material Steel :
Purchases 105 tons @ 42,000
Returned 4 tons @ 42,200
Bricks :
Purchased 1,20,000 bricks @ 8
2. Depreciation on Machine
Cost - Scrap Value = 30,00,000 - 3,00,000
Life 20 Months
= 40%
(12000000/30000000)*100
12,512,000
32,032,000
4,410,000
168,000
960,000
24,000
12,000
5,280,000
132,000
220,000
132,000
1,350,000
18,000
0/30000000)*100
Q.17
Rex Limited commenced a Contract on 1-7-2013. The total contract price was ₹ 5,00,000 but Rex
Limited accepted the same for ₹ 4,50,000. It was decided to estimate the total profit and to take to
the credit of profit & loss account that proportion of estimated profit on cash basis which the work
completed and certified borne to the total contract. Actual expenditure till 31-12-2013 and estimated
expenditure in 2014 are given below:
The plant is subjected to annual depreciation @ 20% of original cost. The contract is likely to be
completed on 30-9-2014.
You are required to prepare the contract account for the year ended 31-12-2013. Working should be
clearly given.
It is the policy of the company to charge depreciation on time basis.
IN THE BOOKS OF REX LIMITED
Contract Account (for Year Ended 31-12-2013)
Dr.
Particulars Rs. Particulars
To Materials 75,000.00 By Plant Returned to Stores
To Labour 55,000.00 (See Note 2)
To Miscellaneous expenses 20,000.00 By Work-in-Progress c/f:
To Plant 40,000.00 - Work Certified 2,00,000
- Work Uncertified 7,500
- Materials on hand 5,000
To Notional Profit c/d 58,500.00 - Plant at site 27,000
(See Note 3)
248,500.00
To Profit & Loss Account (See Note) 26,400.00 By Notional Profit b/d
To Work-in-Progress c/f 32,100.00
58,500.00
Profit credited to Profit & Loss A/c = Estimated Profit x Cash Received/Work Certified*Work Certified/Total
66000*1,80,000/2,00,000*2,00,000/4,50,000
=26000
Balance taken on Reserve (58,500 - 26,400) = 32,100
239,500.00
248,500.00
58,500.00
58,500.00
Cr.
Rs.
27,750.00
450,000.00
3,750.00
481,500.00
The plant is subject to annual depreciation @ 20%p.a. on original cost. It was decided that the profit to be taken credit for sho
portion of estimated net profit to be realised on completion of the contract which the certified value of work as on 31st March
to the total contract price. You are required to prepare Contract Account for the year ended 31st March, 2016 and show your
profit to be credited to the Profit and Loss Account for the year ended 31st March,2016. Calculation should be made to the ne
00 and it is likely to be completed on 31st
enditure upto 31st December, 2016 are
The Perfect Construction Company Ltd. has undertaken the construction of a bridge for a value
of
` 45,00,000 subject to a retention of 20% until one year after the certified completion of the
contract.
The following information is available for the year ended 31st March 2014 :
Particulars Amt
3,966,300 3,966,300
To P & L A/c 584,480 By Notional Profit b/d 1,095,900
To W-I-P (Profit Reserved) 511,420
1,095,900 1,095,900
Contractee Account
Particulars Amount Particulars Amount
To Balance c/d 3,120,000 By Bank 3,120,000
3,120,000 3,120,000
Balance Sheet
Liabilities Rs. Assets Rs.
Profit & Loss A/c 584,480 By Work-in-Progress :
Accrued Wages 28,800 · Work Certified 39,00,000
Accrued Direct Expenses 5,100 · Work Uncertified 43500
· Materials at site 22800
Less: Cash Received 31,20,000
3,966,300 3,966,300
To P & L A/c 584,480 By Notional Profit b/d 1,095,900
To W-I-P (Profit Reserved) 511,420
1,095,900 1,095,900
Contractee Account
Particulars Amount Particulars Amount
To Balance c/d 3,120,000 By Bank 3,120,000
3,120,000 3,120,000
Balance Sheet
Liabilities Rs. Assets Rs.
Profit & Loss A/c 584,480 By Work-in-Progress :
Accrued Wages 28,800 · Work Certified 39,00,000
Accrued Direct Expenses 5,100 · Work Uncertified 43500
· Materials at site 22800
Less: Cash Received 31,20,000
Bal Ram contractors undertook a contract for ` 15,00,000 on 1st July, 2012. The contract was
completed on 31st March, 2014. The contractor prepares his accounts on 31st March. The details of
Provide depreciation @ 20% p.a. on plant. Prepare Contract Accounts for the years ended 31-3-2013
and 31-3-2014.
34/aa-130
BAL RAM CONTRACTORS
Contract Account (From 1-7-2012 to 31-3-2013)
390,000 390,000
Notes :
(1) Profit taken to Reserve : As the work certified (` 3,00,000) is only 20% of the total contract price
of ` 15,00,000. entire profit is taken to Reserves.
(2) Depreciation taken @ 20% on ` 3,00,000 for 9 months.
Note :
Depreciation : Depreciation is taken on WDV basis as follows:
(a) Opening balance (3,00,000 - 45,000) = 2,55,000 x 20% = ` 51,000.
(b) New Plant Issued 1,50,000 x 20% = ` 30,000.
Total Depreciation ` 51,000 + ` 30,000 = ` 81,000
BAL RAM CONTRACTORS
Contract Account (From 1-7-2012 to 31-3-2013)
Particulars Amount Particulars Amount
To Material issued 152,000 By Material returned 22,000
To Direct wages 125,000 By Work-in-Progress :
To Direct Expenses 30,000 · Work Certified 3,00,000
To Materials returned to stores 22,000 · Work Uncertified 48,000
To Office overheads 23,000 · Materials at site 20000 368,000
To Depreciation on Plant 45,000
(3,00,000 x 20% x 9/12)
To Work-in-Progress c/d (Reserve) 15,000
390,000 390,000
Notes :
(1) Profit taken to Reserve : As the work certified (` 3,00,000) is only 20% of the total contract price
of ` 15,00,000. entire profit is taken to Reserves.
(2) Depreciation taken @ 20% on ` 3,00,000 for 9 months.
Note :
Depreciation : Depreciation is taken on WDV basis as follows:
(a) Opening balance (3,00,000 - 45,000) = 2,55,000 x 20% = ` 51,000.
(b) New Plant Issued 1,50,000 x 20% = ` 30,000.
Total Depreciation ` 51,000 + ` 30,000 = ` 81,000