2
2
ACKNOWLEDGMENTS ........................................................................................................ v
NOTATION .............................................................................................................................. vi
1 INTRODUCTION .............................................................................................................. 3
5 CONCLUSION ................................................................................................................... 27
6 REFERENCES ................................................................................................................... 29
TABLES
1 Major Components and Subcomponents Constituting the Resilience Index ........................ 11
iii
FIGURES
iv
ACKNOWLEDGMENTS
The authors gratefully acknowledge the contributions of many people who helped bring
this project to its current state of development, including the Protective Security Coordination
Division management team of the U.S. Department of Homeland Security, Office of
Infrastructure Protection. The authors are particularly thankful to Mike Norman, Donald Erskine,
Derek Matthews, Kariann McAlister, and Sean McAraw, without whom all of this work would
not have been possible. Their leadership and dedication inspired the Argonne National
Laboratory team.
The authors also want to thank Glen Sachtleben, Duane Verner, Jeffrey Murray, Stan
Hanzel, Michael Morral, John Busch, Robert Mooney, and Edward Buikema and their Argonne
colleagues who contributed to the methodology and weighting process.
v
NOTATION
vi
1
R.E. Fisher, G.W. Bassett, W.A. Buehring, M.J. Collins, D.C. Dickinson, L.K. Eaton,
R.A. Haffenden, N.E. Hussar, M.S. Klett, M.A. Lawlor, D.J. Miller, F.D. Petit, S.M. Peyton,
K.E. Wallace, R.G. Whitfield, and J.P. Peerenboom
EXECUTIVE SUMMARY
In 2009, the U.S. Department of Homeland Security (DHS) and its protective security
advisors began assessing high-risk critical infrastructure and key resource (CIKR) assets using a
targeted questionnaire: the infrastructure survey tool. The survey tool produced individual
protective measure and vulnerability values through protective measure and vulnerability indices
(PMI/VI). As sites continue to be assessed using the PMI/VI, academic research, practitioner
emphasis, and public policy formation have increasingly focused on resilience as a necessary
component of risk management and infrastructure protection. This increased attention led to a
detailed study and report by the National Infrastructure Advisory Council, which called for an
increased focus on resilience for U.S. infrastructure protection programs (NIAC 2009). The
report also underlined the importance of an increased understanding of resilience to an overall
risk management strategy for both public and private CIKR.
Considering these issues, Argonne National Laboratory, in collaboration with the DHS
Protective Security Coordination Division, has developed a comprehensive methodology that
uses uniform and consistent data to develop a resilience index (RI) on the basis of data collected
through a modified version of the DHS Enhanced Critical Infrastructure Protection (ECIP)
program. The RI is derived from three categories: robustness, resourcefulness, and recovery.
The RI ranges from 0 (low resilience) to 100 (high resilience). A high RI does not mean
that a specific event will not affect the facility and will not cause severe consequences.
Conversely, a low RI does not mean that a disruptive event will automatically lead to a failure of
the critical infrastructure and to serious consequences. The RI instead compares the level of
resilience at critical infrastructures and guides prioritization of limited resources for improving
resilience. The RI also provides valuable information to owners/operators about their facility’s
standing relative to those of similar sector assets and about ways they can increase resilience.
Applications and uses of the RI for the ECIP program continue to evolve. Concept
improvements and additional enhancements and approaches are expected as the program
2
matures. In addition, the RI will be combined with other indices such as the vulnerability index,
the protective measures index, and the forthcoming criticality index to support overall decision
making about risk, protection, business continuity, and emergency management of CIKR.
3
1 INTRODUCTION
In 2009, DHS and its protective security advisors (PSAs) began assessing CIKR assets
using the ECIP program and ultimately produced individual protective measure and vulnerability
values through the protective measure and vulnerability indices (PMI/VI). The PMI/VI assess the
protective measures posture of individual facilities at their “weakest link,” allowing for a detailed
analysis of the most vulnerable aspects of the facilities (Schneier 2003), while maintaining the
ability to produce an overall protective measures picture. The PMI has six main components
(physical security, security management, security force, information sharing, protective measures
assessments, and dependencies) and focuses on actions taken by a facility to prevent or deter the
occurrence of an incident (Argonne National Laboratory 2009).
The ECIP program and the RI represent a new model (using Appreciative Inquiry
principles) for information sharing between government and industry (Fisher and Petit 2010). A
“dashboard” display, which provides an interactive tool – rather than a static report, presents the
results of the RI in a convenient format. Additional resilience measures can be modeled to
illustrate how such actions would impact the asset’s RI value.
5
Figure 2 indicates where resilience fits into the overall risk management picture, from
threats to consequences, and where potential actions can be taken to prevent realization of the
threats or consequences. The chart aligns the spectrum of risk with the different types of
measures (preparation, mitigation, response, and recovery) that can be used to manage risk and
reinforce the system. This “bow-tie” representation of risk illustrates the importance of
resilience, from its emphasis on robustness and mitigation through recovery and potential
consequences.
The need to better understand current resilience postures, as well as options for increasing
resilience among CIKR culminated in a detailed study and report by the National Infrastructure
Advisory Council (NIAC), which called for an increased focus on resilience for
U.S. infrastructure protection programs (NIAC 2009). The report tackled one of the most
difficult challenges to gaining a broad view of CIKR resilience in the country — clearly defining
the meaning of resilience — and underlined the importance of an increased understanding of
resilience to an overall risk management strategy for both public and private CIKR.
NIAC defined resilience, in the context of CIKR, as the ability to reduce the magnitude and/or
duration of disruptive events. The effectiveness of a resilient infrastructure or enterprise depends
on its ability to anticipate, absorb, adapt to, and rapidly recover from a potentially disruptive
event, whether naturally occurring or human caused (NIAC 2009). Anticipation and absorption
capabilities reflect the capacity of the system to avoid a disruptive event or to decrease the
detrimental impacts of that event. Adaptation and recovery reflect the capacity of the system
during an event to avoid or to decrease the importance of the consequences to the environment
by quickly returning to a normal state of operation (Figure 3).
The robustness component of resilience is the ability to maintain critical operations and
functions in the face of crisis (NIAC 2009). It is directly related to the ability of the system to
absorb the impacts of a hazard and to avoid or decrease the importance of the event that could be
generated by this hazard. Robustness can be seen as the protection and preparation of a system
facing a specific danger. The objective is to define the measures that can help the system
withstand or adapt to a hazard. In contrast to protective measures, for which much of the focus is
on preventing an incident, robustness emphasizes the ability of an asset to withstand the incident
should protective measures fail. Robustness also integrates the capacity of the asset to function in
a degraded state. The importance of robustness is not necessarily defined by how the asset
continues to function in the face of an incident, but rather by how the asset is able to continue to
accomplish its mission and to provide its products and services through preventative measures,
mitigation, or absorption capabilities.
Rapid recovery is the ability to return to and/or reconstitute normal operations as quickly
and efficiently as possible after a disruption (NIAC 2009). The concept of rapid recovery defines
the passage of an asset from a degraded state to one of acceptable operation. This concept builds
off of the robustness component in that, if measures of robustness fail to fully prevent, mitigate,
or allow the asset to absorb the damage event, rapid recovery constrains the impacts of a
stoppage in production. Rapid recovery refers to the ability to not only return to acceptable
operating levels, but also to recover fully from the effects of an incident.
Resourcefulness is the ability to skillfully prepare for, respond to, and manage a crisis or
disruption as it unfolds (NIAC 2009). Resourcefulness begins prior to an event and continues
into the response phase. It comprises the steps taken prior to an event to prepare employees and
management for possible threats and the application of the training and planning once an event
occurs. Resourcefulness can be seen as a complement to robustness and allows for a smooth and
expedited transition from the response phase to the recovery phase.
A resilience analysis must generate reproducible results that can support decision making
in risk management, disaster response, and business continuity. In response, Argonne National
Laboratory has developed a comprehensive methodology of consistent and uniform data
collection and analysis through a resilience index.
The ECIP program’s site visits support the collection of accurate information that is used
to compare CIKR in terms of vulnerabilities, resilience, consequences, and ultimately, overall
risk. Based on a questionnaire containing more than 1,500 data points, the program is appropriate
for a wide range of CIKR facilities, including commercial buildings, electrical substations, and
dams. The ECIP questionnaire allows PSAs to collect, within a limited timeframe (typically 4 to
8 hours), pertinent information that characterizes a facility. PSAs, who are critical infrastructure
and vulnerability assessment specialists assigned to local communities (DHS 2007), are
specifically trained to ensure the uniformity and coherence of the data they collect. They survey
the protection and resilience measures in place at a facility by gathering data at the most
vulnerable point for each measure (e.g., the electric connections). The data are then verified at
both DHS headquarters and Argonne National Laboratory through a quality assurance (QA)
review process that comprises six steps:
1. The questions that are required for RI development are “validated” upon initial
submission. A PSA cannot submit the data about a particular facility until all required
questions are answered.
2. An initial QA review is conducted by DHS personnel who are trained in the methodology
and have direct and immediate access to the questionnaire.
3. A second QA review is conducted by ECIP subject matter experts. This second review
provides for an objective assessment of the initial QA and refinement of the process in
case data were overlooked or the methodology was not appropriately followed. The
subject matter experts can also approve or disapprove of any of the changes suggested
during the initial QA.
4. The PSA reviews the data and the changes to the initial data collection to help clarify
what data are required and help maintain consistency in the methodology.
10
5. After the PSA review, a final QA review is conducted by another round of ECIP subject
matter experts. This final review includes grammatical edits and clarification of any data
that were not clearly understood.
6. A final check is conducted during the development of the RI (scoring process) from the
raw data to ensure that all the selected elements feed into the database properly.
The QA process is an integral part of the larger RI methodology because it maintains the
integrity of the information collected and the products disseminated. The process also helps
ensure the validity of the data and decreases the variance across data collected at different sites.
Additionally, cleaning the data before they are used to produce an RI score reduces the overall
time it takes to return a final product to the owner/operator.
Beyond its benefits to the end product, the QA process also has several other benefits.
The PSA review serves as a constant training opportunity for the PSAs involved, reinforcing,
over time, a consistent application of the methodology. The process can also highlight problems
that may exist in the question set. The questions and their potential responses can be reevaluated
following identification of a pattern of errors. Often, questions are revised to enhance their
clarity and consistency of interpretation.
After the QA review process, the data are stored in an Oracle database, allowing for
management and selection of the data that will be used to define the RI.
To capture resilience, the relevant data collected in the ECIP program are aggregated into
levels of information.
The resilience analysis organizes the information collected into five levels in order of
increasing specificity; raw data are combined into groups at level 5 and are combined further
through levels 4 to 1. The RI combines three level 1 components (robustness, recovery, and
resourcefulness), corresponding to the resilience components defined by NIAC; 12 level 2
components; and 47 level 3 components, defined by subject matter experts (Table 1).
Each question (raw data), and all components and subcomponents of the RI, is assigned a
weight representing its importance relative to other questions/components/subcomponents in its
grouping. The weights were obtained in accordance with the principles of “decision analysis,” an
approach that helps manage risk in terms of uncertainty (Keeney 1992; Keeney and Raiffa 1976).
The methodology is based on a numerical representation of the value pattern, obtained by
comparing different elements of a facility and by using relations “better than” and “equal in
value to” to define their relative importance. Another important element in this decision analysis
tool is the transitivity of the ranking, which means that if an element A is more important than an
element B, and an element B is more important than an element C, then logically A will be more
important than C. This approach produces a relational representation of a facility’s resilience
alternatives by providing a numerical value assignment for each of its components.
11
Robustness Resourcefulness
a. Redundancy (8) a. Training/Exercises (7)
b. Prevention /Mitigation (7) b. Awareness (3)
c. Maintaining Key Functions (3) c. Protective Measures (3)
d. Stockpiles (2)
Recovery e. Response (3)
a. Restoration (3) f. New Resources (2)
b. Coordination (2) g. Alternative Sites (4)
(*) Denotes number of subcomponents.
The methodology involves separating a facility into its component parts and using a
mathematical formula to define possible decisions from the component parts and to propose
different alternatives to increase resilience. This method helps decision makers select simple and
familiar choices in the context of a seemingly complex issue.
A relative weight is assigned to each component that contributes to the RI. The weights
for a set of components depend on the ranges (worst to best) that are included as options in the
question set. Preferences for the specific values within the ranges of single components have
been provided by subject matter experts and sector/subsector representatives via an elicitation
process. Figure 5 shows an example of results of that process, done with three groups of experts,
for components of Business Continuity Plan Training, subcomponents of the Training/Exercises
variable, which is part of the Resourcefulness component.
In the index, Business Continuity Plan Training has five alternatives. Each group of
experts must rank each of these alternatives in relation to the others, from 1 (most important
element for training) to 5 (least important element for training). If the subject matter experts
decide that two elements have the same importance, they can give them the same rank. The
element with rank 1 is given a weight of 100%. Each group defines the weight of each other
element in the category, considering its relative importance compared with the element ranked 1.
Experts can assign equal weights to two elements if they have the same importance or relatively
close weights if the elements are not of equal importance but are separated only by a slight
increase in value. Conversely, the difference in assigned weights can be increased if one element
is considered significantly less important than another.
Figure 5 shows that Groups 1 and 3 ranked the variables the same, even though the
weights they assigned to each element varied. Group 3 weighted the second-, third- and fourth-
ranked elements lower than Group 1 did, meaning that they believed those elements were less
important than Group 1 compared with the element ranked number 1. Group 2 had both different
12
Resourcefulness ‐ Training /Exercises
weights, as well as different rankings for the elements ranked 2 and 3. For Group 2, to have
“only the key personnel trained on the plan at initial employment and at least once a year” is
more important than having “all personnel trained on the plan but only at initial employment.”
When all experts’ ranks and weights are defined for a specific subcomponents group,
final weights are obtained by using an average of weights defined by the subject matter expert
groups. For the Business Continuity Plan Training, the final weights vary from 100, for the most
important element, to 31.67, for the relatively least important element.
Because the function of the RI is modeled after the PMI/VI (Argonne National
Laboratory 2009), the individual variables are arranged so that they can be aggregated from the
raw data (level 5) stage into broader variables, culminating — through an additive process —
into an overall RI value.
The levels of information are rolled up through a tree organization to take into account all
elements that promote resilience and to develop an RI. Figure 6 shows the flow organization of
the first two levels of components.
13
To measure level 4 components, such as the one defining electrical power connections,
raw data (level 5) (in the form of facility answers to individual questions) are collected. Table 2
lists the alternatives used to characterize electric connections; the answers are rolled into an
overall value for electric connections.
The level 5 weights listed in Table 2 imply that elements P.1 and P.4 are more important
than P.2 and P.3 — that it is more important to have more than one service connection, each of
which can handle the entire facility load, than to have more than one service connection, not all
of which can handle the entire facility load. While these two choices are mutually exclusive, the
index also implies that it is more important — in terms of robustness — to have more than one
service connection where each can handle the entire facility load than having power lines from
substations follow independent pathways — although the weighted importance is close. These
two possibilities are not mutually exclusive.
15
Level 5 Weighted
Electric Connections Component (Level 5) Weight Answer Index
P.1 More than one service connection, each can 0.335 Noa 0
handle entire facility load.
P.2 More than one service connection, not all of 0.220 Yesb 22.0
them can handle entire facility load.
P.3 Power lines from the substation(s) follow 0.330 Yesb 33.0
independent pathways (e.g., geographically
different paths) to the area of the asset/facility.
4
EC a i Zi (1)
i 1
where:
EC = electric connections index, level 4 (ranging from 0 to 100);
ai = scaling constant (weight) indicating the relative importance of possibility i
(i = 1,2,3,4) for electric connections; and
Zi = value of component i of electric connections (0, if not present, or 100, if present).
The facility in the example has more than one electric service connection in different
geographic locations. The power lines from the substation follow different geographic pathways,
but each of them alone cannot handle the entire facility load. In Equation 1, the weighted values
of the questions answered affirmatively are combined to give the facility an overall electric
connections index of 88.5 (Table 2).
Level 4 components are aggregated into level 3 components, which represent the main
characteristics of the facility studied, such as its individual dependencies and its emergency and
continuity plans. For example, the electric connections variable, level 4, is one component of the
level 3 electric power variable (Table 3).
16
On the basis of the level 4 weights, it is most important for electric power to have on-site
backup generation (weight of 0.300); nearly as important is internal generation (weight of 0.295).
The facility in the example does not have internal generation, but it does have an on-site backup
for its core operations.
Level 4 components are combined to create a level 3 index. These level 4 components
can be derived from either yes or no values (internal generation) or rolled up from level 5
questions, as is the case with electric connections.
4
EP bi Yi (2)
i 1
where:
EP = electric power index, level 3 (ranging from 0 to 100);
bi = scaling constant (weight) indicating the relative importance of component i
(i = 1, 2, 3, 4) of electric power; and
Yi = index value of component i of electric power (e.g., electric connections).
The relative importance (weight) of electric connections for electric power is 0.210. By
multiplying the value of electric connections (88.5) by its weight, we obtain a weighted electric
connections value of 18.59. This value is added to the other weighted components that constitute
electric power (level 3) to obtain an overall electric power index of 64.59 (Table 3).
Level 3 components are aggregated to define level 2 components. This level represents
the main functions that promote resilience of the facility and the key contributors to robustness,
resourcefulness, or recovery. Categories such as redundancy, prevention, maintenance of key
functions, and training and exercises are level 2 components. Electric power is one of eight
level 3 components that are aggregated to form the redundancy subcomponent of robustness
(Table 4).
17
In the case of redundancy, all the subcomponents that constitute the redundancy
component have the same relative importance and therefore the same relative weight (0.125). An
index value of 100 for these level 3 components indicates that the asset is not dependent on a
specific element (gas and critical products) or that it is dependent but has measures in place to
fully mitigate the potential implications of this dependency (transportation). A value of 0
indicates a dependency with no protective or redundant measures in place. Values between 0 and
100 indicate a dependency with partially redundant or protective measures. In the example
above, the facility has a backup for the telephone with one terminal in the facility (index = 62.8).
There is only one connection to the water network without any backup (index = 0), and the asset
has its own wastewater treatment plant but does not have enough capacity to handle a fully
operational facility (index = 21.5).
Level 2 components are estimated as the weighted sum of level 3 components. The level
2 index for redundancy is obtained by using Equation 3:
8
R ci Xi (3)
i 1
where:
R = redundancy index, level 2 (ranging from 0 to 100);
ci = scaling constant (weight) indicating the relative importance of component i
(i = 1,…, 8) of redundancy; and
Xi = index value of component i of redundancy (e.g., electric power).
Level 2 components are aggregated to define the level 1 components, which represent the
three main concepts of resilience:
• Robustness, which characterizes the capability of a system to resist a specific event. This
level 1 component groups its level 2 subcomponents that characterize redundancy,
prevention, and maintenance of key functions (Appendix 1).
Per the RI, redundancy is the most important subcomponent of robustness, with a weight
of 0.400 (Table 5). Prevention is the least important subcomponent for the determination of
robustness, with a weight of 0.267. The facility analyzed in our example has an index of 59.39
for prevention, which corresponds to a facility with no specific protective measures in terms of
building codes, and one that is located in an area with possible wildfires, severe winter storms,
and high-wind events (thunderstorms or tornados). The facility was constructed considering
these potential hazards. The facility is dependent on several elements, such as water, wastewater,
electricity, information technology, and telecom, but has protective measures, to some degree, in
place for all of these dependencies. The index of the facility for the maintenance of key functions
is 51.71, which corresponds to different elements of planning and procedures; for example, the
facility may have specific procedures for emergency communication, human resources, and the
identification of key personnel. Some potential procedures are still missing, such as work
arrangement or relocation.
The overall robustness index is calculated as the weighted sum of its three
subcomponents using Equation 4:
3
Ro di W i (4)
i 1
where:
Ro = robustness index, level 1 component of resilience (ranging from 0 to 100);
di = scaling constant (weight) indicating the relative importance of component i (i = 1,
2, 3) of robustness; and
Wi = index value of component i of robustness (e.g., redundancy).
Finally, the three Level 1 components are aggregated to define an overall RI (Table 6).
According to the overall weights, robustness is the most important component of facility
resilience with a weight of 0.380, while resourcefulness and recovery are nearly equal in
importance. The facility analyzed in our example has an index for resourcefulness of 60.77,
which corresponds to a facility that has already conducted a vulnerability assessment and
developed training plans for emergency, security, and business continuity. However, the facility
needs further coordination with first responders and the addition of an alternative site (hot or
cold). Furthermore, the training it utilizes might be for key personnel only, and the facility has
only conducted a tabletop exercise, rather than a full-scale exercise, over the past year. The
facility index for recovery is 48.63, which corresponds to a lack of internal coordination and
specific agreements with external authorities and responders.
20
3
RI e V
i 1
i i
(5)
where:
RI = relative resilience index (ranging from 0 to 100);
ei = scaling constant (weight; a number between 0 and 1) indicating the relative
importance of component i (i = 1, 2, 3) of resilience; and
Vi = index value of component i of resilience (i.e., robustness, resourcefulness, and
recovery).
The relative importance (weight) of robustness for resilience is 0.380. By multiplying the
value of the robustness index (58.44) by its weight, we obtain a weighted robustness index of
22.21. This value is added to the other weighted index values of components of resilience to
obtain an overall RI of 56.19 (Table 6).
The RI is defined by the aggregation of five levels of information. Each type of data
collected and each element comprising Levels 5 through 1 have been weighted by a group of
experts to represent the relative importance of variables, subcomponents, and components
compared with other data in the same groupings, but also considering their contribution to the
overall resilience of the critical infrastructure analyzed. The weights for a set of variables depend
on the ranges (worst to best) of each component compared with others in the same group. The
weights represent a general sector (or subsector) and a general threat. Additional weights could
be elicited to develop indices specific to sectors (or subsectors) and threats.
This process results in an overall RI that ranges from 0 (low resilience) to 100 (high
resilience) for the critical infrastructure analyzed, as well as an index value for each level 1
through 5 component. This method of characterizing the resilience of a critical infrastructure
allows DHS to consider the specificity of all subsectors but also to compare the efficiency of
different measures to enhance resilience in the studied system.
It is important to note that the RI is a relative measure. A high RI does not mean that a
specific event will not affect the facility and will not cause severe consequences. A low RI does
not mean that a disruptive event will automatically lead to the failure of the critical infrastructure
and to other serious consequences. Simply stated, the RI is a way to compare the levels of
resilience of critical infrastructures and to help prioritize investment of resources to enhance
resilience.
21
The RI for a single facility has significant value, and using that value to compare similar
facilities with respect to resilience allows for vital additional benefits to owners/operators, as
well as DHS. The comparison of a facility’s RI value to that of other, similar facilities allows for
an appropriate analysis of RI values and their role in facility risk management. Furthermore, the
ECIP program does not collect all information about a facility, just information on the weakest
elements — other characteristics of a facility could easily override these resilience elements.
Thus, combining the RI with other indices or information will help identify areas for needed in-
depth analysis or potential improvements.
An individual score becomes more meaningful when compared with the scores of a set of
similar facilities. Providing the owner/operator of a facility with a detailed analysis of its RI and
a comparison across other similar facilities is useful because it provides perspective about where
the subject facility stands relative to its peer group. The comparison can be made at the highest
level (overall RI), at the next-highest level (e.g., robustness, level 1), or at numerous lower levels
(e.g., electric power, level 3, or telecommunication, also level 3). The lower-level comparisons
provide good starting points for the owner/operator when considering which new resilience
measures may be worthwhile. The higher-level comparisons provide a good indication of how
the overall resilience posture at the facility compares to those of other, similar facilities. The
most useful ways in which the information can be displayed to the owner/operator are being
improved as ECIP program experience increases.
Figure 8 shows a display option that includes an overall RI and the three level 1
components. The sector maximum, average, and minimum values are shown as dots.
In Figure 8, the overall RI and the different values for the first-level components are
above or near the average for this facility. The robustness index is one of the highest levels found
for that type of site and sector, with a value just below the sector maximum. Compared with its
sector, this facility seems to be better prepared in terms of resilience; however, its resilience is
not necessarily sufficient, nor does its high RI guarantee that an event or disruption will not
occur. Figure 9 shows the same chart as Figure 8 for another facility.
22
FIGURE 8 Display Option Showing Values of RI Components for a Facility Compared with Sector
Averages
The overall RI, robustness index, and resourcefulness index of this second facility are
below average. The recovery index value is above average. These values give beneficial
information to the CIKR owner/operators and may help in prioritizing future investments. An
owner/operator may decide that he/she needs to improve the robustness of the facility. In order to
understand the significance of increasing robustness, he/she should consider the resilience
information and protective measures at the facility. Indeed, if the facility is well protected, the
owner/operator may not need to increase its robustness or, therefore, its resilience.
Beyond the first-level RI comparisons, additional charts, such as the one shown in
Figure 10, can be produced for all levels of information available from the ECIP program data
and levels included in the RI calculations. For example, comparisons can be made of electric
connections, electric power, redundancy, robustness, and the overall RI. These additional levels
are vital to understanding why a facility is higher or lower than the average in a given
component. The reasoning may not be a general increase or decrease across all subcomponents,
but the deviation from the average may simply be based on a single low or high value of a
subcomponent.
23
FIGURE 11 Display Option Showing Values of Robustness Components for the Same Facility
Shown in Figure 10, Compared with Sector Averages
24
With the type of information such as that shown in Figures 8 through 11,
owners/operators can decide to implement new procedures to improve training and exercises of
facility personnel to increase the resourcefulness value, and/or to invest in maintenance of key
functions that would increase robustness.
The average comparison should not be seen as the level of resilience that should be
reached by the facility. It is simply an indication and appropriate level for comparison. Even
when the facility is near the sector maximum for a component of resilience, there may be areas in
which it can and should still improve.
Instead of analyzing only one scenario, the Dashboard allows managers to consider as
many scenarios as needed, reducing the uncertainty inherent in risk management by providing
additional information to managers trying to determine the best courses of action to take to
ensure a better-functioning and more resilient facility.
The Dashboard provides different interactive windows that are particularly relevant to
supporting decisions for proactive risk management. One of these windows is an RI scenario
screen that helps identify what resilience measures can be implemented (Figure 12).
25
At the top of the Dashboard screen, different tabs allow users to select one of the three
level 1 RI parameters; Resourcefulness is subdivided into Resourcefulness Pre-Event and Post-
Event. When one of these components is selected, the related level 2 and level 3 components
appear in the middle of the screen, which enables the user to choose the different characteristics
that apply to her/his facility. At the bottom of the screen, the user can see — in real time — the
repercussions of modifying these components in the different RI values that result (bottom of the
screen). Three representations are used to support this functionality (moving clockwise from the
bottom left of the screen):
• A gauge shows the value of the RI for the selected level 1 component
(i.e., resourcefulness);
• Bar charts show the values of indices for the level 2 components and compare them to the
subsector averages.
26
The ability to change the parameters, the speed with which users can see the results, and
the possibility for assessing different scenarios all serve to make the Dashboard a very powerful
tool and particularly relevant for helping to manage risk-related decisions about critical
infrastructures.
Information from the ECIP program methodology can be interpreted and analyzed in
different ways to define multiple indices such as a vulnerability index, resilience index, and
criticality index. These indices can be combined and analyzed to give an owner/operator
additional information to manage the security and safety of his/her facility.
27
5 CONCLUSION
The development of the RI is intended to assist DHS in analyzing the resilience of the
Nation’s CIKR and identifying ways to improve it. This index complements the previously
developed PMI to enhance the current ECIP program. In addition, the index can provide valuable
information to facility owners/operators about their standing relative to similar sector assets and
about various ways to increase resilience. Applications and uses of the RI for the ECIP program
continue to evolve, and concept improvements and additional enhancements and approaches are
expected. Combining the RI with other indices will provide additional benefits, including
allowing for an overall view of risk. The objective is to develop better decision-making tools that
enable comparison of critical infrastructure and promote a proactive approach to improving
robustness, resourcefulness, and recovery capabilities.
28
29
6 REFERENCES
Cooperrider, D.L., P.F. Sorensen, T.F. Yaeger, and D. Whitney, 2005, Appreciative Inquiry —
Foundations in Positive Organization Development, Stipes Publishing, LLC, IL.
Department of Homeland Security, 2007, Protective Security Advisors — Securing the Nation’s
Critical Infrastructure One Community at a Time, Office of Infrastructure Protection, Protective
Security Coordination Division, Washington, D.C., available at http://safetyservices.ucdavis.edu/
emergency-management/dru-1/iaem-ucc-documents/PSA%20brochure.pdf.
Department of Homeland Security, 2008, Protective Security Advisor (PSA) Program: ECIP
Initiative Engagement, Office of Infrastructure Protection, Protective Security Coordination
Division, Washington, D.C., available at http://www.fhwa.dot.gov/security/emergencymgmt/
profcapacitybldg/ecipmemo.pdf.
Fisher, R.E., and M.A. Norman, 2010, “Constructing a Protective Measures Index across the
Security Spectrum,” Journal of Business Continuity & Emergency Planning, in press.
Fisher, R.E., and F.P. Petit, 2010, Applying Appreciative Inquiry to Facility Security Decision
Making, 3rd International Conference and Doctoral Consortium on Organization Development
and Change, Institut de Socio-Economie des Entreprises et des Organisations (ISEOR), Jean
Moulin University, Lyon, France, June 14–16, 2010.
Keeney, R.L., and H. Raiffa, 1976, Decisions with Multiple Objectives: Preferences and Value
Tradeoffs, John Wiley and Sons, New York.
Matthews, D., M.A. Norman, S. McAraw, and R.E. Fisher, 2010, Constructing a Protective
Measures Index across the Security Spectrum, Contingency Planning & Management West
Conference, Las Vegas, Nev., May 11–13, 2010.
National Infrastructure Advisory Council, 2009, Critical Infrastructure Resilience, Final Report
and Recommendations, U.S. Department of Homeland Security, Washington, D.C., available at
http://www.dhs.gov/xlibrary/assets/niac/niac_critical_infrastructure_resilience.pdf.
30
Peerenboom, J., 2002, Energy Infrastructure Vulnerability Surveys and Assessment, Argonne
National Laboratory, Office of Energy Assurance, U.S. Department of Energy, API Security
Directors’ Conference, July 18, 2002.
Schneier, B., 2003, Beyond Fear: Thinking Sensibly about Security in an Uncertain World,
Copernicus Books, New York.
31
Coordination Restoration
Internal Coordination Number of Dependencies
• EOC Loss Due to Natural Disaster
– On-Site • Last Occurrence
– Backup • Duration of Business
• Business Continuity Plan Interruption
Components • Time to Restart Full Operations
– Human Resources Procedures
Restoration Characteristics
– Communications
• Special Material Needs
– Alternative Source for
Customers • Emergency Communications
• Business Continuity Plan Point • Priority Restoration
of Contact • Business Continuity Plan
– Key Personnel
– Essential Infrastructures
– Mutual Aid Agreements
– MOU/MOA
External Coordination
• Dependency
– Priority Plan
– MOU/MOA
• Access to Specialized Materials
• Civil Government Impact
34